Risk Assessment Program
Trainer: Mr. Muizz Anibire, MSc
Tel: +966501296203, Email: muizzanibire10@gmail.com
Introduction
 ‘Risk analysis’ is the second step of the risk assessment process.
 Risk analysis consists of determining the consequences and their
probabilities for identified risk events, taking into account the
presence (or not) and the effectiveness of any existing controls.
The consequences and their probabilities are then combined to
determine a level of risk. (ANSI/ASSE Z690.3-2011)
 The purpose of analyzing risk is to gain an understanding of the
risks that are of importance to the organization.
ANSI Z590.3 Hazard and Risk Analysis Process
Risk Analysis Methods
Risk Analysis methods and the ISO 31000 Risk Management
Risk Factors
 Risk factors are the components of risk derived from an
identified hazard that are estimated and measured to produce a
risk score.
 Risk assessments generally have two-dimensional risk scoring
systems, which use two risk factors such as:
 Severity of consequence (S)
 Likelihood (L) or probability
(P) of occurrence.
Other Risk Factors
 Risk factors used in various three and four dimensional models.
 Exposure (E) is used as a general measure of exposure events/units.
 Frequency of Exposure (F) is used as a number of exposure events
for a unit of time.
 Time Duration of Exposure (T) is used as a time period that a single
exposure occurs.
 Vulnerability (V) is sometimes used in security threat analyses, and
generally refers to weaknesses in a system that are factored into the risk
estimation.
 Detection of Failure (D) is used in many FMEA models as a third risk
factor in the risk level scoring system. The detection rating is based on an
estimate of how easily the potential failure could be detected prior to its
occurrence.
 Control Reliability (CR) is used in machine risk assessments and
factors the reliability of a selected control into the risk estimation.
 Prevention Effectiveness (PE) is a risk factor sometimes used in
FMEA and other methods to evaluate a controls effectiveness in
preventing a failure from occurring.
Consequence Analysis
 Consequences are the results, outcomes or losses of an event
caused by a hazard(s).
 Consequences most often refer to the damage or harm caused to
people, assets/property or the environment.
 The assessment team determines the nature and type of
consequences that could result for exposure to a particular
hazard or event.
 A single hazard or event may produce a number of impacts with
various magnitudes (levels of severity), and could affect multiple
assets or stakeholders.
 The assessment’s context determines the types of consequence
analyzed and stakeholders affected.
 Risk should be evaluated for the worst credible case rather than worst
conceivable risk.
Consequence Analysis
 Consequences are the results, outcomes or losses of an event
caused by a hazard(s).
 As a primary risk factor, the ‘severity levels’ of consequences to
be used in an assessment must be determined upfront, during the
development of the context. This will include the types of
consequences and levels of severity.
 It is important that severity categories are clearly defined so that
consequences can be consistently ranked or scored by the risk
assessment team. Severity Category Injury/Illness Levels Financial Loss Levels
Catastrophic (4) Fatality(s) or permanent total
disability
More than $1M
Critical (3) Hospitalizations, permanent-
partial or temporary disability
in excess of three months
$100K - $1M
Marginal (2) Recordable Injury/Illness,
minor injury, lost workday
incident
$10K - $100K
Negligible (1) First Aid or minor medical
treatment
$0 - $10K
An example of risk severity
categories with descriptions
Consequence Analysis
An example of risk severity categories with descriptions
Consequence Analysis
N.B. For Quantitative Risk Assessment (QRA), there is a different
approach for consequence analysis. See the following resources for
more information:
https://www.dnvgl.com/Images/Introduction%20to%20Consequence%20
Modelling%20presentation%20slides_tcm8-86022.pdf
https://www.epa.gov/cameo/aloha-software
https://arshadahmad.files.wordpress.com/2016/09/raam-p7l2aloha.pdf
https://arshadahmad.wordpress.com/process-safety/quantitative-risk-
assessment/
https://arshadahmad.wordpress.com/mkkh1213-risk-assessment-accident-
modeling/
https://www.icheme.org/media/1557/a5-leaflet-flyer-
4pp_consequenciesmodellingtechniques_web.pdf
Likelihood Analysis
 Determining probability or likelihood generally involves:
1. a review of relevant historical data to identify events or
situations which have occurred;
2. predictive type techniques such as fault tree analysis and
event tree analysis and;
3. a structured systematic process guided by a qualified,
knowledgeable expert(s).
