‘No.4001_Central Kalimantan 2x60 MW Coal-fred Power Plant Turbine Unit Startup Commissioning Plan
= a
CONTENTS
oa) BA... mnsssnnnne 2
COMPILATION PURPOSE.
tl He a
COMPILATION REFERENCE.
VED LB emerrre
COMMISSIONING INSTRUMENTS AND TOOLS
BEBE BBR IB conn
SYSTEM AND MAIN TECHNICAL SPECIFICATIONS.
BM ME A Wy BS OI eo
CONDITIONS BEFORE UNIT STARTUP AND COMMISSIONING.
AM KA BE Rw
UNIT INITIAL STARTUP PROCEDURES AND TEST ITEMS.
LIE BA Bh Ob WR BR
UNIT STARTUP PROCEDURES AND SHUTDOWN ein.
RSME H
SAFETY PRECAUTIONS.
WR 1 MMM oT AR.
APPENDIX 1 TURBINE UNIT INSPECTION LISTS BEFORE
COMMISSIONIN:
CORANNDR TOM MRR HONK OO
10 AER 2 PML HL ME Se ws oh A TT ee.
10 APPENDIX 2 VALVE INSPECTION FORM BEFORE TURBINE UNIT
STARTUP.
4 wR SHH RE i HK...
11 APPENDIX 3 STEAM TURBINE PROTECTION CHECKLIST.
12 WR 4 AMM KT RE
12 APPENDIX 4 RECORD LIST OF STEAM TURBINE FIRST OPERATIO
13 RS APLAR. 50% A. WM HIRT Se
13 APPENDIX 5 PARAMETER LIST OF TURBINE NO-LOAD, 50% LOAD an,
FULL LOAD...
w/t24
af
22
22
23
23
44
44
i 4001 FRR +} dm 2x GOMW 98H oh POUL
No.4001____Central Kalimantan 2x60 MW Coalfred Power Plant Turbine Unit Startup Commissioning Plan
Sati Bi
Compilation Purpose
SCAR LALA OO eS Sh RLM ee OP APART. Bat)
i, +E SHR Sem. ARRADARL WA MEE, wa
HARRIES MAAR, MRI. Aik), 2A. WOPIRET, FERAR
PLO. HANES, Sil.
Turbo-generator integral startup and commissioning is of a crucial stage in the unit basic
construction, and is also a challenge and thorough inspection to the unit design,
equipment manufacture, civil engineering and installation. This plan is prepared to
realize scientific startup and commissioning, standard management, and to clarify
commissioning tasks and each party's responsibility, making the commissioning work
carried out orderly, safely and successfully, ensuring unit commissioning property and
improving unit handover level.
Sa
Compilation Reference
‘Bit bee
Related Material from design institution
TBA
Instruction from manufacturer
SHER
Contract requirement
WRALEA
Commissioning Instruments and Tools
Wik
Velocimeter
AE
Potable vibration indicator
AChR
Infrared thermometer
EEL
Interphone
RGREBRRA
System and Main Technical Specifications.
RRMERRRER
Steam Turbine Major Technical Parameters
RELA RAAB MD 60MW
27a4 4001
ER JB sb om 2 GOMW #8 HE He BT.
FOULS
No.4001 Central Kalimantan 2x60 MW Coabfred Power Plant _ Turbine Unit Startup Commissioning Plan
Rated output (generator _outooming
terminal)
MAK BR. BH. MG. RA
Turbine mode High pressure, single shaff, single casing
and condensing type
WHAX Ea
‘Governing mode Nozzle governing
TMCR LR 60 MW
TMCR power comW
WO Lae 7OMW
‘WO power ToMW
Re eH 3000r/min.
Rated speed ‘B000rimin
LHe ‘S0HZ
Grid frequency ‘B0HZ
eG 243.5th CTIMCR Li)
Inlet steam flow 243.5th (TMCR working condition)
EAE 258th (VWO “ED
Inlet steam flow 258th (VWO working condition)
ERNWRABA 8.83 MPa(a)
‘Steam pressure before the main stop valve | 8.63 MPa(a)
SCT A 535 °C
"Temperature before the main stop valve | 635°C
ERRREA 0.0093MPa(a) (tii (2% 2k HA 33°C)
Normal steam exhaust pressure 0.0083MPa(a) corresponding circulating
water temperature being33°C) ;
RRARARAR RE $19.7 kPa(a)
Steam turbine allowable Max. | $19.7 KPala)
backpressure
i FF | — Bre 1654r/min
#8 | First crtical speed T654rimin
oie | =e 4700rImin
‘Second critical speed “4700rImin
RRR CH) 20 &
ayn42
42
@F 4001
RBs dm 2x GOMW 28H os
ULES
No-4001_Central Kalimantan 260 MW Coalfired Power Plant __ Turbine Unit Startup Commissioning Plan
Turbine rotor (stage) 20stages
2 F We 1 9 2 dE (FATT) 120°C
Rotor fracture transmission temperature
an $120°C
RASKEE 215°C
Final feedwater temperature 215
We 77 A SFB BE FL BE BLS Fa UT SF
Rotary direction ‘Clockwise when seen from the generator
side
ORE Rt KE 32°C
Cooling water temperature a2
HFAE DEN ORAS KE 39°C
Highest cooling water temperature when | 9:c
maintaining rated power
EAR 6 GREE 4. 8. 10, 14, 16. 18m)
Regenerative extraction
6 (individually after 4. 8. 10. 14, 16, 16
stage)
ae 2GI+1CY+3DI
Heater quantity 2GFICYHSDI
BKARER GN) 35t ORF FEE AB)
iets) 28 CRETE AAD
Maximum “hoisting weight (during | 35t (half condenser casing)
installation)
a eS weight (during | gt (upper cylinder exclude the diaphragm
plate)
BAER T Kx Bexi(m)
8.69%7.093.41 atiz=me)
Unit size: lengthxwidthxheight(m)
8.69%7.09%3.41 (operation floor to the top)
DEH Asie RE ER
DEH System Technical Parameters
4/
a43
43
3 4001 6 Je 2x COMW SHE POULT
No.4001___ Central Kalimantan 2x60 MW Coal-fired Power Plant __ Turbine Unit Startup Commissioning Plan
HERE E (20~3600)rimin WE ‘#tr/min
‘Speed control range | (20~3600)r/min Precision | #1r/min
hai BE HE (O~ 115) % BLE Ht mE 40.5%
Load controtrange |'(0~115)%of rated load - | Precision ~ | 40.5%
HER GR 45% (3~6)% iW
‘Speed diversity factor | 4.5% (3~6)% adjustable
KREBRE DF 0.06%
‘System delay rate | Less than 0.06%
KRAMABELRA AM, SAO BCA DF 8% BERR.
‘When turbine rejects load under rated working condition, the max. Speed rising should
less than 9% of the rated speed.
ROMEBRRS MH
Generator Major Technical Parameters
8 MRA + BL RUF RB” SOWX18Z-O54LLT BRAGA RAL. RMR
FMLA ETO. RABASIAAGR. ANSHR PR:
The 50WX18Z-054LLT type non-salient pole synchronous generator
produced by Shandong Jinan Power Equipment Factory Co. Ltd is
employed. Type of excitation for the generator is stationary controllable
silicone excitation. The cooling mode is closed air-cooling. The specific
parameters are listed as below:
a) OS SOWX18Z-054LLT
Mode BOWX16Z-054LLT
BEDE 77.647MVA
‘Apparent power 77.647MVA
AE 60000 KW
Active power 60000 kW
weak 70500
Rated voltage T0500V
wea 4269.5A
Rated current 4269.5A
Hea 0.85 (His)
Power factor 0.85(delay)
sn#4001 FTE eb mn 2 GOMW HEHE oe BA TE FULL INS
No.4001 Central Kalimantan 2x60 MW Coal-fred Power Plant __Turbine Unit Startup Commissioning Plan
5.4
54
5.14
5.44
5.1.2
5.12
5.1.3
5.1.3
5.14
5.1.4
5.15
5.1.5
5.1.6
5.1.6
B17
SA7
5.1.8
5.18
Bee ‘3000 r/min
Rated speed ‘3000 rimin
Beas ‘50 Hz
Rated power ; 0 Hz
PARE ARIE LA RE
Conditions before Unit Startup and Commissioning
PUB DAA EMRE
Conditions Must Be Met at the Commissioning Site.
STK, HBG, ERM, AAMC, RTM ins
ADA GHRZKMZTKSH), ERKMABEAB Hie.
Commissioning site should be flat, passages for fire fighting, transportation and person
ate smooth. Each workshop floor should be complete, clear signs and boundaries
should be attached at the commissioning site and fences and warning signs are set at
dangerous areas.
RKERHMLBFRLLAR, VAT, RETA RRS IE.
Construction scaffolds in the commissioning area should be removed completely, and
the site is cleared up to ensure the safe operation of the operators.
BUBKWT. Fa, Pil, A, PREM, ERROR.
Ladders, platform, passway, handrail and backplate have been installed according to
design and are in operation.
OA, RCRA, WE, MURLRRAS.
Plant inner and outer water discharge device can be in operation, channels are smooth
and coverplates of channels and holes are complete
RAEN LL, HRAKARMLARS ONERA EMEA, HG RACS SM
AEDES Oat HLA TEA.
Industrial and domestic water system and safety sanitation facilities within the
commissioning range can be put into operation normally. The fire fighting system has
been under the acceptance of the local authorities and has been in normal operation.
REAR AAR EN EAH, SAR LAE TE EIR RS Baht.
‘The commissioning site has adequate official lighting. The accidental lighting can be in
automatic operation when the official lighting fails.
PUES ALAA ERA, AIR ET LL, ONT AT A
Sti, SAME TRNKA.
Each commissioning post has official communication device. Add the temporary posts
according to the commissioning requirements. There should be reliable communications
that can build up reliable contacts with the dispatcher.
RERMSARE. RRA GAMER ERR
Air conditioning device, heating and ventilation facilities in the commissioning area can
be in normal operation based on the design.
osm@ 4001 FT JR +} fm 2 @OMW 98 $s BT LALA Bah
Central Kalimantan 2*60 MW Coalred Power Plant Turbine Unit Startup Commissioning Plan
5.1.9 ERS S TREE LAE ILE, RABE.
No.4001
5.1.9
5.1.10
5.1.10
5.4.11
5.1.11
5.1.12
5.1.12
5.1.13
5.1.13
5.1.14
5.4.14
6.1.15
5.4.15
5.1.16
5.1.16
5.1.17
5.1.17
5.2
5.2
5.2.1
5.2.4
6.24.4
Measures for sunstroke prevention and cold prevention should be taken in the hot
‘Seasons or at the hot temperature posts, to ensure personnel safety.
27 RBH, eH, Cee R er eHOmEt.
The main machine hall has been completely sealed up, and accepted by the technical
Supervising departments,
FAR, UL SD BM WU RELA BH BER a,
Environmental protection, occupational safety and health facilities and monitoring
system should be in operation according to design requirements,
Ril, WERE MMSE, RFRA OAERG SARE.
Thermal insulation, paint and pipeline coloring should be finished. Systems and
equipment have official names and signs.
SREB ABHAER OH HE.
Containers of each kind has been under inspection and have been sealed up, without
foreign matters.
SON. BER. RRA IC, Ee, RARER, CETRETL.
Fuels, coals and dematerialized water have been stored adequately, meet the
equirements and is in accordance with the design requirements, Chemicals have bees
stored adequately,
SHEARED REEF.
Spare parts and other necessities are ready and complete.
RALA, (RAST Re.
Tools, instruments and various record forms are ready and complete
PRBS BRE INL BR GRE LM RSH,
Problems of equipment and system exposed in the functional parts and components
testing stage have been eliminated.
RERRRMA RNR
FASMBE ARERR ARG, SHREW LURE BER. BER MEH TF AL
AREER, SUA oH, Re Hi. MNS H eRe
Fe
Conditions for Equipment and System
La
Turbine Section.
PREPS HON, CRE. dz, SIRO, SERIE, Ty aRITE RHR IE
tmi 4001 1 sb om 2x GOMW #8 HE os Hh FOUL A ARTS
No.4001
5.24.4
5.21.2
5.2.1.2
5.2.1.3
5.2.1.3
5.2.1.4
5.214
5.2.1.5
5.2.1.5
5.2.1.6
5.2.1.6
5.247
5.247
5.2.1.8
5.2.1.8
5.2.1.9
5.2.1.9
5.21.10
5.21.10
5.2.1.1
5.21.11
5.21.12
5.2.1.12
Central Kalimantan 2x60 MW Coabfired Power Plant___ Turbine Unit Startup Commissioning Plan
Bie
Valves on the pipeline system, including manual, electrical or pneumatic valves, have
been calibrated and can be operated easily. Direction and opening indication are
correct.
