Required Coordination Between:
Quoting Department, Purchasing, Finance, Program Managers, Top
Management & Corporate
Flow Time Reduction for 747-8 Aircraft Wing Ribs
(Production Manufacturing & Assembly Line)
Ship Set No.“54” Added Approx. 20% More Parts to Each Ship Set.
Ship Set No. “66” Increased Production from 1.5 Ship Sets/Month to
2.0 Ship Sets/Month (33% increase)
Overall Flow Time Reduction = 52+%

Remmele Letter & Results

  • 3.
    Required Coordination Between: QuotingDepartment, Purchasing, Finance, Program Managers, Top Management & Corporate
  • 8.
    Flow Time Reductionfor 747-8 Aircraft Wing Ribs (Production Manufacturing & Assembly Line) Ship Set No.“54” Added Approx. 20% More Parts to Each Ship Set. Ship Set No. “66” Increased Production from 1.5 Ship Sets/Month to 2.0 Ship Sets/Month (33% increase) Overall Flow Time Reduction = 52+%