 Any available data used should be relevant to the focus of the
assessment.
Likelihood Analysis
Descriptions of likelihood of risk
Risk Level Likelihood of
Occurrence (L)
Description
5 Frequent Almost certain to occur. Has occurred more than once
within the last 12 months. Conditions exist for it to
occur.
4 Probable Very Likely to occur. Has occurred once within the
last 12 months. Conditions often exist for it to occur.
3 Occasional Likely to occur if conditions exist. Has occurred within
the last 24 months. Conditions can exist for it to occur.
2 Moderate May occur if conditions exist. Has occurred within the
last 36 months. Conditions sometimes exist for it to
occur.
1 Unlikely Unlikely to occur. Has not occurred within last 5 years.
Conditions rarely exist for it to occur.
Category description Time Period Frequency
Improbable Century Every 100 Years or more
Remote Decade Every 10 – 100 years
Occasional Annually Every 1 – 10 years
Probable Monthly Every 1 – 12 months
Frequent Weekly Every 1 – 4 weeks
Likelihood Analysis - Exposure
 Where historical data shows a very low frequency of occurrence,
it may be difficult to properly estimate probability. Therefore, it
may be necessary to consider exposure frequency, time, and duration to
a certain hazard or event in the likelihood analysis.
 Exposure is an indication of the extent to which the organization
is subject to the consequences based of the amount of exposure
in numbers.
 Exposure can be measured as the frequency of an event or
exposure, its duration, and/or the assets exposed to risk.
 Some of the variables for exposure might include:
 the number of employees or people exposed
 how frequent an activity is performed
 the miles driven or number of vehicles used in transportation
 the number of customers or products for a product risk assessment
 the number of locations or facilities for a property risk assessment
Likelihood Analysis - Exposure
Descriptions of likelihood of risk considering the frequency of exposure and occurrence
Severity and Probability Descriptions- Example
Severity and Probability Descriptions- Example
Severity and Probability Descriptions- Example
Risk Level Likelihood of
Occurrence (L)
Description
5 Frequent Almost certain to occur. Has occurred more than once
within the last 12 months. Conditions exist for it to
occur.
4 Probable Very Likely to occur. Has occurred once within the
last 12 months. Conditions often exist for it to occur.
3 Occasional Likely to occur if conditions exist. Has occurred within
the last 24 months. Conditions can exist for it to occur.
2 Moderate May occur if conditions exist. Has occurred within the
last 36 months. Conditions sometimes exist for it to
occur.
1 Unlikely Unlikely to occur. Has not occurred within last 5 years.
Conditions rarely exist for it to occur.
Risk Level Severity of
Consequence (S)
Description
4 Catastrophic One or more fatalities; multiple serious
hospitalizations; incident resulting in more than $250 K
3 Critical Disabling injury or illness; permanent impairment;
incident resulting in more than $ 50 K
2 Marginal Medical treatment or restricted work; recordable
incidents; incident resulting in more than $ 1 K
1 Low First aid or non-treatment incidents; incident resulting
in less than $ 1 K
Risk Level Risk Score Action
Very High 12 or greater Operation not permissible; immediate action required
High 8 to 10 Remedial action required; high priority
Moderate 4 to 6 Remedial action suggested
Low 1 to 3 Remedial action discretionary
Assessment of Controls
 The adequacy and effectiveness of existing control measures
greatly affect the level of risk and must be assessed.
 This assessment of controls should include determining the type
of controls for each specific risk, and a judgment of their
effectiveness based on the Hierarchy of Controls.
Risk Formula
Severity x (Likelihood x Protection Factor) = Risk
Protection Factor (PF) Multiplier
Elimination 0.1
Substitution 0.4
Engineering - Multiple 0.6
Engineering - Single 0.7
Warning 0.8
Administrative 0.9
PPE 0.95
No Controls 1
Example of controls’ protection factor
Assessment of Controls
Example of controls’ reduction factor
Risk Scoring
 Two-dimensional risk assessment matrices using likelihood (L) of
event occurrence and severity of consequence (S) have been
commonly used in risk assessment exercises.
Risk Scoring
Standard/
System
Values Risk Factors Matrix
Type
Risk Levels/Categories
ANSI B11.0
-2010
Qualitative Probability (P)
of Occurrence
x
Severity (S) of
Harm
4 x 4 4 risk levels
 High
 Medium
 Low
 Negligible
ANSI Z10-
2012
Qualitative Likelihood (L)
or Exposure
x
Severity (S) of
Injury or Illness
5 x 4 4 risk levels with actions
required
 High
 Serious
 Medium
 Low
ISO 31010/
ANSI
Z690.3-2012
Semi-
quantitative
Likelihood (L)
x
Consequence
(C)
5 x 6 5 risk levels
 I (Highest)
 II
 III
 IV
 V (Lowest)
MIL-STD
882E
Qualitative Probability (P)
x
Severity (S)
6 x 4 5 risk levels
 High
 Serious
 Medium
 Low
 Eliminated
ANSI
Z590.3 PtD
Semi-
quantitative
Severity (S)
x
Probability (P)
5 x 5 4 descriptive risk levels
 Very high risk
 High risk
 Moderate risk
 Low risk
Examples of risk scoring systems
Risk Scoring
 Risk scoring systems with three or four risk factors are becoming
more common, adding a third or fourth factor such as failure
detectability, control effectiveness, vulnerability or other.
 When three or more risk factors are used, a risk priority number
(RPN) is produced.
 To more accurately score risk levels, Manuele proposes that
severity receive a 50% weighting to reflect the impact severity has
on incident outcomes. In the following equation, the rating for
occurrence probability and rating for frequency of exposure are
added together and then multiplied with severity.
Severity x (Probability + Frequency of Exposure) = Risk
Risk Priority Number = Severity x Likelihood x Detection
Session 04_Risk Assessment Program for YSP_Risk Analysis I

More Related Content

PPTX
Session 01 _Risk Assessment Program for YSP_Introduction, Definitions and Sta...
PPTX
Session 06_Risk Assessment Program for YSP_Risk Analysis III
PPTX
Session 07_Risk Assessment Program for YSP_Risk Evaluation
PPTX
Session 02 Risk Assessment Program for YSP_The Risk Assessment Process
PPTX
Session 08_Risk Assessment Program for YSP_Risk Treatment and Communication
PPTX
Session 03_Risk Assessment Program for YSP_Risk Identification
PPTX
Session 05_Risk Assessment Program for YSP_Risk Analysis II
PPTX
Risk Assessment Program For Young Safety Professionals (YSP)
Session 01 _Risk Assessment Program for YSP_Introduction, Definitions and Sta...
Session 06_Risk Assessment Program for YSP_Risk Analysis III
Session 07_Risk Assessment Program for YSP_Risk Evaluation
Session 02 Risk Assessment Program for YSP_The Risk Assessment Process
Session 08_Risk Assessment Program for YSP_Risk Treatment and Communication
Session 03_Risk Assessment Program for YSP_Risk Identification
Session 05_Risk Assessment Program for YSP_Risk Analysis II
Risk Assessment Program For Young Safety Professionals (YSP)

What's hot (20)

PPTX
Construction Safety Training_Session 10_Risk Assessment, Hierarchy of Control...
