Project Monitoring and Control
Martin Sillaots
2019
# 13
Project Phases and Processes
Initiation
Planning
Execution Control
Closing
www.projektor.ee/pm/#control
Monitoring and Control
Information
distribution
Project
execution
Procurement
management
Reporting
Team
development
Schedule
control
Scope
verification
Cost
control
Quality
control
Risk
monitoring
Change
management
Planning
Closing
www.projektor.ee/pm/#control
Project Control
• Monitor project process
– Collect and measure information
– Compare actual process with plans
– Assess trends and forecast
• Take preventive actions
• Take corrective actions
• Provide information for status reporting
www.projektor.ee/pm/#control
Schedule Control
www.projektor.ee/pm/#control
Schedule Control
Information
distribution
Project
execution
Procurement
management
Reporting
Team
development
Schedule
control
Scope
verification
Cost
control
Quality
control
Risk
monitoring
Change
management
Planning
Closing
www.projektor.ee/pm/#control
Schedule Control
• Determine the current status of the project
• Influence the factors that cause changes
• Identify schedule changes
• Evaluate change requests
• Manage change requests
– Plan changes
– Execute changes
www.projektor.ee/pm/#control
Inputs:
- Project plan
- Schedule baseline
- Performance reports
- Approved change
requests
Methods:
- Progress reporting
- Progress
measurement
- Comparison
techniques
- Variance analysis
- Schedule change
control system
- PMIS
Outputs
- Project plan updates
- Schedule updates
- Baseline updates
- Change requests
- Corrective actions
- Lessons learned
Schedule Control
www.projektor.ee/pm/#control
Baseline
Time baseline is a fixed schedule
which is used to measure the
performance of the project
The value or condition against
which all future measurements will
be compared
www.projektor.ee/pm/#control
Schedule Progress Data
• Actual start dates
• Actual finish dates
• Remaining duration for unfinished activities
• Calculating:
– Percent complete
– Schedule variance (SV)
– Schedule performance index (SPI = EV/PV)
www.projektor.ee/pm/#control
Tracking Gantt
www.projektor.ee/pm/#control
Slack
The amount of time that a task in
a project schedule can be delayed
without causing a delay in other
tasks or in project deadline
www.projektor.ee/pm/#control
Free Slack
Total Slack
Slack
www.projektor.ee/pm/#control
Corrective Actions
• Overtime job
• Applying additional resources
• Updating tasks and schedule
– Shortening durations
– Deleting tasks
www.projektor.ee/pm/#control
What Corrective Action (Before)?
www.projektor.ee/pm/#control
What Corrective Action (After)?
www.projektor.ee/pm/#control
Scope Verification and Control
www.projektor.ee/pm/#control
Scope Verification and Control
Information
distribution
Project
execution
Procurement
management
Reporting
Team
development
Schedule
control
Scope
verification
Cost
control
Quality
control
Risk
monitoring
Change
management
Planning
Closing
www.projektor.ee/pm/#control
Scope*
Product Scope: The features and
functionalities that describe project
outcome
Project Scope: The work that needs to
be done to deliver a project outcome
www.projektor.ee/pm/#control
Scope Verification
Process for obtaining stakeholder’s formal
acceptance to the project scope and
deliverables
www.projektor.ee/pm/#control
Scope Control
Management of scope changes
• Avoiding scope changes
• Identifying scope changes
• Evaluating change requests
• Planning and executing changes
• Communicating changes
• Archiving
www.projektor.ee/pm/#control
Inputs:
- Project scope
statement
- WBS
- Project plan
- Performance reports
- Deliverables
Methods:
- Inspection
- Scope Change
control system
- Variance analysis
- Configuration
management system
Outputs
- Deliverables
- Change requests
- Corrective actions
- Plan updates
Scope Verification and Control
www.projektor.ee/pm/#control
Scope Inspection (Review)
• Measuring
• Examining
• Verifying
Does the project work and deliverables meet
acceptance criteria?
www.projektor.ee/pm/#control
Scope Change Control System
Procedures how the scope can be
changed (documentation, tracking,
approval procedures)
www.projektor.ee/pm/#control
Cost Control
www.projektor.ee/pm/#control
Cost Control
Information
distribution
Project
execution
Procurement
management
Reporting
Team
development
Schedule
control
Scope
verification
Cost
control
Quality
control
Risk
monitoring
Change
management
Planning
Closing
www.projektor.ee/pm/#control
Inputs:
- Project plan
- Project budget
- Funding