RGR, SEAS AA, BRET, RMT. HLM, SRR, A.
KELME, RABRETOA HE. .
Water tanks and containers of the deaerator and condenser hot well are cleaned up.
Water level gauge and oil level gauge work normally with clear indication. All the
steam-water pipes have been flushed and meet the requirements. Deaerator safety
valves are calibrated and meet the requirements.
ETS, DEH SREB, WH. sn RIE.
ETS and DEH functional tests and inspection are over with correct logic, activation and
indication.
HW ERA RRS RBA
‘Turbine control and protection system static test meets the requirements.
HAG. MRK. RETHEAH.
Pipe purging of the auxiliary system and gland seal system meets the requirements
RRA. TRS, ARTA, MM, MIE, SALE
aA.
Lubricating oil system, jacking oil system and oil circulation cleaning are finished. The oil
quality test meets the requirements, oil tank oil level is normal and the tuming gear can
be put into operation normally.
KEARTEN, MORAG, RGASHMALTAER.
Vacuum system operates normally, water filing for leakage inspection of condenser and
system cold-state evacuation meet the requirements.
LEAR RAI, BKB REE, FEMME.
Water spray and atomization of the LP rear casing water spray device is good after
being washed. The two sides are even.
OKRA LARISA, TAB AN EIA
Individual system and equipment commissioning of electrical feed pump group has met
the requirements. Functional check acts correctly.
AR. LKR. BYR. SUKRPRLR FO CIE.
dustrial water pump, condensate
ents through testing and are
Auxiliary equipments like circulating water pump, it
pump and closed type water pump meet the req
accepted and signed.
i, ARR SE BA BK RP ATE BR
HP and LP heaters and each drain protections can be put into operation normally.
RARRRMRTEE, ERA
HP bypass system commissioning has been finished and can be put into operation
normally.
ayn®% 4001 FB st im 2x GOMU M$ Hy STH ROU R SHAR R
No.4001
5.3
53
5.3.4
5.3.1
5.3.2
5.3.2
5.3.3
5.3.3
5.3.4
5.3.5
5.3.5
5.3.6
5.3.6
5.3.7
5.3.7
Cental Kalimantan 260 MW Coal-fred Power Plant Turbine Unt Startup Commissioning Plan
BRU, ARE MRE
Organization, Staff Arrangement and Technical Documents Preparations.
TEE SAMUS ROT OUR, BUUARHOKERAR TRH, fit
BURNIE, 2. .
Company in charge of the project should build up unit startup and acceptance
committee and its branch institutes, clear about the responsibilities and. task
assignments, according to the startup and acceptance specifications.
EMU ayaa aE ALT ahi oe THE
The ‘construction company should assist the trial running department in the
Comprehensive management work of startup and commissioning,
eA ia wet ALA ae oh RI ys, ARKH, HREAHNWMRAR, 5
FA TABS BA Be EEA.
trae Commissioning company should acts according to the authorized unit startup and
{hal running plan, prepare qualified commissioning operators and has a clear post
responsibility system,
VaR fa mI OLE Re sbitiZitRI, FRE AABN ARTA MRMARES st
aH, HAS SWAHARARRAZIE. ORGS BB Aa ERT]
HOARE BAER,
at startup and trial running programme, plan and testing plan for commissioning items
having great influence have been approved by the chief, ‘commissioning commander and
SEAT RT RAL aE, RSS MMMBTAR RIOR, Jee BR MRO HH
FEM. EAT IEA AMR UNSERE, REE AR LL tT RR,
Operational department should prepare operational and laboratory staff of each post
and has ‘2 clear post responsiblity system according to the unit startup. ‘and
commissioning plan. To ensure the operational operations and trouble shooting
reasures, the operational staff should be trained and meet the post requirements
through testing
MINE RRR ATT, REE SERIO. GP RE EO AE
GT ROR. AT MABEM BARAK, SUL SSL KEES Aah
BURA, FRR,
HL MRS hE RINER, Fit LACIE AHA, SH CB
LSE EEIhL. SHA | RS RAR cE LER REAR, Se HERB i ee
PREBLE, RR. SRM ERR ETE.
The construction company should prepare enough maintenance staff and have a clear
Post responsibilty system. Maintenance staff should be familiar with the post equipment
osm#4001 bn 2% GOMW He HE Bh POLL aT
No.4001__ Central Kalimantan 2x60 MW Coal-fred Power Plant __Turbine Unit Startup Commissioning Plan
5.38
5.3.8
5.39
5.3.9
5.3.10
5.3.10
64
61
6.1.1
6.44
6.1.2
6.1.2
(Gystem) performance and be capable of the maintenance work under the uniform
command, without equipment & personal accidents and interrupt of commissioning
work.
MIMUMSARERS (AR) MARGIE, HM, WE TAAR, Wie
EG, RASH ERIEER,
The construction company should prepare. all the installation and acceptance
certificates of the trial running equipments and functional parts and components testing,
and commissioning and setting records. The acceptance certificates meet the
requirements, documents are ready and complete, meeting the trial running
requirements.
RERANAMRKAH, REAR LEER.
Fire fighting equipment at the trial running site. Safety and security meet the
requirement.
SANSA ERR OSA AEE, MERE RABE, RE AAA
wa LHe.
involved in the unit startup and commissioning work should do the
under the uniform command based on the individual responsibilities.
HABKADEF RRBA
Unit Initial Startup Procedures and Test Items
BSAA MRM
‘Test Must Be finished Before Commissioning and Startup.
‘SURES a STN se RA He RNR PRY MFT Sie AER. ETS BRIAR. Sea
BALL. FP. IRI, ES WE EE THe HE
ALA SURE DAR.
‘Transmission tests before unit commissioning and startup not only include MFT
operational test, ETS trip test, generator & transformer protection test, turbine, boiler
and electrical interlock test, and also includes other interlock tests and valve -
transmission tests of each specialization. For the detailed lists,, refer to the
commissioning and startup plans of each specialization.
MFT sh feikae
MFT Operation Test
FSSS ASEM MAINE TPES MTR, BIE MFT RAPER, MET
SIHE SAPARD IT, FURS — RH
FSSS system monitors the some equipment operational conditions during boiler
operation. Once some MFT condition happens, the MFT will be activated, all the fuels in
the furnace will be cut off and the initial trip cause indication will be sent out.
