100% found this document useful (1 vote)
1K views66 pages

Construction Build-Up Rate Analysis

The document provides costing information for various construction works including excavation, concreting, formwork, reinforcement, damp proofing, etc. It includes details of material costs, labor costs, equipment costs and rates per unit of measurement. Calculations are shown for determining the final unit rates with considerations for profit and overhead costs.

Uploaded by

Izzul Haqeemi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
1K views66 pages

Construction Build-Up Rate Analysis

The document provides costing information for various construction works including excavation, concreting, formwork, reinforcement, damp proofing, etc. It includes details of material costs, labor costs, equipment costs and rates per unit of measurement. Calculations are shown for determining the final unit rates with considerations for profit and overhead costs.

Uploaded by

Izzul Haqeemi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
  • Materials and Dimensions List
  • Measurement Calculations
  • Cost Analysis for Excavation
  • Material Costing
  • Calculation Breakdowns
  • Brickwork and Installation Costs
  • Doors and Windows Cost Structure
  • Comprehensive Price Calculations
  • Finishing Costs and Skirtings
  • Final Cost Calculations

EXCAVATION REDUCE LEVEL

EXCAVATION PIT
EXCAVATION TRENCH
HARDCORE (150mm thick)
HARDCORE (300 mm thick)
LEAN CONCRETE (GRADE 15)
REINFORCED CONCRETE (GRADE 35)
FORMWORK
REINFORCEMENT HIGH TENSILE STEEL BAR (10mm & 12mm)
REINFORCEMENT HIGH TENSILE STEEL BAR (16mm, 20mm & 12mm)
REINFORCEMENT MILD STEEL BAR (6mm, 8mm & 10mm)
BRC (A8)
BRC (A7)
DAMP PROOF COURSE
ANTI-TERMITE
REINFORCED CONCRETE (GRADE 30)
GROOVE LINE
Steel Roof Structure
ROOF COVERING
ROOF INSULATION
WATERPROOFING SYSTEM
RAINWATER DOWNPIPE
GUTTER
PULL OUT TEST
FASCIA BOARD
FORMWORK IN METER
TREAD
RISER
SOFFIT
STRING
RAIL POST
HAND RAILING
MS MESH
TILES NOSING
BRICKWORK
BLOCKWORK
DRY WALL
BONDING TIES
GLASS BLOCK
BRICKWORK
BLOCKWORK (2 HOURS FIRE RATED)
LINTEL
SINGLE LEAF TIMBER DOOR (D1)
SINGLE LEAF TIMBER DOOR (D1a)
DOUBLE LEAF TIMBER DOOR (D2)
DOUBLE LEAF TIMBER DOOR (D3)
DOUBLE LEAF TIMBER DOOR (D4)
DOUBLE LEAF TIMBER DOOR (D4a)
ALUMINIUM LOUVERED COMPOSITE DOOR (FD1)
ALUMINIUM LOUVERED COMPOSITE DOOR (FD2)
ALUMINIUM LOUVERED COMPOSITE DOOR (F4)
ALUMINIUM FRAME SLIDING DOOR (SD1)
ALUMINIUM FRAME SLIDING DOOR (SD2)
ALUMINIUM FRAME SLIDING DOOR (SD3)
ROLLER SHUTTER (RS1)
ROLLER SHUTTER (RS2)
FIRE RATED DOOR
LINTEL
(W1)
(W1a)
(W1b)
(W2)
(W2a)
(W2b)
(W3a)
(W4)
(W4a)
(W5)
(W7)
CEMENT RENDER
HARDENER
TILES 600MM
TILES 3000MM
Skirting (600mm x 100mm)
Skirting (300mm x 100mm)
PLASTERING
PAINTING
PERFORATED CEILING BOARD
SKIM COAT
ALUMINIUM STRIP CEILING
CEMENT BOARD
STONE COAT FINISH
COLUMN FINISHES
HOSEREEL
ALUMINIUM LOUVRES
5700mm x 600mm
11650mm x 600mm
14850mm x 393mm
8800mm x 393mm
15300mm x 600mm
18150mm x 600mm
12300mm x750mm
12200mm x 393mm
12300mm x 600mm
12300mm x 393mm
17855mm x 745mm
17850mm x 394mm
15100mm x 450mm
15100mm x 900mm
7.71
7.42
9.27
15.20
23.81
16.54
291.84
47.87
3.94
4.31
3.94
18.71
12.51
18.24
62.24
267.69
17.62
107.39
50.54
13.24
9.75
11.43
29.15
525.00
35.22
32.92
9.97
9.99
13.04
9.69
56.79
71.22
24.97
87.11
28.28
31.41
20.70
6.23
22.85
28.28
30.24
43.16
403.13
403.13
764.46
644.40
717.08
717.08
403.13
403.13
644.40
1,972.65
1,610.63
1,212.16
1,100.90
920.86
644.63
42.47
2,016.35
2,722.74
2,510.83
634.97
634.97
587.88
2,218.01
1,070.88
1,668.59
927.19
625.31
13.04
7.23
63.85
55.10
10.40
10.28
46.71
67.99
21.26
5.27
30.32
22.35
166.46
56.56
324.21

1,814.18
3,701.18
3,091.21
1,834.27
4,858.75
5,762.61
4,882.54
2,540.97
3,907.32
2,561.58
7,037.52
3,723.91
3,598.11
7,189.75
EXCAVATION REDUCE LEVEL
A EQUIPMENT
EXCAVATOR
RENTAL COST
OPERATOR
DIESEL
LUBRICATION OIL
OPERATION COST PER DAY
OPERATION COST PER HOUR

MACHINE OUTPUT m³
MACHINE OUTPUT m²
PROFIT & OVERHEAD
COST PER m²

EXCAVATION PIT
A EQUIPMENT
EXCAVATOR
RENTAL COST
OPERATOR
DIESEL
LUBRICATION OIL
OPERATION COST PER DAY
OPERATION COST PER HOUR

MACHINE OUTPUT m³
PROFIT & OVERHEAD
COST PER m³

EXCAVATION TRENCH
A EQUIPMENT
EXCAVATOR
RENTAL COST
OPERATOR
DIESEL
LUBRICATION OIL
OPERATION COST PER DAY
OPERATION COST PER HOUR

MACHINE OUTPUT m³
PROFIT & OVERHEAD
COST PER m³

HARDCORE (150mm thick)


