PHDS SSU Normalisation Checklist

1. The document provides a checklist procedure for normalizing the PHDS SSU power distribution system. 2. It involves disabling and enabling breakers and equipment at multiple stations to transfer power from one source to another. 3. Key steps include verifying voltages, opening and closing specific breakers, confirming status updates, checking alarms, and enabling equipment once power has been stabilized across all affected stations.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
67 views2 pages

PHDS SSU Normalisation Checklist

1. The document provides a checklist procedure for normalizing the PHDS SSU power distribution system. 2. It involves disabling and enabling breakers and equipment at multiple stations to transfer power from one source to another. 3. Key steps include verifying voltages, opening and closing specific breakers, confirming status updates, checking alarms, and enabling equipment once power has been stabilized across all affected stations.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

Attachment 1 : Procedure Checklist Page 1 of 1

S
Normalisation of PHDS SSU Rev : 01

Project No. : RRSB/GCS/CTT/025/2017 Doc. No. :OMSBK/GRSB/CL/001

ACTION CHECK
ITEMS
Location Panel Gear Status Remark × √

1.0 Tool box briefing explanations of Procedure SOP and Safety.

All PIC (LV and HV Charge-man) ensure voltages are stable for equipment’s in 33kV and LV rooms at
2.0 all stations (SURS, MUDS, BAUS, TTDS, PHDS, PBDS &SEMS). All PIC record the voltage reading in
Attachment 2.

3.0 GRSB Check and verify 33kV available at incomer R1 and R2 at PHDE.

3.0 MUDE B2 52B2 DISABLE NVAC disable mode & GR confirm at STN “Done”.

4.0 PHDE B2 52B2 DISABLE NVAC disable mode & GR confirm at STN “Done”.

5.0 SEME B2 52B2 DISABLE NVAC disable mode & GR confirm at STN “Done”.

6.0 SURE B2 52B2 DISABLE NVAC disable mode & GR confirm at STN “Done”.

7.0 Rapid Rail shutdown all the equipment that has been bypass from UPS.

10.0 SURE LM4 52LM4 OPEN OCC “OPEN” breaker & GRSB confirm at STN “OK”

11.0 PHDE R2 52R2 CLOSE OCC “CLOSE” breaker & GR confirm at STN “OK”.

GRSB Chargeman verify mimic at OCC all South Bound Station has 33kV.
12.0
GRSB Chargeman at site check and confirm all South Bound Station has 33kV.

13.0 SURE LM2 52LM2 OPEN OCC “OPEN” breaker & GRSB confirm at STN “OK”.

14.0 PHDE R1 52R1 CLOSE OCC “CLOSE” breaker & GR confirm at STN “OK”.

GRSB Chargeman verify mimic at OCC all North Bound Station has 33kV.
15.0
GRSB Chargeman at site check and confirm all North Bound Station has 33kV.

All PIC (LV and HV Charge-man) check and reset any alarm at relay, battery charger and voltage are
16.0 stable for equipment’s in 33kV and LV rooms at all stations (SURS,MUDS, BAUS, TTDS, PHDS, PBDS
&SEMS).

17.0 Rapid Rail normalize all the equipment that has been shutdown

18.0 MUDE B2 52B2 ENABLE NVAC enable mode & GR confirm at STN “Done”.

19.0 PHDE B2 52B2 ENABLE NVAC enable mode & GR confirm at STN “Done”.

20.0 SEME B2 52B2 ENABLE NVAC enable mode & GR confirm at STN “Done”.

21.0 SURE B2 52B2 ENABLE NVAC enable mode & GR confirm at STN “Done”.
Attachment 1 : Procedure Checklist Page 2 of 1
S
Normalisation of PHDS SSU Rev : 01

Project No. : RRSB/GCS/CTT/025/2017 Doc. No. :OMSBK/GRSB/CL/001

Checked
Checkedbyby(B0 Chargeman),
GRSB (B0 Chargeman), Witness by Rapid Rail Sdn Bhd

________________________
Name:
Date:
________________________ ________________________
Name: Name:
Date: Date: