100% found this document useful (3 votes)
5K views1 page

Earthing and Bonding Installation Checklist

The document provides a checklist for installing an earthing and bonding system with 10 items to check including: verifying layout and drawings, civil clearances, sleeve sizes and sealing, earthing wire sizes, equipotential bonding, earth bar locations and sizes, earthing wire connections, earth pit level and location, earth pit fixing, earthing wire connections to rods, and ensuring earth resistance is less than 2 ohms.

Uploaded by

Prashant Kadam
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
100% found this document useful (3 votes)
5K views1 page

Earthing and Bonding Installation Checklist

The document provides a checklist for installing an earthing and bonding system with 10 items to check including: verifying layout and drawings, civil clearances, sleeve sizes and sealing, earthing wire sizes, equipotential bonding, earth bar locations and sizes, earthing wire connections, earth pit level and location, earth pit fixing, earthing wire connections to rods, and ensuring earth resistance is less than 2 ohms.

Uploaded by

Prashant Kadam
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
  • Installation of Earthing and Bounding System

PROJECT NAME & LOGOS

CHECK LIST FOR:


Form No:
INSTALLATION OF EARTHING AND BOUNDING SYSTEM
Rev. No: 00
SUBCONTRACTOR X CONTRACTOR Page : 1 of 1

SECTION OF WORK: Electrical LOCATION:


LEVEL: WIR No.:
STAGE ITEM Checked by Checked by Date
S/C CONT CONS.
SETTING OUT Check Layout

MEP/CIVIL Civil clearance to the level

1. Check against approved electrical shop


drawings.
Pre-Installation 2. Check if the sleeve level and thickness of the
pipes are as per approved shop drawings. Seal
all sleeves as per specification.
3. Check if sizes of the earthing wires are as per
the approved shop drawing.
4. Check cable trays, trunking, and equipment
Equipotential bonded as per project
specification.
5. Check if locations and sizes of earth bar are as
specification and approved shop drawings.

6. Check if that earthing wire(s) is connected to


equipment as per shop drawing in proper way.
Installation
7. Check the level & location of earth pit as per
approved shop drawings.
8. Check if earth pit fixing is as specification
and approved shop drawings.

9. Check the connection(s) of earthing wire to


earthing rod electrode.

10. The resistance of the earth shall be less than


2Ω or as per local regulation.

For S/C QA/QC: Date: FOR CONTRACTOR Date: For CONS. Rep.: Date:
QA/QC:

Name: Sign: Name: Sign: Name: Sign: