Oracle Primavera P6 Pro R8 Tips & Tricks:• Fill Down Command
• XML File Import
• Primavera Hotkeys
• Indicators for Schedule Performance
• User Defined Fields to Manage Layouts
• How to display the “true current schedule”
• Set a “Day of Week” Column for Start
• Activity Steps – details and earned value
• Dealing with “fractured durations”
• Dealing with “12:00am” start dates
Fill Down Command:When the same value needs to be copied to other rows in a column, the fill
down feature lets you do that quickly.
• Process:
1) Works in all windows with table views.
2) Select a source “cell” in a row
3) Select one or more “destination” rows
4) Copy the source value to the destination rows using either “Edit, Fill Down” or
“Ctrl-E”.
Example – Fill Down:-

XML File Import:The XML file import format allows a greater level of control
for importing "Global" data than XER imports.
• Process:
1) File, Import...
• XML Export/Import is limited to a single project
• XER Export/Import supports multiple projects
• P6 EPPM (web) only supports XML
• XML supports more choices for Global Data Import
Control.
XML File Import:-

Primavera Hotkeys:- There are various Hotkeys available within P6 Client.
Indicators for Critical Activities:• User Defined Fields, Type = Indicator
• Manage manually or with Global Change
• Example:
1. Create an Indicator for “Critical”
2. Create a Global Change to Set Indicator to Red if the activity is critical
Using a combination of Global Change and “Indicators” you can graphically
communicate in a Layout.
Indicator for Critical Activity:• For Activity List Reports (no bar chart)
1. Create a User Defined Field

2. Set up as a column in a Layout
3. Create and Execute a Global Change

4. Global Change populates the column

User Defined Fields to Manage Layouts
• User Defined Fields can be very flexible to use
• UDF’s are Global Data, so you need to be careful onoveruse.
Sometimes we need something faster, easier and more flexible to help manage
special presentation Layouts.
• User Defined Fields can be very flexible to use
• UDF’s are Global Data, so you need to be careful on overuse.
User Defined Fields in Layouts
• In this Layout, we are comparing the current critical path with the activity status
of the previous month.

• The Filter UDF is used to manually select the specific activities to include in the
layout.
• The Sort UDF is used to arrange the activities in a specific order that might not
bepossible with traditional sorting options.
• The final Layout is captured (SnagIt) and pasted into PowerPoint and annotated
for presentation to client.
How to display the “True Current Schedule”
• Possible cause: When you status an activity, P6 saves the current ES/EF (at the
time the activity is statused) as the “Current” Start and Finish dates.
Occasionally, before recalculating a schedule I am reviewing (to determine if the
schedule was calculated) I save the currentschedule as a baseline and get a
surprise or two.

• Possible cause: When you status an activity, P6 saves the current ES/EF (at the
time the activity is statused) as the “Current” Start and Finish date.
How to display the “True Current Schedule”
Quick solution: Create User Defined Fields to capture the actual “Current Dates”
with a Global Change. Then set up a Bar using the UDF’s to define the start finish.
Solution: Create User Defined Fields to capture the actual “Current Dates” with a
Global Change. Then set up a Bar using the UDF’s to define the start and finish.

This Layout shows the “True Current Schedule”.
This Layout is useful when receiving a schedule submittal from a contractor and
you want to calculate the schedule and check for variances after the calculation.
(Variances would be caused by modifying the schedule but not calculating the
schedule before creating the submittal copy).
Set a “Day of Week” Column for Start
Add a “Day of week” column to make your tabular report or Activity Label
communicate better..
• Create a User Define Text Field “Day of Week”
• Create and execute a Global Change that sets the UDF to “Day of Week” for the
Activity Start Date.
• Create and execute a Global Change that sets the UDF to “Day of Week” for the
Activity Start Date.

