MICHELE ZUKERBERG
PROJECT MANAGER
Natural Areas Restoration and Development Project Portfolio
2
Environmental Education and Public
Access Development
Woodard Bay NRCA, Thurston County
Project Manager: Michele Zukerberg
Consulting Partners: Barker Landscape Architects (Design), Squaxin Island
and Nisqually Tribes (Cultural Interpretation), Shelley Kirk-Rudeen (Sign
Text).
Funding Partners: Washington State Recreation and Conservation Office
(RCO), Squaxin Island Tribe.
Contractor: OSG Dozing Inc. and Turnstone Construction Inc.
Year Completed: 2015
PROJECT SUMMARY
Project included development of cultural and environmental education
facilities at Woodard Bay Natural Resources Conservation Area.
Construction included parking lot expansion, installation of a welcome
kiosk, kayak ramp, bike shelter, learning shelter, interpretive signage and
elements.
Total Project Cost: $1.3M
3
Woodard Bay NRCA Environmental Education and
Public Access Development Cont’d.
Parking lot retaining wall installation. Interpretive building relocation.
Interpretive sign installation and Solar panel installation.
Learning Shelter construction.
Concrete tribal canoe construction. Basket pattern paver installation.
4
Wetland Complex and Riparian Habitat
Restoration
Woodard Bay NRCA, Thurston County
Project Manager: Michele Zukerberg
Consulting Partners: Sound Native Plants
Funding Partners: RCO
Contractor: Sound Native Plants
Year Completed: In progress
PROJECT SUMMARY
Project includes restoration of approximately 30 acres of riparian habitat
including conversion of pastures and farm fields to reconnect wetland
complexes within the Woodard Bay Natural Resources Conservation Area.
Specific restoration actions include weed control, installation of down
wood and snags, planting native trees and shrubs, installation of plant
protection materials and irrigation and maintenance.
Total Project Cost: $400,000.
5
Estuary Restoration: Removal of Creosoted
Structures & Enhancement of Bat Habitat
Woodard Bay NRCA, Thurston County, Henderson Inlet
Project Manager: Michele Zukerberg
Consulting Partners: WindWard Environmental and Sargent Engineers
Funding Partners: Washington State Department of Ecology, Washington
Department of Fish and Wildlife (WDFW), and RCO.
Contractors: Phase 1-NW Marine Inc., Phase 2-Orion Marine Group, Phase
3-Quigg Bros Inc.
Year Completed: 2013
PROJECT SUMMARY
Project was executed in three phases and included the removal of 2100
tons of creosoted materials from Woodard Bay, Chapman Bay and
Henderson Inlet. Portions of the Chapman Bay Pier were reconstructed to
enhance habitat for the largest known maternity bat roost in western
Washington and pilings were retained to support Harbor Seal haul-out
habitat.
Total Project Cost: $1.05M.
Before
After
During
6
Estuary Restoration: Fill Removal
Woodard Bay NRCA, Thurston County, Henderson Inlet
Project Manager: Michele Zukerberg
Consulting Partners: WindWard Environmental and RW Droll Landscape
Architect.
Funding Partners: WDFW and RCO.
Contractor: Nordland Construction NW
Year Completed: 2013
PROJECT SUMMARY
Project included removal of 12,000 cubic yards of fill from Woodard Bay to
restore natural process and function to the estuary.
Total Project Cost: $500,000.
Before
DuringAfter
7
Pocket Estuary Restoration
Stavis NRCA, Kitsap County, Hood Canal
Project Manager: Michele Zukerberg
Consulting Partners: Smayda Environmental Associates
Funding Partners: WDFW
Contractor: Pilchuck Excavating and Sloans Inc.
Year Completed: 2011
PROJECT SUMMARY
Project included removal of 765 feet of bulkhead, demolition of 6
structures, excavation of 10,000 cubic yards of fill, installation of 200
pieces of snags and large woody debris, and native plantings to restore a
pocket estuary and stream channel on Hood Canal.
Total Project Cost: $300,000.
Before
During
After
8
Interpretive Site Development
Kennedy Creek NAP, Mason County, Totten Inlet
Project Manager: Michele Zukerberg
Consulting Partners: RW Droll Landscape Architect, Shelley Kirk-Rudeen-
Sign Text, and Sandra Noel- Sign Artist.
Contractor: Boyson Construction
Year completed: 2008
PROJECT SUMMARY
Project included development of environmental and cultural interpretive
signage and an estuary-viewing platform at the Kennedy Creek Natural
Area Preserve.
Total Project Cost: $105,000.
During
After
9
Hatchery Removal & Stream Restoration
Skookum Inlet NAP, Mason County, Little Skookum Inlet
Project Manager: Michele Zukerberg
Consulting Partners: Fisheries Engineers and Natural Systems Design,
Earthcorps and Squaxin Island Tribe.
Funding Partners: RCO and Squaxin Island Tribe
Contractor: RG Forestry Consultant
Year Completed: 2004
PROJECT SUMMARY
Project included the removal of abandoned fish hatchery structures,
removal of a perched culvert/fish passage barrier, stream channel
excavation, placement of gravels and large woody debris, and native
riparian plant restoration.
