Project Performance Management
Dr. Huy Nguyen
• What is a Project Monitoring System?
• Examples of Progress Report;
• What is the Project Control Process and why is it useful?
• How do we monitor Time Performance?
• Shortcomings of Monitoring Systems;
• Earned Value Management;
• Integrated Cost / Schedule System;
• Project Baselines.
Project Performance Management
2
• It involves determining what data to collect, how, when and who will collect
the data, analysis of the data, and reporting progress.
• You need to know what information is needed to satisfy you and your
stakeholders.
• Think about the Information System Structure.
What is a Project Monitoring System?
Monitoring System
Gather Analyse Report
3
• What data are collected?
– Current status of project (schedule and cost);
– Remaining cost to complete project;
– Date that project will be complete;
– Potential problems to be addressed currently;
– Out-of-control activities requiring intervention;
– Cost and/or schedule overruns & their reasons;
– Forecasting overruns at time of completion.
What is a Project Monitoring System? (cont.)
4
• Collecting data and analysis:
– Who will collect project data?
– How will data be collected?
– When will the data be collected?
– Who will compile and analyze the data?
– Who will receive the reports?
– How will the reports be transmitted?
– When will the reports be distributed?
What is a Project Monitoring System? (cont.)
5
• Progress Report Format:
– Progress since last report;
– Current status of project:
• Schedule;
• Cost;
• Scope.
– Problems and issues since last report:
• Actions and resolution of earlier problems;
• New variances and problems identified.
– Corrective action planned.
• How long should a project status report be?
– From 5 - 10 pages.
Examples of Progress Report
6
• Project Control Process:
– The process of comparing actual performance against plan to identify
deviations, evaluate courses of action, and take appropriate corrective
action.
• Project Control Step:
WhatistheProjectControlProcessandwhyisituseful?
Set and baseline
a plan
Measuring
progress and
performance
Comparing the
plan to the facts
Taking action
7
• Monitoring Time Performance:
– Tools used to catch negative variances from plan and communicate
project schedule status;
– Tracking and baseline Gantt charts:
• Show expected, actual, and trend data for event duration performance;
– Control charts:
• Plot the difference in scheduled time on the critical path with the actual point
on the critical path.
How do we monitor Time Performance?
8
Tracking Gantt chart showing status through periods
Baseline Gantt chart
How do we monitor Time Performance? (cont.)
• Gantt chart:
9
How do we monitor Time Performance? (cont.)
• Control chart:
10
• Monitoring Systems Disparities:
– Time-Phase Baseline Plan:
– Correct the failure of most monitoring systems to connect a project’s
actual performance to its schedule and forecast budget;
– Systems that measure only cost variances do not identify resource and
project cost problems associated with falling behind or progressing
ahead of schedule;
• Earned Value Cost / Schedule System:
– An integrated project management system based on the earned value
concept that uses a time-phased budget baseline to compare actual and
planned schedule and costs.
Shortcomings of Monitoring Systems?
11
• What is Earned Value Management
(EVM)?
– A project performance
measurement technique that
integrates scope, time, and cost
data;
– Give a baseline (original plan plus
approved changes) to determine
how well the project is meeting its
goals;
– Must enter actual information
periodically to use EVM.
• Terms to learn:
– PV: Planned Value;
– AC: Actual Cost;
– EV: Earned Value;
– CV: Cost Variance;
– SV: Schedule Variance;
– CPI: Cost Performance Indicator;
– SPI: Schedule Performance
Indicator.
Earned Value Management
12
• BAC - Budget at Completion:
– Planned budget of the project.
• PV - Planned Value (Budget):
– This is that portion of the approved total cost estimate planned to be spent
on an activity during a given period.
• AC - Actual Cost:
– The total of direct and indirect costs incurred in finishing work on an activity
during a given period.
• EV - Earned Value:
– An estimate of the value of the physical work actually completed.
• CV - Cost Variance:
– Earned value minus the actual cost. Shows the difference between the
estimated cost of an activity and the actual cost of that activity.
• SV - Schedule Variance:
– Earned value minus the planned value. Shows the difference between the
schedule completion of an activity and the actual completion of that activity.
Earned Value Management (cont.)
13
• CPI - Cost Performance Indicator:
– The ratio of earned value to actual cost and can be used to estimate the
projected cost of completing the project;
– If the CPI is equal to 1 or 100% then the planned and actual costs are
equal, or the costs are as budgeted;
– If the CPI is less than 1 or less than 100%, the project is over budget;
– If the CPI is greater than 1 or more than 100%, the project is under
budget.
• SPI - Schedule Performance Indicator:
– The ratio of earned value to planned value and can be used to estimate
the projected time to complete the project;
– Similar to the CPI, an SPI of 1 or 100% means the project is on schedule;
– If the SPI is greater than 1 or 100% then the project is ahead of schedule;
– If the SPI is less than 1 or 100%, the project is behind schedule.
Earned Value Management (cont.)
14
Earned Value Management (cont.)
• Term:
– Earned Value
– Cost Variance
– Schedule Variance
– Cost Performance Indicator
– Schedule Performance Indicator
– Estimate at Completion (EAC)
– Estimated time to Complete (ETC)
– Estimated cost to Complete (ETC)
– Variance at Completion (VAC)
• Formula:
– EV = PV to date X percent complete
– CV = EV – AC
– SV = EV – PV
– CPI = EV / AC
– SPI = EV / PV
– EAC = BAC / CPI
– ETC = Original time estimate / SPI
– ETC = EAC – AC
– VAC = BAC – EAC
15
Earned Value Management (cont.)
• Rules for Earned Value Numbers:
– Negative numbers for cost and schedule variance indicate problems in
those areas;
– The project is costing more than planned or taking longer than planned if
CPI and SPI less than 100%.
• There are methods used to revise estimates of future project costs:
– EVM allows experts in the field to change original baseline durations and
costs because new information tells them the original estimates are not
accurate;
– EVM uses actual costs-to-date plus an efficiency index to project final costs
in large projects where the original budget is unreliable.
Index Cost (CPI) Schedule (SPI)
> 1.0 Under cost Ahead of schedule
= 1.0 On cost On schedule
< 1.0 Over cost Behind schedule
16
Integrated Cost / Schedule System
• Developing an Integrated Cost / Schedule System:
Report &
Action
Calculate &
Compute
Collect
Schedule
Resource
plan
WBS
Budget
Plan
Monitor
17
Integrated Cost / Schedule System (cont.)
• Define the work using a WBS:
– Scope;
– Work packages;
– Deliverables;
– Organization units;
– Resources;
– Budgets.
• Develop work and resource schedules:
– Schedule resource to activities;
– Time-phased work packages into a network.
• Develop a time-phased budget using work packages included in an activity -
Accumulate budgets (PV);
• At the work package level, collect the actual costs for the work performed
(AC);
• Multiply percent complete time by original budget (EV);
• Compute the schedule variance (EV – PV) and the cost variance (EV – AC).
18
Integrated Cost / Schedule System (cont.)
• Sample of an Integrated Cost / Schedule System:
19
Project Baseline
• Measure change against the project baseline;
• Baseline is:
– An anchor point for measuring performance;
– A planned cost and expected schedule against which actual cost and
schedule are measured;
– A basis for cash flows and awarding progress payments;
– A summation of time-phased budgets (cost accounts as summed work
packages) along a project timeline.
• What costs are included in baselines?
– Labor;
– Equipment;
– Materials;
– Project direct overhead costs (DOC).
20
Project Baseline (cont.)
• Scope changes to a baseline:
21
• Project monitoring system includes data collection, analysis and reporting.
• Project control steps include baseline plan, progress measurement,
comparing actual against projected plan, and actions.
• Performance can be monitored using tools such as: tracking Gantts, control
charts, baseline plans and earned value management.
• Earned value management (EVM) is a technique which incorporated scope,
time and cost data to determine the health of the project.
• Integrated Cost / Schedule systems are developed by creating WBS, work /
resource schedules, budget, and EVM.
• Project baselines are an anchor point for measuring performance.