requirements
- Performance reports
Methods:
- Cost control system
- Performance
measurement
analysis
- Performance reviews
- Variance analysis
- Forecasting
- PMIS
Outputs
- Cost estimation
updates
- Budget updates
- Project plan updates
- Forecasts
- Corrective actions
- Trends
Cost Control
www.projektor.ee/pm/#control
Cost Control System
• Comparing actual costs with baseline costs
• Reflecting schedule and scope changes in the
budget
• Avoiding non-eligible expenses
• Change communication
• Bringing cost overruns within accepted limit
www.projektor.ee/pm/#control
Earned Value Method*
Method that measures
performance of the project and
forecast future performance based
on past performance
work completed ratio × budget price
www.projektor.ee/pm/#control
Variance Analysis
Task Name Fixed
Cost
Total Cost Baseline Variance Actual Remaining
Mullatööd 0,00 € 9 840,00 € 8 640,00 € 1 200,00 € 9 840,00 € 0,00 €
Pinnase
eemaldamine
0,00 € 2 400,00 € 1 200,00 € 1 200,00 € 2 400,00 € 0,00 €
Süvendi kaevamine 0,00 € 2 400,00 € 2 400,00 € 0,00 € 2 400,00 € 0,00 €
Pinnase äravedu 0,00 € 4 400,00 € 4 400,00 € 0,00 € 4 400,00 € 0,00 €
Planeerimine 0,00 € 640,00 € 640,00 € 0,00 € 640,00 € 0,00 €
Vundament ja põrand 0,00 € 11 000,00 € 11 000,00 € 0,00 € 4 493,33 € 6 506,67 €
Tihendatud aluse
rajamine
0,00 € 1 880,00 € 1 880,00 € 0,00 € 1 880,00 € 0,00 €
Vundamendi ja
põranda valamine
0,00 € 7 840,00 € 7 840,00 € 0,00 € 2 613,33 € 5 226,67 €
Vundamendi
soojustamine
0,00 € 1 280,00 € 1 280,00 € 0,00 € 0,00 € 1 280,00 €
www.projektor.ee/pm/#control
Cost Forecasting Method
• CPI - Cost Performance Index (CPI= EV/AC)
• ETC - Estimate to Complete - the remaining cost of
the project
• EAC - Estimate at Completion - the total cost of the
project at the end
www.projektor.ee/pm/#control
Quality Control
www.projektor.ee/pm/#control
Quality Control
Information
distribution
Project
execution
Procurement
management
Reporting
Team
development
Schedule
control
Scope
verification
Cost
control
Quality
control
Risk
monitoring
Change
management
Planning
Closing
www.projektor.ee/pm/#control
Quality Control VS Scope
Control*
Scope control is about accepting
the deliverables
Quality control is about meeting
the quality requirements specified
for the deliverables
www.projektor.ee/pm/#control
Inputs:
- Project plan
- Quality plan
- Quality metrics
- Quality criteria
- Performance
information
- Deliverables
Methods:
- Audits
- Process analysis
- Quality control tools
and techniques
Outputs
- Change requests
- Corrective actions
- Plan updates
- Lessons learned
Quality Control
www.projektor.ee/pm/#control
Quality Control Tools and Techniques
• Cause and effect diagrams
• Control charts
• Flow charts
• Histograms
• Pareto charts
• Run charts - trends
• Scatter diagrams
• Statistical sampling
• Inspections
• Defect repair reviews
www.projektor.ee/pm/#control
Pareto Principle
80/20 Principle
80% of quality loss is caused by 20% of
defects
www.projektor.ee/pm/#control
PMBOK Guide 2009
Pareto Chart
Risk Monitoring and Control
www.projektor.ee/pm/#control
Risk Monitoring and Control
Information
distribution
Project
execution
Procurement
management
Reporting
Team
development
Schedule
control
Scope
verification
Cost
control
Quality
control
Risk
monitoring
Change
management
Planning
Closing
www.projektor.ee/pm/#control
Purpose of Risk Monitoring and Control
• Keeping track on identified risks
• Monitor new risks
• Executing risk response plans
• Evaluating risk response effectiveness
• Variance and trend analysis
www.projektor.ee/pm/#control
Inputs:
- Project plan
- Risk management
plan
- Risk register
- Performance
information
Methods:
- Risk audits
- Risk reassessment
- Variance and trend
analysis
- Technical and
performance
measurement
- Reserve analysis
- Status meetings
Outputs
- Risk register updates
- Change requests
- Corrective actions
- Preventive actions
- Plan changes
- Lessons learned
Risk Monitoring and Control
www.projektor.ee/pm/#control
Risk Register
• List of identified risks
• Risk owners
• Risk response plans
• Symptom and warning signs
• Residual and secondary risks
• Watch list of small risks
• Time and cost
www.projektor.ee/pm/#control
Risk Register Example
www.projektor.ee/pm/#control
Team Development and
Management
www.projektor.ee/pm/#control
Team Development and Management
Information
distribution
Project
execution
Procurement
management
Reporting
Team
development
Schedule
control
Scope
verification
Cost
control
Quality
control
Risk
monitoring
Change