A MATERIAL COST
MATERIAL PRICE

WASTAGE

TOTAL MATERIAL PRICE

B LABOUR COST
GENERAL LABOUR
TOTAL LABOUR COST

C EQUIPMENT
COMPACTOR
RENTAL COST (INCLUDE FUEL)
PER HOUR
PRODUCTIVITY

TOTAL COST PER m²


PROFIT & OVERHEAD
TOTAL CRANE RENTAL COST

D UNIT RATE & PROFIT


MATERIAL + EQUIPMENT COST
PROFIT & OVERHEAD
PRICE PER m²

HARDCORE (300 mm thick)


A MATERIAL COST
MATERIAL PRICE

WASTAGE

TOTAL MATERIAL PRICE

B LABOUR COST
GENERAL LABOUR
TOTAL LABOUR COST

C EQUIPMENT
COMPACTOR
RENTAL COST (INCLUDE FUEL)
PER HOUR
PRODUCTIVITY

TOTAL COST PER m²


PROFIT & OVERHEAD
TOTAL CRANE RENTAL COST

D UNIT RATE & PROFIT


MATERIAL + EQUIPMENT COST
PROFIT & OVERHEAD
PRICE PER m²

LEAN CONCRETE (GRADE 15)


A MATERIAL COST
CEMENT
SAND
AGGREGATES
TOTAL MATERIAL PRICE
WASTAGE & SHRINKAGE
TOTAL MATERIAL PRICE FOR 7m³
TOTAL MATERIAL PRICE FOR 1m³
TOTAL MATERIAL PRICE FOR 1m²

B LABOUR COST
LIFTING & POURING
UNSKILL LABOUR
TOTAL LABOUR COST

C EQUIPMENT
CONCRETE MIXER
RENTAL COST
OPERATOR
DIESEL
LUBRICATION OIL
OPERATION COST PER DAY
OPERATION COST PER HOUR

MACHINE OUTPUT m²
TOTAL COST PER m²

D UNIT RATE & PROFIT


MATERIAL + LABOUR + EQUIPMENT COST
PROFIT & OVERHEAD
PRICE PER m²

REINFORCED CONCRETE (GRADE 35)


A MATERIAL COST
MATERIAL PRICE
WASTAGE
TOTAL MATERIAL PRICE

B LABOUR COST
LIFTING & POURING
UNSKILLED LABOUR
TOTAL LABOUR COST

C EQUIPMENT
MOBILE CRANE
RENTAL COST
OPERATOR
DIESEL
LUBRICATION OIL
OPERATION COST PER DAY
OPERATION COST PER HOUR

MACHINE OUTPUT m³
TOTAL COST PER m³

D UNIT RATE & PROFIT


MATERIAL + LABOUR + EQUIPMENT COST
PROFIT & OVERHEAD
PRICE PER m³

FORMWORK
A MATERIAL COST
PLYWOOD

0.06m³ OF STRUTTING
PRICE FOR 6 TIME USAGE
PRICE FOR 1 TIME USAGE
NAIL

WASTAGE
TOTAL MATERIAL PRICE

B LABOUR COST
INSTALLATION
SKILLED LABOUR
UNSKILLED LABOUR
REMOVING
UNSKILLED LABOUR
TOTAL LABOUR COST

D UNIT RATE & PROFIT


MATERIAL + LABOUR COST
PROFIT & OVERHEAD
PRICE PER m²

REINFORCEMENT HIGH TENSILE STEEL BAR (10mm & 12mm)


A MATERIAL COST
MATERIAL PRICE
WASTAGE
TOTAL MATERIAL PRICE

B LABOUR COST
SKILLED LABOUR
GENERAL WORKER
TOTAL LABOUR COST

C EQUIPMENT
CRANE
RENTAL COST ( INCLUDE FLUE)
OPERATOR
TOTAL COST PER DAY
TOTAL COST PER HOURS
PRODUCTIVITY

BENDING MACHINE & CUTTING


RENTAL COST
TOTAL COST PER DAY
TOTAL COST PER HOURS
PRODUCTIVITY

TOTAL COST
PROFIT & OVERHEAD
TOTAL EQUIPMENT COST

D UNIT RATE & PROFIT


MATERIAL + LABOUR + EQUIPMENT COST
PROFIT & OVERHEAD
PRICE PER kg

REINFORCEMENT HIGH TENSILE STEEL BAR (16mm, 20mm & 12mm)


A MATERIAL COST
MATERIAL PRICE
WASTAGE
TOTAL MATERIAL PRICE

B LABOUR COST
SKILLED LABOUR
GENERAL WORKER
TOTAL LABOUR COST

C EQUIPMENT
CRANE
RENTAL COST ( INCLUDE FLUE)
OPERATOR
TOTAL COST PER DAY
TOTAL COST PER HOURS
PRODUCTIVITY

BENDING MACHINE & CUTTING


RENTAL COST
TOTAL COST PER DAY
TOTAL COST PER HOURS
PRODUCTIVITY

TOTAL COST
PROFIT & OVERHEAD
TOTAL EQUIPMENT COST

D UNIT RATE & PROFIT


MATERIAL + LABOUR + EQUIPMENT COST
PROFIT & OVERHEAD
PRICE PER kg

REINFORCEMENT MILD STEEL BAR (6mm, 8mm & 10mm)


A MATERIAL COST
MATERIAL PRICE
WASTAGE
TOTAL MATERIAL PRICE

B LABOUR COST
SKILLED LABOUR
GENERAL WORKER
TOTAL LABOUR COST

C EQUIPMENT
CRANE
RENTAL COST ( INCLUDE FLUE)
OPERATOR
TOTAL COST PER DAY
TOTAL COST PER HOURS
PRODUCTIVITY

BENDING MACHINE & CUTTING


RENTAL COST
TOTAL COST PER DAY
TOTAL COST PER HOURS
PRODUCTIVITY

TOTAL COST
PROFIT & OVERHEAD
TOTAL EQUIPMENT COST

D UNIT RATE & PROFIT


MATERIAL + LABOUR + EQUIPMENT COST
PROFIT & OVERHEAD
PRICE PER kg

BRC (A8)
A MATERIAL COST
MATERIAL COST
LAPPING
WASTAGE
TOTAL MATERIAL PRICE

B LABOUR COST
GENERAL LABOUR
TOTAL LABOUR COST

C EQUIPMENT
CRANE
RENTAL COST ( INCLUDE FLUE)
OPERATOR
TOTAL COST PER DAY
TOTAL COST PER HOURS
PRODUCTIVITY
PROFIT OVERHEAD
TOTAL EQUIPMENT COST

D UNIT RATE & PROFIT


MATERIAL + LABOUR + EQUIPMENT COST
PROFIT & OVERHEAD
PRICE PER m²

BRC (A7)
A MATERIAL COST
MATERIAL COST
LAPPING
WASTAGE
TOTAL MATERIAL PRICE

B LABOUR COST
GENERAL LABOUR
TOTAL LABOUR COST

C EQUIPMENT
CRANE
RENTAL COST ( INCLUDE FLUE)
OPERATOR
TOTAL COST PER DAY
TOTAL COST PER HOURS
PRODUCTIVITY
PROFIT OVERHEAD
TOTAL EQUIPMENT COST

D UNIT RATE & PROFIT


MATERIAL + LABOUR + EQUIPMENT COST
PROFIT & OVERHEAD
PRICE PER m²

DAMP PROOF COURSE


A MATERIAL COST
MATERIAL PRICE
WASTAGE
TOTAL MATERIAL PRICE

B LABOUR COST
UNSKILLED LABOUR
TOTAL LABOUR COST

D UNIT RATE & PROFIT


MATERIAL + LABOUR COST
PROFIT & OVERHEAD
PRICE PER m²

ANTI-TERMITE
A MATERIAL COST
MATERIAL PRICE
WASTAGE
TOTAL MATERIAL PRICE

B LABOUR COST
UNSKILLED LABOUR
TOTAL LABOUR COST

D UNIT RATE & PROFIT


MATERIAL + EQUIPMENT COST
PROFIT & OVERHEAD
PRICE PER m²
CALCULATION RM

800.00
60.00
6 LITRE X 8 HOURS X RM2.15 103.20
2 LITRE X RM18.63 37.26
1,000.46
RM1000.46 / 8 HOURS 125.06

RM125.06 / 12m³ 10.42


RM10.42 X 0.3m² 3.13
15% X RM3.13 0.47
14.02

CALCULATION RM

800.00
60.00
6 LITRE X 8 HOURS X RM2.15 103.20
2 LITRE X RM18.63 37.26
1,000.46
RM1000.46 / 8 HOURS 125.06

RM125.06 / 10m³ 12.51


15% X RM12.51 1.88
14.39

CALCULATION RM

800.00
60.00
6 LITRE X 8 HOURS X RM2.15 103.20
2 LITRE X RM18.63 37.26
1,000.46
RM1000.46 / 8 HOURS 125.06

RM125.06 / 8m³ 15.63


15% X RM15.63 2.34
17.97

CALCULATION RM

RM 18.30 x 150/1000 2.75

5% x RM 2.75 0.14

RM2.75 + RM0.14 2.89

1 x RM60/8hrs x 0.15hr/m² 1.13


1.13

RM60/day 60.00
RM60.00 /8hour 7.50
RM 7.50/15m²/h 0.50

RM7.50 + RM 0.50 8.00


15% x RM 8.00 1.20
RM 8.00 + RM1.20 9.20

RM2.89 + RM1.13+ RM9.20 13.22


15% x RM13.22 1.98
RM13.22 + RM 1.98 15.20

CALCULATION RM

RM 32.94 x 300/1000 9.88

5% x RM 9.88 0.49

RM 9.88 + RM0.49 10.37

1 x RM60/8hrs x 0.15hr/m² 1.13


1.13
RM60/day 60.00
RM60.00 /8hour 7.50
RM 7.50/15m²/h 0.50

RM7.50 + RM 0.50 8.00


15% x RM 8.00 1.20
RM 8.00 + RM1.20 9.20

RM 10.37 + RM1.13+ RM9.20 20.70


15% x RM 20.70 3.11
RM 20.70 + RM 3.11 23.81

CALCULATION RM

1m³ x 28.7 bags x RM 18.00 516.60


2m³ x RM43.18/tonne 86.36
4m³ x RM38.64/tonne 154.56
757.52
50% x RM757.52 378.76
1,136.28
RM1,136.28 / 7m³ 162.33
RM162.33 X 0.05m² 8.12

1 x RM60.00 / 8hrs x 0.33hrs / m² 2.48


2.48

14.00
60.00
0.5 LITRE X 8 HOURS X RM1.43 5.72
0.5 LITRE X RM18.63 9.32
89.04
RM89.04 / 8 HOURS 11.13

RM11.13 X 0.34m² 3.78


3.78

RM8.12 + RM2.48 + RM2.48 14.38


15% X RM14.38 2.16
16.54

CALCULATION RM

RM220.00 / m³ 220.00
5% x RM220.00 11.00
231.00

3 x RM60.00 / 8 HOURS x 0.75 HOURS / m³ 16.88


16.88

600.00
60.00
5 LITRE X 8 HOURS X RM1.43 57.20
2 LITRE X RM18.63 37.26
754.46
RM754.46 / 8 HOURS 94.31

RM94.31 / 16m³ 5.89


5.89

RM231.00 + RM16.88 + RM5.89 253.77


15% X RM253.77 38.07
291.84

CALCULATION RM

2.4m X 1.2m = 2.88m² 35.00


1m² = RM35.00 / 2.88m² 12.15
0.06m³ / m² X RM1,920.00 / m² 82.29
94.44
RM94.44 / 6 15.74
0.35kg X RM7.00 / kg 2.47
18.21
5% X RM18.21 0.91
19.12
1 X RM90.00 / 8 HOURS X 1 HOURS 11.25
1 X RM60.00 / 8 HOURS X 0.75 HOURS 5.63

1X RM60.00 / 8 HOURS X 0.75 HOURS 5.63


22.51

RM19.12 + RM22.51 41.63


15% X RM41.63 6.24
47.87

CALCULATION RM

RM2.55/kg 2.55
5% x RM5.25 0.12
RM3.22 + RM0.16 2.67

1 x RM90/8hrs x 0.025hr/kg 0.28


1 x RM60/8hrs x 0.025hr/kg 0.19
RM0.28 + RM0.19 0.47

RM700.00 / DAY 700.00


RM60.00 / DAY 60.00
760.00
RM760.00 / 8 HOURS 95.00
RM95.00 / 1000KG 0.10

RM30.00 / DAY 30.00


RM30.00 / DAY 30.00
RM30.00 / 8 HOURS 3.75
RM3.75 / 25kg 0.15

RM0.10 + RM0.15 0.25


15% RM0.25 0.04
0.29

RM2.67 + RM0.47 + RM0.29 3.43


15% x RM3.43 0.51
3.94

CALCULATION RM

RM2.85/kg 2.85
5% x RM5.25 0.14
2.99

1 x RM90/8hrs x 0.025hr/kg 0.28


1 x RM60/8hrs x 0.025hr/kg 0.19
RM0.28 + RM0.19 0.47

RM700.00 / DAY 700.00


RM60.00 / DAY 60.00
760.00
RM760.00 / 8 HOURS 95.00
RM95.00 / 1000KG 0.10

RM30.00 / DAY 30.00


RM30.00 / DAY 30.00
RM30.00 / 8 HOURS 3.75
RM3.75 / 25kg 0.15

RM0.10 + RM0.15 0.25


15% RM0.25 0.04
0.29

RM2.99 + RM0.47 + RM0.29 3.75


15% x RM3.75 0.56
4.31

CALCULATION RM

RM2.55/kg 2.55
5% x RM5.25 0.12
RM3.22 + RM0.16 2.67
1 x RM90/8hrs x 0.025hr/kg 0.28
1 x RM60/8hrs x 0.025hr/kg 0.19
RM0.28 + RM0.19 0.47

RM700.00 / DAY 700.00


RM60.00 / DAY 60.00
760.00
RM760.00 / 8 HOURS 95.00
RM95.00 / 1000KG 0.10

RM30.00 / DAY 30.00


RM30.00 / DAY 30.00
RM30.00 / 8 HOURS 3.75
RM3.75 / 25kg 0.15

RM0.10 + RM0.15 0.25


15% RM0.25 0.04
0.29

RM2.67 + RM0.47 + RM0.29 3.43


15% x RM3.43 0.51
3.94

CALCULATION RM

RM12.80/m² 12.80
10% x RM12.80 1.28
5% x RM12.80 0.64
14.72

1 x RM60.00/8hrs x 0.19hr/m² 1.43


1.43

RM700.00 / DAY 700.00


RM60.00 / DAY 60.00
760.00
RM760.00 / 8 HOURS 95.00
RM95.00 / 1000KG 0.10
15% X RM0.10 0.02
0.12

RM14.72 + RM1.43 + RM0.12 16.27


15% x RM16.27 2.44
18.71

CALCULATION RM

RM8.11/m² 8.11
10% x RM8.11 0.81
5% x RM8.11 0.41
9.33

1 x RM60.00/8hrs x 0.19hr/m² 1.43


1.43

RM700.00 / DAY 700.00


RM60.00 / DAY 60.00
760.00
RM760.00 / 8 HOURS 95.00
RM95.00 / 1000KG 0.10
15% X RM0.10 0.02
0.12

RM9.33 + RM1.43 + RM0.12 10.88


15% x RM10.88 1.63
12.51

CALCULATION RM

RM60.00 / 4.5m² 13.33


5% X RM13.33 0.67
14.00

1 X RM60.00 / 8 HOURS X 0.25 HOURS / m² 1.86


1.86

RM14.00 + RM1.86 15.86


15% X RM15.86 2.38
18.24

CALCULATION RM

0.5 / m² 49.75
5% rm49.75 2.49
52.24

1 X RM60.00 / 8 HOURS X 0.25 1.88


1.88

RM52.24 + RM1.88 54.12


15% X RM54.12 8.12
62.24
BRICKWORK

A MATERIAL COST
MATERIAL PRICE
Clay brickwork
wastage

Exmet
Wastage

Total
C&S
Cement
sand
Total
Wastage
MATERIAL COST FOR 7m³
MATERIAL COST FOR 1m³
MATERIAL COST FOR 1m2
B LABOUR COST
SKILLED LABOUR
UNSKILLED LABOUR
TOTAL LABOUR COST
D UNIT RATE & PROFIT
MATERIAL + LABOUR COST
PROFIT & OVERHEAD
TOTAL INSTALLATION COST
CALCULATION RM

0.33
RM0.33 x 5% 0.02
0.35
RM5.00 x 0.45kg 2.25
RM2.25 x 5% 0.11
2.36
2.71

1m³ x 28.7 bags x RM 15.00 430.50


6m³ x RM75.00/tonne 450.00
880.50
RM880.50 x 5% 44.03
RM880.50 + RM44.03 924.53
RM924.53/7m³ 132.08
RM132.08x 0.050m 6.60

1 x RM90/8hrs x 0.60hrs 6.75


2 x RM60/8hrs x 0.60hrs 9.00
15.75

RM2.71 + RM6.60 + RM15.75 25.06


15% x RM25.06 3.76
RM25.06 + RM3.76 28.82
BRICKWORK

A MATERIAL COST
MATERIAL PRICE
Clay brickwork
wastage

Exmet
Wastage

Total
C&S
Cement
sand
Total
Wastage
MATERIAL COST FOR 7m³
MATERIAL COST FOR 1m³
MATERIAL COST FOR 1m2
B LABOUR COST
SKILLED LABOUR
UNSKILLED LABOUR
TOTAL LABOUR COST
D UNIT RATE & PROFIT
MATERIAL + LABOUR COST
PROFIT & OVERHEAD
TOTAL INSTALLATION COST
CALCULATION RM

0.33
RM0.33 x 5% 0.02
0.35
RM5.00 x 0.45kg 2.25
RM2.25 x 5% 0.11
2.36
2.71

1m³ x 28.7 bags x RM 15.00 430.50


6m³ x RM75.00/tonne 450.00
880.50
RM880.50 x 5% 44.03
RM880.50 + RM44.03 924.53
RM924.53/7m³ 132.08
RM132.08 x 0.050m 6.60

1 x RM90/8hrs x 0.60hrs 6.75


2 x RM60/8hrs x 0.60hrs 9.00
15.75

RM2.71 + RM6.60 + RM15.75 25.06


15% x RM25.06 3.76
RM25.06 + RM3.76 28.82
LINTEL
A MATERIAL COST
REINFORCED CONCRETE GRADE 30
FORMWORK
R12
R10
R6

WASTAGE
TOTAL MATERIAL PRICE

B LABOUR COST
SKILLED LABOUR
UNSKILLED LABOUR
TOTAL LABOUR COST

D UNIT RATE & PROFIT


MATERIAL + EQUIPMENT COST
PROFIT & OVERHEAD
PRICE PER m

ALUMINIUM FRAME GLASS DOOR (D1)


A MATERIAL COST
MATERIAL COST
ALUMINIUM FRAME GLASS DOOR

TOTAL

WASTAGE

TOTAL MATERIAL PRICE

B LABOUR COST
SKILLED LABOUR

UNSKILLED LABOUR

TOTAL LABOUR COST


D UNIT RATE & PROFIT
MATERIAL + LABOUR COST
PROFIT & OVERHEAD
PRICE

FRAMELESS GLASS DOOR (D1a)


A MATERIAL COST
MATERIAL COST
FRAMELESS GLASS DOOR

TOTAL

WASTAGE

TOTAL MATERIAL PRICE

B LABOUR COST
SKILLED LABOUR

UNSKILLED LABOUR

TOTAL LABOUR COST

D UNIT RATE & PROFIT


MATERIAL + LABOUR COST
PROFIT & OVERHEAD
PRICE

METAL FRAME SKELETON DOOR (D2)


A MATERIAL COST
MATERIAL COST
METAL FRAME SKELETON DOOR

TOTAL

WASTAGE

TOTAL MATERIAL PRICE

B LABOUR COST
SKILLED LABOUR

UNSKILLED LABOUR

TOTAL LABOUR COST

D UNIT RATE & PROFIT


MATERIAL + LABOUR COST
PROFIT & OVERHEAD
PRICE

METAL FRAME SKELETON DOOR (D3)


A MATERIAL COST
MATERIAL COST
METAL FRAME SKELETON DOOR

TOTAL

WASTAGE

TOTAL MATERIAL PRICE

B LABOUR COST
SKILLED LABOUR

UNSKILLED LABOUR

TOTAL LABOUR COST

D UNIT RATE & PROFIT


MATERIAL + LABOUR COST
PROFIT & OVERHEAD
PRICE

METAL FRAME DOUBLE LEAF DOOR (D4)


A MATERIAL COST
MATERIAL COST
METAL FRAME DOUBLE LEAF DOOR

TOTAL
WASTAGE

TOTAL MATERIAL PRICE

B LABOUR COST
SKILLED LABOUR

UNSKILLED LABOUR

TOTAL LABOUR COST

D UNIT RATE & PROFIT


MATERIAL + LABOUR COST
PROFIT & OVERHEAD
PRICE

METAL FRAME SINGLE LEAF DOOR (D5)


A MATERIAL COST
MATERIAL COST
METAL FRAME SINGLE LEAF DOOR

TOTAL

WASTAGE

TOTAL MATERIAL PRICE

B LABOUR COST
SKILLED LABOUR

UNSKILLED LABOUR

TOTAL LABOUR COST

D UNIT RATE & PROFIT


MATERIAL + LABOUR COST
PROFIT & OVERHEAD
PRICE

METAL FRAME TIMBER FLUSH DOOR (D6)


A MATERIAL COST
MATERIAL COST
METAL FRAME TIMBER FLUSH DOOR

TOTAL

WASTAGE

TOTAL MATERIAL PRICE

B LABOUR COST
SKILLED LABOUR

UNSKILLED LABOUR

TOTAL LABOUR COST

D UNIT RATE & PROFIT


MATERIAL + LABOUR COST
PROFIT & OVERHEAD
PRICE

METAL FRAME TIMBER FLUSH DOOR (D7)


A MATERIAL COST
MATERIAL COST
METAL FRAME TIMBER FLUSH DOOR

TOTAL

WASTAGE

TOTAL MATERIAL PRICE

B LABOUR COST
SKILLED LABOUR

UNSKILLED LABOUR

TOTAL LABOUR COST

D UNIT RATE & PROFIT


MATERIAL + LABOUR COST
PROFIT & OVERHEAD
PRICE

METAL FRAME DOUBLE LEAF DOOR (D8)


A MATERIAL COST
MATERIAL COST
METAL FRAME DOUBLE LEAF DOOR

TOTAL

WASTAGE

TOTAL MATERIAL PRICE

B LABOUR COST
SKILLED LABOUR

UNSKILLED LABOUR

TOTAL LABOUR COST

D UNIT RATE & PROFIT


MATERIAL + LABOUR COST
PROFIT & OVERHEAD
PRICE

METAL FRAME SINGLE LEAF DOOR (D9)


A MATERIAL COST
MATERIAL COST
METAL FRAME SINGLE LEAF DOOR

TOTAL

WASTAGE

TOTAL MATERIAL PRICE

B LABOUR COST
SKILLED LABOUR
UNSKILLED LABOUR

TOTAL LABOUR COST

D UNIT RATE & PROFIT


MATERIAL + LABOUR COST
PROFIT & OVERHEAD
PRICE

METAL FRAME SINGLE LEAF DOOR (D10)


A MATERIAL COST
MATERIAL COST
METAL FRAME SINGLE LEAF DOOR

TOTAL

WASTAGE

TOTAL MATERIAL PRICE

B LABOUR COST
SKILLED LABOUR

UNSKILLED LABOUR

TOTAL LABOUR COST

D UNIT RATE & PROFIT


MATERIAL + LABOUR COST
PROFIT & OVERHEAD
PRICE

METAL FRAME 1H FIRE RATED DOOR (FD1a)


A MATERIAL COST
MATERIAL COST
METAL FRAME 1H FIRE RATED DOOR

TOTAL

WASTAGE
TOTAL MATERIAL PRICE

B LABOUR COST
SKILLED LABOUR

UNSKILLED LABOUR

TOTAL LABOUR COST

D UNIT RATE & PROFIT


MATERIAL + LABOUR COST
PROFIT & OVERHEAD
PRICE

METAL FRAME 1H FIRE RATED DOOR (FD1a)


A MATERIAL COST
MATERIAL COST
METAL FRAME 1H FIRE RATED DOOR

TOTAL

WASTAGE

TOTAL MATERIAL PRICE

B LABOUR COST
SKILLED LABOUR

UNSKILLED LABOUR

TOTAL LABOUR COST

D UNIT RATE & PROFIT


MATERIAL + LABOUR COST
PROFIT & OVERHEAD
PRICE

METAL FRAME 1H FIRE RATED DOOR (FD1b)


A MATERIAL COST
MATERIAL COST
METAL FRAME 1H FIRE RATED DOOR

TOTAL

WASTAGE

TOTAL MATERIAL PRICE

B LABOUR COST
SKILLED LABOUR

UNSKILLED LABOUR

TOTAL LABOUR COST

D UNIT RATE & PROFIT


MATERIAL + LABOUR COST
PROFIT & OVERHEAD
PRICE

METAL FRAME 1H FIRE RATED DOOR (FD1c)


A MATERIAL COST
MATERIAL COST
METAL FRAME 1H FIRE RATED DOOR

TOTAL

WASTAGE

TOTAL MATERIAL PRICE

B LABOUR COST
SKILLED LABOUR

UNSKILLED LABOUR

TOTAL LABOUR COST

D UNIT RATE & PROFIT


MATERIAL + LABOUR COST
PROFIT & OVERHEAD
PRICE
METAL FRAME 2H FIRE RATED DOOR (FD2)
A MATERIAL COST
MATERIAL COST
METAL FRAME 1H FIRE RATED DOOR

TOTAL

WASTAGE

TOTAL MATERIAL PRICE

B LABOUR COST
SKILLED LABOUR

UNSKILLED LABOUR

TOTAL LABOUR COST

D UNIT RATE & PROFIT


MATERIAL + LABOUR COST
PROFIT & OVERHEAD
PRICE

ROLLER SHUTTER (RS1)


A MATERIAL COST
MATERIAL COST
ROLLER SHUTTER
IRONMONGERIES
TOTAL

WASTAGE

TOTAL MATERIAL PRICE

B LABOUR COST
SKILLED LABOUR

UNSKILLED LABOUR
TOTAL LABOUR COST

D UNIT RATE & PROFIT


MATERIAL + LABOUR COST
PROFIT & OVERHEAD
PRICE PER NO.

ROLLER SHUTTER (RS2)


A MATERIAL COST
MATERIAL COST
ROLLER SHUTTER
IRONMONGERIES
TOTAL

WASTAGE

TOTAL MATERIAL PRICE

B LABOUR COST
SKILLED LABOUR

UNSKILLED LABOUR

TOTAL LABOUR COST

D UNIT RATE & PROFIT


MATERIAL + LABOUR COST
PROFIT & OVERHEAD
PRICE PER NO.

ROLLER SHUTTER (RS3)


A MATERIAL COST
MATERIAL COST
ROLLER SHUTTER
IRONMONGERIES
TOTAL

WASTAGE
TOTAL MATERIAL PRICE

B LABOUR COST
SKILLED LABOUR

UNSKILLED LABOUR

TOTAL LABOUR COST

D UNIT RATE & PROFIT


MATERIAL + LABOUR COST
PROFIT & OVERHEAD
PRICE PER NO.

ROLLER SHUTTER (RS4)


A MATERIAL COST
MATERIAL COST
ROLLER SHUTTER
IRONMONGERIES
TOTAL

WASTAGE

TOTAL MATERIAL PRICE

B LABOUR COST
SKILLED LABOUR

UNSKILLED LABOUR

TOTAL LABOUR COST

D UNIT RATE & PROFIT


MATERIAL + LABOUR COST
PROFIT & OVERHEAD
PRICE PER NO.

ALUMINIUM LOUVERED COMPOSITE DOOR (SD1)


A MATERIAL COST
MATERIAL COST
ALUMINIUM LOUVERED COMPOSITE DOOR
IRONMONGERIES
TOTAL

WASTAGE

TOTAL MATERIAL PRICE

B LABOUR COST
SKILLED LABOUR

UNSKILLED LABOUR

TOTAL LABOUR COST

D UNIT RATE & PROFIT


MATERIAL + LABOUR COST
PROFIT & OVERHEAD
PRICE PER NO.

COMPOSITE DOOR (SD2)


A MATERIAL COST
MATERIAL COST
ALUMINIUM LOUVERED COMPOSITE DOOR
IRONMONGERIES
TOTAL

WASTAGE

TOTAL MATERIAL PRICE

B LABOUR COST
SKILLED LABOUR

UNSKILLED LABOUR

TOTAL LABOUR COST

D UNIT RATE & PROFIT


MATERIAL + LABOUR COST
PROFIT & OVERHEAD
PRICE PER NO.
CALCULATION RM

0.13 X 0.25 X RM230.00 7.48


RM25.90 x 0.03 m² 0.77
RM3250 / mt X 4 13.00
RM3250 / mt X 4 13.00
RM3350 / mt x 4 x 2 26.80
61.05
5% X RM61.05 3.05
64.10

RM90.00 / 8 HOURS X 0.5 HOURS 5.63


RM60.00 / 8 HOURS X 0.5 HOURS 3.75
9.38

RM64.10 + RM9.38 73.48


15% X RM73.48 11.02
84.50

CALCULATION RM

RM250 / door x 5 1,250.00

1,250.00

5% x RM1250 62.50

RM1250 + RM62.50 1,312.50

1 x RM90/8hrs 11.25

1 x RM60/8hrs 7.50

RM11.25 + RM7.50 18.75


RM1312.50 + RM18.75 1,331.25
15% x RM1331.25 199.69
RM1331.25 + RM199.69 1,530.94

CALCULATION RM

220.00

220.00

5% x RM220.00 11.00

RM220 + RM11.00 231.00

1 x RM90/8hrs 11.25

1 x RM60/8hrs 7.50

RM11.25 + RM7.50 18.75

RM231.00 + RM18.75 249.75


15% x RM249.75 37.46
RM249.75 + RM37.46 287.21

CALCULATION RM

RM193.00 x 17 3,281.00

3,281.00

5% x RM3281.00 164.05

RM3281 + RM164.05 3,445.05


1 x RM90/8hrs 11.25

1 x RM60/8hrs 7.50

RM11.25 + RM7.50 18.75

RM3445.05 + RM18.75 3,463.80


15% x RM 3463.80 519.57
RM3463.80 + RM519.57 3,983.37

CALCULATION RM

RM180.00 x 98 17,640.00

17,640.00

5% x RM17640.00 882.00

RM17640 + RM882.00 18,522.00

1 x RM90/8hrs 11.25

1 x RM60/8hrs 7.50

RM11.25 + RM7.50 18.75

RM18522.00 + RM18.75 18,540.75


15% x RM18540.75 2,781.11
RM18540.75 + RM2781.11 21,321.86

CALCULATION RM

385.00

385.00
5% x RM385.00 164.05

RM3281 + RM164.05 3,445.05

1 x RM90/8hrs 11.25

1 x RM60/8hrs 7.50

RM11.25 + RM7.50 18.75

RM3445.05 + RM18.75 3,463.80


15% x RM 3463.80 519.57
RM3463.80 + RM519.57 3,983.37

CALCULATION RM

RM385.00 x 4 1,540.00

1,540.00

5% x RM1540 77.00

RM1540 + RM77 1,617.00

1 x RM90/8hrs 11.25

1 x RM60/8hrs 7.50

RM11.25 + RM7.50 18.75

RM1617 + RM18.75 1,635.75


15% x RM1635.75 245.36
RM1635.75 + RM245.36 1,881.11

CALCULATION RM
CALCULATION RM

RM220.00 x 10 2,200.00

2,200.00

5% x RM2200.00 110.00

RM2200.00 + RM110.00 2,310.00

1 x RM90/8hrs 11.25

1 x RM60/8hrs 7.50

RM11.25 + RM7.50 18.75

RM2310 + RM18.75 2,328.75


15% x RM2328.75 349.31
RM2328.75 + RM349.31 2,678.06

CALCULATION RM

RM234.00 x 17 3,978.00

3,978.00

5% x RM3978.00 198.90

RM3978.00 + RM198.90 4,176.90

1 x RM90/8hrs 11.25

1 x RM60/8hrs 7.50

RM11.25 + RM7.50 18.75

RM4176.90 + RM18.75 4,195.65


15% x RM4195.65 629.35
RM4195.65 + RM629.35 4,825.00

CALCULATION RM

253.00

253.00

5% x RM253.00 12.65

RM253.00 + RM12.65 265.65

1 x RM90/8hrs 11.25

1 x RM60/8hrs 7.50

RM11.25 + RM7.50 18.75

RM265.65 + RM18.75 284.40


15% x RM284.40 42.66
RM284.40 + RM42.66 327.06

CALCULATION RM

385.00

385.00

5% x RM385.00 19.25

RM385.00 + RM19.25 404.25

1 x RM90/8hrs 11.25
1 x RM60/8hrs 7.50

RM11.25 + RM7.50 18.75

RM404.25 + RM18.75 423.00


15% x RM423.00 63.45
RM423.00 + RM63.45 486.45

CALCULATION RM

RM240.00 x 4 960.00

960.00

5% x RM960.00 48.00

RM960.00 + RM48.00 1,008.00

1 x RM90/8hrs 11.25

1 x RM60/8hrs 7.50

RM11.25 + RM7.50 18.75

RM1008.00 + RM18.75 1,026.75


15% x RM1026.75 154.01
RM1026.75 + RM154.01 1,180.76

CALCULATION RM

RM1800.00 x 7 12,600.00

12,600.00

5% x RM12600.00 630.00
RM1800.00 + RM630.00 13,230.00

1 x RM90/8hrs 11.25

1 x RM60/8hrs 7.50

RM11.25 + RM7.50 18.75

RM13230.00 + RM18.75 13,248.75


15% x RM13248.75 1,987.31
RM13248.75 + RM1987.31 15,236.06

CALCULATION RM

RM1800.00 x 7 12,600.00

12,600.00

5% x RM12600.00 630.00

RM1800.00 + RM630.00 13,230.00

1 x RM90/8hrs 11.25

1 x RM60/8hrs 7.50

RM11.25 + RM7.50 18.75

RM13230.00 + RM18.75 13,248.75


15% x RM13248.75 1,987.31
RM13248.75 + RM1987.31 15,236.06

CALCULATION RM
RM900.00 x 91 81,900.00

81,900.00

5% x RM81900.00 4,095.00

RM81900.00 + RM4095.00 85,995.00

1 x RM90/8hrs 11.25

1 x RM60/8hrs 7.50

RM11.25 + RM7.50 18.75

RM85995.00 + RM18.75 86,013.75


15% x RM86013.75 12,902.06
RM86013.75 + RM12902.06 98,915.81

CALCULATION RM

RM900.00 x 24 21,600.00

21,600.00

5% x RM21600.00 1,080.00

RM21600.00 + RM1080.00 22,680.00

1 x RM90/8hrs 11.25

1 x RM60/8hrs 7.50

RM11.25 + RM7.50 18.75

RM22680.00 + RM18.75 22,698.75


15% x RM22698.75 3,404.81
RM22698.75 + RM3404.81 26,103.56
CALCULATION RM

RM900.00 x 5 4,500.00

4,500.00

5% x RM4500.00 225.00

RM4500.00 + RM225.00 4,725.00

1 x RM90/8hrs 11.25

1 x RM60/8hrs 7.50

RM11.25 + RM7.50 18.75

RM4725.00 + RM18.75 4,743.75


15% x RM4743.75 711.56
RM4743.75 + RM711.56 5,455.31

CALCULATION RM

RM298 x 2 596.00
RM30/ set x 1 set 30.00
RM596 + RM30.00 626.00

5% x RM626.00 31.30

RM626.00 + RM31.30 657.30

1 x RM90/8hrs 11.25

1 x RM60/8hrs 7.50
RM11.25 + RM7.50 18.75

RM657.30 + RM18.75 676.05


15% x RM676.05 101.41
RM676.05 + RM101.41 777.46

CALCULATION RM

RM341 x 2 682.00
RM30/ set x 1 set 30.00
RM682.00 + RM30.00 712.00

5% x RM712.00 35.60

RM712.00 + RM35.60 747.60

1 x RM90/8hrs 11.25

1 x RM60/8hrs 7.50

RM11.25 + RM7.50 18.75

RM747.60 + RM18.75 766.35


15% x RM766.35 114.95
RM766.35 + RM114.95 881.30

CALCULATION RM

RM300 x 2 600.00
RM30/ set x 1 set 30.00
RM600.00 + RM30.00 630.00

5% x RM630.00 31.50
RM630.00 + RM31.50 661.50

1 x RM90/8hrs 11.25

1 x RM60/8hrs 7.50

RM11.25 + RM7.50 18.75

RM661.50 + RM18.75 680.25


15% x RM680.25 102.04
RM680.25 + RM102.04 782.29

CALCULATION RM

RM241 x 3 723.00
RM30/ set x 1 set 30.00
RM723.00 + RM30.00 753.00

5% x RM753.00 37.65

RM753.00 + RM37.65 790.65

1 x RM90/8hrs 11.25

1 x RM60/8hrs 7.50

RM11.25 + RM7.50 18.75

RM790.65 + RM18.75 809.40


15% x RM809.4 121.41
RM809.4 + RM121.41 930.81

CALCULATION RM
RM241 x 2 482.00
RM30/ set x 1 set 30.00
RM482 + RM30 512.00

5% x RM512 25.60

RM512.00 + RM25.60 537.60

1 x RM90/8hrs 11.25

1 x RM60/8hrs 7.50

RM11.25 + RM7.50 18.75

RM537.60 + RM18.75 556.35


15% x RM556.35 83.45
RM556.35 + RM83.45 639.80

CALCULATION RM

158.00
RM30/ set x 1 set 30.00
RM158.00 + RM30 188.00

5% x RM188.00 9.40

RM188.00 + RM9.40 197.40

1 x RM90/8hrs 11.25

1 x RM60/8hrs 7.50

RM11.25 + RM7.50 18.75

RM197.40 + RM18.75 216.15


15% x RM216.15 32.42
RM216.15 + RM32.42 248.57
CEMENT RENDER

A MATERIAL COST
MATERIAL PRICE
Cement
sand
Total
Wastage
MATERIAL COST FOR 4m³
MATERIAL COST FOR 1m³
MATERIAL COST FOR 1m²

B LABOUR COST
CEMENT AND SCREED MIXING
UNSKILLED LABOUR
PAVING WORKS
SKILLED LABOUR
UNSKILLED LABOUR
TOTAL LABOUR COST

C UNIT RATE & PROFIT


MATERIAL + LABOUR COST
PROFIT & OVERHEAD
TOTAL INSTALLATION COST

TILES

A MATERIAL COST
MATERIAL PRICE
TILES
Homogeneous Tiles (300mm x 300mm)

Wastage
Cost of 1m2 tile
C & S AND SCREED
Cement
sand

Wastage
MATERIAL COST FOR 4m³
MATERIAL COST FOR 1m³
MATERIAL COST FOR 1m²

B LABOUR COST
MIXING WORK
Unskilled Labour
LAYING TILES
Skilled Labour
Unskilled Labour
TOTAL LABOUR COST

C UNIT RATE & PROFIT


MATERIAL + LABOUR COST
PROFIT & OVERHEAD
TOTAL INSTALLATION COST

Skirting (150mm x 300mm)

A MATERIAL COST
MATERIAL PRICE
SKIRTING
Skirting (150mm x 300mm)

Wastage
TOTAL SKIRTING COST
C&S AND SCREED
Cement
sand

Wastage
MATERIAL COST FOR 4m³
MATERIAL COST FOR 1m³
MATERIAL COST FOR 1m2

B LABOUR COST
SKILLED LABOUR
TOTAL LABOUR COST

C UNIT RATE & PROFIT


MATERIAL + LABOUR COST
PROFIT & OVERHEAD
TOTAL INSTALLATION COST

TILES

A MATERIAL COST
MATERIAL PRICE
TILES
Ceramic Tiles (300mm x 300mm)

Wastage
Cost of 1m2 tile
C & S AND SCREED
Cement
sand

Wastage
MATERIAL COST FOR 4m³
MATERIAL COST FOR 1m³
MATERIAL COST FOR 1m²

B LABOUR COST
MIXING WORK
Unskilled Labour
LAYING TILES
Skilled Labour
Unskilled Labour
TOTAL LABOUR COST

C UNIT RATE & PROFIT


MATERIAL + LABOUR COST
PROFIT & OVERHEAD
TOTAL INSTALLATION COST

TILES

A MATERIAL COST
MATERIAL PRICE
TILES
Ceramic Tiles (300mm x 600mm)
Wastage
Cost of 1m2 tile
C & S AND SCREED
Cement
sand

Wastage
MATERIAL COST FOR 4m³
MATERIAL COST FOR 1m³
MATERIAL COST FOR 1m²

B LABOUR COST
MIXING WORK
Unskilled Labour
LAYING TILES
Skilled Labour
Unskilled Labour
TOTAL LABOUR COST

C UNIT RATE & PROFIT


MATERIAL + LABOUR COST
PROFIT & OVERHEAD
TOTAL INSTALLATION COST

TILES

A MATERIAL COST
MATERIAL PRICE
TILES
Ceramic Tiles (600mm x 600mm)

Wastage
Cost of 1m2 tile
C & S AND SCREED
Cement
sand

Wastage
MATERIAL COST FOR 4m³
MATERIAL COST FOR 1m³
MATERIAL COST FOR 1m²
B LABOUR COST
MIXING WORK
Unskilled Labour
LAYING TILES
Skilled Labour
Unskilled Labour
TOTAL LABOUR COST

C UNIT RATE & PROFIT


MATERIAL + LABOUR COST
PROFIT & OVERHEAD
TOTAL INSTALLATION COST
CALCULATION RM

1m³ x 28.7 bags x RM 15.00 430.50


3m³ x RM75.00/mt 225.00
655.50
5% X RM655.50 32.78
688.28
RM688.28/4m³ 172.07
RM172.07 x 0.020m 3.44

RM60/8hrs x 0.33hrs/m² 2.48

RM90/8hrs x 0.30hrs/m² 3.38


RM60/8hrs x 0.30hrs/m² 2.25
8.11

RM3.44 + RM8.11 11.55


15% x RM11.55 1.73
13.28

CALCULATION RM

9.40
RM9.40 / 0.09 / m² 104.44
5% X RM104.44 5.22
109.66

1m³ x 28.7 bags x RM15.00 430.50


3m³ x RM75.00/mt 225.00
655.50
5% X RM655.50 32.78
688.28
RM688.28/4m³ 172.07
RM172.07 x 0.020m 3.44

RM60/8hrs x 2.0hrs/m3 x 0.020m 0.30

RM90/8hrs x 0.5hrs/m2 5.63


RM60/8hrs x 0.5hrs/m2 3.75
9.68

RM109.66 + RM3.44 + RM9.68 122.78


15% x RM122.78 18.42
141.20

CALCULATION RM

9.40

RM9.4 x 5% 0.47
9.87

1m³ x 28.7 bags x RM 15.00 430.50


3m³ x RM75.00/tonne 225.00
655.50
RM655.50 x 5% 32.78
RM655.50 + RM32.78 688.28
RM688.28/4m³ 172.07.
RM172.07 x 0.020m 3.44

1 x RM90/8hrs x 0.30hrs/m2 3.38


3.38

RM9.87 + RM3.44 + RM3.38 16.69


15% x RM16.69 2.50
RM16.69 + RM2.50 19.19

CALCULATION RM

9.40
RM9.40 / 0.09 / m² 104.44
5% X RM104.44 5.22
109.66

1m³ x 28.7 bags x RM15.00 430.50


3m³ x RM75.00/mt 225.00
655.50
5% X RM655.50 32.78
688.28
RM688.28/4m³ 172.07
RM172.07 x 0.020m 3.44

RM60/8hrs x 2.0hrs/m3 x 0.020m 0.30

RM90/8hrs x 0.5hrs/m2 5.63


RM60/8hrs x 0.5hrs/m2 3.75
9.68

RM109.66 + RM3.44 + RM9.68 122.78


15% x RM122.78 18.42
141.20

CALCULATION RM

9.40
RM9.40 / 0.18 / m² 52.22
5% X RM52.22 2.61
54.83

1m³ x 28.7 bags x RM15.00 430.50


3m³ x RM75.00/mt 225.00
655.50
5% X RM655.50 32.78
688.28
RM688.28/4m³ 172.07
RM172.07 x 0.020m 3.44

RM60/8hrs x 2.0hrs/m3 x 0.020m 0.30

RM90/8hrs x 0.5hrs/m2 5.63


RM60/8hrs x 0.5hrs/m2 3.75
9.68

RM54.83 + RM3.44 + RM9.68 67.95


15% x RM67.95 10.19
78.14

CALCULATION RM

9.40
RM9.40 / 0.36 / m² 26.11
5% X RM26.11 1.31
27.42

1m³ x 28.7 bags x RM15.00 430.50


3m³ x RM75.00/mt 225.00
655.50
5% X RM655.50 32.78
688.28
RM688.28/4m³ 172.07
RM172.07 x 0.020m 3.44
RM60/8hrs x 2.0hrs/m3 x 0.020m 0.30

RM90/8hrs x 0.5hrs/m2 5.63


RM60/8hrs x 0.5hrs/m2 3.75
9.68

RM27.42 + RM3.44 + RM9.68 40.54


15% x RM40.54 6.08
46.62

You might also like