Review
22
Thank You
Next topic:
Project Schedule Management
23

Topic 10 - Project Performance Management.pdf

  • 1.
  • 2.
    • What isa Project Monitoring System? • Examples of Progress Report; • What is the Project Control Process and why is it useful? • How do we monitor Time Performance? • Shortcomings of Monitoring Systems; • Earned Value Management; • Integrated Cost / Schedule System; • Project Baselines. Project Performance Management 2
  • 3.
    • It involvesdetermining what data to collect, how, when and who will collect the data, analysis of the data, and reporting progress. • You need to know what information is needed to satisfy you and your stakeholders. • Think about the Information System Structure. What is a Project Monitoring System? Monitoring System Gather Analyse Report 3
  • 4.
    • What dataare collected? – Current status of project (schedule and cost); – Remaining cost to complete project; – Date that project will be complete; – Potential problems to be addressed currently; – Out-of-control activities requiring intervention; – Cost and/or schedule overruns & their reasons; – Forecasting overruns at time of completion. What is a Project Monitoring System? (cont.) 4
  • 5.
    • Collecting dataand analysis: – Who will collect project data? – How will data be collected? – When will the data be collected? – Who will compile and analyze the data? – Who will receive the reports? – How will the reports be transmitted? – When will the reports be distributed? What is a Project Monitoring System? (cont.) 5
  • 6.
    • Progress ReportFormat: – Progress since last report; – Current status of project: • Schedule; • Cost; • Scope. – Problems and issues since last report: • Actions and resolution of earlier problems; • New variances and problems identified. – Corrective action planned. • How long should a project status report be? – From 5 - 10 pages. Examples of Progress Report 6
  • 7.
    • Project ControlProcess: – The process of comparing actual performance against plan to identify deviations, evaluate courses of action, and take appropriate corrective action. • Project Control Step: WhatistheProjectControlProcessandwhyisituseful? Set and baseline a plan Measuring progress and performance Comparing the plan to the facts Taking action 7
  • 8.
    • Monitoring TimePerformance: – Tools used to catch negative variances from plan and communicate project schedule status; – Tracking and baseline Gantt charts: • Show expected, actual, and trend data for event duration performance; – Control charts: • Plot the difference in scheduled time on the critical path with the actual point on the critical path. How do we monitor Time Performance? 8
  • 9.
    Tracking Gantt chartshowing status through periods Baseline Gantt chart How do we monitor Time Performance? (cont.) • Gantt chart: 9
  • 10.
    How do wemonitor Time Performance? (cont.) • Control chart: 10
  • 11.
    • Monitoring SystemsDisparities: – Time-Phase Baseline Plan: – Correct the failure of most monitoring systems to connect a project’s actual performance to its schedule and forecast budget; – Systems that measure only cost variances do not identify resource and project cost problems associated with falling behind or progressing ahead of schedule; • Earned Value Cost / Schedule System: – An integrated project management system based on the earned value concept that uses a time-phased budget baseline to compare actual and planned schedule and costs. Shortcomings of Monitoring Systems? 11
  • 12.
    • What isEarned Value Management (EVM)? – A project performance measurement technique that integrates scope, time, and cost data; – Give a baseline (original plan plus approved changes) to determine how well the project is meeting its goals; – Must enter actual information periodically to use EVM. • Terms to learn: – PV: Planned Value; – AC: Actual Cost; – EV: Earned Value; – CV: Cost Variance; – SV: Schedule Variance; – CPI: Cost Performance Indicator; – SPI: Schedule Performance Indicator. Earned Value Management 12
  • 13.
    • BAC -Budget at Completion: – Planned budget of the project. • PV - Planned Value (Budget): – This is that portion of the approved total cost estimate planned to be spent on an activity during a given period. • AC - Actual Cost: – The total of direct and indirect costs incurred in finishing work on an activity during a given period. • EV - Earned Value: – An estimate of the value of the physical work actually completed. • CV - Cost Variance: – Earned value minus the actual cost. Shows the difference between the estimated cost of an activity and the actual cost of that activity. • SV - Schedule Variance: – Earned value minus the planned value. Shows the difference between the schedule completion of an activity and the actual completion of that activity. Earned Value Management (cont.) 13
  • 14.