management
Planning
Closing
www.projektor.ee/pm/#control
Inputs:
- Staff assignments
- Staffing plan
- Resource
availability
- Roles and
responsibilities
- Org chart
- Performance
information
Methods:
- Management skills
- Training
- Team building
- Ground rules
- Co-location
- Recognitions and
reward
- Observations and
conversations
- Conflict
management
Outputs
- Team performance
assessment
- Issue log
- Change requests
- Corrective actions
- Preventive actions
- Plan updates
- Lessons learned
Team Development and
Management
www.projektor.ee/pm/#control
Staffing Management Plan
Describes when and how human resources
are exploited
www.projektor.ee/pm/#control
Staffing Management Plan
• Staff acquisition
• Timetable
• Release criteria
• Training needs
• Recognitions and rewards
• Compliance
• Safety
www.projektor.ee/pm/#control
General Management Skills
• Leadership ability
• Communication skills
• Negotiation skills
• Flexibility and adaptability
• Energy level
• Ability to Synthesize
• Work ethic
• Honesty and integrity
• Initiative
• Business judgment
• Self confidence
• Technical skills
• Decisiveness
• Problem solving ability
careers-in-business.com/gmskill.htm
Team Building Activities
Improve interpersonal relationships
www.projektor.ee/pm/#control
Team Building Activity Examples
• Ice breaking social games – e.g. Name ball
• Problem solving games – e.g. Tower building
• Mapping team members’ skills
• Creating the WBS
• WP0 activities
www.projektor.ee/pm/#control
Conflict Prevention Examples
• Set ground rules
• Set Group norms
• Solid PM practices
• Clear communication schedule
• Clear roles
www.projektor.ee/pm/#control
Conflict Solving Examples
• Discussion
• Written communication
• Mediation
• Compromise
• Voting
smallbusiness.chron.com/five-types-conflict-resolution-strategies-19251.html
Integrated Change
Management
www.projektor.ee/pm/#control
Project Integration*
• Project integration with the main organisation
• Project process and outcome integration
• Integration of project processes and stages
• Project documentation integration
www.projektor.ee/pm/#control
Integrated Change Management
Information
distribution
Project
execution
Procurement
management
Reporting
Team
development
Schedule
control
Scope
verification
Cost
control
Quality
control
Risk
monitoring
Change
management
Planning
Closing
www.projektor.ee/pm/#control
Inputs:
- Project plan
- Performance
information
- Deliverables
- Accepted or rejected
change requests
Methods:
- PM methodology
- PMIS
- EVM
- Expert judgment
Outputs
- Corrective actions
- Preventive actions
- Change requests
- Defect repairs
- Forecasts
- Project plan updates
- Deliverables
Integrated Change Management
www.projektor.ee/pm/#control
Change Management
Is needed because projects
seldom run exactly according to
the project management plan
www.projektor.ee/pm/#control
Change Management
• Identifying needs for changes
• Documenting change requests
• Reviewing and approving/rejecting requests, corrective and
preventive actions
• Managing approved changes and actions
• Updating the scope, quality, budget and schedule based on
approved changes
• Maintaining the integrity of baselines
• Documenting impact of changes
• Validating defect repair
• Controlling project quality
www.projektor.ee/pm/#control
Project Management
Methodology
Process that aids a project
management team in monitoring
and controlling the project work
according to the project plan
www.projektor.ee/pm/#control
Project Management
Information System
An automated system that is used
to monitor, control and forecast
the execution of project activities
www.projektor.ee/pm/#control
Configuration Management System
Change Control Process
• Identify changes
• Assess the effectiveness of those changes
• Continuously improve the project
• Communicate changes to the stakeholders
• Configuration identification
• Configuration status reporting
• Configuration verification and auditingwww.projektor.ee/pm/#control
Expert Judges
• Other departments
• Consultants
• Customers
• Sponsors
• Professional associations
• Professional networks
• Stakeholders
www.projektor.ee/pm/#control
Corrective Action
Documented recommendations to
bring future project performance
into conformance with the project
plan
www.projektor.ee/pm/#control
Preventive Action
Documented recommendations
that reduce probability of negative
consequence of project risks
www.projektor.ee/pm/#control
www.projektor.ee/pm/#control
Control End
martinsillaots@gmail.com