ETS Bei
ETS Trip Test
ARGH ARAN LEE ASH REMAN RS, ALUN SRD
CARRY, ATLA, RAED.
Turbine emergent trip system is a system to monitor some important turbine signals and
10/74001 JE bn 2x GOMW We Ht a POUL RI
Central Kalimantan 260 MW Coalfired Power Plant __ Turbine Unit Startup Commissioning Plan
ensure turbine safety. When the monitored parameter is over the limit, all the steam
6.1.3
6.1.3
6.1.4
614
6.1.4.1
6141
6.1.4.2
6.1.4.2
6.1.4.3
6.1.4.3
62
62
6.21
6.21
6.21.4
621.4
6.22
6.22
6.22.4
6.221
6.222
6.222
6.223
6.2.2.3
623
6.2.3
6.2.3.4
6.23.1
6.2.3.2
6.232
6.23.3
admission valves will be closed to realize emergency shutdown.
BEAR RY
Generator and Transformer Protection Test.
BL. BP. RGR
Turbine, Boller and Electrical Interlock Test.
$84" MFT ETS 24848 TRIP
Boller MFT—-+ turbine ETS— generator and transformer group TRIP
483" MFT AGL ETS 23844 TRIP
Boller MFT—+ turbine ETS—+ generator and transformer group TRIP
$93! MET BL ETS 238/81 TRIP
Boller MFT—-+ turbine ETS—+ generator and transformer group TRIP
BRAT RE TD
Tests to Be Done in the Process of Turbine Speed Rising in the Startup and
Commissioning,
POPU Orpm ith
When turbine speed is 0 tpm:
WER ALE Te ee.
Measure the insulation resistance of generator stator windings.
‘FOULS 29 500rpm Ht:
When turbine speed is 500 rpm.
aT, ARBRE.
Trip and frication inspection,
FRAMES IAL F 30min.
Warming time no less than 30 min,
REM.
Vibration Monitoring.
FABLES 1300 rpm ft}:
When turbine speed is up to 1300 rpm.
FRBL, REEL TEA F 30min.
Warming up and the duration no less than 30 min.
S32R7E 600 rpm it: ATTA A shi
When the speed is up to 600 rpm, check the Jacking oil pump is withdrawn from
‘operation automatically.
Ra.
usyn1 4001 Je in 2x GOMW Me POUL ATR
No4001 ___Central Kalimantan 260 MW Coafred Power Plant _ Turbine Unit Startup Commissioning Plan
6.2.3.3 Vibration Monitoring.
6.24 PULSE 2300 rpm ft:
624 Turbine speed is 2300 rpm.
6.2.4. REL, WEAN AAD F 30min.
6.24 Warming and the warming time no less than 30 min.
6.24.2 HR
6.24.2 Unit passing the critical speed.
624.3 Hah.
6.2.4.3 Vibration Monitorig
6.25 — HLEEH 3000 rpm Bf
6.2.5 When turbine speed is up to 3000 rpm.
625.1 HRRARIRS), AULT SM, BRAKOM.
62.5.1 Measure bearing vibration. Check the turbine thoroughly and record the relative
parameters.
625.2 aLPanT ite.
626.2 — Turbine Manual Trip Test.
625.3 KbLEM RR.
625.3 Turbine Main Oil Pump Changeover Test.
6.25.4 EARN I.
6.25.4 — Emergency Governor Oil Filing Test.
6.25.5 OPC HRM: 109% MBE HE.
6.2.5.5 OPC overspeed protection test: 103% of the rated speed,
625.6 iaaeEtEe.
Electrical Overspeed Test.
SARA B SOMME EAENIT. TITER.
When the main steam pressure is 50% larger than the rated steam pressure, perform
the tightness test of the main stop valve and governing valve.
RULER BTM:
Electrical test after turbine speed is fixed.
SDL RR,
Generator Outlet Short Circuit Test.
ROMER B= A
Generator connected to the main transformer three-phase short circuit test.
SAAR Es CSR
Generator connected to HV station transformer outlet short circuit test.
RAMS
wy@% 4001 61 JB im 2 BOMW #8 3 os BT POURRA R
No.4001
6.264
6.26.5
6.26.5
6.266
6.2.6.6
6.267
6.267
6.27
6.27
6.27.4
6.27.1
6.27.2
6.27.2
63
63
6.3.1
6.3.1
6.3.1.1
63.1.4
6.3.1.2
6.3.1.2
6.3.1.3
6.3.1.3
632
6.3.2
6.3.2.4
6.3.2.1
6.3.22
6.3.22
6.3.23
6.3.2.3
64
Central Kalimantan 2x60 MW Coal-fired Power Plant __ Turbine Unit Startup Commissioning Plan
‘Generator No Load Test.
RST GR
Excitation regulator test under generator no load.
PLAT BEAT (BE ©
Generator no load de-excitation time constant measurement.
WER BPE FRR RA.
Generator stator winding residual voltage and phase sequence measurement.
ELF AE MAE
Fake synchronization test and quasi-synchronization test.
HERE, HH SERGI.
Put the #1 main transformer and #1 station transformer into operation.
MTRBLM OFAN FHA RM, FRR.
Perform the fake synchronization and quasi-synchronization test of the switches at the
‘outlet of the generator and record the waves at the same time.
ATE
Trial Running When on Initial Load.
SLE, 4 SMM Ht
‘Turbine Synchronization with 5% of initial load on.
EEPT. CTIUAMAMAR, MAR DMAME RT BRN ERE.
Measure the phase relation of PT and CT. Check the correctness of the protections like
generator lost excitation
pL hh ta Fae
Shaft voltage measurement under motor on load.
MB.
Magnestat Test.
EB 20WME RM BEIEAT 4 NOT.
‘When the load is up to 20% of the rated load, operate stably for 4 h.
APURT
Motor Removal.
PRE.
Mechanical Overspeed Test.
PTET POLE.
Trip the turbine for idling test.
AA RATE.
w/t4001 Je ob mn 2% GOMW Me ak FOUL RAR.