• Review audit report
• Custom Field available for Layouts and Reports

Activity Steps – Detail for Summary Activities:Keeping the schedule from getting too detailed is a constant battle. Try “Steps” to
capture detail within activities.
• Activity Steps can be used to define more detailed elements of an activity.
• Very useful when you want to limit the number of detailed activities but still
provide visibility to detailed elements of the work.
• Steps can also be used to drive activity percent complete to support earned
value metrics.
Activity Steps – Detail for Summary Activities:Keeping the schedule from getting too detailed is a constant battle. Try “Steps” to
capture detail within activities.
Dealing with “fractured durations”
• Before submitting a schedule update, turn on durations decimals and display
time to see if you have this problem.

• Follow the logic to the source (in this case, Activity E1300) and change the
completion time to 5:00 PM and reschedule (F9).

• The problem is corrected from the Data Date forward.
• Dealing with “12:00am” start dates:-

• Notice all the “12:00 AM” Actual Starts?
• Some schedulers insist that if you don’t “Turn on Time” that P6 will default to
12:00 AM dates for Actuals instead of the Calendar Start and Finish times.
• I’ve found that to not be true in schedules that originate in P6 but seems to be
very common in schedules originating in P3 and then imported to P6.
• When you import from P3 to P6, always check your times and correct them (this
is normal “cleanup” when importing P3 files).
• Always turn on “Display Time” to be sure you don’t have this problem.

More Related Content

PPTX
Eot claims hr__may2012
PDF
Delay Analysis and Concurrent Delay
PDF
S Curves Made Easy With Primavera P6
PPTX
Earned Value Management - Leading & Misleading in Project Control
PDF
Favorite Delay Analysis Methodologies Town Hall SEI
PPTX
Forensic schedule analysis acesss
PDF
Project Scheduling & Controls
PDF
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
Eot claims hr__may2012
Delay Analysis and Concurrent Delay
S Curves Made Easy With Primavera P6
Earned Value Management - Leading & Misleading in Project Control
Favorite Delay Analysis Methodologies Town Hall SEI
Forensic schedule analysis acesss
Project Scheduling & Controls
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...

What's hot (20)

PDF
Introduction, development and analysis of banana curve in project management....
PPT
7. (lecture 5) Project scheduling..ppt
DOCX
MS Project
PDF
50 Planning Fundamentals V5.0 - procedures only
PPT
Project Control- Overview Presentation Tafseer
PPTX
Baseline schedule review and analysis
PPTX
VERTEX Construction Delays and Forensic Schedule Analyses
PPTX
Project scope management
PDF
PMBOK® Guide Processes Flow – 6th Edition
PPTX
Claim Presentation Rev 03 FINAL
PPTX
Construction Delay Analysis, Simplified
PPT
08-Project-Control-ppt.ppt
PPTX
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
PDF
Primavera p6 advanced project planning
PDF
Second edition epc project rule of credit and progress measurement promo
PDF
Schedule Updates
PDF
Tilos for linear project
PDF
Schedule Recovery Using Earned Value
PDF
أسس علم التخطيط في 50 سؤال وجواب - الاصدار الخامس
PDF
Delay analysis ... wise after the event.
Introduction, development and analysis of banana curve in project management....
7. (lecture 5) Project scheduling..ppt
MS Project
50 Planning Fundamentals V5.0 - procedures only
Project Control- Overview Presentation Tafseer
Baseline schedule review and analysis
VERTEX Construction Delays and Forensic Schedule Analyses
Project scope management
PMBOK® Guide Processes Flow – 6th Edition
Claim Presentation Rev 03 FINAL
Construction Delay Analysis, Simplified
08-Project-Control-ppt.ppt
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
Primavera p6 advanced project planning
Second edition epc project rule of credit and progress measurement promo
Schedule Updates
Tilos for linear project
Schedule Recovery Using Earned Value
أسس علم التخطيط في 50 سؤال وجواب - الاصدار الخامس
Delay analysis ... wise after the event.
Ad