More Related Content

PPT
Project Cost Management
PDF
Construction Project Management
PPTX
Project controls
PPTX
Project Risk Management - PMBOK6
PDF
Planning and Scheduling Construction Projects, Part 1: The Planning Process
PDF
Project Scheduling & Controls
PPT
Project Management PPT
PDF
50 Planning Fundamentals V5.0 - procedures only
Project Cost Management
Construction Project Management
Project controls
Project Risk Management - PMBOK6
Planning and Scheduling Construction Projects, Part 1: The Planning Process
Project Scheduling & Controls
Project Management PPT
50 Planning Fundamentals V5.0 - procedures only

What's hot (20)

PDF
Project Controlling and Project Monitoring
PDF
construction project planing
PDF
Construction Project management
PPTX
03 Construction Project Planning and Scheduling
PPTX
Introduction to Project Management (workshop) - v.1
PPTX
An Introduction to Project Management
PPT
Final Project Closing
PPTX
Construction project management
PPSX
Project Management Fundamentals
PDF
Construction Management - New Trends
PPTX
Earned Value Analysis
PDF
Introduction to Project Management by Javid Hamdard
PPTX
Earned Value Management - Leading & Misleading in Project Control
PDF
Construction delays
PDF
Delay Analysis and Concurrent Delay
PPTX
Smart project management - Best Practices to Manage Project effectively
PPTX
Construction Project Management
PPTX
Project cost & control
PDF
Methods of delay analysis
Project Controlling and Project Monitoring
construction project planing
Construction Project management
03 Construction Project Planning and Scheduling
Introduction to Project Management (workshop) - v.1
An Introduction to Project Management
Final Project Closing
Construction project management
Project Management Fundamentals
Construction Management - New Trends
Earned Value Analysis
Introduction to Project Management by Javid Hamdard
Earned Value Management - Leading & Misleading in Project Control
Construction delays
Delay Analysis and Concurrent Delay
Smart project management - Best Practices to Manage Project effectively
Construction Project Management
Project cost & control
Methods of delay analysis
Ad

