Road Drainage Design Principles
Road Drainage Design Principles
DRAINAGE DESIGN
4.1 General Considerations
Roads will affect the natural surface and subsurface drainage pattern of a watershed or individual
hillslope. Road drainage design has as its basic objective the reduction and/or elimination of
energy generated by flowing water. The destructive power of flowing water, as stated in Section
3.2.2, increases exponentially as its velocity increases. Therefore, water must not be allowed to
develop sufficient volume or velocity so as to cause excessive wear along ditches, below
culverts, or along exposed running surfaces, cuts, or fills.
Provision for adequate drainage is of paramount importance in road design and cannot be
overemphasized. The presence of excess water or moisture within the roadway will adversely
affect the engineering properties of the materials with which it was constructed. Cut or fill
failures, road surface erosion, and weakened subgrades followed by a mass failure are all
products of inadequate or poorly designed drainage. As has been stated previously, many
drainage problems can be avoided in the location and design of the road: Drainage design is most
appropriately included in alignment and gradient planning.
Hillslope geomorphology and hydrologic factors are important considerations in the location,
design, and construction of a road. Slope morphology impacts road drainage and ultimately road
stability. Important factors are slope shape (uniform, convex, concave), slope gradient, slope
length, stream drainage characteristics (e.g., braided, dendritic), depth to bedrock, bedrock
characteristics (e.g., fractured, hardness, bedding), and soil texture and permeability. Slope shape
(Figure 59) gives an indication of surface and subsurface water concentration or dispersion.
Convex slopes (e.g., wide ridges) will tend to disperse water as it moves downhill. Straight
slopes concentrate water on the lower slopes and contribute to the buildup of hydrostatic
pressure. Concave slopes typically exhibit swales and draws. Water in these areas is concentrated
at the lowest point on the slope and therefore represent the least desirable location for a road.
Hydrologic factors to consider in locating roads are number of stream crossings, side slope, and
moisture regime. For example, at the lowest point on the slope, only one or two stream crossings
may be required. Likewise, side slopes generally are not as steep, thereby reducing the amount of
excavation. However, side cast fills and drainage requirements will need careful attention since
water collected from upper positions on the slope will concentrate in the lower positions. In
general, roads built on the upper one-third of a slope have better soil moisture conditions and,
therefore, tend to be more stable than roads built on lower positions on the slope.
Natural drainage characteristics of a hillslope, as a rule, should not be changed. For example, a
drainage network will expand during a storm to include the smallest depression and draw in
order to collect and transport runoff. Therefore, a culvert should be placed in each draw so as not
to impede the natural disposition of stormflow. Culverts should be placed at grade and in line
with the centerline of the channel. Failure to do this often results in excessive erosion of soils
above and below the culvert. Also, debris cannot pass freely through the culvert causing plugging
and oftentimes complete destruction of the road prism. Headwater streams are of particular
concern (point A, Figure 60) since it is common to perceive that measurable flows cannot be
generated from the moisture collection area above the crossings. However, little or no drainage
on road crossings in these areas is notorious for causing major slide and debris torrents,
especially if they are located on convex slope breaks.
Increased risks of road failures are created at points A and B. At point A, water will pond above
the road fill or flow downslope through the roadside ditch to point B. Ponding at A may cause
weakening and/or erosion of the subgrade . If the culvert on Stream 1 plugs, water and debris
will flow to point A and from A to B. Hence, the culvert at B is handling discharge from all three
streams. If designed to minimum specifications, it is unlikely that either the ditch or the culvert at
B will be able to efficiently discharge flow and debris from all three streams resulting in
overflow and possible failure of the road at point B.
Slope shape and its impact on slope hydrology. Slope
shape determines whether water is dispersed or concentrated. (US
Forest Service, 1979).
Figure 59.
A road drainage system must satisfy two main criteria if it is to be effective throughout its design
life:
1. It must allow for a minimum of disturbance of the natural drainage pattern.
2. It must drain surface and subsurface water away from the roadway and dissipate it in a
way that prevents excessive collection of water in unstable areas and subsequent
downstream erosion.
The design of drainage structures is based on the sciences of hydrology and hydraulics-the
former deals with the occurrence and form of water in the natural environment (precipitation,
streamflow, soil moisture, etc.) while the latter deals with the engineering properties of fluids in
motion.
1. The size of the drainage area. The larger the area, the greater the volume of
runoff. An estimate of basin area is needed in order to use runoff formulas and charts.
2. Topography. Runoff volume generally increases with steepness of slope. Average slope,
basin elevation, and aspect, although not often called for in most runoff formulas and
charts, may provide helpful clues in refining a design.
3. Soil. Runoff varies with soil characteristics, particularly permeability and infiltration
capacity. The infiltration rate of a dry soil, by nature of its intrinsic permeability, will
steadily decrease with time as it becomes wetted, given a constant rainfall rate. If the
rainfall rate is greater than the final infiltration rate of the soil (infiltration capacity), that
quantity of water which cannot be absorbed is stored in depressions in the ground or runs
off the surface. Any condition which adversely affects the infiltration characteristics of
the soil will increase the amount of runoff. Such conditions may include hydrophobicity,
compaction, and frozen earth.
A number of different methods are available to predict peak flows. Flood frequency analysis is
the most accurate method employed when sufficient hydrologic data is available. For instance,
the United States Geological Survey has published empirical equations providing estimates of
peak discharges from streams in many parts of the United States based on regional data collected
from "gaged" streams. In northwest Oregon, frequency analysis has revealed that discharge for
the flow event having a 25-year recurrence interval is Most closely correlated with drainage area
and precipitation intensity for the 2-year, 24-hour storm event. This is, by far, the best means of
estimating peak flows on an ungaged stream since the recurrence interval associated with any
given flow event can be identified and used for evaluating the probability of failure.
The probability of occurrence of peak flows exceeding the design capacity of a proposed stream
crossing installation should be determined and used in the design procedure. To incorporate this
information into the design, the risk of failure over the design life must be specified. By
identifying an acceptable level of risk, the land manager is formally stating the desired level of
success (or failure) to be achieved with road drainage structures. Table 25 lists flood recurrence
intervals for installations in relation to their design life and probability of failure.