Similar to Oracle Primavera P6 PRO R8 Tips & tricks (20)

PPTX
MICROSOFT PROJECT
PDF
P6 enhancement requests opsig - Oracle Primavera P6 Collaborate 14
PPTX
Project Scheduling
PPTX
3 - Using MS Project 12-05-17.pptx
PDF
Automation in Excel Reporting - Marco Kiesewetter
PPSX
P6 Version 7 Tricks and Traps
PPT
Closing Cockpit Ver6
PDF
Salesforce Innovation: Advanced Tips for Maximizing Salesforce
PPT
Software Project Management lecture 9
PPTX
Microsoft Project Foundations Course.pptx
PPTX
MS Project Management (Overviews) | Software Mange Tool | Software Project Ma...
PDF
SAP IBP 200 Training 17 -19 Feb.pdf by FZ
PPT
agile-simple-guide-to-creating-project-burndown-chart-201025172824.ppt
PPTX
The strength of a spatial database
PPTX
Project management course lecture Notes from Yom college
PPTX
Spry Scheduling and Haulage model - Tutorial
PPT
Agile: A guide to creating a project burndown chart
PPTX
AXUG Summit 2016 Budget planning session
PPT
msproject.ppt MARTIN DE BORAS PRAGASH M PPT
PPT
Microsoft Project Presentation For Beginners
MICROSOFT PROJECT
P6 enhancement requests opsig - Oracle Primavera P6 Collaborate 14
Project Scheduling
3 - Using MS Project 12-05-17.pptx
Automation in Excel Reporting - Marco Kiesewetter
P6 Version 7 Tricks and Traps
Closing Cockpit Ver6
Salesforce Innovation: Advanced Tips for Maximizing Salesforce
Software Project Management lecture 9
Microsoft Project Foundations Course.pptx
MS Project Management (Overviews) | Software Mange Tool | Software Project Ma...
SAP IBP 200 Training 17 -19 Feb.pdf by FZ
agile-simple-guide-to-creating-project-burndown-chart-201025172824.ppt
The strength of a spatial database
Project management course lecture Notes from Yom college
Spry Scheduling and Haulage model - Tutorial
Agile: A guide to creating a project burndown chart
AXUG Summit 2016 Budget planning session
msproject.ppt MARTIN DE BORAS PRAGASH M PPT
Microsoft Project Presentation For Beginners
Ad

More from CADD Centre Software Solutions Private Limited (20)

PPTX
A b-c-d-(e) of ccsspl corporate presentation
PDF
Login methodology for Primavera V8.3 (EPPM)
PDF
Oracle Primavera Team member 8.3
PDF
PDF
Recurring task IN MS project
PDF
Oracle Primavera contract management
DOCX
Uses of Project Status field
PDF
Oracle primavera Universal content management
PPS
Pert master risk analysis tool
PDF
User preference Option in Oracle Primavera EPPM P6
PDF
Team member in iphones and android
PDF
Activity Duration Types Explained with example in Primavera
PDF
Tested configuration for different Primavera versions
PDF
Difference between versions of primavera 6,7,R8.1,R8.2,R8.3
PDF
Features comparison between Primavera and Microsoft Project
PDF
Project management software consulting
A b-c-d-(e) of ccsspl corporate presentation
Login methodology for Primavera V8.3 (EPPM)
Oracle Primavera Team member 8.3
Recurring task IN MS project
Oracle Primavera contract management
Uses of Project Status field
Oracle primavera Universal content management
Pert master risk analysis tool
User preference Option in Oracle Primavera EPPM P6
Team member in iphones and android
Activity Duration Types Explained with example in Primavera
Tested configuration for different Primavera versions
Difference between versions of primavera 6,7,R8.1,R8.2,R8.3
Features comparison between Primavera and Microsoft Project
Project management software consulting

Recently uploaded (20)

