PRESENTATION
         ON
PRODUCTION SCHEDULING




      PRESENTED BY:-
                 POOJA
                 HEMANGI
                 KIRAN
                 ANURADHA
ROADMAP
What is scheduling
Examples
Objectives
Elements
Priority Planning
Master Production scheduling (MPS)
Objectives of MPS
Functions of MPS
Problems of sequencing in scheduling
SCHEDULING
 Scheduling is one of the most important elements in
  production planning.

 Scheduling calls for through understanding of all aspects of
  the production process and is an outcome of the integration
  of the efforts of planners in the planning group and the
  people in the shop-floor.

 Scheduling integrates the people, machine, materials,
  customer demands, and quality requirements in finalizing the
  priorities. Scheduling makes it possible by determining
  starting and completion data each of the operations.
EXAMPLES OF SCHEDULING

Timetabling Scheduling of the Computer :A number
 of different courses (tasks) have to be given using the
 PC room(resource)
Workforce scheduling : Assign shifts for nurses and
 doctors in a Hospital
Sports Scheduling
Drug Scheduling
scheduling
CONT……….

  Scheduling effects from 2 environmental factors that are
 internal and external to the organization.
Internal environment
External environment
OBJECTIVES OF SCHEDULING

Maximize throughput
Be predictable:
Minimize overhead
Balance resource use
Achieve a balance between response and utilization
Avoid indefinite postponement
Enforce Priorities
Give preference to process holding
Degrade gracefully under heavy loads
ELEMENTS OF SCHEDULING


The processors
The tasks
The processing timings
The precedence relations
PRIORITY PLANNING

 Planning is the process by which the elements
 required to perform a task are determined in advance
 of the job start. The process is as follows :
Operations soft constraints
Management policy constraints
Engineering hard constraints
scheduling
MASTER PRODUCTION SCHEDULING
     Master scheduling is a part of scheduling.

 A Master Production Schedule is a Schedule of the
    completions of the end items and these completions are
    very much planned in nature.

 A MPS is also in management language referred to as the
    master of all the schedules as this schedule provides the
    production, planning, purchasing & top management, the
    most needed information required for planning and
    control of the whole manufacturing process or the
    operation.
scheduling
OBJECTIVES OF MASTER SCHEDULING



Keeping the inventories
Setting up the due dates for the availability of items
Maintaining the customer service
Setting proper schedules
FUNCTIONS OF MASTER
             SCHEDULING

Specifies planning periods as daily, weekly, or monthly.
Group work order processing
Tracks accuracy of order forecasting as percentage.
Classifies supply into types such as materials, purchased,
 flow, work order, and transfer.
Schedule can be edited, changed, or consolidated.
PROBLEMS OF SEQUENCING IN
        SCHEDULING



SHORTEST PROCESSING TIME (SPT)
WEIGHTED SHORTEST PROCESSING TIME (WSPT)
EXAMPLE:-
 The data about a set of single operation jobs that is to be processed in
  a CNC lathe and the processing times of the jobs in the given set of jobs
  are as given in table.
 Find the optimal sequence which will minimize the mean flow time and
  also obtain the corresponding minimum mean flow time.

                     Job, j                Processing time, tj
                       1                             7
                       2                            18
                       3                             6
                       4                             8
                       5                            12
SOLUTION:-
 For the given problem, the number of jobs is equal to
 5. The jobs are arranged as per the SPT ordering.

             Job, j          Processing time, tj
               3                       6
               1                       7
               4                       8
               5                      12
               2                      18


Therefore, the job sequence which will minimize the
 mean flow time is 3-1-4-5-2.
CONT
The computation of flow time for the optimal sequence
 (3-1-4-5-2).
               COMPUTATION FLOW TIME
            Job, j     Processing time, tj   Completion time, cj(fj)

                3              6                       6

                1              7                       13

                4              8                       21

                5              12                      33

                2              18                      51
CONT
Since the ready time rj is zero for all the values of j, the flow
  time (fj) = cj for all j.
Therefore,
1/5 ∑ Fj = 1/5 (6+13+21+33+51)
              = 1/5 (124)
              = 24.8 hours
Therefore, the optimal mean flow time = 24.8 hours.
WSPT
Example
           Job, j     Processing time, tj   Weight , wj

             1                7                 1
             2                18                2
             3                6                 1
             4                8                 2
             5                12                3

Determine the sequence which will minimize the
 weighted flow time of this problem. Also find the
 corresponding weighted mean flow time.
SOLUTION:-

 The weighted processing times of various jobs are
 summarized by using the formula tj/wj, j = 1,2,3,4, and 5
           Job, j   Processing time,   Weight , wj   Tj/wj
                           tj
             1             7               1          7

             2            18               2          9

             3             6               1          6

             4             8               2          4

             5            12               3          4
CALCULATIONS OF WEIGHTED
        FLOW TIMES
Job, j   Processing time,   Cj (Fj)   Weight , wj   Fjwj
                tj
  4             8             8           2         16
  5            12             20          3         60
  3             6             26          1         26
  1             7             33          1         33
  2            18             51          2         102
scheduling

More Related Content

PPTX
Presentation on scheduling
PPT
Operation scheduling
PPTX
Planning
PPTX
Examination of urine
PPT
Delegation Skills
PPT
Planning and scheduling
PPTX
Pull Vs. Push Production
PPTX
Nutrition and wound healing
Presentation on scheduling
Operation scheduling
Planning
Examination of urine
Delegation Skills
Planning and scheduling
Pull Vs. Push Production
Nutrition and wound healing

What's hot (20)

PPTX
Just In Time (JIT)
PPTX
TIME STUDY
PPT
Scheduling and sequencing
PPTX
Material requirement planning, MRP.
PPTX
Inventory
PPTX
Jonson"s Rule Production scheduling
PPT
PPTX
PPTX
Line balancing
PDF
Production Planning and Control
PDF
Basics of Industrial Engineering
PPTX
MAINTENANCE MANAGEMENT
PPT
Method study
PPTX
PPTX
Material management
PPTX
Production planning control ppt
PPT
INDUSTRIAL ENGINEERING - PLANT LAYOUT
PPTX
JIT- JUST IN TIME PPT
Just In Time (JIT)
TIME STUDY
Scheduling and sequencing
Material requirement planning, MRP.
Inventory
Jonson"s Rule Production scheduling
Line balancing
Production Planning and Control
Basics of Industrial Engineering
MAINTENANCE MANAGEMENT
Method study
Material management
Production planning control ppt
INDUSTRIAL ENGINEERING - PLANT LAYOUT
JIT- JUST IN TIME PPT
Ad

Similar to scheduling (20)

PPT
Chapter 16 - Scheduling in Management.ppt
PPTX
Scheduling production
PDF
Operations Research_18ME735_module 5 sequencing notes.pdf
PPT
Power Point Presentation on Flow Shop Scheduling
PDF
Exam110121
PDF
Global seek optimization in real time database
PPTX
Flowshop scheduling
PPT
SBS - SMED Training (Set Up Reduction)
PPT
Litttle knowledge of lean concept helps
PDF
Optimal three stage flow shop scheduling in which processing time, set up tim...
PDF
11.optimal three stage flow shop scheduling in which processing time, set up ...
PDF
R0260950100
PDF
11.flow shop scheduling problem, processing time associated with probabilitie...
PDF
Flow shop scheduling problem, processing time associated with probabilities i...
PDF
A case study on Machine scheduling and sequencing using Meta heuristics
PDF
A case study on Machine scheduling and sequencing using Meta heuristics
PDF
Programación de operaciones (GTO) Ingeniería civil industrial
PPTX
Job Shop Scheduling.pptx
PDF
Application of branch and bound technique for nx3 flow shop scheduling, in wh...
PPTX
Sequencing and shedulding problems for Operations management
Chapter 16 - Scheduling in Management.ppt
Scheduling production
Operations Research_18ME735_module 5 sequencing notes.pdf
Power Point Presentation on Flow Shop Scheduling
Exam110121
Global seek optimization in real time database
Flowshop scheduling
SBS - SMED Training (Set Up Reduction)
Litttle knowledge of lean concept helps
Optimal three stage flow shop scheduling in which processing time, set up tim...
11.optimal three stage flow shop scheduling in which processing time, set up ...
R0260950100
11.flow shop scheduling problem, processing time associated with probabilitie...
Flow shop scheduling problem, processing time associated with probabilities i...
A case study on Machine scheduling and sequencing using Meta heuristics
A case study on Machine scheduling and sequencing using Meta heuristics
Programación de operaciones (GTO) Ingeniería civil industrial
Job Shop Scheduling.pptx
Application of branch and bound technique for nx3 flow shop scheduling, in wh...
Sequencing and shedulding problems for Operations management
Ad

Recently uploaded (20)

PPTX
IndustrialAIGuerillaInnovatorsARCPodcastEp3.pptx
PPTX
Biomass_Energy_PPT_FIN AL________________.pptx
PPTX
OS ALL UNITS MATxtdtc5ctc5cycgctERIAL.pptx
DOCX
Center Enamel Enabling Precision and Sustainability in the Netherlands' Advan...
DOCX
Handbook of entrepreneurship- Chapter 10 - Feasibility analysis by Subin K Mohan
PDF
audit case scenario .pdf by icai ca inter
PDF
109422672-Doc-8973-05-Security-Manual-Seventh-Edition.pdf
PDF
From Legacy to Velocity: how we rebuilt everything in 8 months.
PDF
The Impact of Immigration on National Identity (www.kiu.ac.ug)
PPTX
Capital Investment in IS Infrastracture and Innovation (SDG9)
PDF
Handouts for Housekeeping.pdfhsjsnvvbdjsnwb
PDF
The Future of Marketing: AI, Funnels & MBA Careers | My Annual IIM Lucknow Talk
PPTX
003 seven PARTS OF SPEECH english subject.pptx
DOCX
ola and uber project work (Recovered).docx
PDF
How to run a consulting project from scratch
PDF
Handouts for Housekeeping.pdfbababvsvvNnnh
PDF
Не GPT єдиним: можливості AI в бізнес-аналізі | Вебінар з Тетяною Перловською
 
PDF
The Dynamic CLOs Shaping the Future of the Legal Industry in 2025.pdf
PPT
BCG内部幻灯片撰写. slide template BCG.slide template
PDF
The Evolution of Legal Communication through History (www.kiu.ac.ug)
IndustrialAIGuerillaInnovatorsARCPodcastEp3.pptx
Biomass_Energy_PPT_FIN AL________________.pptx
OS ALL UNITS MATxtdtc5ctc5cycgctERIAL.pptx
Center Enamel Enabling Precision and Sustainability in the Netherlands' Advan...
Handbook of entrepreneurship- Chapter 10 - Feasibility analysis by Subin K Mohan
audit case scenario .pdf by icai ca inter
109422672-Doc-8973-05-Security-Manual-Seventh-Edition.pdf
From Legacy to Velocity: how we rebuilt everything in 8 months.
The Impact of Immigration on National Identity (www.kiu.ac.ug)
Capital Investment in IS Infrastracture and Innovation (SDG9)
Handouts for Housekeeping.pdfhsjsnvvbdjsnwb
The Future of Marketing: AI, Funnels & MBA Careers | My Annual IIM Lucknow Talk
003 seven PARTS OF SPEECH english subject.pptx
ola and uber project work (Recovered).docx
How to run a consulting project from scratch
Handouts for Housekeeping.pdfbababvsvvNnnh
Не GPT єдиним: можливості AI в бізнес-аналізі | Вебінар з Тетяною Перловською
 
The Dynamic CLOs Shaping the Future of the Legal Industry in 2025.pdf
BCG内部幻灯片撰写. slide template BCG.slide template
The Evolution of Legal Communication through History (www.kiu.ac.ug)

scheduling

  • 1. PRESENTATION ON PRODUCTION SCHEDULING PRESENTED BY:- POOJA HEMANGI KIRAN ANURADHA
  • 2. ROADMAP What is scheduling Examples Objectives Elements Priority Planning Master Production scheduling (MPS) Objectives of MPS Functions of MPS Problems of sequencing in scheduling
  • 3. SCHEDULING  Scheduling is one of the most important elements in production planning.  Scheduling calls for through understanding of all aspects of the production process and is an outcome of the integration of the efforts of planners in the planning group and the people in the shop-floor.  Scheduling integrates the people, machine, materials, customer demands, and quality requirements in finalizing the priorities. Scheduling makes it possible by determining starting and completion data each of the operations.
  • 4. EXAMPLES OF SCHEDULING Timetabling Scheduling of the Computer :A number of different courses (tasks) have to be given using the PC room(resource) Workforce scheduling : Assign shifts for nurses and doctors in a Hospital Sports Scheduling Drug Scheduling
  • 6. CONT………. Scheduling effects from 2 environmental factors that are internal and external to the organization. Internal environment External environment
  • 7. OBJECTIVES OF SCHEDULING Maximize throughput Be predictable: Minimize overhead Balance resource use Achieve a balance between response and utilization Avoid indefinite postponement Enforce Priorities Give preference to process holding Degrade gracefully under heavy loads
  • 8. ELEMENTS OF SCHEDULING The processors The tasks The processing timings The precedence relations
  • 9. PRIORITY PLANNING Planning is the process by which the elements required to perform a task are determined in advance of the job start. The process is as follows : Operations soft constraints Management policy constraints Engineering hard constraints
  • 11. MASTER PRODUCTION SCHEDULING  Master scheduling is a part of scheduling.  A Master Production Schedule is a Schedule of the completions of the end items and these completions are very much planned in nature.  A MPS is also in management language referred to as the master of all the schedules as this schedule provides the production, planning, purchasing & top management, the most needed information required for planning and control of the whole manufacturing process or the operation.
  • 13. OBJECTIVES OF MASTER SCHEDULING Keeping the inventories Setting up the due dates for the availability of items Maintaining the customer service Setting proper schedules
  • 14. FUNCTIONS OF MASTER SCHEDULING Specifies planning periods as daily, weekly, or monthly. Group work order processing Tracks accuracy of order forecasting as percentage. Classifies supply into types such as materials, purchased, flow, work order, and transfer. Schedule can be edited, changed, or consolidated.
  • 15. PROBLEMS OF SEQUENCING IN SCHEDULING SHORTEST PROCESSING TIME (SPT) WEIGHTED SHORTEST PROCESSING TIME (WSPT)
  • 16. EXAMPLE:-  The data about a set of single operation jobs that is to be processed in a CNC lathe and the processing times of the jobs in the given set of jobs are as given in table.  Find the optimal sequence which will minimize the mean flow time and also obtain the corresponding minimum mean flow time. Job, j Processing time, tj 1 7 2 18 3 6 4 8 5 12
  • 17. SOLUTION:- For the given problem, the number of jobs is equal to 5. The jobs are arranged as per the SPT ordering. Job, j Processing time, tj 3 6 1 7 4 8 5 12 2 18 Therefore, the job sequence which will minimize the mean flow time is 3-1-4-5-2.
  • 18. CONT The computation of flow time for the optimal sequence (3-1-4-5-2).  COMPUTATION FLOW TIME Job, j Processing time, tj Completion time, cj(fj) 3 6 6 1 7 13 4 8 21 5 12 33 2 18 51
  • 19. CONT Since the ready time rj is zero for all the values of j, the flow time (fj) = cj for all j. Therefore, 1/5 ∑ Fj = 1/5 (6+13+21+33+51) = 1/5 (124) = 24.8 hours Therefore, the optimal mean flow time = 24.8 hours.
  • 20. WSPT Example Job, j Processing time, tj Weight , wj 1 7 1 2 18 2 3 6 1 4 8 2 5 12 3 Determine the sequence which will minimize the weighted flow time of this problem. Also find the corresponding weighted mean flow time.
  • 21. SOLUTION:-  The weighted processing times of various jobs are summarized by using the formula tj/wj, j = 1,2,3,4, and 5 Job, j Processing time, Weight , wj Tj/wj tj 1 7 1 7 2 18 2 9 3 6 1 6 4 8 2 4 5 12 3 4
  • 22. CALCULATIONS OF WEIGHTED FLOW TIMES Job, j Processing time, Cj (Fj) Weight , wj Fjwj tj 4 8 8 2 16 5 12 20 3 60 3 6 26 1 26 1 7 33 1 33 2 18 51 2 102