Total Project Cost: $140,000
Before During
After
After

Portfolio EP5-Zukerberg

  • 1.
    MICHELE ZUKERBERG PROJECT MANAGER NaturalAreas Restoration and Development Project Portfolio
  • 2.
    2 Environmental Education andPublic Access Development Woodard Bay NRCA, Thurston County Project Manager: Michele Zukerberg Consulting Partners: Barker Landscape Architects (Design), Squaxin Island and Nisqually Tribes (Cultural Interpretation), Shelley Kirk-Rudeen (Sign Text). Funding Partners: Washington State Recreation and Conservation Office (RCO), Squaxin Island Tribe. Contractor: OSG Dozing Inc. and Turnstone Construction Inc. Year Completed: 2015 PROJECT SUMMARY Project included development of cultural and environmental education facilities at Woodard Bay Natural Resources Conservation Area. Construction included parking lot expansion, installation of a welcome kiosk, kayak ramp, bike shelter, learning shelter, interpretive signage and elements. Total Project Cost: $1.3M
  • 3.
    3 Woodard Bay NRCAEnvironmental Education and Public Access Development Cont’d. Parking lot retaining wall installation. Interpretive building relocation. Interpretive sign installation and Solar panel installation. Learning Shelter construction. Concrete tribal canoe construction. Basket pattern paver installation.
  • 4.
    4 Wetland Complex andRiparian Habitat Restoration Woodard Bay NRCA, Thurston County Project Manager: Michele Zukerberg Consulting Partners: Sound Native Plants Funding Partners: RCO Contractor: Sound Native Plants Year Completed: In progress PROJECT SUMMARY Project includes restoration of approximately 30 acres of riparian habitat including conversion of pastures and farm fields to reconnect wetland complexes within the Woodard Bay Natural Resources Conservation Area. Specific restoration actions include weed control, installation of down wood and snags, planting native trees and shrubs, installation of plant protection materials and irrigation and maintenance. Total Project Cost: $400,000.
  • 5.
    5 Estuary Restoration: Removalof Creosoted Structures & Enhancement of Bat Habitat Woodard Bay NRCA, Thurston County, Henderson Inlet Project Manager: Michele Zukerberg Consulting Partners: WindWard Environmental and Sargent Engineers Funding Partners: Washington State Department of Ecology, Washington Department of Fish and Wildlife (WDFW), and RCO. Contractors: Phase 1-NW Marine Inc., Phase 2-Orion Marine Group, Phase 3-Quigg Bros Inc. Year Completed: 2013 PROJECT SUMMARY Project was executed in three phases and included the removal of 2100 tons of creosoted materials from Woodard Bay, Chapman Bay and Henderson Inlet. Portions of the Chapman Bay Pier were reconstructed to enhance habitat for the largest known maternity bat roost in western Washington and pilings were retained to support Harbor Seal haul-out habitat. Total Project Cost: $1.05M. Before After During
  • 6.
    6 Estuary Restoration: FillRemoval Woodard Bay NRCA, Thurston County, Henderson Inlet Project Manager: Michele Zukerberg Consulting Partners: WindWard Environmental and RW Droll Landscape Architect. Funding Partners: WDFW and RCO. Contractor: Nordland Construction NW Year Completed: 2013 PROJECT SUMMARY Project included removal of 12,000 cubic yards of fill from Woodard Bay to restore natural process and function to the estuary. Total Project Cost: $500,000. Before DuringAfter
  • 7.
    7 Pocket Estuary Restoration StavisNRCA, Kitsap County, Hood Canal Project Manager: Michele Zukerberg Consulting Partners: Smayda Environmental Associates Funding Partners: WDFW Contractor: Pilchuck Excavating and Sloans Inc. Year Completed: 2011 PROJECT SUMMARY Project included removal of 765 feet of bulkhead, demolition of 6 structures, excavation of 10,000 cubic yards of fill, installation of 200 pieces of snags and large woody debris, and native plantings to restore a pocket estuary and stream channel on Hood Canal. Total Project Cost: $300,000. Before During After
  • 8.
    8 Interpretive Site Development KennedyCreek NAP, Mason County, Totten Inlet Project Manager: Michele Zukerberg Consulting Partners: RW Droll Landscape Architect, Shelley Kirk-Rudeen- Sign Text, and Sandra Noel- Sign Artist. Contractor: Boyson Construction Year completed: 2008 PROJECT SUMMARY Project included development of environmental and cultural interpretive signage and an estuary-viewing platform at the Kennedy Creek Natural Area Preserve. Total Project Cost: $105,000. During After
  • 9.
    9 Hatchery Removal &Stream Restoration Skookum Inlet NAP, Mason County, Little Skookum Inlet Project Manager: Michele Zukerberg Consulting Partners: Fisheries Engineers and Natural Systems Design, Earthcorps and Squaxin Island Tribe. Funding Partners: RCO and Squaxin Island Tribe Contractor: RG Forestry Consultant Year Completed: 2004 PROJECT SUMMARY Project included the removal of abandoned fish hatchery structures, removal of a perched culvert/fish passage barrier, stream channel excavation, placement of gravels and large woody debris, and native riparian plant restoration. Total Project Cost: $140,000 Before During After After