No.4001
Central Kalimantan 2x60 MW Coal-fred Power Plant __ Turbine Unit Startup Commissioning Pian
64
641
6.44
6.4.1.4
64.1.4
6.4.1.2
6.4.1.2
64.1.3
6.4.1.3
6.4.1.4
64.1.4
6.4.1.5
6.4.1.5
6.4.1.6
6.4.1.6
6.42
642
64.2.4
64.2.1
6422
6422
6.4.2.3
6.4.2.3
64.2.4
64.24
6.4.3
6.4.3
6.4.3.1
6.4.3.1
6.4.3.2
64.3.2
6.4.3.3
Unit on Load for Trail Running.
ADAM, BHAE 0M AM, MMBTEE ARRAS. HOCK
it.
Unit synchronization with initial load, then the load will be increased to 20% of the rated
load, After the unit operates stably, try to put the coal system into operation. Monitor the
steam and water to meet the requirements.”
FimWeite.
Power Supply Switchover Test.
FG a.
Close the automatic initial regulation,
HASH.
Pad vibration and shaft vibration monitoring.
mA, BHA.
Put the LP and HP heaters into operation.
RL RB.
Start up the dust removal system.
BHR. BRAG.
Start up dust and slag removal system.
A ISOMER, UTM RRL WE.
Unit is on 35% of the rated load to perform the initial adjustment of the combustion
system.
BIKAR EH
Monitor the steam and water quality, which meet the requirements.
Wal, EKITS RH.
Put the main steam temperature and main feedwater regulation into trial running
operation automatically.
ARKH.
Thermal expansion inspection.
RRR
Pad vibration and shaft vibration monitoring.
PLA 50%~80%BLE NA»
Unit is on 50%~80% of the rated load,
TMA DARA RH ATR
Perform the combustion automatic governing test and other
RRR
Pad vibration and shaft vibration monitoring.
RRS
usr®F 4001 Jen 2x GOMW Ht He 8 AOU
eset pital Kalimantan 2x60 MW Coal-red Power Plant Turbine Unit Startup Commissioning Plan
6.4.3.3 Put the soot blowing system into operation.
6.4.3.4 SOMW Sister ee eae eID
843.4 When the load is up to 52MW, perform the vacuum tightness test
644 BUA 100% BIE Ay.
644 Unit is on 100% of rated load,
6.4.4.1 FBNRvERtES, PRA Stee.
844.1 Boller combustion adjustment test and boiler steam tightness inspection.
6442 ATA STB
6442 Thermal automatic regulation device adjustment test.
64.4.3 AVR Hi TriRye.
6.4.4.3 AVR Load Thrown -on Test
64.4.4 peel TES RARER Sah RPE NTE On, MERE EAA
6.4.4.4 Measure the uneven output of the HV station transformer, generator and generator
transformer protection differential current. Check the correctness of the negative
‘sequence power.
644.5 ROM K eH
84.4.5 Monitor steam and water to meet the requirements,
6446 aR TL A.
8446 Pad vibration and shaft vibration monitoring,
7 BLASER rie
a Unit startup Procedures and Shutdown
7 AR
71 Cold Startup
PULA ORANGE 5), 2 RPE 0.98~1.47MPa, SEARAUEE 300~350'C, ez
SWAT 50°C UL _Liv thir, ERAURAT Me Bie 50~80°C, ROL aR aS
ARMA BHR.
REPUB 60kPa DLL, PUPS oie. BUR HRAOTOR, DEH Bele,
PFBZ 30001m wee.
When the condenser vacuum is over 60kPa, confirm the main steam meets the
DeHTements. Increase the turbine speed to 3000 rpm and then fix the speed through
DEH, according to the startup curve requirements,
SAUER S, MASH. REFERA, ROU, # scene, BBL 30min,
REBAR RRA RA
6/714001 6 JB + fm 2 BOM M8 $8 os BT OU
Nooo Central Kalimantan 2+60 MW Coa/fred Power Plant Turbine Unit Startup Commissioning Plan
After turbine speed is fixed,
Inspect the unit thoroughly. After the unit is stable and
Normal, make it on 5% initial load and warm up for 30 min. And then increase the load
according to the load curve,
UPAR EER, FRNA eRe Bah eR TRE.
The following is the.general ste}
ps and the detailed can refer to the commissioning and
‘startup plans and operational codes of each specialization.
a Me DR TE A at om BR BH
‘Step [Operation contents [Additional specification
B31 SEAR, A—-BRA, REG ROE]
ATER.
[Start up one circulating water pump and the other]
[standby Check the normal operation condition off
‘circulating water system.
Aa- BARR A-GSH, REM RoE
(Start up one closed type pump and the other
‘standby. Check the normal operation condition of|
\circulating water system,
OK, FL, EMSA,
[Fae AE. (0.
ie 2 a EH Ft F 0.08 ~|
15Mpa. WikAREE 35 Bi] 45°C
{Start up AC oil pump, exhaust fan and the DC oil
lump is standby. The lube oil system in operation. _|°
ci
heck lube oil pressure within}
.08 ~ 0.15Mpa and temperature|
ithin 35-4570,
[aa ES a SR.
[AER UAE 1.96MPa EA
|Start up HP oil pump.
[Check oil pressure around 1.96]
MPa.
TR, AAA RIS, TRS BER
[Dek iA GB Bea AE
HOHE TAA a RE OMpa ZAR #3
SEAU2E > Ze Raha 2h MeoREE A,
[Start up jacking oll pump. Confirm the shaft has}
lbeen projected. Record jacking oil pressure of each|
[pad and shaft projected height. Put the turning gear]
into operation,
(Check jacking oil pressure at 9
Mpa. Put
joperation 2 h before the startup at
least.
tuming gear _ into
a3) SR REAR, PRK. fA
bY.
[Start up one or two demineralized water pump(s) t
make up water to the condensate makeup water
tank.
‘To the high water level.
RASS, ARABI. i
hE IER AKA.
[Start up condensate delivery pump to make up water
ito the condenser.
[To the normal water level.
Ba SREKR, ABER, MRR EK,
ATURE RGD
16/1#1 4001 sb tn 2x GOMW HH BH
No.4001_Central Kalimantan 2x60 MW Coalfred Power Plant
[Start up one condensate pump and the other
[standby. Fill water to the deaerator to flush t
lcondensate system.
. Ae
Turbine Unit Startup
‘Commissioning Plan
Mae KEE RRET RARER, A
Seika Ak RL RRR. PURE.
JAfter the adequate pipe warming to the steam
[supplying system by using the live steam source, put
the desuperheating water system into operation an
keep the steam pressure and temperature stable.
ERAT RA, ERA OKRA
HRHR<200PPb. HRA EH a, Hb ate ae
AFM, SARK BEAF 100°C.