    • CPI -Cost Performance Indicator: – The ratio of earned value to actual cost and can be used to estimate the projected cost of completing the project; – If the CPI is equal to 1 or 100% then the planned and actual costs are equal, or the costs are as budgeted; – If the CPI is less than 1 or less than 100%, the project is over budget; – If the CPI is greater than 1 or more than 100%, the project is under budget. • SPI - Schedule Performance Indicator: – The ratio of earned value to planned value and can be used to estimate the projected time to complete the project; – Similar to the CPI, an SPI of 1 or 100% means the project is on schedule; – If the SPI is greater than 1 or 100% then the project is ahead of schedule; – If the SPI is less than 1 or 100%, the project is behind schedule. Earned Value Management (cont.) 14
  • 15.
    Earned Value Management(cont.) • Term: – Earned Value – Cost Variance – Schedule Variance – Cost Performance Indicator – Schedule Performance Indicator – Estimate at Completion (EAC) – Estimated time to Complete (ETC) – Estimated cost to Complete (ETC) – Variance at Completion (VAC) • Formula: – EV = PV to date X percent complete – CV = EV – AC – SV = EV – PV – CPI = EV / AC – SPI = EV / PV – EAC = BAC / CPI – ETC = Original time estimate / SPI – ETC = EAC – AC – VAC = BAC – EAC 15
  • 16.
    Earned Value Management(cont.) • Rules for Earned Value Numbers: – Negative numbers for cost and schedule variance indicate problems in those areas; – The project is costing more than planned or taking longer than planned if CPI and SPI less than 100%. • There are methods used to revise estimates of future project costs: – EVM allows experts in the field to change original baseline durations and costs because new information tells them the original estimates are not accurate; – EVM uses actual costs-to-date plus an efficiency index to project final costs in large projects where the original budget is unreliable. Index Cost (CPI) Schedule (SPI) > 1.0 Under cost Ahead of schedule = 1.0 On cost On schedule < 1.0 Over cost Behind schedule 16
  • 17.
    Integrated Cost /Schedule System • Developing an Integrated Cost / Schedule System: Report & Action Calculate & Compute Collect Schedule Resource plan WBS Budget Plan Monitor 17
  • 18.
    Integrated Cost /Schedule System (cont.) • Define the work using a WBS: – Scope; – Work packages; – Deliverables; – Organization units; – Resources; – Budgets. • Develop work and resource schedules: – Schedule resource to activities; – Time-phased work packages into a network. • Develop a time-phased budget using work packages included in an activity - Accumulate budgets (PV); • At the work package level, collect the actual costs for the work performed (AC); • Multiply percent complete time by original budget (EV); • Compute the schedule variance (EV – PV) and the cost variance (EV – AC). 18
  • 19.
    Integrated Cost /Schedule System (cont.) • Sample of an Integrated Cost / Schedule System: 19
  • 20.
    Project Baseline • Measurechange against the project baseline; • Baseline is: – An anchor point for measuring performance; – A planned cost and expected schedule against which actual cost and schedule are measured; – A basis for cash flows and awarding progress payments; – A summation of time-phased budgets (cost accounts as summed work packages) along a project timeline. • What costs are included in baselines? – Labor; – Equipment; – Materials; – Project direct overhead costs (DOC). 20
  • 21.
    Project Baseline (cont.) •Scope changes to a baseline: 21
  • 22.
    • Project monitoringsystem includes data collection, analysis and reporting. • Project control steps include baseline plan, progress measurement, comparing actual against projected plan, and actions. • Performance can be monitored using tools such as: tracking Gantts, control charts, baseline plans and earned value management. • Earned value management (EVM) is a technique which incorporated scope, time and cost data to determine the health of the project. • Integrated Cost / Schedule systems are developed by creating WBS, work / resource schedules, budget, and EVM. • Project baselines are an anchor point for measuring performance. Review 22
  • 23.
    Thank You Next topic: ProjectSchedule Management 23