Flood recurrence interval (years) in relation to design
life and probability of failure.* (Megahan, 1977).
Table 23.
Design
Life
(years)
10
20
30
40
50
60
70
48
23
15
10
10
95
45
29
20
15
11
15
100+
68
43
30
22
17
13
20
100+
90
57
40
229
22
17
25
200+
100+
71
49
37
28
21
30
200+
100+
85
59
44
33
25
40
300+
100+
100+
79
58
44
34
50
400+
200+
100+
98
73
55
42
When streamflow records are not available, peak discharge can be estimated by the "rational"
method or formula and is recommended for use on channels draining less than 80 hectares (200
acres):
Q = 0.278 C i A
where: Q = peak discharge, (m3/s)
Type of Surface
Factor
C
0.05-0.10
0.10-0.15
0.15-0.20
0.13-0.22
0.18-0.22
0.25-0.35
Asphaltic pavements
0.80-0.95
Concrete pavements
0.70-0.95
Numerous assumptions are necessary for use of the rational formula: (1) the rate of runoff must
equal the rate of supply (rainfall excess) if train is greater than or equal to tc; (2) the maximum
discharge occurs when the entire area is contributing runoff simultaneously; (3) at equilibrium,
the duration of rainfall at intensity I is t = tc; (4) rainfall is uniformly distributed over the basin;
(5) recurrence interval of Q is the same as the frequency of occurrence of rainfall intensity I; (6)
the runoff coefficient is constant between storms and during a given storm and is determined
solely by basin surface conditions. The fact that climate and watershed response are variable and
dynamic explain much of the error associated with the use of this method.
Manning's formula is perhaps the most widely used empirical equation for estimating discharge
since it relies solely on channel characteristics that are easily measured. Manning's formula is:
Q = n-1 A R2/3 S1/2
where: Q = discharge (m3/s)
channel)
n = roughness coefficient
of the channel.)
Values for Manning's roughness coefficient are presented in Table 27.
Manning's n for natural stream channels (surface width at
flood stage less than 30 m) (Highway Task Force, 1971).
Table 27.
0.030 0.035
0.035 0.050
0.050 0.070
0.060 0.080
0.010 0.020
0.010 0.020
0.010 0.020
0.040 0.050
0.050 0.070
Area and wetted perimeter are determined in the field by observing high water marks on the
adjacent stream banks (Figure 61). Look in the stream bed for scour effect and soil discoloration.
Scour and soil erosion found outside the stream channel on the floodplains may be caused by the
10-year peak flood. Examining tree trunks and brush in the channel and floodplain may reveal
small floatable debris hung up in the vegetation. Log jams are also a good indication of flood
marks because their age can be estimated and old, high log jams will show the high watermark
on the logs. The difficulty in associating high water marks with flow events of a specified
recurrence interval makes values obtained by this method subject to gross inaccuracy. If the 10year flood can be determined, flow levels for events with a higher recurrence interval can be
determined roughly from Table 28.
Relationship of peak flow with different return periods.
(Nagy, et al, 1980).
Table 28.
(years)
Factor of flood
intensity
10
1.00
25
1.25
50
1.50
100
1.80
A key assumption in the use of Manning's equation is that uniform steady flow exists. It is
doubtful that high gradient forested streams ever exhibit this condition. (Campbell, et al., 1982)
When sufficient hydrologic data is lacking, however, Manning's equation, together with
observations of flow conditions in similar channels having flow and/or precipitation records,
provide the best estimate of stream discharge for purposes of designing stream crossings. An
example illustrating the use of Manning's equation to calculate peak discharge is as follows:
EXAMPLE: A trapezoidal
2. Inadequate outlet design. By constricting flow through a small area, water velocity (along
with its erosive power) will increase. Outlets need to be properly designed in order to
withstand high flow velocities and thus avoid excessive downstream erosion and eventual
road failure.
3. Poor location of crossing. Crossings need to be located along relatively stable stretches
where stream bottoms and banks exhibit little signs of excessive erosion or deposition.
Meandering and/or multiple channels often indicate unstable conditions. If there is no
choice but to use a poor location, careful consideration of the type of crossing selected,
along with bank and stream bottom stabilization and protection measures, should be
given.
There are three generally accepted methods used to cross channels on low volume roads-bridges, fords, and culverts. The selection is based on traffic volume and characteristics, site
conditions (hydrologic/hydraulic conditions of channel), and management needs such as
occasional closure, continuous use, safety considerations, resource impact (fish, wildlife,
sediment). Factors to consider when selecting a crossing type are listed as follows:
1. Bridges: high traffic volume, large and variable water volume, high debris-potential,
sensitive channel bottom and banks, significant fish resource, large elevation difference
between channel and road grade
2. Culvert: Medium to low water volume, medium to low debris potential, fish resource not
significant, elevation difference between channel and road grade less than 10 meters, high
traffic volume
3. Ford: low to intermittent water flow, high debris potential, no fish resource, road grade
can be brought down to channel bottom, low traffic volume
All three channel crossing types require a careful analysis of both vertical and horizontal
alignment. In particular, careful analysis of curve widening requirements is imperative in relation
to the specified critical vehicle. Channel crossings are fixed structures where the road way width
cannot be temporarily widened. Road width, curvature, approach, and exit tangents govern the
vehicle dimensions which can pass the crossing.
Except for bridge locations, roads should climb away from channel crossings in both directions
wherever practical so high water will not flow along the road surface. This is particularly true for
ford installations.
4.3.2 Fords
Fords are a convenient way to provide waterway crossing in areas subject to flash floods,
seasonal high storm runoff peaks, or frequent heavy passage of debris or avalanches. Debris will
simply wash over the road structure. After the incident, some clearing may be necessary to allow
for vehicle passage. Figure 62 shows a very simple ford construction where rock-filled gabions
are used to provide a road bed through the stream channel.
