Project Management 4
Module 5: Project risk management
Module 5: Project risk management After completing this module, you will be able to: contribute to the assessment of the impact and likelihood of identified risks contribute to the development of risk management statements and plans monitor and control the project risks
1. CONTRIBUTE TO THE ASSESSMENT OF THE IMPACT AND LIKELIHOOD OF IDENTIFIED RISKS After completing this outcome, you will be able to: explain a range of the risk elements of a project assess and describe likelihood of risk causes of the project in consultation with appropriate stakeholders discuss and describe impact of risk effects on the project
1.1 Explain a range of risk elements of a project The goal of the risk and constraint analysis is to establish the feasibility of the project within the economy, politics, laws and organisational structure that limit your business Project risk is management is: “ the systematic processes of identifying, analysing and responding to project risk”  (PMBOK) Risk is: “ factors that may cause a failure to meet the project’s objectives” (APMBOK)
Activity 1 – Project risks Individually or in a group, brainstorm a list of all the possible risks elements that may influence the outcome of a project
Goals of project risk management Identify factors, or risks, that can negatively impact a project Quantify each possible risk Assess each risk and predict the possible impact on the project Accept or reject risks based on stakeholders level or risk tolerance Maximise positive outcomes and minimise negative outcomes by closely monitoring all accept risks
Components of risk management Risk identification Risk assessment Risk response  Risk control
Understanding project risk Risks are generally associated with uncertain outcomes or a lack of knowledge of future events  Risks are measured according to the probability of their occurrence and the consequences of not achieving project goals  Compare actual project and product results to the project’s quality standards
Common sources of risk The project deliverables or objectives are not clearly defined Technical data is missing Several alternatives are possible at any given time during the project Performance standards are unrealistic Project objectives change Errors occur during the design phase and are not recognised No contingency plans are developed Cost estimates are not developed effectively The schedule is vague or unrealistic Staff members lack the skills to complete the project successfully and in time
Common sources of risk Once a project team identifies possible sources of risk for their project, they should: Estimate the probability that a risk will result from each source Estimate how frequently a risk will result from each source Describe possible consequences of that risk Identify the time at which the risk could occur
Risk identification Risk identification involves recognising and classifying all of the areas of potential risk related to a project Risk is part of project planning Risk identification is ongoing and should be performed through the project’s life cycle
Classifying project risks Once risks have been identified, it is important to classify them.  There are various ways to classify project risks: According to the type of risk being faced According to whether they are internal or external Based on their source
Tools for identifying risk Brainstorming Sensitivity analysis Work breakdown structure Network diagrams Historical information Interviews with stakeholders
Types of risks Known risks Predictable risks Unpredictable risks Insurable risks
The risk continuum Scope of risk management Unknown-unknown Known-unknown Known No information Partial information Complete information Enter new market Feasibility study identifies unknown issues Close-out report Project successfully completed
Activity 2 – Classification of project risks Divide into groups and complete the risk classification, with the help of realistic examples of each risk for each of the three projects as mentioned.  Facilitators should help learners with background knowledge about the project if learners are not familiar with the project. The fourth project should be a project from your immediate environment or area that they are busy with – write down examples of risk elements that may influence it.
 
 
 
 
1.2 Discuss and describe the impact of risk effect on the project Risk areas Funding / budget Time Staffing Customer relations Project size Overall structure External factors
1.2 Discuss and describe the impact of risk effect on the project Business risks Market acceptance Time-to-market Incompatible product fit Difficult to sell Loss of political support
2. CONTRIBUTE TO THE DEVELOPMENT OF RISK MANAGEMENT STATEMENTS AND PLANS After completing this outcome, you will be able to: discuss and describe development of risk statements and plans discuss the communication process for risk threat prevention, recovery activities and opportunity
2.1 Discuss and describe the development of risk management statements and plans Risk management plan and control Document risk management plan Define objectives Identify risk Quantify risk Develop response
Activity 3 Pay a visit to a nearby business (any type) or have a conversation either with somebody in business or with your parents (if they’ve got their own business), or anyone with previous project experience. Refer to any of the risk areas and find out if they experience it, how they deal with it and what they do to counter or overcome the risk? Indicate how government decisions, changes or legislation (over the last couple of years) influences the outcome of a project.  Write down the influence and how it influences the project.
Taking risks stage by stage Risks during the project/idea initiation phase: Unavailable subject matter experts Poor definition of problem or project No feasibility study No or unclear objectives No buy-in from the organisation or other “to be stakeholders”
Taking risks stage by stage Risks during the project planning phase: No risk management plan Spotty planning Underdeveloped requirements and specifications Unclear statement of work No management or stakeholder support Poor role definition Inexperienced team Definite lack of skills
Taking risks stage by stage Risks during the project execution/construction phase: Changes in scope Changes in schedule No control systems in place Unskilled labour Material availability or poor quality material Unreliable suppliers Unexpected price increase (not budget for it) Strikes Weather Regulatory requirements
Taking risks stage by stage Risks during the project close-out / termination phase: Unacceptable to customer Poor quality product/project Budget problems Penalties to be paid for exceeding the time parameter of the project
The basics of risk management Identify the risk Analyse the probability the risk will occur and the potential impact of the risk Determine the overall severity of the risk Determine which risks are the most important for further action Document a response plan for the risk Accept the risk Avoid the risk Monitor the risk Transfer the risk
The basics of risk management Identify the risk Analyse the probability the risk will occur and the potential impact of the risk Determine the overall severity of the risk Determine which risks are the most important for further action Document a response plan for the risk Accept the risk Avoid the risk Monitor the risk Transfer the risk
Project standards for risk management Risk management plan Procurement Contingency reserves Alternative strategies Insurance
Project reserves Management reserves Created for unpredictable risks Contingency reserves Created for predictable risks Approaches used for developing contingency allowances: Budgeting a standard allowance for contingencies and applying it to all projects. Identifying a percentage of additional cost or time needed, based on past experience. Pinpointing the most likely risks for a project, assessing the probability that they will occur, identifying the possible consequences, and then allotting contingencies based on these results.
Constraints Constraints can be identified in advance Real world limits on the possibilities for your projects
Constraints
Constraints Budget constraints Schedule constraints People constraints Real world constraints Facilities and equipment restraints
2.2 Communication process for risk threat prevention, recovery activities and opportunity Questions the project team should ask when determining if a risk is worthwhile: Why should the risk be accepted? What are the potential benefits? Are the potential benefits worth the risk? What are the potential losses? What is the possibility of failure?
When a risk should be avoided When the risk outweighs the possible benefit When there are no specific benefits to be gained When the odds are not in favour of a positive outcome When there are several possible alternatives When there is not enough data to identify possible outcomes When the risk does not help achieve the project goals
Managing project risks Outline the actual risks associated with the project so project stakeholders are aware of them Calculate the probability that the risk could occur Identify the severity of consequences if the risk does occur
Risk assessment Goals for risk assessment Making sure risks are adequately considered in a structured and systematic manner Determining the impact of a risk on achievement of the project’s goals Establishing the effects that a risk will have on all aspects of a project Categorising risks that should be accepted and risks that should be avoided Identifying risks that require attention
Risk assessment process Calculate the probability of occurrence. Assess the possible consequences. Select the most important risks
Benefits of risk assessment Confidence that risks have been thoroughly examined and included in project plans, resulting in risk reduction Information about possible risks is available throughout the project, resulting in a better decision-making process Project objectives might be affected by certain risks, allowing the objectives to be improved upon Confidence that many of the project weaknesses have been identified in advance and are incorporated into the project plan Decrease the number of changes made to the project plan during project execution, resulting in higher chances of project success
3. MONITORING AND CONTROLLING THE PROJECT RISK After completing this outcome, you will be able to: explain the monitoring and control systems linked to the risk management statements and plans explain the need to communicate and document lessons learned in attending to risks
3.1 Explain the monitoring and control systems linked to the risk management statements and plans Risk control entails executing the risk management plan in order to control the effects of project risks Risk control is a continuous process A workaround is an unplanned response or alternative solution The risk control function implements the risk management plan
Disaster recovery planning The management of the disaster recovery plan should be assigned to a manager with responsibility to set up a team to: Develop the disaster recovery plan Control the disaster recovery When the time comes, implement the disaster recovery plan quickly and effectively
3.2 Explain the need to communicate and document lessons learned in attending to risks Lessons learned from project risks include the following: A risk management plan must be developed and explain to all the role-players how risk will be managed The continual monitoring of the project to identify any new or increasing risks The continual monitoring of the effectiveness of the risk management plan Regular reports to the project sponsor and steering committee on the risk as well as the implementation of the risk management plan

NCV 4 Project Management Hands-On Support Slide Show - Module5

  • 1.
  • 2.
    Module 5: Projectrisk management
  • 3.
    Module 5: Projectrisk management After completing this module, you will be able to: contribute to the assessment of the impact and likelihood of identified risks contribute to the development of risk management statements and plans monitor and control the project risks
  • 4.
    1. CONTRIBUTE TOTHE ASSESSMENT OF THE IMPACT AND LIKELIHOOD OF IDENTIFIED RISKS After completing this outcome, you will be able to: explain a range of the risk elements of a project assess and describe likelihood of risk causes of the project in consultation with appropriate stakeholders discuss and describe impact of risk effects on the project
  • 5.
    1.1 Explain arange of risk elements of a project The goal of the risk and constraint analysis is to establish the feasibility of the project within the economy, politics, laws and organisational structure that limit your business Project risk is management is: “ the systematic processes of identifying, analysing and responding to project risk” (PMBOK) Risk is: “ factors that may cause a failure to meet the project’s objectives” (APMBOK)
  • 6.
    Activity 1 –Project risks Individually or in a group, brainstorm a list of all the possible risks elements that may influence the outcome of a project
  • 7.
    Goals of projectrisk management Identify factors, or risks, that can negatively impact a project Quantify each possible risk Assess each risk and predict the possible impact on the project Accept or reject risks based on stakeholders level or risk tolerance Maximise positive outcomes and minimise negative outcomes by closely monitoring all accept risks
  • 8.
    Components of riskmanagement Risk identification Risk assessment Risk response Risk control
  • 9.
    Understanding project riskRisks are generally associated with uncertain outcomes or a lack of knowledge of future events  Risks are measured according to the probability of their occurrence and the consequences of not achieving project goals  Compare actual project and product results to the project’s quality standards
  • 10.
    Common sources ofrisk The project deliverables or objectives are not clearly defined Technical data is missing Several alternatives are possible at any given time during the project Performance standards are unrealistic Project objectives change Errors occur during the design phase and are not recognised No contingency plans are developed Cost estimates are not developed effectively The schedule is vague or unrealistic Staff members lack the skills to complete the project successfully and in time
  • 11.
    Common sources ofrisk Once a project team identifies possible sources of risk for their project, they should: Estimate the probability that a risk will result from each source Estimate how frequently a risk will result from each source Describe possible consequences of that risk Identify the time at which the risk could occur
  • 12.
    Risk identification Riskidentification involves recognising and classifying all of the areas of potential risk related to a project Risk is part of project planning Risk identification is ongoing and should be performed through the project’s life cycle
  • 13.
    Classifying project risksOnce risks have been identified, it is important to classify them. There are various ways to classify project risks: According to the type of risk being faced According to whether they are internal or external Based on their source
  • 14.
    Tools for identifyingrisk Brainstorming Sensitivity analysis Work breakdown structure Network diagrams Historical information Interviews with stakeholders
  • 15.
    Types of risksKnown risks Predictable risks Unpredictable risks Insurable risks
  • 16.
    The risk continuumScope of risk management Unknown-unknown Known-unknown Known No information Partial information Complete information Enter new market Feasibility study identifies unknown issues Close-out report Project successfully completed
  • 17.
    Activity 2 –Classification of project risks Divide into groups and complete the risk classification, with the help of realistic examples of each risk for each of the three projects as mentioned. Facilitators should help learners with background knowledge about the project if learners are not familiar with the project. The fourth project should be a project from your immediate environment or area that they are busy with – write down examples of risk elements that may influence it.
  • 18.
  • 19.
  • 20.
  • 21.
  • 22.
    1.2 Discuss anddescribe the impact of risk effect on the project Risk areas Funding / budget Time Staffing Customer relations Project size Overall structure External factors
  • 23.
    1.2 Discuss anddescribe the impact of risk effect on the project Business risks Market acceptance Time-to-market Incompatible product fit Difficult to sell Loss of political support
  • 24.
    2. CONTRIBUTE TOTHE DEVELOPMENT OF RISK MANAGEMENT STATEMENTS AND PLANS After completing this outcome, you will be able to: discuss and describe development of risk statements and plans discuss the communication process for risk threat prevention, recovery activities and opportunity
  • 25.
    2.1 Discuss anddescribe the development of risk management statements and plans Risk management plan and control Document risk management plan Define objectives Identify risk Quantify risk Develop response
  • 26.
    Activity 3 Paya visit to a nearby business (any type) or have a conversation either with somebody in business or with your parents (if they’ve got their own business), or anyone with previous project experience. Refer to any of the risk areas and find out if they experience it, how they deal with it and what they do to counter or overcome the risk? Indicate how government decisions, changes or legislation (over the last couple of years) influences the outcome of a project. Write down the influence and how it influences the project.
  • 27.
    Taking risks stageby stage Risks during the project/idea initiation phase: Unavailable subject matter experts Poor definition of problem or project No feasibility study No or unclear objectives No buy-in from the organisation or other “to be stakeholders”
  • 28.
