Construction Build-Up Rate Analysis
Construction Build-Up Rate Analysis
EXCAVATION PIT
EXCAVATION TRENCH
HARDCORE (150mm thick)
HARDCORE (300 mm thick)
LEAN CONCRETE (GRADE 15)
REINFORCED CONCRETE (GRADE 35)
FORMWORK
REINFORCEMENT HIGH TENSILE STEEL BAR (10mm & 12mm)
REINFORCEMENT HIGH TENSILE STEEL BAR (16mm, 20mm & 12mm)
REINFORCEMENT MILD STEEL BAR (6mm, 8mm & 10mm)
BRC (A8)
BRC (A7)
DAMP PROOF COURSE
ANTI-TERMITE
REINFORCED CONCRETE (GRADE 30)
GROOVE LINE
Steel Roof Structure
ROOF COVERING
ROOF INSULATION
WATERPROOFING SYSTEM
RAINWATER DOWNPIPE
GUTTER
PULL OUT TEST
FASCIA BOARD
FORMWORK IN METER
TREAD
RISER
SOFFIT
STRING
RAIL POST
HAND RAILING
MS MESH
TILES NOSING
BRICKWORK
BLOCKWORK
DRY WALL
BONDING TIES
GLASS BLOCK
BRICKWORK
BLOCKWORK (2 HOURS FIRE RATED)
LINTEL
SINGLE LEAF TIMBER DOOR (D1)
SINGLE LEAF TIMBER DOOR (D1a)
DOUBLE LEAF TIMBER DOOR (D2)
DOUBLE LEAF TIMBER DOOR (D3)
DOUBLE LEAF TIMBER DOOR (D4)
DOUBLE LEAF TIMBER DOOR (D4a)
ALUMINIUM LOUVERED COMPOSITE DOOR (FD1)
ALUMINIUM LOUVERED COMPOSITE DOOR (FD2)
ALUMINIUM LOUVERED COMPOSITE DOOR (F4)
ALUMINIUM FRAME SLIDING DOOR (SD1)
ALUMINIUM FRAME SLIDING DOOR (SD2)
ALUMINIUM FRAME SLIDING DOOR (SD3)
ROLLER SHUTTER (RS1)
ROLLER SHUTTER (RS2)
FIRE RATED DOOR
LINTEL
(W1)
(W1a)
(W1b)
(W2)
(W2a)
(W2b)
(W3a)
(W4)
(W4a)
(W5)
(W7)
CEMENT RENDER
HARDENER
TILES 600MM
TILES 3000MM
Skirting (600mm x 100mm)
Skirting (300mm x 100mm)
PLASTERING
PAINTING
PERFORATED CEILING BOARD
SKIM COAT
ALUMINIUM STRIP CEILING
CEMENT BOARD
STONE COAT FINISH
COLUMN FINISHES
HOSEREEL
ALUMINIUM LOUVRES
5700mm x 600mm
11650mm x 600mm
14850mm x 393mm
8800mm x 393mm
15300mm x 600mm
18150mm x 600mm
12300mm x750mm
12200mm x 393mm
12300mm x 600mm
12300mm x 393mm
17855mm x 745mm
17850mm x 394mm
15100mm x 450mm
15100mm x 900mm
7.71
7.42
9.27
15.20
23.81
16.54
291.84
47.87
3.94
4.31
3.94
18.71
12.51
18.24
62.24
267.69
17.62
107.39
50.54
13.24
9.75
11.43
29.15
525.00
35.22
32.92
9.97
9.99
13.04
9.69
56.79
71.22
24.97
87.11
28.28
31.41
20.70
6.23
22.85
28.28
30.24
43.16
403.13
403.13
764.46
644.40
717.08
717.08
403.13
403.13
644.40
1,972.65
1,610.63
1,212.16
1,100.90
920.86
644.63
42.47
2,016.35
2,722.74
2,510.83
634.97
634.97
587.88
2,218.01
1,070.88
1,668.59
927.19
625.31
13.04
7.23
63.85
55.10
10.40
10.28
46.71
67.99
21.26
5.27
30.32
22.35
166.46
56.56
324.21
1,814.18
3,701.18
3,091.21
1,834.27
4,858.75
5,762.61
4,882.54
2,540.97
3,907.32
2,561.58
7,037.52
3,723.91
3,598.11
7,189.75
EXCAVATION REDUCE LEVEL
A EQUIPMENT
EXCAVATOR
RENTAL COST
OPERATOR
DIESEL
LUBRICATION OIL
OPERATION COST PER DAY
OPERATION COST PER HOUR
MACHINE OUTPUT m³
MACHINE OUTPUT m²
PROFIT & OVERHEAD
COST PER m²
EXCAVATION PIT
A EQUIPMENT
EXCAVATOR
RENTAL COST
OPERATOR
DIESEL
LUBRICATION OIL
OPERATION COST PER DAY
OPERATION COST PER HOUR
MACHINE OUTPUT m³
PROFIT & OVERHEAD
COST PER m³
EXCAVATION TRENCH
A EQUIPMENT
EXCAVATOR
RENTAL COST
OPERATOR
DIESEL
LUBRICATION OIL
OPERATION COST PER DAY
OPERATION COST PER HOUR
MACHINE OUTPUT m³
PROFIT & OVERHEAD
COST PER m³
WASTAGE
B LABOUR COST
GENERAL LABOUR
TOTAL LABOUR COST
C EQUIPMENT
COMPACTOR
RENTAL COST (INCLUDE FUEL)
PER HOUR
PRODUCTIVITY
WASTAGE
B LABOUR COST
GENERAL LABOUR
TOTAL LABOUR COST
C EQUIPMENT
COMPACTOR
RENTAL COST (INCLUDE FUEL)
PER HOUR
PRODUCTIVITY
B LABOUR COST
LIFTING & POURING
UNSKILL LABOUR
TOTAL LABOUR COST
C EQUIPMENT
CONCRETE MIXER
RENTAL COST
OPERATOR
DIESEL
LUBRICATION OIL
OPERATION COST PER DAY
OPERATION COST PER HOUR
MACHINE OUTPUT m²
TOTAL COST PER m²
B LABOUR COST
LIFTING & POURING
UNSKILLED LABOUR
TOTAL LABOUR COST
C EQUIPMENT
MOBILE CRANE
RENTAL COST
OPERATOR
DIESEL
LUBRICATION OIL
OPERATION COST PER DAY
OPERATION COST PER HOUR
MACHINE OUTPUT m³
TOTAL COST PER m³
FORMWORK
A MATERIAL COST
PLYWOOD
0.06m³ OF STRUTTING
PRICE FOR 6 TIME USAGE
PRICE FOR 1 TIME USAGE
NAIL
WASTAGE
TOTAL MATERIAL PRICE
B LABOUR COST
INSTALLATION
SKILLED LABOUR
UNSKILLED LABOUR
REMOVING
UNSKILLED LABOUR
TOTAL LABOUR COST
B LABOUR COST
SKILLED LABOUR
GENERAL WORKER
TOTAL LABOUR COST
C EQUIPMENT
CRANE
RENTAL COST ( INCLUDE FLUE)
OPERATOR
TOTAL COST PER DAY
TOTAL COST PER HOURS
PRODUCTIVITY
TOTAL COST
PROFIT & OVERHEAD
TOTAL EQUIPMENT COST
B LABOUR COST
SKILLED LABOUR
GENERAL WORKER
TOTAL LABOUR COST
C EQUIPMENT
CRANE
RENTAL COST ( INCLUDE FLUE)
OPERATOR
TOTAL COST PER DAY
TOTAL COST PER HOURS
PRODUCTIVITY
TOTAL COST
PROFIT & OVERHEAD
TOTAL EQUIPMENT COST
B LABOUR COST
SKILLED LABOUR
GENERAL WORKER
TOTAL LABOUR COST
C EQUIPMENT
CRANE
RENTAL COST ( INCLUDE FLUE)
OPERATOR
TOTAL COST PER DAY
TOTAL COST PER HOURS
PRODUCTIVITY
TOTAL COST
PROFIT & OVERHEAD
TOTAL EQUIPMENT COST
BRC (A8)
A MATERIAL COST
MATERIAL COST
LAPPING
WASTAGE
TOTAL MATERIAL PRICE
B LABOUR COST
GENERAL LABOUR
TOTAL LABOUR COST
C EQUIPMENT
CRANE
RENTAL COST ( INCLUDE FLUE)
OPERATOR
TOTAL COST PER DAY
TOTAL COST PER HOURS
PRODUCTIVITY
PROFIT OVERHEAD
TOTAL EQUIPMENT COST
BRC (A7)
A MATERIAL COST
MATERIAL COST
LAPPING
WASTAGE
TOTAL MATERIAL PRICE
B LABOUR COST
GENERAL LABOUR
TOTAL LABOUR COST
C EQUIPMENT
CRANE
RENTAL COST ( INCLUDE FLUE)
OPERATOR
TOTAL COST PER DAY
TOTAL COST PER HOURS
PRODUCTIVITY
PROFIT OVERHEAD
TOTAL EQUIPMENT COST
B LABOUR COST
UNSKILLED LABOUR
TOTAL LABOUR COST
ANTI-TERMITE
A MATERIAL COST
MATERIAL PRICE
WASTAGE
TOTAL MATERIAL PRICE
B LABOUR COST
UNSKILLED LABOUR
TOTAL LABOUR COST
800.00
60.00
6 LITRE X 8 HOURS X RM2.15 103.20
2 LITRE X RM18.63 37.26
1,000.46
RM1000.46 / 8 HOURS 125.06
CALCULATION RM
800.00
60.00
6 LITRE X 8 HOURS X RM2.15 103.20
2 LITRE X RM18.63 37.26
1,000.46
RM1000.46 / 8 HOURS 125.06
CALCULATION RM
800.00
60.00
6 LITRE X 8 HOURS X RM2.15 103.20
2 LITRE X RM18.63 37.26
1,000.46
RM1000.46 / 8 HOURS 125.06
CALCULATION RM
5% x RM 2.75 0.14
RM60/day 60.00
RM60.00 /8hour 7.50
RM 7.50/15m²/h 0.50
CALCULATION RM
5% x RM 9.88 0.49
CALCULATION RM
14.00
60.00
0.5 LITRE X 8 HOURS X RM1.43 5.72
0.5 LITRE X RM18.63 9.32
89.04
RM89.04 / 8 HOURS 11.13
CALCULATION RM
RM220.00 / m³ 220.00
5% x RM220.00 11.00
231.00
600.00
60.00
5 LITRE X 8 HOURS X RM1.43 57.20
2 LITRE X RM18.63 37.26
754.46
RM754.46 / 8 HOURS 94.31
CALCULATION RM
CALCULATION RM
RM2.55/kg 2.55
5% x RM5.25 0.12
RM3.22 + RM0.16 2.67
CALCULATION RM
RM2.85/kg 2.85
5% x RM5.25 0.14
2.99
CALCULATION RM
RM2.55/kg 2.55
5% x RM5.25 0.12
RM3.22 + RM0.16 2.67
1 x RM90/8hrs x 0.025hr/kg 0.28
1 x RM60/8hrs x 0.025hr/kg 0.19
RM0.28 + RM0.19 0.47
CALCULATION RM
RM12.80/m² 12.80
10% x RM12.80 1.28
5% x RM12.80 0.64
14.72
CALCULATION RM
RM8.11/m² 8.11
10% x RM8.11 0.81
5% x RM8.11 0.41
9.33
CALCULATION RM
CALCULATION RM
0.5 / m² 49.75
5% rm49.75 2.49
52.24
A MATERIAL COST
MATERIAL PRICE
Clay brickwork
wastage
Exmet
Wastage
Total
C&S
Cement
sand
Total
Wastage
MATERIAL COST FOR 7m³
MATERIAL COST FOR 1m³
MATERIAL COST FOR 1m2
B LABOUR COST
SKILLED LABOUR
UNSKILLED LABOUR
TOTAL LABOUR COST
D UNIT RATE & PROFIT
MATERIAL + LABOUR COST
PROFIT & OVERHEAD
TOTAL INSTALLATION COST
CALCULATION RM
0.33
RM0.33 x 5% 0.02
0.35
RM5.00 x 0.45kg 2.25
RM2.25 x 5% 0.11
2.36
2.71
A MATERIAL COST
MATERIAL PRICE
Clay brickwork
wastage
Exmet
Wastage
Total
C&S
Cement
sand
Total
Wastage
MATERIAL COST FOR 7m³
MATERIAL COST FOR 1m³
MATERIAL COST FOR 1m2
B LABOUR COST
SKILLED LABOUR
UNSKILLED LABOUR
TOTAL LABOUR COST
D UNIT RATE & PROFIT
MATERIAL + LABOUR COST
PROFIT & OVERHEAD
TOTAL INSTALLATION COST
CALCULATION RM
0.33
RM0.33 x 5% 0.02
0.35
RM5.00 x 0.45kg 2.25
RM2.25 x 5% 0.11
2.36
2.71
WASTAGE
TOTAL MATERIAL PRICE
B LABOUR COST
SKILLED LABOUR
UNSKILLED LABOUR
TOTAL LABOUR COST
TOTAL
WASTAGE
B LABOUR COST
SKILLED LABOUR
UNSKILLED LABOUR
TOTAL
WASTAGE
B LABOUR COST
SKILLED LABOUR
UNSKILLED LABOUR
TOTAL
WASTAGE
B LABOUR COST
SKILLED LABOUR
UNSKILLED LABOUR
TOTAL
WASTAGE
B LABOUR COST
SKILLED LABOUR
UNSKILLED LABOUR
TOTAL
WASTAGE
B LABOUR COST
SKILLED LABOUR
UNSKILLED LABOUR
TOTAL
WASTAGE
B LABOUR COST
SKILLED LABOUR
UNSKILLED LABOUR
TOTAL
WASTAGE
B LABOUR COST
SKILLED LABOUR
UNSKILLED LABOUR
TOTAL
WASTAGE
B LABOUR COST
SKILLED LABOUR
UNSKILLED LABOUR
TOTAL
WASTAGE
B LABOUR COST
SKILLED LABOUR
UNSKILLED LABOUR
TOTAL
WASTAGE
B LABOUR COST
SKILLED LABOUR
UNSKILLED LABOUR
TOTAL
WASTAGE
B LABOUR COST
SKILLED LABOUR
UNSKILLED LABOUR
TOTAL
WASTAGE
TOTAL MATERIAL PRICE
B LABOUR COST
SKILLED LABOUR
UNSKILLED LABOUR
TOTAL
WASTAGE
B LABOUR COST
SKILLED LABOUR
UNSKILLED LABOUR
TOTAL
WASTAGE
B LABOUR COST
SKILLED LABOUR
UNSKILLED LABOUR
TOTAL
WASTAGE
B LABOUR COST
SKILLED LABOUR
UNSKILLED LABOUR
TOTAL
WASTAGE
B LABOUR COST
SKILLED LABOUR
UNSKILLED LABOUR
WASTAGE
B LABOUR COST
SKILLED LABOUR
UNSKILLED LABOUR
TOTAL LABOUR COST
WASTAGE
B LABOUR COST
SKILLED LABOUR
UNSKILLED LABOUR
WASTAGE
TOTAL MATERIAL PRICE
B LABOUR COST
SKILLED LABOUR
UNSKILLED LABOUR
WASTAGE
B LABOUR COST
SKILLED LABOUR
UNSKILLED LABOUR
WASTAGE
B LABOUR COST
SKILLED LABOUR
UNSKILLED LABOUR
WASTAGE
B LABOUR COST
SKILLED LABOUR
UNSKILLED LABOUR
CALCULATION RM
1,250.00
5% x RM1250 62.50
1 x RM90/8hrs 11.25
1 x RM60/8hrs 7.50
CALCULATION RM
220.00
220.00
5% x RM220.00 11.00
1 x RM90/8hrs 11.25
1 x RM60/8hrs 7.50
CALCULATION RM
RM193.00 x 17 3,281.00
3,281.00
5% x RM3281.00 164.05
1 x RM60/8hrs 7.50
CALCULATION RM
RM180.00 x 98 17,640.00
17,640.00
5% x RM17640.00 882.00
1 x RM90/8hrs 11.25
1 x RM60/8hrs 7.50
CALCULATION RM
385.00
385.00
5% x RM385.00 164.05
1 x RM90/8hrs 11.25
1 x RM60/8hrs 7.50
CALCULATION RM
RM385.00 x 4 1,540.00
1,540.00
5% x RM1540 77.00
1 x RM90/8hrs 11.25
1 x RM60/8hrs 7.50
CALCULATION RM
CALCULATION RM
RM220.00 x 10 2,200.00
2,200.00
5% x RM2200.00 110.00
1 x RM90/8hrs 11.25
1 x RM60/8hrs 7.50
CALCULATION RM
RM234.00 x 17 3,978.00
3,978.00
5% x RM3978.00 198.90
1 x RM90/8hrs 11.25
1 x RM60/8hrs 7.50
CALCULATION RM
253.00
253.00
5% x RM253.00 12.65
1 x RM90/8hrs 11.25
1 x RM60/8hrs 7.50
CALCULATION RM
385.00
385.00
5% x RM385.00 19.25
1 x RM90/8hrs 11.25
1 x RM60/8hrs 7.50
CALCULATION RM
RM240.00 x 4 960.00
960.00
5% x RM960.00 48.00
1 x RM90/8hrs 11.25
1 x RM60/8hrs 7.50
CALCULATION RM
RM1800.00 x 7 12,600.00
12,600.00
5% x RM12600.00 630.00
RM1800.00 + RM630.00 13,230.00
1 x RM90/8hrs 11.25
1 x RM60/8hrs 7.50
CALCULATION RM
RM1800.00 x 7 12,600.00
12,600.00
5% x RM12600.00 630.00
1 x RM90/8hrs 11.25
1 x RM60/8hrs 7.50
CALCULATION RM
RM900.00 x 91 81,900.00
81,900.00
5% x RM81900.00 4,095.00
1 x RM90/8hrs 11.25
1 x RM60/8hrs 7.50
CALCULATION RM
RM900.00 x 24 21,600.00
21,600.00
5% x RM21600.00 1,080.00
1 x RM90/8hrs 11.25
1 x RM60/8hrs 7.50
RM900.00 x 5 4,500.00
4,500.00
5% x RM4500.00 225.00
1 x RM90/8hrs 11.25
1 x RM60/8hrs 7.50
CALCULATION RM
RM298 x 2 596.00
RM30/ set x 1 set 30.00
RM596 + RM30.00 626.00
5% x RM626.00 31.30
1 x RM90/8hrs 11.25
1 x RM60/8hrs 7.50
RM11.25 + RM7.50 18.75
CALCULATION RM
RM341 x 2 682.00
RM30/ set x 1 set 30.00
RM682.00 + RM30.00 712.00
5% x RM712.00 35.60
1 x RM90/8hrs 11.25
1 x RM60/8hrs 7.50
CALCULATION RM
RM300 x 2 600.00
RM30/ set x 1 set 30.00
RM600.00 + RM30.00 630.00
5% x RM630.00 31.50
RM630.00 + RM31.50 661.50
1 x RM90/8hrs 11.25
1 x RM60/8hrs 7.50
CALCULATION RM
RM241 x 3 723.00
RM30/ set x 1 set 30.00
RM723.00 + RM30.00 753.00
5% x RM753.00 37.65
1 x RM90/8hrs 11.25
1 x RM60/8hrs 7.50
CALCULATION RM
RM241 x 2 482.00
RM30/ set x 1 set 30.00
RM482 + RM30 512.00
5% x RM512 25.60
1 x RM90/8hrs 11.25
1 x RM60/8hrs 7.50
CALCULATION RM
158.00
RM30/ set x 1 set 30.00
RM158.00 + RM30 188.00
5% x RM188.00 9.40
1 x RM90/8hrs 11.25
1 x RM60/8hrs 7.50
A MATERIAL COST
MATERIAL PRICE
Cement
sand
Total
Wastage
MATERIAL COST FOR 4m³
MATERIAL COST FOR 1m³
MATERIAL COST FOR 1m²
B LABOUR COST
CEMENT AND SCREED MIXING
UNSKILLED LABOUR
PAVING WORKS
SKILLED LABOUR
UNSKILLED LABOUR
TOTAL LABOUR COST
TILES
A MATERIAL COST
MATERIAL PRICE
TILES
Homogeneous Tiles (300mm x 300mm)
Wastage
Cost of 1m2 tile
C & S AND SCREED
Cement
sand
Wastage
MATERIAL COST FOR 4m³
MATERIAL COST FOR 1m³
MATERIAL COST FOR 1m²
B LABOUR COST
MIXING WORK
Unskilled Labour
LAYING TILES
Skilled Labour
Unskilled Labour
TOTAL LABOUR COST
A MATERIAL COST
MATERIAL PRICE
SKIRTING
Skirting (150mm x 300mm)
Wastage
TOTAL SKIRTING COST
C&S AND SCREED
Cement
sand
Wastage
MATERIAL COST FOR 4m³
MATERIAL COST FOR 1m³
MATERIAL COST FOR 1m2
B LABOUR COST
SKILLED LABOUR
TOTAL LABOUR COST
TILES
A MATERIAL COST
MATERIAL PRICE
TILES
Ceramic Tiles (300mm x 300mm)
Wastage
Cost of 1m2 tile
C & S AND SCREED
Cement
sand
Wastage
MATERIAL COST FOR 4m³
MATERIAL COST FOR 1m³
MATERIAL COST FOR 1m²
B LABOUR COST
MIXING WORK
Unskilled Labour
LAYING TILES
Skilled Labour
Unskilled Labour
TOTAL LABOUR COST
TILES
A MATERIAL COST
MATERIAL PRICE
TILES
Ceramic Tiles (300mm x 600mm)
Wastage
Cost of 1m2 tile
C & S AND SCREED
Cement
sand
Wastage
MATERIAL COST FOR 4m³
MATERIAL COST FOR 1m³
MATERIAL COST FOR 1m²
B LABOUR COST
MIXING WORK
Unskilled Labour
LAYING TILES
Skilled Labour
Unskilled Labour
TOTAL LABOUR COST
TILES
A MATERIAL COST
MATERIAL PRICE
TILES
Ceramic Tiles (600mm x 600mm)
Wastage
Cost of 1m2 tile
C & S AND SCREED
Cement
sand
Wastage
MATERIAL COST FOR 4m³
MATERIAL COST FOR 1m³
MATERIAL COST FOR 1m²
B LABOUR COST
MIXING WORK
Unskilled Labour
LAYING TILES
Skilled Labour
Unskilled Labour
TOTAL LABOUR COST
CALCULATION RM
9.40
RM9.40 / 0.09 / m² 104.44
5% X RM104.44 5.22
109.66
CALCULATION RM
9.40
RM9.4 x 5% 0.47
9.87
CALCULATION RM
9.40
RM9.40 / 0.09 / m² 104.44
5% X RM104.44 5.22
109.66
CALCULATION RM
9.40
RM9.40 / 0.18 / m² 52.22
5% X RM52.22 2.61
54.83
CALCULATION RM
9.40
RM9.40 / 0.36 / m² 26.11
5% X RM26.11 1.31
27.42