An alternative to the above described ford is a "hardened" fill with culvert (Figure 64). This
approach is an attractive alternative for crossing streams which are prone to torrents. The
prevailing low flow conditions are handled by a small culvert and the occasional flash flood or
debris avalanche will simply wash over the road surface. The fill surface has to be hardened
either by concrete or large rock able to withstand the tremendous kinetic energy associated with
floods and torrents. Vertical curve design through the stream has to include an adverse grade as
discussed for the typical ford.
Hardened fill stream crossings provide an attractive
alternative for streams prone to torrents or debris avalanches
(Amimoto, 1978).
Figure 64.
4.3.3. Culverts
Culverts are by far the most commonly used channel crossing structure used on forest roads.
Culvert types normally used, and the conditions under which they are used, areas follows:
Corrugated metal pipe (CMP) ........................................ All conditions except those noted below
CMP with paved invert .................................................. Water carries sediments erosive to metal
CM pipe-arch .............................................................. Low fills; limited head room
Multi-plate .................................................................. Large sizes (greater than 1.8 meters)
Reinforced concrete pipe (RCP) ....................................Corrosive soil or water, as salt water;
short haul from plant; unloading and placing equipment available
Reinforced concrete box .............................................. Extra large waterway; migratory fish way
Although more expensive than round culverts, pipe-arch or plate arch types are preferred over
ordinary round pipes. Pipe-arch culverts, beers having a more efficient opening per unit area than
round pipe for a given discharge, will collect bottom sediments over time when it is installed
slightly below the stream grade. They also require lower fills. However, during periods of low
flow, water in pipes with this shape may be spread so thin across the bottom that fish passage is
impossible. A plate-arch set in concrete footings is the most desirable type from a fish passage
standpoint since it has no bottom. The stream can remain virtually untouched if care is exercised
during its installation. (Yee and Roelofs, 1980)
Regardless of the type of culvert, they should all conform to proper design standards with
regards to alignment with the channel, capacity, debris control, and energy dissipation. They
should all perform the following functions:
1. The culvert with its appurtenant entrance and outlet structures should efficiently
discharge water, bedload, and floating debris at all stages of flow.
2. It should cause no direct or indirect property damage.
3. It should provide adequate transport of water, debris, and sediment without drastic
changes in flow patterns above or below the structure.
4. It should be designed so that future channel, and highway improvements can be made
without much difficulty.
5. It should be designed to function properly after fill has settled.
6. It should not cause objectionable stagnant pools in which mosquitoes could breed.
7. It should be designed to accommodate increased runoff occasioned by anticipated land
development.
8. It should be economical to build, hydraulically adequate to handle design discharge,
structurally durable, and easy to maintain.
9. It should be designed to avoid excessive ponding at the entrance which may cause
property damage, accumulation of sediment, culvert clogging, saturation of fills, or
detrimental upstream deposits of debris.
10. Entrance structures should be designed to screen out material which will not pass through
the culvert, reduce entrance losses to a minimum, make use of velocity of approach
insofar as practical, and by use of transitions and increased slopes, as necessary, facilitate
channel flow entering the culvert.
11. The outlet design should be effective in re-establishing tolerable non-erosive channel
flow within the right-of-way or within a reasonably short distance below the culvert, and
should resist undercutting and washout.
12. Energy dissipators should be simple, easy to build, economical and reasonably selfcleaning during periods of low flow.
13. Alignment should be such that water enters and exits the culvert directly. Any abrupt
change in direction at either end will retard flow and cause ponding, erosion, or a buildup
of debris at the culvert entrance. All of these conditions could lead to failure. (See Figure
65 for suggested culvert-channel alignment configurations and Figure 66 for suggested
culvert grades. In practice, culvert grade lines generally coincide with the average
streambed above and below the culvert.)
Possible culvert alignments to minimize channel
scouring. (USDA, Forest Service, 1971).
Figure 65.
Figure 66.
If there are existing roads in the watershed, examination of the performance of existing culverts
often serves as the best guide to determining the type, size, and accompanying inlet/outlet
improvements needed for the proposed stream crossing. For estimating streamflow on many
forest watersheds, existing culvert installations may be used as "control sections". Flow can be
calculated as the product of water velocity (V) and cross-sectional area (A):
Q =A* V
Cross-sectional area of water flowing in a round- culvert is difficult to measure, however a rough
estimate can be calculated from the following equation:
:
d = measured depth of flow
= angle () between radial lines to the bottom of the
culvert and to the water surface (Figure 62)
= cos-1 [(r-d) / r]
Definition sketch of variables used in flow
calculations.
Figure 67.
(see
Figur
e 67)
Values for coefficient of roughness (n) for culverts are given in Table 29.
Values for coefficient of roughness (n) for culverts.
(Highway Task Force,1971).
Table 29.
Culvert diameter
(ft)*
corrugate
1 to 8
d metal
concrete
Annular
corrugations
(in)*
2-2/3 x 1/2
0.024
3 to 8
3x1
0.027
all diameters
---
0.012
Once the design peak discharge has been determined by one of the methods discussed above, the
size of pipe required to handle the discharge can be determined from available equations, charts,
tables, nomographs, etc., such as the ones presented in Figures 70, 71, 72, 73 and 74. Figure 69
provides an example of a work sheet which can be used for diameter and flow capacity
calculations. If outlet control is indicated (for example, in a low gradient reach where "backwater
effects" may be created at the outlet end), the reader is referred to Handbook of Steel Drainage
and Highway Construction Products (1971) or Circular No. 5 published by the U. S. Department
of Commerce (1963). Outlet control conditions are shown in Figure 74 for a corrugated metal
pipe.
It is important to keep in mind that in addition to discharge from areas upstream of the
installation, the culvert must be able to handle accumulated water from roadside ditches recalling
that roadside ditches on roads lower on the slope intercept more subsurface water than those on
roads higher on the slope. Sudden surges from rapid snowmelt (if applicable) must also be
allowed for. Organic debris and bedload sediments can plug a culvert and can greatly reduce
culvert efficiency. For these reasons, an "oversized" culvert design may be indicated.