Similar to Project Control (20)

PPTX
Project Execution
PPTX
Project Cost Management
PDF
Warehouse Operations Redefining methodology
PDF
Lecture 8 monitoring & controlling (1)
PPTX
B-PMP Preparation Course, April09 - Ch 04 - Integration&Professional-v3.pptx
PPTX
Project Scope Management
PDF
Building Commissioning, Ongoing Commissioning and quality management using BACS
PDF
Topic 12 - Project Cost Management.pdf
PPT
PMP Module 4 - Cost
PPTX
61T01411 - PEP for Valeo Fosha New Facility - rev 0.0 -draft
PPTX
Editable Elements
PDF
C03.08-09-ExecutionMonitoringControl.key.pdf
PPTX
BML Business Profile
PDF
Bridging the cost schedule divide - integrating primavera and cost systems ppt
DOC
Ken's_Resume_April 2015 r2
PDF
Engineering and_SAP_Solutions_for_ECO_Presentation.pdf
PPTX
Project Risk Management
PPTX
Presintation on Project constraint
PPT
File 3 removed 4 slides 1
PPTX
07 projectcostmanagement
Project Execution
Project Cost Management
Warehouse Operations Redefining methodology
Lecture 8 monitoring & controlling (1)
B-PMP Preparation Course, April09 - Ch 04 - Integration&Professional-v3.pptx
Project Scope Management
Building Commissioning, Ongoing Commissioning and quality management using BACS
Topic 12 - Project Cost Management.pdf
PMP Module 4 - Cost
61T01411 - PEP for Valeo Fosha New Facility - rev 0.0 -draft
Editable Elements
C03.08-09-ExecutionMonitoringControl.key.pdf
BML Business Profile
Bridging the cost schedule divide - integrating primavera and cost systems ppt
Ken's_Resume_April 2015 r2
Engineering and_SAP_Solutions_for_ECO_Presentation.pdf
Project Risk Management
Presintation on Project constraint
File 3 removed 4 slides 1
07 projectcostmanagement
Ad

More from Martin Sillaots (20)

PPTX
eAdventureEN
PPTX
Documents
PPTX
Game Monetisation and Marketing
PPTX
Prototyping
PPTX
User Interface
PPTX
Level Design
PPTX
PPTX
Characters
PPTX
Game World
PPTX
Game Balancing
PPTX
Core Mechanics
PPTX
Gameplay
PPTX
Game Concept
PPTX
Game Idea
PPTX
Game Design Process
PPTX
Game Elements
PPTX
Introduction to Game Design
PPTX
Project Closing
PPTX
Project Plan Presentation Example
PPTX
Project Integration Management
eAdventureEN
Documents
Game Monetisation and Marketing
Prototyping
User Interface
Level Design
Characters
Game World
Game Balancing
Core Mechanics
Gameplay
Game Concept
Game Idea
Game Design Process
Game Elements
Introduction to Game Design
Project Closing
Project Plan Presentation Example
Project Integration Management

Recently uploaded (20)