[Change the water in the deaerator and heat until the]
iron content at the deaerator outlet is less than 200|
IPPb.
AaB AR, ARP EK RADE 2 Dabae
BRAD F 4 Pit.
HR AP Sek 4 RP OBE BE
Weeait 42°C.
‘Start up electrical feedwater pump to fill water to the!
boiler, no less than 2 h in summer and 4 in winter,
[Temperature difference between|
ithe boiler feedwater to the boiler|
imetal temperature no more than|
\42'C.
aaP ERP BE.
[Boiler water filing for cleaning.
ara ka a a.
|Confirmed inspection items before boiler ignition.
Baines esa.
(Confirmed inspection items before electrical startup.
VA 35 Bi OR RRS
|Confirm the HP bypass pressure reducing valve is at
closed state.
ASR TMS, ILA Re.
Ma ee eR |
0.101~0.127 MPa.
[Start up the vacuum pump for evacuation and pul
ithe gland seal into operation.
[Pressure behind the steam seal
regulator within 0.101~0.127 Mpa
Saar. FR.
LAS SAH RT
[Boiler temperature and pressure rising.
[Perform according to unit cod start!
lup temperature and pressure rising)
|curve,
PLATE 773 0.98 3] 1.47Mpa, WE 250 5) 300 |
[RMR MRAR EMRE TL, HEI BL INE
ote sg
ws8 4001
No.4001
[When pressure within 0.98-1.47, temperature within)
Te st dn 2 GOMW 8H os ST
Central Kalimantan 2x60 MW Coalfred Power Plant
a FUER SHER R
Turbine Unit Startup Commissioning Plan
8 — [250-300°C, boller maintains stable combustion) no"OUGh inspection before unit
lworking condition to be ready for turbine start. S
19 |OUR SAAR, EME 500mm)
Paha ia, METRE.
[Turbine use cold state Startup mode. When setting
9 [the speed at 500 rpm after being latched on, trip
Imanually for fication inspection.
20 IEA. LRAT, MLE EW 500rpm. EBL 30min HEAT ET eee.
‘29 [batch on turbine again after t operates normally. Set\Warming for3O min for thorough
Iurbine startup speed at 500 rpm. inspection.
PRIM 30 SOF, PERI ELAUIKH|
24 JE% FREI 1300 rpm BE ADR LA De Sah a Ae SEH
IRAE 6OOrpm AsHiE HH.
Medium speed warming for 30 min|
l21 _|Inerease the speed to 1300 rom after the normale” ePe Teo cou
ake differential expansion and vibration.
J22 TE FFR I 2300 rpm ea See
IRecord_the parameters _when]
az |inetease the speed to 2300 rpm ater the normal scsi an eee eres within el
pose lrange and warm up for 30 min,
1. Seana.
eal? MRD.
los, ULF 3000rpm EIR, PLASMA, IATA Fist 3. 39007. (areata.
4. FAALBL ah BIT
5. BTA AR
7 Vibration analysis and
monitoring,
l2. Oil pump changeover test.
; la. Main stop valve andl
Fix the speed when turbine speed increased to 3000] : :
[23 pm. Check the unit thoroughly and do the relative) Governing valve tightness
tests.
l4. Turbine local manual tripping
test.
lS. Perform the relative electrical
tests.
24 EM, ASHE, MAUR.
[Apply for synchronization from the dispatching]
[24 center and synchronize the unit after the approval is
\got.
1/71‘mE 4001 1 JB oh mn 2% GOMW WE He 4
No.4001___ Central Kalimantan 2x60 MW Goal-fred Power Plant
a POLL RIT
Turbine Unit Startup Commissioning Plan
25
(Fe ES SFP.
ACR. RULER
[Check exciting voltage and current!
25 _|Use automatic Synchronization method. iatgeetinny
26 PLAIN 5% Ble ther, RAL TT RBL 30 FFF.
\Unit on 96 rated load during synchronization an
28 check unit operational conditions. fWerning|up for 20) rmin.,
PAZERA, HR O“MEAA. ARR. 3
27 laMvvimin, EBL 4 “hit, SERLATARSEMRE peor
[After unit operates normally, increase to 20% Ofl>s form piant service power supp
lb fated oad snth aril rte of Shin, Warm ca F Pee
lor 4h and do the relative tests. een
PURE Star, AEALMET, YOLEN 3000rpm. ifr
28 ear» [OPC is, HA, HARE RI.
[Decrease load, disconnect the generator and Keep|OPC overspeed test, _ electri
128 turbine operating in 3000rpm and perform turbineloverspeed and mechanical
relative tests. loverspeed test
29 BR TERG, FUBLIERE 3000 rpm.
29 [After the overspeed tests, fix speed at 3000 rpm.
(30 PRALT IE AL, CAMPHT RAT RMR PE.
50 [Tip turbine, and perform boiler safely valve
inspection and tightness test.
(31 RRP SET TA PERI, BLL PRK SE | a Hh a
[Synchronize again afler boiler valve
si) pepe coer eae Electrical on load test.
PLEATS 20% BE Ha:
APM E SEUI aR .
sa i ee A i. AOA, BEANS
PRL AHR a. OI ARR
FANON.
PET PPE
1 Unit on 20% of the rated load gradually.
2 inital adjustment of boiler combustion system. bes auting HP and LP heaters
[3 Adjustment test of thermal automatic controlinto operation, do not recycle the|
132 device ldrain water. Change over the|
'4 Turbine bearing vibration monitoring. jauxiliary steam and deaerator)
; : [steam source.
'5 Put LP heater into operation.
16 Flush HP heater and putit into operation.
33 (APE sexe es BAS Xm RHEE, Bi
w/t4001 1 JB =H im 2 GOMW 98 4 Hs HHT
No4001___Central Kalimantan 2x60 MW Coalfred Power Plant
EBLAA Soret, WORE. ARERR SH TET
Aha oa 2s RH.
@
Turbine Unit Startup Commissioning Plan
JER SBREN seek FA), BLA AH Ria
I33,
lUnit on 35% of the rated load gradually.
[During unit load increase, observe HP and LP;
lbypass working conditions.
(Generally, when up to 25% of thel
rated load, the HP bypass will bel
iclosed and unit is in sliding
pressure operation mode.
PUL NIT
Waa He E 50% Bie HH
aE A Sah PRP HY SSL
AL Gaia Bee
[Unit on 50% of the rated load gradually.