PPTX
Climate Change and Its Global Impact.pptx
PPTX
PLASMA AND ITS CONSTITUENTS 123.pptx
PPTX
Reproductive system-Human anatomy and physiology
PDF
Fun with Grammar (Communicative Activities for the Azar Grammar Series)
PDF
Environmental Education MCQ BD2EE - Share Source.pdf
PPTX
What’s under the hood: Parsing standardized learning content for AI
PDF
M.Tech in Aerospace Engineering | BIT Mesra
PPTX
2025 High Blood Pressure Guideline Slide Set.pptx
PDF
Solved Past paper of Pediatric Health Nursing PHN BS Nursing 5th Semester
PDF
Journal of Dental Science - UDMY (2022).pdf
PDF
Journal of Dental Science - UDMY (2021).pdf
PDF
semiconductor packaging in vlsi design fab
PDF
African Communication Research: A review
PDF
Disorder of Endocrine system (1).pdfyyhyyyy
PDF
fundamentals-of-heat-and-mass-transfer-6th-edition_incropera.pdf
PDF
0520_Scheme_of_Work_(for_examination_from_2021).pdf
PDF
LIFE & LIVING TRILOGY - PART - (2) THE PURPOSE OF LIFE.pdf
PPTX
UNIT_2-__LIPIDS[1].pptx.................
PDF
1.Salivary gland disease.pdf 3.Bleeding and Clotting Disorders.pdf important
PDF
Farming Based Livelihood Systems English Notes
Climate Change and Its Global Impact.pptx
PLASMA AND ITS CONSTITUENTS 123.pptx
Reproductive system-Human anatomy and physiology
Fun with Grammar (Communicative Activities for the Azar Grammar Series)
Environmental Education MCQ BD2EE - Share Source.pdf
What’s under the hood: Parsing standardized learning content for AI
M.Tech in Aerospace Engineering | BIT Mesra
2025 High Blood Pressure Guideline Slide Set.pptx
Solved Past paper of Pediatric Health Nursing PHN BS Nursing 5th Semester
Journal of Dental Science - UDMY (2022).pdf
Journal of Dental Science - UDMY (2021).pdf
semiconductor packaging in vlsi design fab
African Communication Research: A review
Disorder of Endocrine system (1).pdfyyhyyyy
fundamentals-of-heat-and-mass-transfer-6th-edition_incropera.pdf
0520_Scheme_of_Work_(for_examination_from_2021).pdf
LIFE & LIVING TRILOGY - PART - (2) THE PURPOSE OF LIFE.pdf
UNIT_2-__LIPIDS[1].pptx.................
1.Salivary gland disease.pdf 3.Bleeding and Clotting Disorders.pdf important
Farming Based Livelihood Systems English Notes

