This document discusses procurement systems for construction projects. It outlines several key procurement options including traditional/conventional methods where the designer completes the design and then a contractor is hired to build based on the completed design. Other options discussed include design-build where the contractor is responsible for both design and construction, management contracting where the contractor manages the design and construction process, and construction management where the client directly hires subcontractors but the contractor advises on design and management. The document compares advantages and disadvantages of each approach and notes there is no single best option, as the appropriate route depends on factors like project objectives, the client's role, and environmental conditions.
In this document
Powered by AI
Introduction to procurement systems and their management in building projects.
Different project objectives necessitate various procurement routes to meet time, cost, and quality.
Involvement in design control and constructor timing influence procurement decisions.
Team selection and payment method (price vs cost) are critical in procurement choices.
Form of contract used influences obligations and variations among parties in construction.
There are over 100 procurement options, but most common are Traditional, Design & Build, and Management routes.
In traditional procurement, clients hire designers, contractors tender post-design completion.
Advantages include design control; disadvantages include slower pace and potential conflicts.
Variants such as nominated subcontractors and accelerated tenders impact responsibility and cost certainty.
In this route, contractors handle both design and construction, shifting more risk onto them.
Advantages of overlap in design and construction; risks of quality loss and adversarial issues.
Variants include novation of design teams and Guaranteed Maximum Price contracts impacting risk.
Similar to design & build but clients hire contractors to manage packages and assist design.
It allows for rapid procurement but places high risk on clients and requires significant involvement.
Clients directly hire package contractors, increasing direct control but also risks.
Recommendation of texts covering procurement routes, contracts, and legal aspects in construction.
Procurement Systems
“The organisationalstructure adopted by the client for the
management of the design and construction of a building
project”
Masterman, An introduction to building procurement systems.
PROCUREMENT OPTIONS
2.
The need fordifferent procurement routes
Differing project objectives
Time, Cost and Quality aims
Differing clients
Degree of involvement, risk attitudes, experience
Operating in a changing environment
Political, economic, legal etc…
No single route will suit all circumstances
PROCUREMENT OPTIONS
3.
The key variablesin the procurement process
Design control
Who employs/directs the designers?
Usually a choice between client & contractor
Constructors’ involvement
When do you employ the contractors?
Usual choice is between when outline design is complete or
when design is finally complete
Contract to construct or to manage construction?
Who employs the subcontractors?
PROCUREMENT OPTIONS
4.
The key variablesin the procurement process
Team selection
Competition or negotiation for selection?
Open or selected tendering?
Paying for the construction
Pay on “Price” or “Cost”?
Price – contractor tenders to do work for a total amount =
estimated costs + profit + overheads +/- risk adjustments
Cost – contractor tenders to do the work for actual costs
(calculated as work proceeds) + allowance for profit etc…
Pay in timed instalments or on completion of stages?
PROCUREMENT OPTIONS
5.
The key variablesin the procurement process
Form of contract used
Contracts specify obligations of parties to one another –
client & designers, client & contractor, contractor &
subcontractor etc…
Main variation in client/contractor contract
Main choice influenced by basic procurement route used
“Standard” forms exist for most routes e.g. JCT Forms
Modification of contracts is common to suit “strong”
party’s requirements
PROCUREMENT OPTIONS
6.
The available routes
The range of options
In excess of 100 recognised variants
In fact permutations are infinite
Better to treat options as lying on continuous spectra of
the procurement variables
The most common routes
Four systems dominated the UK industry in recent times
Traditional, Design & Build, Management Contracting &
Construction Management
PROCUREMENT OPTIONS
7.
The “Traditional” orconventional route
The process
Client employs designers to produce complete design
Contractor tenders on PRICE after design complete
Tenders sought typically on competitive, selected basis
Often lowest price wins
Winning contractor carries out construction through
employed sub-contractors
Client pays price in monthly instalments based on amount
of work done
PROCUREMENT OPTIONS
8.
The “Traditional” orconventional route
Advantages
Client retains good control of design process
Widely used - all parties understand roles etc…
Fairly even split of financial risk between main parties
Cost “certain” after tender and tenders easily comparable
Disadvantages
Slow because design and construction sequential
Contractor’s expertise not used in design
Creates “sides” – potential for adversarial attitudes, conflict
PROCUREMENT OPTIONS
9.
The “Traditional” orconventional route
Variants
Subcontractors may be “nominated” – specified by client –
potential for divided loyalties, blurs responsibilities
“Accelerated” – tenders sought on outline design – may be
quicker but cost certainty lost, time pressures on design etc
PROCUREMENT OPTIONS
10.
The design &build route
The process
Client employs designers to produce outline design
Contractor tenders PRICE to complete design and perform
construction
Tendering usually competitive & selected & best “overall
submission” should win – price, design, programme etc…
Winning contractor carries out design and construction
through employed design consultants and sub-contractors
Client pays price in monthly instalments as traditional
Significant shift in risk to contractor c.f. Traditional
PROCUREMENT OPTIONS
11.
The design &build route
Advantages
Design & construction overlapped – rapid procurement
Contractor’s expertise influences design – cost savings
Early cost “certainty” possible
Client has single point of contact with team
Disadvantages
Client relinquishes control over design – quality problems?
Client changes difficult after contract let
Adversarial attitudes remain, perhaps worse than traditional
PROCUREMENT OPTIONS
12.
The design &build route
Variants
Client may require contractor to employ same design team
as client employed – “Novation” – potential conflict of
interest, blurs responsibility, authority etc…
Tenders may be sought on “Guaranteed Maximum Price”
basis – redistributes risk as savings may be split between
parties. Arriving at the right “Maximum” is the key issue.
Most extreme form – “Package” or “Turnkey” – approach.
Contractor provides full service – ALL design, even
finding site, finance etc in some cases.
PROCUREMENT OPTIONS
13.
The management contractingroute
The process
Client employs designers to produce outline design
Contractor tenders on estimated COST to perform
construction + fee to manage process
Tendering usually competitive & selected
Best “overall submission” should win – fee, management,
programme, track record etc…
Winning contractor joins team – advises designers in
completion of design, organises construction in parallel by
employing “works package contractors”
Client pays COST of packages + fee on monthly basis
PROCUREMENT OPTIONS
14.
The management contractingroute
Advantages
Design & construction overlapped – rapid procurement
Contractor’s expertise influences design – cost savings
Contractor in team reduces adversarial nature of process
Client retains control of design
Late changes in design can be accommodated
Disadvantages
Client assumes high level of TCQ performance risk
Client involvement high
Possible time pressures on design
PROCUREMENT OPTIONS
15.
The construction managementroute
The process
Same as management contracting except that client
employs each package contractor directly
Advantages
Client can exercise high degree of control over entire
procurement process
Disadvantages
Client share of risk is even higher than MC
Client commitment/involvement is very high
PROCUREMENT OPTIONS
16.
Further reading
Manytexts give general descriptions of the procurement routes
and associated contracts as part of coverage of the industry: e.g.
Chapters 7 & 8 of Harvey & Ashworth, The construction industry
of GB, Newnes and Chapter 6 of Cadman & Topping, Property
development, Spon.
More detailed consideration of the routes can be found in:
Masterman, An introduction to building procurement systems,
Spon and Franks, Building procurement systems, Spon.
Murdoch & Hughes, Construction contracts – law and
management, Spon.As its name suggests gives an in-depth
coverage of the legal aspects and case law etc…