[Check the differential current value of each electrical
lprotection.
[Adjustment tests of thermal automatic control
ldevice.
REL ARP AOR I 6
Lesa rE 80% Mise tii:
AES SSR ES RS RR
A MRA. BATE RARE.
saEAT REPRE.
35
[Try to put boiler body sootblower into operation.
|Unit on 80% of the rated load gradually.
|Perform combustion automatic adjustment test and)
jother systems tests.
[Perform the vacuum tightness test.
[Put the CCS system into operation for load change}
fest
PALE AE 100% Me Mets
WARE COMMER, MIRAE KAT AK.
AL Ana TRE Ae.
| i aL HR.
(Ai Soh PRP A SLL.
(A BE Be HL Se FR
1. PL He
2. RAD MRP MERA
3. RASMA BM.
14. Zeta BL, HRA ZK Ah BH
ky AREAL. PPLE RET A
ERE PBK A BASEL 8
i36
[Unit on 100% of the rated load.
|When unit load is to 90% of the rated load, turbine|
|comes to fixed pressure operational mode.
|Thermal automatic adjustment device adjustment
test.
11. Unit thorough inspection.
2. Put all the protections andi
instrument into operation.
‘3. Put the entire automatic device}
into operation.
20 / 719 4001 5 Im 2 GOMW 2 SEH
4001 __ Central Kalimantan 2x60 MW Coal-fied Power Plent__ Turbine Unit Staitup Commissioning Plan
[Generator shaft voltage measurement. Jé- At load thrown-on stage, change]
Differential current value of each differential he, whole, system water andl
ee lean containers according to|
[protection inspection, steam- water conditions during}
ICheck generator stator earthing protection for three! each turbine and _ boiler
times and the values are all wave values. "| shutdown.
[720 aT eR TT, MIL Fae
+ RBS RL
APT
PRB
Ain
CRB RIER
5. RP BRAK 100%
| MAAHRERASRAT RAE OER.
5 AR
9. RAGE
‘Trial running testing for 720 h under full load, meet
|the following conditions:
1. Generator keeps the rated power on the!
nameplate.
Boiler oil is interrupted and put coal into
operation.
Put ESP into operation.
Put HP heater into operation.
Normal switchover of plant service power supply.
Utilization of protection device is 100%
Thermal automatic device utilization andl
adjustment performance meet _the|
ACCEPTANCE requirements.
‘Steam and water quality meet the requirements.
Soot blowing system is in operation normally.
37
ex SF Fos
y
37
Te TES
oo
72 PUA. A BARA
72 Unit Warm-, hot- and Extreme-hot state Startup.
724 ARMA DUS RMPRSR:
7.24 ‘Turbine Hot State Classification and Start Parameters.
ayn4001 FB H+ Mm 2x GOMW #R HE oh 3 ~ PALAU Bari
No.4001 Central Kalimantan 2x60 MW Coal-fired Power Plant Turbine Unit Startup Commissioning Plan
RSH a Ak oe B
ARS (te) AURA (MPa) EMR CC)
we 3150 2147 2250
ae 150-300 22.58 3350
RE 300~400 3.0 535
BRE 2400 9.0 535
fain steam | Metal temperature at i
4 Main steam pressure | Main steam
ameter | governing stage | ar temperature (°C)
Startup mode Ce)
Cold state =150 3147 2250
Warm state 150300 2258 2360
Hot state 300~400 30 535
Extreme hot state | 2400 30 335
7.2.2 H. ASHAPRXBH RE MAEM ARS.
7.2.2 Control the high temperature part supercooling and negative differential expansion is
crucial during warm and hot startup.
7.23 ABR RE RIT:
7.23 Startup operation and Considerations:
7231 8. ASAT, HARA A, BS Me, HO, FUE IR ERLE L,
BARRA. EA. HR, Sit BU OL AES aS BPM EAT FL EK,
Pit, FB ab nh eR a ae a OE.
7-31 During warm or hot startup, especially the extreme-hot startup, due to the high
temperature of each part, after the turbine startup, speed up, synchronize and throw en
load as long as the inspection can catch up. When the load is increased to a value that
the casing temperature is the same to the casing temperature at the corresponding load
under cold startup, increase the load to the rated value according to the startup curve
and specified working condition procedures.
7.23.2 UARUKRU, RRA SALED, BOaUT FREE.
7232 Before and after boller ignition, except operating according to the cold state startup
Specifications, the following should also be performed:
1) aH ME 40°C,
1) Oil cooler outlet oil temperature no less than 40°C.
2) AAEM, FAIS, RAMS emia, Lee Ra.
2) ‘Supply steam to the gland seal first and then evacuate. Shorten the time from the steam
supply to the turbine starting and mask sure no too high vacuum before turbine starting,
3) SERB AE-0.04MPa, MRRP ALK, SPRIRIRH ERA.
ayni 4001 FRB sh fm 2x GOMU #8 os TE MALLE ahi
No.4001 __Central Kalimantan 2x60 MW Coal-fired Power Plant __Turbine Unit Startup Commissioning Plan
3) When the condenser vacuum is -0.04MPa, inform the boiler to ignite and put the bypass
into operation according to boiler needs.
4) SAUER A FEL SOCUL, MPLAB. WITS S
Be, ERARULE A 50~100 CHAE
4) When the main steam temperature is more than 50°C higher than that of the HP inner
lower casing, stop the self start because the auto main stop valve and governing valve
are not tight. Principally, the main steam should have a superheat degree of 50~100°C.
5) HFPRSRRE, ERADEMIA. WR. RRA, POLE
5) Pay attention to see if the auto main stop valve, governing valve and extraction check
valve are tight, due to the high rolling parameters, to avoid turbine seff rolling.
6) EMR. WMP MSR, AS AERA Re, Donn
8) Main stop valve and governing valve are cooled down quickly after boiler shutdown. Pay
attention to monitor the inner and outer wall temperature of the valve shell during startup.
No too quick heating.
7) FALE — PE FRR MARSA O.03mm, BUCBNIT MEHL, BAe.
SURA, MRR aaah.
7 If the unit bearing cover vibration under the primary critical speed exceeds 0.03mm, trip
the turbine immediately and put the tuming gearing into continuous operation. Ascertain
the causes and restart up it after the faults are eliminated,
8) DUDE AS i, CARE NFR SE ME EI 5 LAS SU BT RA EL
2-0.060MPa, HFMHBESBO°C
8) After confirming the unit is normal, increase the speed in the specified speed rising rate
to the rated speed. During warm state sliding parameter startup, condenser vacuum
should be no less than -0.060MPa and steam exhaust temperature no more than 80°C.