Inlet characteristics can greatly influence flow efficiency through the culvert. The end either (1)
projects beyond the fill, (2) is flush with a headwall, or (3) is supplemented with a manufactured
mitered steel end section. Inlets with headwalls are generally the most efficient followed by
culverts with mitered inlets and finally culverts with projecting entrances. When headwater
depths are 1 to 2 times greater than culvert diameter, culverts with headwalls have an increase in
flow capacity of approximately 11 and 15%, respectively, over culverts with projecting
entrances.
Procedure for Selection of Culvert Size
Note: Culvert design sheets, similar to Figure 69 should be used to record design data.
Step 1:
a. Refer to the inlet control nomograph for the culvert type selected.
b. Using an HW/D (Headwater depth/Diameter)) of approximately 1.5 and the scale for the
entrance type to be used, find a trial size culvert by following the instructions for use of the
nomographs. If a lesser or greater relative headwater depth should be needed, another value of
HW/D may be used.
c. If the trial size for the culvert is obviously too large because of limited height of embankment
or size availability, try different HW/D values or multiple culverts by dividing the discharge
equally for the number of culverts used. Raising the embankment height or using a pipe arch and
box culvert which allow for lower fill heights is more efficient hydraulically than using the
multiple culvert approach. Given equal end areas, a pipe arch will handle a larger flow than two
round culverts. Selection should be based on an economic analysis.
Step 3:
a. Determine and record. HW depth by use of the appropriate inlet control nomograph. Tailwater
(TW) conditions are to be neglected in this determination. HW in this case is found by simply
multiplying HW/D (obtained from the nomograph) by D.
Step 4:
a. If inlet control governs, outlet velocity can be assumed to equal normal velocity in openchannel flow as computed by Manning's equation for the barrel size, roughness, and slope of
culvert selected.
Note: In computing outlet velocities, charts and tables such as those provided by U.S.
Army Corp of Engineers, Bureau of Reclamation, and Department of Commerce are
helpful (see Literature Cited).
Step 5: Try a culvert of
procedure.
Record final selection of culvert with size, type, outlet velocity, required HW and
economic justification. A good historical record of culvert design, installation, and performance
observations can be a valuable tool in planning and designing future installations.
Step 6:
a. Connect with a straight edge the given culvert diameter or height (D) and the discharge Q, or
Q/B for box culverts; mark intersection of straightedge on HW/D scale mark (1).
b. If HW/D scale mark (1) represents entrance type used, read HW/D on scale (1). If some other
entrance type is used, extend the point of intersection found in (a) horizontally to scale (2) or (3)
and read HW/D.
c. Compute HW by multiplying HW/D by D.
2. To determine culvert size:
a. Given an HW/D value, locate HW/D on scale for appropriate entrance type. If scale (2) or (3)
is used, extend HW/D point horizontally to scale (1).
b. Connect point on HW/D scale (1) as found in (a) above to given discharge and read diameter
of culvert required.
3. To determine discharge (Q):
a. Given HW and D, locate HW/D on scale for appropriate entrance type. Continue as in 2a.
b. Connect point on HW/D scale (1) as found in (a) above, the size of culvert on the left scale,
and read Q or Q/B on the discharge scale.
c. If Q/B is read in (b) multiply by B to find Q.
Good installation practices are essential for proper functioning of culverts, regardless of the
material used in the construction of the culvert (Figure 75). Flexible pipe such as aluminum,
steel, or polyethylene, requires good side support and compaction, particularly in the larger sizes.
It is recommended that the road be constructed to grade or at least a meter above the top of the
pipe, the fill left to settle and then excavated to form the required trench.
The foundation dictates if bedding is needed or not. Proper foundation maintains the conduit on a
uniform grade. Most times, the culvert can be laid without bedding, however; a few centimeters
of bedding helps in installation of the culvert. When bedding is required, the depth should be 8
cm if the foundation material is soil and 30 cm if it is rock.
Backfilling is the most important aspect of culvert installation. Ten percent of the loading is
taken by the pipe and 90 percent is taken by the material surrounding the pipe if backfilling is
done correctly. Backfill material should consist of earth, sand, gravel, rock or combinations
thereof, free of humus, organic matter, vegetative matter, frozen material, clods, sticks and debris
and containing no stones greater than 8 cm (3 in) in diameter. It should be placed in layers of no
greater than 15 cm (6 in) and compacted up to 95% of Proctor density at or near the optimum
moisture content for the material.
Figure 69.
read from chart 46, 47 ''Design Charts for Open Channel Flow". (see p. 5-14). Velocities as
read from charts are about the same for each size, indicating change
in size has little effect. Size selected would be based on accuracy of
flood estimate. If 180 c.f.s. is conservative, select 54". Note that TW
must be greater than 10.1' for outlet control to govern for 54" pipe
flowing 180 c.f.s. This points out that accuracy in estimating TW
depths is unnecessary in some cases.
Nomograph for concrete pipes inlet control (U.S. Dept. of
Commerce, 1963).
Figure 70.
2. Various types of mechanical structures (Figures 76, 77 and 78) can be placed above the
inlet to catch any debris that may become entrained.
3. A bridge may be substituted in place of a culvert.
Figure 76.
Under high fills, inlets can be provided with upstream protection by rock riprap up to the high
water mark (Figure 78). Cambering may also be necessary to ensure the proper grade after fill
settlement.
4.3.5. Bridges
Bridges often represent the preferred channel crossing alternative in areas where aquatic
resources are extremely sensitive to disturbance. However, poor location of footings,
foundations, or abutments can cause channel scour and contribute to debris blockage.
Bridges have been designed using a variety of structural materials for substructure and
superstructure. Selection of a bridge type for a specific site should take into consideration the
functional requirements of the site, economics of construction at that site, live load requirements,
foundation conditions, maintenance evaluations, and expertise of project engineer.