PPTX
ISO 31000 risk management process
PDF
Risk assessment tools and techniques
PPT
Risk analysis
PDF
Risk Analysis PowerPoint Presentation Slides
PPT
Introduction to Risk Management
PDF
risk analysis
PPSX
Risk analysis
PDF
Risk managment in aviation environment
PPT
Practical Application Of System Safety For Performance Improvement
PDF
Implementing Risk Management
PPT
Risk assesment
PPTX
Unit 5 risk assessment and management
PPT
Calculate the Risk
PPTX
Risk analysis
PPT
Risk Assessment Process NIST 800-30
PDF
HAZARD ANALYSES
PDF
Risk Assessment vs. Risk Management in Manufacturing
PDF
Threat Based Risk Assessment
PDF
Management of risks and implication on the nigerian manufacturing sector
Construction Safety Training_Session 10_Risk Assessment, Hierarchy of Control...
ISO 31000 risk management process
Risk assessment tools and techniques
Risk analysis
Risk Analysis PowerPoint Presentation Slides
Introduction to Risk Management
risk analysis
Risk analysis
Risk managment in aviation environment
Practical Application Of System Safety For Performance Improvement
Implementing Risk Management
Risk assesment
Unit 5 risk assessment and management
Calculate the Risk
Risk analysis
Risk Assessment Process NIST 800-30
HAZARD ANALYSES
Risk Assessment vs. Risk Management in Manufacturing
Threat Based Risk Assessment
Management of risks and implication on the nigerian manufacturing sector
Ad

Similar to Session 04_Risk Assessment Program for YSP_Risk Analysis I (20)

PPT
Hazard identification and Risk assessment .ppt
PPT
Performing Risk Assessments1
PDF
Lecture 03 Risk Assessment.pdhnnnnnnnnnnnf
PPTX
Risk Assessment Training and Development.pptx
PPT
Risk assessment-training
PPT
Risk assessment-training
PDF
Quantitative Risk Assessment | QRA | Risk Assessment | Gaurav Singh Rajput
PPT
Topic5
PPTX
Fire Safety & Risk Assessment: An Approach on Matrix Model
PPTX
HIRA training
PPT
HSE-BMS-006 Risk Assessment & JSA.ppt
PDF
Risk Assessment & Job Safety Analysis | JSA | RA
PDF
Risk Assessment and Job Safety Analysis
PPTX
hira-training-190407052212.pptx
PPT
pilot-Risk_Assessment_at_Workplace.ppt
PPT
pilot-Risk_Assessment_at_Workplace.ppt
PDF
safety oil & gas industry for engineers
PPTX
VCAL WRS2 - Risk assessment and analysis
PPTX
PRINCIPLES-OF-RISK-AND-MANAGEMENT.pptx
PDF
07 - Risk Assessment Creating a Risk Matrix.pdf
Hazard identification and Risk assessment .ppt
Performing Risk Assessments1
Lecture 03 Risk Assessment.pdhnnnnnnnnnnnf
Risk Assessment Training and Development.pptx
Risk assessment-training
Risk assessment-training
Quantitative Risk Assessment | QRA | Risk Assessment | Gaurav Singh Rajput
Topic5
Fire Safety & Risk Assessment: An Approach on Matrix Model
HIRA training
HSE-BMS-006 Risk Assessment & JSA.ppt
Risk Assessment & Job Safety Analysis | JSA | RA
Risk Assessment and Job Safety Analysis
hira-training-190407052212.pptx
pilot-Risk_Assessment_at_Workplace.ppt
pilot-Risk_Assessment_at_Workplace.ppt
safety oil & gas industry for engineers
VCAL WRS2 - Risk assessment and analysis
PRINCIPLES-OF-RISK-AND-MANAGEMENT.pptx
07 - Risk Assessment Creating a Risk Matrix.pdf
Ad

More from Muizz Anibire (20)

DOCX
Questionnaire Template.docx
PDF
Turing’s Computing Machinery and Intelligence.pdf
PPTX
أحكام الجنائز -FUNERAL RITES
PPTX
A MACHINE LEARNING-BASED FRAMEWORK FOR DELAY MITIGATION IN TALL BUILDING PROJ...
PPTX
CAUSES OF DELAY IN TALL BUILDING PROJECTS IN GCC COUNTRIES
PDF
Guidelines on writing a research paper
PDF
Tall buildings in urban context
PPTX
Session 09_Risk Assessment Program for YSP_Risk Assessment Tools and Practica...
PPTX
Construction Safety Training_Session 08_Demolition using Explosives
PPTX
Construction Safety Training_Session 07_Construction Demolition, Hazards and ...
PPTX
Construction Safety Training_Session 05_Access Equipment and Fall Protection
PPTX
Construction Safety Training_Session 04_Working at Heights and Over Water
PPTX
Construction Safety Training_Session 03_Confined Spaces and Underground Works
PPTX
Construction Safety Training_Session 02_Excavation Works, Hazards and Controls
PPTX
Construction Safety Training_Session 01_Overview of the Construction Industry
PDF
Sample risk assessment report for dcc safety students
PPTX
A holistic framework for the post occupancy evaluation of campus residential ...
PDF
An integrated fire safety assessment of a student housing facility
PDF
Fire drill report
PDF
Before the deming’s 14 points for management
Questionnaire Template.docx
Turing’s Computing Machinery and Intelligence.pdf
أحكام الجنائز -FUNERAL RITES
A MACHINE LEARNING-BASED FRAMEWORK FOR DELAY MITIGATION IN TALL BUILDING PROJ...
CAUSES OF DELAY IN TALL BUILDING PROJECTS IN GCC COUNTRIES
Guidelines on writing a research paper
Tall buildings in urban context
Session 09_Risk Assessment Program for YSP_Risk Assessment Tools and Practica...
Construction Safety Training_Session 08_Demolition using Explosives
Construction Safety Training_Session 07_Construction Demolition, Hazards and ...
Construction Safety Training_Session 05_Access Equipment and Fall Protection
Construction Safety Training_Session 04_Working at Heights and Over Water
Construction Safety Training_Session 03_Confined Spaces and Underground Works
Construction Safety Training_Session 02_Excavation Works, Hazards and Controls
Construction Safety Training_Session 01_Overview of the Construction Industry
Sample risk assessment report for dcc safety students
A holistic framework for the post occupancy evaluation of campus residential ...
An integrated fire safety assessment of a student housing facility
Fire drill report
Before the deming’s 14 points for management

Recently uploaded (20)

PPTX
ASME PCC-02 TRAINING -DESKTOP-NLE5HNP.pptx
PDF
Computer System Architecture 3rd Edition-M Morris Mano.pdf
PDF
Java Basics-Introduction and program control
PPTX
ai_satellite_crop_management_20250815030350.pptx
PDF
Applications of Equal_Area_Criterion.pdf
PPTX
CN_Unite_1 AI&DS ENGGERING SPPU PUNE UNIVERSITY
PDF
LOW POWER CLASS AB SI POWER AMPLIFIER FOR WIRELESS MEDICAL SENSOR NETWORK
PPTX
Petroleum Refining & Petrochemicals.pptx
PDF
Unit I -OPERATING SYSTEMS_SRM_KATTANKULATHUR.pptx.pdf
PDF
20250617 - IR - Global Guide for HR - 51 pages.pdf
PPTX
Graph Data Structures with Types, Traversals, Connectivity, and Real-Life App...
PPTX
AUTOMOTIVE ENGINE MANAGEMENT (MECHATRONICS).pptx
PDF
Influence of Green Infrastructure on Residents’ Endorsement of the New Ecolog...
PPTX
mechattonicsand iotwith sensor and actuator
PDF
MLpara ingenieira CIVIL, meca Y AMBIENTAL
PDF
Introduction to Power System StabilityPS
PDF
Unit1 - AIML Chapter 1 concept and ethics
PPTX
wireless networks, mobile computing.pptx
PPTX
Management Information system : MIS-e-Business Systems.pptx
PDF
Computer organization and architecuture Digital Notes....pdf
ASME PCC-02 TRAINING -DESKTOP-NLE5HNP.pptx
Computer System Architecture 3rd Edition-M Morris Mano.pdf
Java Basics-Introduction and program control
ai_satellite_crop_management_20250815030350.pptx
Applications of Equal_Area_Criterion.pdf
CN_Unite_1 AI&DS ENGGERING SPPU PUNE UNIVERSITY
LOW POWER CLASS AB SI POWER AMPLIFIER FOR WIRELESS MEDICAL SENSOR NETWORK
Petroleum Refining & Petrochemicals.pptx
Unit I -OPERATING SYSTEMS_SRM_KATTANKULATHUR.pptx.pdf
20250617 - IR - Global Guide for HR - 51 pages.pdf
Graph Data Structures with Types, Traversals, Connectivity, and Real-Life App...
AUTOMOTIVE ENGINE MANAGEMENT (MECHATRONICS).pptx
Influence of Green Infrastructure on Residents’ Endorsement of the New Ecolog...
mechattonicsand iotwith sensor and actuator
MLpara ingenieira CIVIL, meca Y AMBIENTAL
Introduction to Power System StabilityPS
Unit1 - AIML Chapter 1 concept and ethics
wireless networks, mobile computing.pptx
Management Information system : MIS-e-Business Systems.pptx
Computer organization and architecuture Digital Notes....pdf

Session 04_Risk Assessment Program for YSP_Risk Analysis I

  • 1. Risk Assessment Program Trainer: Mr. Muizz Anibire, MSc Tel: +966501296203, Email: [email protected]
  • 2. Introduction  ‘Risk analysis’ is the second step of the risk assessment process.  Risk analysis consists of determining the consequences and their probabilities for identified risk events, taking into account the presence (or not) and the effectiveness of any existing controls. The consequences and their probabilities are then combined to determine a level of risk. (ANSI/ASSE Z690.3-2011)  The purpose of analyzing risk is to gain an understanding of the risks that are of importance to the organization. ANSI Z590.3 Hazard and Risk Analysis Process
  • 3. Risk Analysis Methods Risk Analysis methods and the ISO 31000 Risk Management
  • 4. Risk Factors  Risk factors are the components of risk derived from an identified hazard that are estimated and measured to produce a risk score.  Risk assessments generally have two-dimensional risk scoring systems, which use two risk factors such as:  Severity of consequence (S)  Likelihood (L) or probability (P) of occurrence.
  • 5. Other Risk Factors  Risk factors used in various three and four dimensional models.  Exposure (E) is used as a general measure of exposure events/units.  Frequency of Exposure (F) is used as a number of exposure events for a unit of time.  Time Duration of Exposure (T) is used as a time period that a single exposure occurs.  Vulnerability (V) is sometimes used in security threat analyses, and generally refers to weaknesses in a system that are factored into the risk estimation.  Detection of Failure (D) is used in many FMEA models as a third risk factor in the risk level scoring system. The detection rating is based on an estimate of how easily the potential failure could be detected prior to its occurrence.  Control Reliability (CR) is used in machine risk assessments and factors the reliability of a selected control into the risk estimation.  Prevention Effectiveness (PE) is a risk factor sometimes used in FMEA and other methods to evaluate a controls effectiveness in preventing a failure from occurring.