9) WS VLR, RESETS HIT, DK H I, URIMR AE, Peat sie ray ia)
QANTAS EA F Ra HEY 003mm
9) During the hot startup and extreme-hot startup, the continuous turing gear rotation
‘should not be interrupted. If interrupted, then use the interrupted tuming gear rotation.
Restore turning gear operational time over 2 h. The shaft bent value is not 0.03 mm
larger than the original value.
9) ERCERST, HHA GMS, HACE 0.101~0.127Mpa, ASE
WRASAYy 150~260'C. #as. HAAS Iy 250~350°C
9) Under the barring state, supply steam to the shaft seal first and then vacuumize. The
shaft seal steam supply main pipe pressure is within 0.101~0.127Mpa. Front steam seal
temperature is within 150~260°C under warm state, while 250~350°C under hot and
extreme-hot state.
10) BUA RI BER I6 2 Bk, CEB SDR, LABORED IER 5 SPNEAL.
PURE REM OT OR
10) Drain water fully before unit startup. When starting under extreme —hot state, casing
water drainage should be started 5 min and then closed after the unit starting.
Meanwhile, pay attention to stop the HP bypass from operation after the unit starting.
11) TERGELR, HERS A RRR
11) After starting the turbine, pay special attention to the inner frication sound,
23/71#5 4001 1 JR sb dn 2 GOMW #8 HE os Bh TE POLL
No.4001 Central Kalimantan 2x60 MW Coalfred Power Plant _ Turbine Unit Startup Commissioning Plan.
12)
12)
13)
13)
7233
7.2.3.3
73
73
7.3.4
wa.
7.3.2
7.3.2
7.3.24
7.3.2.1
7.3.2.2
7.3.2.2
73.23
73.23
7.3.2.4
PHBE 500pm TERME FRAME 5), PERS
FEA IMAF 15min
After unit starting, check thoroughly when the unit speed is at 500 rpm and confirm (the
stay time should be no more than 5 min.),the idle running time after the unit speed
fixation should be less than 15 min.
FE PSO Bh Rs GT PC BE
FR. TERT, Babe S WANT. 2E. ARZS. MBA
PRE DE ALE AAT,
‘After the synchronization, increase the load to the load corresponding to the upper
casing upper wall temperature of the governing stage as quickly as possible and the
casing temperature has no obvious change. During the load, increasing, pay attention
that the casing temperature rising, temperature rising of auto main stop valve and
governing valve, temperature difference, expansion differential and axial displacement
do not exceed the limit and pay close attention to the unit vibration condition.
FEA ABN HME SEE OR ET
Finish other operational items during cold startup and load thrown on.
DARE
Unit shutdown
PLATES LAE
SP NR Me 5 UE a HA a 5 a TO a ELIT EH
Preparation before the unit is shut down
‘Test the AC and DC lube oil pump, speed-regulating pump, jacking oil pump and turing
gear motor separately and make sure they will work normally.
SERA. MYULAMEMRE, BRE.
Make sure each main steam valve and extraction non-return valve are flexible and not
jammed.
ATMA AHA. SRRA. RASSAAM NBL.
Perform the pipe warming of gland seal auxiliary steam source, bypass system and
standby gas sources of dearator.
WAG:
Load reducing
WAMST, WR WLR, WG 10 SHMER—K
Record tank temperature when the load is reducing. Keep record from then on in every
10 minutes.
Ph 1-2MWimin ASIST
Reduce load at the speed of 1~2MWimin.
ARPT ARI
Put bypass system in service at any time according to the boiler operation status.
DRI, PERUAARIEINAEG, SARA, RAIA, ARE
wasn#5 4001 © Jee in 2 GOMW A HE OB Hh POUR
No.4001___Central Kalimantan 2x60 MW Coalfied Power Plant __Turbine Unit Startup Commissioning Plan
73.24
7.3.2.7
7.3.27
73.28
73.28
7.33
733
7.33.4
7331
7332
7.3.3.2
7.3.33
733.3
7.3.3.4
2)
3)
4)
5)
ARRSE CIEE. SASHA RRMA MLA, RMR AE
SRT
Pay attention to the differential expansion change when reducing the load. If the
differential expansion is large, slow the load reducing speed and input the high
temperature gas sources of gland seal to keep the differential expansion within permitted
range. If negative differential expansion is increasing and the measures taken is invalid
and will influence the unit safety, slow the load to zero or latch of the unit.
RSME H LIE MGS SS. IR PRR ACA A Te
Pay attention to the level adjustment of condenser, heater and dearator during load
reducing.
RE. 2 # EGER INAS Rh NF BRE 7) O.3MPa BY, He ARMIES AIM, ERR
“mime.
‘When load is reduced to be the same of the pressure of #2 high temperature heater
while lower than 0.3MPa of the dearator pressure, retum HP heater drainage to #4 LH
heater and relieve “HP Heater Protection”.
PTR 2OMW HAT, TFA TAIT
Open all drainage valves of steam turbine main body when load is reduced to 20MW.
AED, SEMAN, RASTER DPE. BER, ERT
fae
Watch the unit vibration situation closely during load reducing. Stop temperature and
pressure decreasing when there is abnormal vibration. Latch off the unit if necessary.
HL
Shutdown
RE SHB RA, RRBURARAEL, PERMA CAM ALA
STIIPPOL), SSCA, RE. IMRT UA BAL Ai.
Contact electrical engineer to shut down the generator when load is reduced to 3% rated
load. Notice that the steam turbine can keep idle running (or latch off the steam turbine
immediately). Start up AC lube oil pump, the HP and LP heater shall stop operating with
the steam turbine.
FMF, READER, WAAR MRP, BERRA FB
Latch off to stop the steam turbine. Check to make sure the main steam valve, regulating
valve and each extraction non-retum valve are closed. Note to slow the rotating speed.
DREARY)
Remove every protective device (except low oil pressure protection)
See Fie PRE:
ERAUTLAR ES, DHA, WK, Wi, AREER.
PORES 600r/min, EATNMRAAH, AFD.
FERMES 300rmin, PukKe wit
REZ 100rmin, FARMER:
RTE, SBS, PLAN, PRB.