Some arbitrary rules for judging the minimum desirable horizontal and vertical stream clearances
in streams not subject to navigation may be established for a specific area based on judgment and
experience. In general, vertical clearances should be greater than or equal to 1.5 meters (5 feet)
above the 50-year flood level plus 0.02 times the horizontal distance between piers. Horizontal
clearance between piers or supports in forested lands or crossings below forested lands should
not be less than 85 percent of the anticipated tree height in the forested lands or the lateral width
of the 50-year flood. (US Environmental Protection Agency, 1975)
Of course, longer bridge spans will require careful economic evaluations since higher
superstructure costs are often involved. Subaqueous foundations are expensive and involve a
high degree of skill in the construction of protective cofferdams, seal placement and cofferdam
dewatering. In addition to threats to water quality that can occur from a lost cofferdam, time and
money losses will be significant. Subaqueous foundations often limit the season of construction
relative to water level and relative to fish spawning activity. Thus, construction timing must be
rigidly controlled.
It is suggested that the maximum use be made of precast or prefabricated superstructure units
since the remoteness of many mountain roads economically precludes bridge construction with
unassembled materials that must be transported over great distances. However, the use of such
materials may be limited by the capability to transport the units over narrow, high curvature
roads to the site, or by the horizontal geometry of the bridge itself.
Another alternative is the use of locally available timber for log stringer bridges. An excellent
reference for the design and construction of single lane log bridges is Log Bridge Construction
Handbook, by M. M. Nagy, et al., and is published by the Forest Engineering Research Institute
of Canada. The reader is referred to this publication for more detailed discussions of these topics.
Transverse
grade
Sediment
Delivery
tonnes/ha/year
conventional
970
0-2%
5%
400
9%
300
12 %
260
Temporary roads or roads with very light traffic can be outsloped where side slopes do not
exceed 40 percent. For safety reasons, when side slopes exceed 40 percent, traffic restrictions
should be in force during inclement weather. When outsloping is used for surface drainage, cross
drains or dips should be installed on the road surface (Figure 75). Spacing will depend on soil
type, road surface and road grade.
is used where a more reliable drainage system is required such as on permanent
roads, roads with high anticipated traffic volumes and/or loads, or in areas with sensitive soils or
severe climatic conditions. Insloping is achieved by grading the road surface towards the uphill
side of the road at a 3 to 5 percent grade. Water draining from insloped road surfaces is collected
and carried along the inside of the road either on the road surface itself or more commonly in a
ditch line. The ditch line can be omitted from the road template, thereby reducing the overall
road width. This may be desirable in steep terrain in order to reduce excavation (see also Section
3.2). However, this option must be weighed against potential drainage problems along the uphill
side of the road. Dips, cross drains, or culverts must be installed and maintained to remove water
from the road prism.
Insloping
provide the fastest water removal since the distance water has to travel is cut
in half. The crowned surface slopes at 3 to 10 percent from either side of the road centerline.
Crowned surfaces and any associated cross drains or dips are difficult to maintain. Water has to
be controlled on both sides of the road through a ditch line and stable areas have to be provided
for runoff water. Ballast thickness is typically the largest in the center in order to achieve the
correct crown shape.
Crowned surfaces
There are three types of cross drains used for intercepting road surface water: intercept-ing or
rolling dips, open top culverts, and cross ditches. Cross drains serve a dual purpose. First they
must intercept longitudinal road surface flow, and second they must carry ditch water across the
road prism at a frequency interval small enough to prevent concentration of flow. Ditch relief is
discussed in more detail in section 4.4.3 and 4.4.4.
(Figures 80 and 81) when properly constructed, are cheaper to maintain
and more permanent than open-top culverts. However, their usefulness is limited to road grades
less than 10 percent. At steeper grades, they become difficult to construct and maintain.
Intercepting dips
Dip locations are determined at the time the grade line is established on the ground or during
vertical alignment design. The total length of the two vertical curves comprising the dip should
be sufficient to allow the design vehicle to pass safely over them at the design speed. The
minimum vertical distance between the crest and sag of the curves should be at least 30 cm (1 ft).
It is important that the dip be constructed at a 30 degree or greater angle downgrade and that the
dips have an adverse slope on the downroad side. The downroad side of the dip should slope
gently downward from the toe of the road cut to the shoulder of the fill. The discharge point of
the dip should be armored with rock or equipped with a down-drain to prevent erosion of the fill.
Equipment operators performing routine maintenance should be aware of the presence and
function of the dips so that they are not inadvertently destroyed.
are most effective on steeper road grades. Open top culverts (Figure 82)
can be made of durable treated lumber or poles or they may be prefabricated from corrugated,
galvanized steel. The trough should be 7 to 10 cm (3 to 4 in) wide and from 10 to 20 cm (4 to 8
in) deep. The gradient required in order for open top culverts to be self cleaning is 4 percent or
greater and, as with dips, they should be angled 30 degrees downslope. In order to maintain their
functionality they should be inspected and cleaned on a frequent and regular basis.
Open top culverts
or water bars, are typically used on temporary roads. They are the easiest and
most inexpensive method for cross drain installation (Figure 83). However, they impede traffic,
wear out quickly, and are difficult to maintain and are, therefore, not recommended except on
very low standard roads. In order to be effective, the cross ditch should be excavated into the
mineral soil or subgrade and not just into the dirt or surface layer. Water bars should be installed
at a 30 degree angle to the centerline of the road, and ditch and berm should be carefully
extended to the cut bank in order to avoid ditch water bypass. A berm should be placed in the cut
bank ditch to divert water into the cross ditch. Care should be taken that the berm and ditch is not
beaten or trampled down by traffic or livestock.
Cross ditches
Spacing requirements for surface cross drains depend on road grade, surfacing material, rain
intensities, and slope and aspect. Spacing guides for surface cross drains are given in Table 31.
Cross drain spacing required to prevent rill or gully
erosion deeper than 2.5 cm on unsurfaced logging roads built in
the upper topographic position [1] of north-facing slopes [2]
having gradient of 80 % [3] (Packer, 1967).
Table 31.
Road Material
Grad
e
(%) Hard
51
47
42
41
32
29
46
42
38
37
27
24
44
40
35
34
25
22
42
38
33
32
23
20
10
39
35
29
29
20
17
12
36
32
27
27
17
15
14
33
29
24
23
14
11
spacing guide provides for considerably wider spacings. This is a good illustration of a case
where local conditions take precedent over general guidelines developed for large geographical
areas.)