  • 6. Consequence Analysis  Consequences are the results, outcomes or losses of an event caused by a hazard(s).  Consequences most often refer to the damage or harm caused to people, assets/property or the environment.  The assessment team determines the nature and type of consequences that could result for exposure to a particular hazard or event.  A single hazard or event may produce a number of impacts with various magnitudes (levels of severity), and could affect multiple assets or stakeholders.  The assessment’s context determines the types of consequence analyzed and stakeholders affected.  Risk should be evaluated for the worst credible case rather than worst conceivable risk.
  • 7. Consequence Analysis  Consequences are the results, outcomes or losses of an event caused by a hazard(s).  As a primary risk factor, the ‘severity levels’ of consequences to be used in an assessment must be determined upfront, during the development of the context. This will include the types of consequences and levels of severity.  It is important that severity categories are clearly defined so that consequences can be consistently ranked or scored by the risk assessment team. Severity Category Injury/Illness Levels Financial Loss Levels Catastrophic (4) Fatality(s) or permanent total disability More than $1M Critical (3) Hospitalizations, permanent- partial or temporary disability in excess of three months $100K - $1M Marginal (2) Recordable Injury/Illness, minor injury, lost workday incident $10K - $100K Negligible (1) First Aid or minor medical treatment $0 - $10K An example of risk severity categories with descriptions
  • 8. Consequence Analysis An example of risk severity categories with descriptions
  • 9. Consequence Analysis N.B. For Quantitative Risk Assessment (QRA), there is a different approach for consequence analysis. See the following resources for more information: https://www.dnvgl.com/Images/Introduction%20to%20Consequence%20 Modelling%20presentation%20slides_tcm8-86022.pdf https://www.epa.gov/cameo/aloha-software https://arshadahmad.files.wordpress.com/2016/09/raam-p7l2aloha.pdf https://arshadahmad.wordpress.com/process-safety/quantitative-risk- assessment/ https://arshadahmad.wordpress.com/mkkh1213-risk-assessment-accident- modeling/ https://www.icheme.org/media/1557/a5-leaflet-flyer- 4pp_consequenciesmodellingtechniques_web.pdf
  • 10. Likelihood Analysis  Determining probability or likelihood generally involves: 1. a review of relevant historical data to identify events or situations which have occurred; 2. predictive type techniques such as fault tree analysis and event tree analysis and; 3. a structured systematic process guided by a qualified, knowledgeable expert(s).  Any available data used should be relevant to the focus of the assessment.
  • 11. Likelihood Analysis Descriptions of likelihood of risk Risk Level Likelihood of Occurrence (L) Description 5 Frequent Almost certain to occur. Has occurred more than once within the last 12 months. Conditions exist for it to occur. 4 Probable Very Likely to occur. Has occurred once within the last 12 months. Conditions often exist for it to occur. 3 Occasional Likely to occur if conditions exist. Has occurred within the last 24 months. Conditions can exist for it to occur. 2 Moderate May occur if conditions exist. Has occurred within the last 36 months. Conditions sometimes exist for it to occur. 1 Unlikely Unlikely to occur. Has not occurred within last 5 years. Conditions rarely exist for it to occur. Category description Time Period Frequency Improbable Century Every 100 Years or more Remote Decade Every 10 – 100 years Occasional Annually Every 1 – 10 years Probable Monthly Every 1 – 12 months Frequent Weekly Every 1 – 4 weeks
  • 12. Likelihood Analysis - Exposure  Where historical data shows a very low frequency of occurrence, it may be difficult to properly estimate probability. Therefore, it may be necessary to consider exposure frequency, time, and duration to a certain hazard or event in the likelihood analysis.  Exposure is an indication of the extent to which the organization is subject to the consequences based of the amount of exposure in numbers.  Exposure can be measured as the frequency of an event or exposure, its duration, and/or the assets exposed to risk.  Some of the variables for exposure might include:  the number of employees or people exposed  how frequent an activity is performed  the miles driven or number of vehicles used in transportation  the number of customers or products for a product risk assessment  the number of locations or facilities for a property risk assessment