    Taking risks stageby stage Risks during the project planning phase: No risk management plan Spotty planning Underdeveloped requirements and specifications Unclear statement of work No management or stakeholder support Poor role definition Inexperienced team Definite lack of skills
  • 29.
    Taking risks stageby stage Risks during the project execution/construction phase: Changes in scope Changes in schedule No control systems in place Unskilled labour Material availability or poor quality material Unreliable suppliers Unexpected price increase (not budget for it) Strikes Weather Regulatory requirements
  • 30.
    Taking risks stageby stage Risks during the project close-out / termination phase: Unacceptable to customer Poor quality product/project Budget problems Penalties to be paid for exceeding the time parameter of the project
  • 31.
    The basics ofrisk management Identify the risk Analyse the probability the risk will occur and the potential impact of the risk Determine the overall severity of the risk Determine which risks are the most important for further action Document a response plan for the risk Accept the risk Avoid the risk Monitor the risk Transfer the risk
  • 32.
    The basics ofrisk management Identify the risk Analyse the probability the risk will occur and the potential impact of the risk Determine the overall severity of the risk Determine which risks are the most important for further action Document a response plan for the risk Accept the risk Avoid the risk Monitor the risk Transfer the risk
  • 33.
    Project standards forrisk management Risk management plan Procurement Contingency reserves Alternative strategies Insurance
  • 34.
    Project reserves Managementreserves Created for unpredictable risks Contingency reserves Created for predictable risks Approaches used for developing contingency allowances: Budgeting a standard allowance for contingencies and applying it to all projects. Identifying a percentage of additional cost or time needed, based on past experience. Pinpointing the most likely risks for a project, assessing the probability that they will occur, identifying the possible consequences, and then allotting contingencies based on these results.
  • 35.
    Constraints Constraints canbe identified in advance Real world limits on the possibilities for your projects
  • 36.
  • 37.
    Constraints Budget constraintsSchedule constraints People constraints Real world constraints Facilities and equipment restraints
  • 38.
    2.2 Communication processfor risk threat prevention, recovery activities and opportunity Questions the project team should ask when determining if a risk is worthwhile: Why should the risk be accepted? What are the potential benefits? Are the potential benefits worth the risk? What are the potential losses? What is the possibility of failure?
  • 39.
    When a riskshould be avoided When the risk outweighs the possible benefit When there are no specific benefits to be gained When the odds are not in favour of a positive outcome When there are several possible alternatives When there is not enough data to identify possible outcomes When the risk does not help achieve the project goals
  • 40.
    Managing project risksOutline the actual risks associated with the project so project stakeholders are aware of them Calculate the probability that the risk could occur Identify the severity of consequences if the risk does occur
  • 41.
    Risk assessment Goalsfor risk assessment Making sure risks are adequately considered in a structured and systematic manner Determining the impact of a risk on achievement of the project’s goals Establishing the effects that a risk will have on all aspects of a project Categorising risks that should be accepted and risks that should be avoided Identifying risks that require attention
  • 42.
    Risk assessment processCalculate the probability of occurrence. Assess the possible consequences. Select the most important risks
  • 43.
    Benefits of riskassessment Confidence that risks have been thoroughly examined and included in project plans, resulting in risk reduction Information about possible risks is available throughout the project, resulting in a better decision-making process Project objectives might be affected by certain risks, allowing the objectives to be improved upon Confidence that many of the project weaknesses have been identified in advance and are incorporated into the project plan Decrease the number of changes made to the project plan during project execution, resulting in higher chances of project success
  • 44.
    3. MONITORING ANDCONTROLLING THE PROJECT RISK After completing this outcome, you will be able to: explain the monitoring and control systems linked to the risk management statements and plans explain the need to communicate and document lessons learned in attending to risks
  • 45.
    3.1 Explain themonitoring and control systems linked to the risk management statements and plans Risk control entails executing the risk management plan in order to control the effects of project risks Risk control is a continuous process A workaround is an unplanned response or alternative solution The risk control function implements the risk management plan
  • 46.
    Disaster recovery planningThe management of the disaster recovery plan should be assigned to a manager with responsibility to set up a team to: Develop the disaster recovery plan Control the disaster recovery When the time comes, implement the disaster recovery plan quickly and effectively
  • 47.
    3.2 Explain theneed to communicate and document lessons learned in attending to risks Lessons learned from project risks include the following: A risk management plan must be developed and explain to all the role-players how risk will be managed The continual monitoring of the project to identify any new or increasing risks The continual monitoring of the effectiveness of the risk management plan Regular reports to the project sponsor and steering committee on the risk as well as the implementation of the risk management plan