Spacing standard for open-top culverts on forest road
surfaces, Japanese Islands. (Minematsu and Minamikata, 1983).
Figure 84.
Equal attention must be given to location of cross drains in relation to road and topographic
features. Natural features such as slope breaks or ideal discharge locations which disperse water
should be identified and incorporated into the drainage plan as needed. Possible locations for
cross drains are shown in Figure 85.
Guide for locating cross drains. Several locations
require cross drains independent of spacing guides. A and J,
divert water from ridge; A, B, and C, cross drain above and below
junction; C and D, locate drains below log landing areas; D and
H, drains located with regular spacing;. E, drain above incurve
to prevent bank cutting and keep road surface water from entering
draw; F, ford or culvert in draw; G, drain below inside curve to
prevent water from running down road; I, drain below seeps and
springs. (Megahan, 1977).
Figure 85.
lower erosion potential than will a narrow, deep cross section. Maximum permissible velocities
for unlined ditches of a given soil type are listed in Table 32.
Maximum permissible velocities in erodible channels,
based on uniform flow in straight, continuously wet, aged
channels. For sinuous channels, multiply allowable velocity by
0.95 for slightly sinuous, 0.9 for moderately sinuous, and 0.8
for highly sinuous channels. (U. S. Environmental Protection Agency, 1975).
Table 32.
Maximum permissible
velocities (m/s)
Clear
water
Water
Water
carrying
carrying
sand and
fine silt
gravel
Fine sand
(noncolloidal)
0.46
0.76
0.46
Sandy loam
(noncolloidal)
0.52
0.76
0.61
Silt loam
(noncolloidal)
0.61
0.91
0.61
0.76
1.07
0.67
Volcanic ash
0.76
1.07
0.61
Fine gravel
1.76
1.52
1.13
1.13
1.52
0.91
Graded, loam to
cobbles
(noncolloidal)
1.13
1.52
1.52
Graded, silt to
cobbles (colloidal)
1.22
1.68
1.52
Alluvial silts
(noncolloidal)
0.61
1.07
0.61
Alluvial silts
(colloidal)
1.13
1.52
0.91
Coarse gravel
(noncolloidal)
1.22
1.83
1.98
1.68
1.98
1.83
1.52
Table 33.
Ditch lining
Mannig's
n
V
max
1. Natural earth
a. Without vegetation
ft / meters /
sec sec
1)
Rock
0.035 0.040
20
0.040 0.045
15 - 18 4.5 - 5.4
2)
6.0
Soils
Coarse
grained
Unified USDA
GW
Gravel
0.022 0.024
6-7
1.8 - 2.1
GP
Gravel
0.023 0.026
7-8
2.1 - 2.4
0.023 0.025
3-5
0.9 - 1.5
0.022 0.020
2-4
0.6 - 1.2
Gravelly
Loam
Gravelly
Clay
0.024 0.026
5-7
1.5 - 2.1
Sand
0.020 -
1-2
0.3 - 0.6
Gravel and
gravelly soils
GM
GC
Loamy
Gravel
0.024
SP
0.022 0.024
1-2
0.3 - 0.6
0.020 0.023
2-3
0.6 - 0.9
0.021 0.023
2-3
0.4 - 0.9
Sand
soils
Loamy
Sand
Fine
grained
Silts and
clays
50
LL
SC
Sandy
Loam
0.023 0.025
3-4
0.9 - 1.2
CL
Clay Loam
Sandy Clay
Loam
Silty Clay
0.022 0.024
2-3
0.6 - 0.9
ML
Silt Loam
Very Fine
Sand Silt
0.023 0.024
3-4
0.9 - 1.2
OL
Mucky
Loam
0.022 0.024
2-3
0.6 - 0.9
CH
Clay
0.022 0.023
2-3
0.6 - 0.9
MH
Silty Clay
3-5
0.9 - 1.5
50
LL
0.023 0.024
OH
Mucky
Clay
0.022 0.024
2-3
0.6 - 0.9
PT
Peat
0.022 0.025
2-3
0.6 - 0.9
0.050 0.070
4-5
1.2 - 1.5
0.030 0.050
3-4
0.9 - 1.2
0.070 0.090
6-8
1.8 - 2.4
0.040 0.050
5-6
1.5 - 1.8
0.050 0.080
4-5
1.2 - 1.5
0.040 -
5-7
1.5 - 2.1
Highly Organic
2. With vegetation
a. Average turf
b. Dense turf
1) No sprouts
0.050
2) With sprouts
0.060 0.080
6-8
1.8 - 2.4
e. Dense woods
0.080 0.120
5-6
1.5 - 1.8
f. Dense brush
0.100 0.140
4-5
1.3 - 1.5
g. Dense willows
0.150 0.200
8-9
2.4 - 2.7
3. Paved
(Construction)
Good Poor
1) Trowel finish
0.012 0.014
20
6.0
2) Float finish
0.013 0.015
20
6.0
3) Formed, no finish
0.014 0.016
20
6.0
0.015 -
18 - 20 5.4 - 6.0
0.017
0.017 0.020
17 - 19 5.1 - 5.7
0.020 0.025
15
4.5
0.025 0.030
15
4.5
1) Formed concrete
0.017 0.020
10
3.0
0.020 0.023
8 - 10 2.4 - 3.0
0.023 0.033
8 - 10 2.4 - 3.0
d. Brick
0.014 0.017
10
3) Asphalt
0.013 0.016
18 - 20 5.4 - 6.0
Maximum
recommended velocities
3.0
The procedure for calculating flow rates is the same as that discussed in Section 4.2. The
corresponding roughness factors (Manning's n) for open channels are given in Table 33. Ditches
in highly erodible soils may require riprap, rock rubble lining, jute matting, or grass seeding.
Riprap or rubble-lined ditches will tend to retard flow enough to allow water movement while
retaining the sediment load at low flow periods. Lining ditches can reduce erosion by as much as
50 percent and may provide economical benefits by reducing the required number of lateral cross
drains when materials can be obtained at low cost.
Ditch water should not be allowed to concentrate, nor should it be allowed to discharge directly
into live streams. A cross drain such as a culvert should carry the ditch water across and onto a
protected surface (Figure 81). Spacing of ditch relief culverts is discussed in Section 4.4.4 and
4.5.
The ditch grade will normally follow the roadway grade. However, the minimum grade for an
unpaved ditch should be 1 percent. Runoff intensity or discharge values needed to calculate ditch
size can be determined by calculations described below for culvert design. However, allowances
should be made for sedimentation, plus at least 0.3 m between the bottom of the roadway
subgrade and the full flow water surface. The suggested minimum size of roadside ditches is
shown in Figure 87.
Figure 87.
Velocity of the ditch water is a function of cross section, roughness and grade. For a typical
triangular cross section the velocity can be calculated from Manning's equation:
V = n-1 * R2/3 * S1/2
where V equals velocity in meters/second and the other values are as defined in Chapter 4.2. For
a triangular channel with sideslopes of 1:1 and 2:1, flowing 0.3 meters deep, the hydraulic
radius, R, equals 0.12 m. Table 34 lists ditch velocities as a function of roughness coefficients
and grade, and Figure 88 provides a nomograph for the solution of Manning's equation.
In most cases ditch lines should be protected to withstand the erosion. For channels with grades
steeper that 10 percent, a combination of cross section widening, surface protection and
increased surface roughness may be required.
n
Slope
(%)
0.02
0.03
0.04
meters/sec
1.7
1.2
0.9
2.5
1.6
1.2
3.0
2.0
1.5
3.5
2.3
1.7
10
3.9
2.6
1.9
12
4.3
2.9
2.1
15
4.8
3.2
2.4
18
5.3
3.5
2.6
Figure 88.
EXAMPLE:
Determine whether the water velocity for a road ditch will be below critical levels for erosion. If
velocities are too high, make and evaluate changes (see also U.S. Forest Service, 1980). Ditch
dimension is a symmetrical, triangular channel, 0.39 m deep with 2.5:1 slopes with sandy banks
(SW) and a slope of 0.003 m/m.
Solution:
1. The hydraulic radius, R, is equal to area divided by wetted perimeter.
R = 0.38 m / 2.1 m = 0.18 m
maximum
velocity
0.87 m/sec
The ditch has too great a velocity given the conditions stated above. Therefore, measures must be
taken that will reduce the water velocity. Water velocity in ditches can be reduced by protecting
the channel with vegetation, rock, or by changing the channel shape. (With vegetative protection,
the friction factor (n) becomes 0.030 - 0.050 and the maximum recommended velocity becomes
0.9 - 1.2 m/sec.)
6. Obtain velocity for specified ditch with vegetative protection by referring to Figure 88 (1.9
feet per second).
7. Compare the calculated ditch velocity with the maximum recommended velocity for
vegetation protected channels (average turf) with easily eroded soils:
Specified
ditch
maximum
velocity
0.57 m/sec
8. If the specified ditch has a lower velocity than the recommended maximum velocities, it
should be stable as long as the vegetation remains intact.
Berms can be constructed of native material containing sufficient fines to make the berm
impervious and to allow it to be shaped and compacted to about 90 percent maximum density.
Berm dimensions are illustrated in Figure 89.
Figure 89.
As with dips, open top culverts, and water bars, ditch relief and lateral drain culverts should
cross the roadway at an angle greater than or equal to 30 downgrade. This helps insure that
water is diverted from the roadside ditch and that sediment will not accumulate at the inlet.
Accelerated ditch erosion may (1) erode the road prism making it unstable and unusable, and (2)
cause culverts to plug or fail, thereby degrading water quality.
Selection of proper location is as important as spacing. Spacing recommendations should be used
as a guide in determining the frequency of cross drain spacing. Final location is dictated by
topographic and hydrologic considerations. Considerations discussed for for cross drain locations
are also valid for culverts (see Figure 85). Considerations given for stream culvert installation,
inlet and outlet protection, should also be used for ditch relief culverts.
Culvert outlets with no outlet protection are very often the cause of later road failures. Normally,
culvert outlets should extend approximately 30 - 50 cm beyond the toe of the fill. Minimal
protection is required below the outlet for shallow fills. However, on larger fill slopes where the
outlet may be a considerable distance above the toe of the fill, a downspout anchored to the fill
slope should be used (Figure 90). Culvert outlets should be placed such that at least 50 meters is
maintained between it and any live stream. If this is not possible, the rock lining of the outlet
should be extended to 6 meters to increase its sediment trapping capacity (Figure 91). Coarse
slash should be placed near the outlet to act as a sediment barrier.
Where fills consist entirely of heavy rock fragments, it is safe to allow culverts to discharge on to
the slop. The size and weight of fragments must be sufficient to withstand the expected velocity
of the design discharge. Rock aprons (Figure 92) are the least costly and easiest to install. A
guide for selecting rock for use as riprap is illustrated in Figure 93.
Ditch relief culvert installation showing the use of
headwall, downspout and a splash barrier/energy dissipator at the
outlet. Minimum culvert grade is 3 to 5 percent. Exit velocities
should be checked. (U. S. Environmental Protection Agency, 1975).
Figure 90.
Figure 92.
The determination of culvert spacing for lateral drainage across the roadway is based on soil
type, road grade, and rainfall characteristics. These variables have been incorporated into a
maximum spacing guide for lateral drainage culverts developed by the Forest Soils Committee of
the Douglas-fir Region in 1957. The spacing estimates are designed for sections of road 20 feet
wide and include average cut bank and ditch one foot deep. Table 2 (Chapter 1.4.1) groups soils
by standard soil textural classes into ten erosion classes having erodibility indices from 10 to
100, respectively. (Class I contains the most erodible soils and Class X the least erodible soils.)
In order to arrive at an erosion class for a particular soil mixture, multiply the estimated content
of the various components by their respective erosion index and add the results.
Example:
Name of
Erosion
Index
component
Content
rock
20
100
20
Fine Gravel
50
90
45
Silt Loam
30
70
21
86
86 = Erosion
Class VIII
The spacing of lateral-drainage culverts can then be obtained from Table 34. The summary
equation used to calculate values in Table 34, expressed in metric units, is:
Y = (1,376 e0.0156X )(G R)-1
where:
X = erosion index
Values in Table 34 are based on rainfall intensities of 2.5 to 5 cm per hour (1 to 2 in/hr) falling in
a fifteen minute period with an expected recurrence interval of 25 years. For areas having greater
rainfall intensities for the 25 year storm, divide the values in the table by the following factors:
Rainfall intensity
Factor
5 to 7.5 cm/hr (2 to 3
in/hr)
1.50
7.5 to 10 cm/hr (3 to 4
1.75
in/hr)
10 to 12.5 cm/hr (4 to 5
2.00
in/hr)
Roads having grades less than 2 percent have a need for water removal to prevent water from
soaking the subgrade or from overrunning the road surface. Thus, spacing for roads with 0.5
percent grades is closer than for roads with 2 percent grades. Usually, local experience will
determine the spacing needed for road grades at these levels.
Guide for maximum spacing (in feet) of lateral drainage
culverts by soil erosion classes and road grade (2% to 18%).
(Forest Soils Comm., Douglas Fir Reg., PNW, 1957).
Table 35.
Erosion clases
Road
grade
(percent)
[1] I
II
[2] 10 20
meters
III
IV
VI
VII
VIII
IX
30
40
50
60
70
80
90
100
270
368
180
245
321
361
135
183
240
271
305
108
147
204
218
243
260
300
90
123
161
182
203
216
251
303
77
105
137
155
174
186
215
260
309
363
68
92
120
135
152
162
188
227
270
317
60
81
107
120
135
144
167
201
240
282
10
54
74
96
108
122
131
150
182
216
254
11
50
66
87
99
111
118
137
165
197
231
12
45
62
80
92
102
108
125
152
180
212
13
42
57
74
84
93
101
116
140
167
195
14
39
53
69
78
87
93
107
129
155
182
15
36
50
65
72
81
90
101
122
144
170
16
35
47
60
68
77
84
93
114
135
159
17
32
44
57
65
72
80
89
107
127
150
18
30
41
54
60
68
75
84
107
120
148
(2) Drilled drains. This system consists of perforated metal pipes placed in holes drilled into
cut or fill slopes after construction.
(3) French drains. This system consists of trenches backfilled with porous material, such as
very coarse sand or gravel. This type of drain is apt to become clogged with fines and is not
recommended.
A major difficulty in selecting a drainage system is the lack of adequate performance data for
various drainage methods. A good knowledge of seasonal groundwater fluctuations, variation in
lateral and vertical permeability, and the ratio of vertical to lateral permeability are critical. Long
term monitoring of drainage performance is important in determining appropriate prescriptions
for future installations. For example, perforated drains are commonly prescribed but often will
not function properly as a result of clogging of pores with fines or from geochemical reactions
leading to the formation of precipitates. Several methods may be used to prevent plugging
depending on soil characteristics and material availability. The first is to enclose the perforated
pipe with geotextile fabric. Second, surround the pipe with an open graded aggregate material,
which in turn is surrounded by a fabric. The use of fabric eliminates the need for an inverted
filter consisting of various sized gravel and sand layers. Third, if fabric is not available, surround
the pipe with a graded aggregate filter. Although the cost of installing such a drainage system is
high, it may effectively reduce final road costs by decreasing the depth of base rock needed,
thereby reducing subgrade widths and associated costs for clearing, excavating, and
maintenance.
LITERATURE CITED
Amimoto, P. Y. 1978. Erosion and sediment control handbook. California Division of Mines and
Geology, Department of Conservation. 197 p.
Beschta, R. L. 1981. Streamflow estimates in culverts. Oregon State University, Forest Researph
Laboratory, Res. Note. 67. 4 p.
Darrach, A. G., W. J. Sauerwein, and C. E. Halley. 1981. Building water pollution control into
small private forest and ranchland roads. U. S. Department of Agriculture, Forest Service and
Soil Conservation Service.
Forest Soils Committee of the Douglas Fir Region. 1957. An introduction to the forest soils of
the Douglasfir Region of the Pacific Northwest. University of Washington.
Highway Task Force. 1971. Handbook of steel drainage and highway construction products (2nd
Ed). American Iron and Steel Institute, 150 E 2nd Street; New York. 368 p.
Megahan, W.F. 1977. Reducing erosional impacts of roads. In: Guidelines for Watershed
Management. Food and Agriculture Organization, United Nations, Rome. p 237-261.
Minematsu, H. and Y. Minamikata, 1983. Optimum spacing for open - top culverts on forest
roads. University of Agriculture and Technique, Tokyo. Jour. of J.F.S. 65(12):465-470.
Packer, P. 1967. Criteria for designing and locating logging roads to control sediments. Vol.1,
No. 13.
Pearce, J. K. 1960. Forest engineering handbook. U. S. Department of Interior, Bureau of Land
Management. 220 p.
Reid, L.M. 1981. Sediment production from gravel-surfaced forest roads, Clearwater basin,
Washington. Publ. FRI-UW--8108, Univ. of Washington, Seattle. 247 p.
Searcy, J. K. 1967. Use of riprap for bank protection. Federal Highway Administration,
Washington D. C. 43 p.
USDA, Forest Service. 1971. Transportation engineering handbook. Handbook No. 7709.11.
________________. 1979. Technical guide, erosion prevention and control on timber sales areas.
Intermountain Region.
Yee, C. S. and T. D. Roelofs. 1980. Planning forest roads to protect salmonid habitat. U. S.
Department of Agriculture, Forest Service. General Technical Report PNW-109. 26 p.
U.S. Dept. of Commerce, Bureau of Public Roads. 1963. Hydraulic Charts for the Selection of
Highway Culverts, Hydraulic Engineering Circular No. 5.
U.S. Dept. of the Interior, Bureau of Reclamation. 1974. Earth Manual, a water resources
technical publication. Second edition. Government Printing Office, Washington D.C.