  • 13. Likelihood Analysis - Exposure Descriptions of likelihood of risk considering the frequency of exposure and occurrence
  • 14. Severity and Probability Descriptions- Example
  • 15. Severity and Probability Descriptions- Example
  • 16. Severity and Probability Descriptions- Example Risk Level Likelihood of Occurrence (L) Description 5 Frequent Almost certain to occur. Has occurred more than once within the last 12 months. Conditions exist for it to occur. 4 Probable Very Likely to occur. Has occurred once within the last 12 months. Conditions often exist for it to occur. 3 Occasional Likely to occur if conditions exist. Has occurred within the last 24 months. Conditions can exist for it to occur. 2 Moderate May occur if conditions exist. Has occurred within the last 36 months. Conditions sometimes exist for it to occur. 1 Unlikely Unlikely to occur. Has not occurred within last 5 years. Conditions rarely exist for it to occur. Risk Level Severity of Consequence (S) Description 4 Catastrophic One or more fatalities; multiple serious hospitalizations; incident resulting in more than $250 K 3 Critical Disabling injury or illness; permanent impairment; incident resulting in more than $ 50 K 2 Marginal Medical treatment or restricted work; recordable incidents; incident resulting in more than $ 1 K 1 Low First aid or non-treatment incidents; incident resulting in less than $ 1 K Risk Level Risk Score Action Very High 12 or greater Operation not permissible; immediate action required High 8 to 10 Remedial action required; high priority Moderate 4 to 6 Remedial action suggested Low 1 to 3 Remedial action discretionary
  • 17. Assessment of Controls  The adequacy and effectiveness of existing control measures greatly affect the level of risk and must be assessed.  This assessment of controls should include determining the type of controls for each specific risk, and a judgment of their effectiveness based on the Hierarchy of Controls. Risk Formula Severity x (Likelihood x Protection Factor) = Risk Protection Factor (PF) Multiplier Elimination 0.1 Substitution 0.4 Engineering - Multiple 0.6 Engineering - Single 0.7 Warning 0.8 Administrative 0.9 PPE 0.95 No Controls 1 Example of controls’ protection factor
  • 18. Assessment of Controls Example of controls’ reduction factor
  • 19. Risk Scoring  Two-dimensional risk assessment matrices using likelihood (L) of event occurrence and severity of consequence (S) have been commonly used in risk assessment exercises.
  • 20. Risk Scoring Standard/ System Values Risk Factors Matrix Type Risk Levels/Categories ANSI B11.0 -2010 Qualitative Probability (P) of Occurrence x Severity (S) of Harm 4 x 4 4 risk levels  High  Medium  Low  Negligible ANSI Z10- 2012 Qualitative Likelihood (L) or Exposure x Severity (S) of Injury or Illness 5 x 4 4 risk levels with actions required  High  Serious  Medium  Low ISO 31010/ ANSI Z690.3-2012 Semi- quantitative Likelihood (L) x Consequence (C) 5 x 6 5 risk levels  I (Highest)  II  III  IV  V (Lowest) MIL-STD 882E Qualitative Probability (P) x Severity (S) 6 x 4 5 risk levels  High  Serious  Medium  Low  Eliminated ANSI Z590.3 PtD Semi- quantitative Severity (S) x Probability (P) 5 x 5 4 descriptive risk levels  Very high risk  High risk  Moderate risk  Low risk Examples of risk scoring systems
  • 21. Risk Scoring  Risk scoring systems with three or four risk factors are becoming more common, adding a third or fourth factor such as failure detectability, control effectiveness, vulnerability or other.  When three or more risk factors are used, a risk priority number (RPN) is produced.  To more accurately score risk levels, Manuele proposes that severity receive a 50% weighting to reflect the impact severity has on incident outcomes. In the following equation, the rating for occurrence probability and rating for frequency of exposure are added together and then multiplied with severity. Severity x (Probability + Frequency of Exposure) = Risk Risk Priority Number = Severity x Likelihood x Detection