Oracle Primavera P6 PRO R8 Tips & tricks

  • 1. Oracle Primavera P6 Pro R8 Tips & Tricks:• Fill Down Command • XML File Import • Primavera Hotkeys • Indicators for Schedule Performance • User Defined Fields to Manage Layouts • How to display the “true current schedule” • Set a “Day of Week” Column for Start • Activity Steps – details and earned value • Dealing with “fractured durations” • Dealing with “12:00am” start dates Fill Down Command:When the same value needs to be copied to other rows in a column, the fill down feature lets you do that quickly. • Process: 1) Works in all windows with table views. 2) Select a source “cell” in a row 3) Select one or more “destination” rows 4) Copy the source value to the destination rows using either “Edit, Fill Down” or “Ctrl-E”.
  • 2. Example – Fill Down:- XML File Import:The XML file import format allows a greater level of control for importing "Global" data than XER imports. • Process: 1) File, Import... • XML Export/Import is limited to a single project • XER Export/Import supports multiple projects • P6 EPPM (web) only supports XML • XML supports more choices for Global Data Import Control.
  • 3. XML File Import:- Primavera Hotkeys:- There are various Hotkeys available within P6 Client.
  • 4. Indicators for Critical Activities:• User Defined Fields, Type = Indicator • Manage manually or with Global Change • Example: 1. Create an Indicator for “Critical” 2. Create a Global Change to Set Indicator to Red if the activity is critical Using a combination of Global Change and “Indicators” you can graphically communicate in a Layout. Indicator for Critical Activity:• For Activity List Reports (no bar chart) 1. Create a User Defined Field 2. Set up as a column in a Layout
  • 5. 3. Create and Execute a Global Change 4. Global Change populates the column User Defined Fields to Manage Layouts • User Defined Fields can be very flexible to use • UDF’s are Global Data, so you need to be careful onoveruse. Sometimes we need something faster, easier and more flexible to help manage special presentation Layouts. • User Defined Fields can be very flexible to use
  • 6. • UDF’s are Global Data, so you need to be careful on overuse. User Defined Fields in Layouts • In this Layout, we are comparing the current critical path with the activity status of the previous month. • The Filter UDF is used to manually select the specific activities to include in the layout. • The Sort UDF is used to arrange the activities in a specific order that might not bepossible with traditional sorting options. • The final Layout is captured (SnagIt) and pasted into PowerPoint and annotated for presentation to client.
  • 7. How to display the “True Current Schedule” • Possible cause: When you status an activity, P6 saves the current ES/EF (at the time the activity is statused) as the “Current” Start and Finish dates. Occasionally, before recalculating a schedule I am reviewing (to determine if the schedule was calculated) I save the currentschedule as a baseline and get a surprise or two. • Possible cause: When you status an activity, P6 saves the current ES/EF (at the time the activity is statused) as the “Current” Start and Finish date.
  • 8. How to display the “True Current Schedule” Quick solution: Create User Defined Fields to capture the actual “Current Dates” with a Global Change. Then set up a Bar using the UDF’s to define the start finish.
  • 9. Solution: Create User Defined Fields to capture the actual “Current Dates” with a Global Change. Then set up a Bar using the UDF’s to define the start and finish. This Layout shows the “True Current Schedule”. This Layout is useful when receiving a schedule submittal from a contractor and you want to calculate the schedule and check for variances after the calculation. (Variances would be caused by modifying the schedule but not calculating the schedule before creating the submittal copy). Set a “Day of Week” Column for Start Add a “Day of week” column to make your tabular report or Activity Label communicate better.. • Create a User Define Text Field “Day of Week” • Create and execute a Global Change that sets the UDF to “Day of Week” for the Activity Start Date.
  • 10. • Create and execute a Global Change that sets the UDF to “Day of Week” for the Activity Start Date. • Review audit report
  • 11. • Custom Field available for Layouts and Reports Activity Steps – Detail for Summary Activities:Keeping the schedule from getting too detailed is a constant battle. Try “Steps” to capture detail within activities. • Activity Steps can be used to define more detailed elements of an activity. • Very useful when you want to limit the number of detailed activities but still provide visibility to detailed elements of the work. • Steps can also be used to drive activity percent complete to support earned value metrics.
  • 12. Activity Steps – Detail for Summary Activities:Keeping the schedule from getting too detailed is a constant battle. Try “Steps” to capture detail within activities.
  • 14. • Before submitting a schedule update, turn on durations decimals and display time to see if you have this problem. • Follow the logic to the source (in this case, Activity E1300) and change the completion time to 5:00 PM and reschedule (F9). • The problem is corrected from the Data Date forward. • Dealing with “12:00am” start dates:- • Notice all the “12:00 AM” Actual Starts? • Some schedulers insist that if you don’t “Turn on Time” that P6 will default to 12:00 AM dates for Actuals instead of the Calendar Start and Finish times. • I’ve found that to not be true in schedules that originate in P6 but seems to be very common in schedules originating in P3 and then imported to P6.
  • 15. • When you import from P3 to P6, always check your times and correct them (this is normal “cleanup” when importing P3 files). • Always turn on “Display Time” to be sure you don’t have this problem.