PDF
Civil Department's presentation Your score increases as you pick a category
PDF
PUBH1000 - Module 6: Global Health Tute Slides
PPTX
Integrated Management of Neonatal and Childhood Illnesses (IMNCI) – Unit IV |...
PDF
Compact First Student's Book Cambridge Official
PDF
Solved Past paper of Pediatric Health Nursing PHN BS Nursing 5th Semester
PDF
Hospital Case Study .architecture design
PDF
Health aspects of bilberry: A review on its general benefits
PDF
Literature_Review_methods_ BRACU_MKT426 course material
PDF
Myanmar Dental Journal, The Journal of the Myanmar Dental Association (2015).pdf
PDF
Journal of Dental Science - UDMY (2020).pdf
PDF
M.Tech in Aerospace Engineering | BIT Mesra
PDF
Mucosal Drug Delivery system_NDDS_BPHARMACY__SEM VII_PCI Syllabus.pdf
PDF
LIFE & LIVING TRILOGY - PART - (2) THE PURPOSE OF LIFE.pdf
PDF
Horaris_Grups_25-26_Definitiu_15_07_25.pdf
PPTX
4. Diagnosis and treatment planning in RPD.pptx
PDF
anganwadi services for the b.sc nursing and GNM
PDF
Chevening Scholarship Application and Interview Preparation Guide
PDF
Journal of Dental Science - UDMY (2021).pdf
PPT
REGULATION OF RESPIRATION lecture note 200L [Autosaved]-1-1.ppt
PDF
Fun with Grammar (Communicative Activities for the Azar Grammar Series)
Civil Department's presentation Your score increases as you pick a category
PUBH1000 - Module 6: Global Health Tute Slides
Integrated Management of Neonatal and Childhood Illnesses (IMNCI) – Unit IV |...
Compact First Student's Book Cambridge Official
Solved Past paper of Pediatric Health Nursing PHN BS Nursing 5th Semester
Hospital Case Study .architecture design
Health aspects of bilberry: A review on its general benefits
Literature_Review_methods_ BRACU_MKT426 course material
Myanmar Dental Journal, The Journal of the Myanmar Dental Association (2015).pdf
Journal of Dental Science - UDMY (2020).pdf
M.Tech in Aerospace Engineering | BIT Mesra
Mucosal Drug Delivery system_NDDS_BPHARMACY__SEM VII_PCI Syllabus.pdf
LIFE & LIVING TRILOGY - PART - (2) THE PURPOSE OF LIFE.pdf
Horaris_Grups_25-26_Definitiu_15_07_25.pdf
4. Diagnosis and treatment planning in RPD.pptx
anganwadi services for the b.sc nursing and GNM
Chevening Scholarship Application and Interview Preparation Guide
Journal of Dental Science - UDMY (2021).pdf
REGULATION OF RESPIRATION lecture note 200L [Autosaved]-1-1.ppt
Fun with Grammar (Communicative Activities for the Azar Grammar Series)

Project Control

Editor's Notes

  • #8: Identifying, evaluating change requests, planning and executing changes
  • #9: SOW - Statement of Work
  • #10: Project has 3 baselines: Schedule, cost, scope
  • #15: Approved Investigating what is the clients opinion
  • #24: AKA Review, Audit, Walkthrough
  • #28: SOW - Statement of Work
  • #32: Exercises based on equations: - ETC based on new estimate - ETC based on Atypical variance ETC = BAC - EVC - ETC based on typical variance ETC = (BAC - EVC)/CPIC - EAC using a new estimate EAC = ACC + ETC - EAC using remaining budget: EAC = ACC + BAC - EV - EAC using CPIC: EAC = ACC + (BAC – EV)/CPIC BAC: Budget at completion
  • #36: SOW - Statement of Work
  • #43: SOW - Statement of Work
  • #48: SOW - Statement of Work
  • #51: Interpersonal skills, Soft skills.
  • #54: Rules – e.g. how commands will be given?
  • #55: Conflicts arise due the lack of communication
  • #56: Change Control
  • #58: Change Control
  • #59: SOW - Statement of Work
  • #60: Plans are made for changes Different stakeholders make change proposals (requests) Project team has to reject or accept requests according to the project scope and customer needs.
  • #61: New: cost estimates Schedule activity sequences Milestones Resources Risks Risk responses
  • #63: + configuration management system = identifiing, documenting and making changes to the baseline
  • #64: Change con