0% found this document useful (0 votes)
245 views1 page

Estimasi Kebutuhan Unit

The document estimates the ore hauling unit requirements for a mine over the course of a month. It provides data on inventory levels, working hours, haul distance, hauling equipment specifications, and cycle times to calculate the production rate and required number of units for each hauling equipment type. The estimates show that 12 units of Hino FM 260 JD trucks would be required to haul the 10,000 tons of ore over the month.

Uploaded by

Rachmat Risejet
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
245 views1 page

Estimasi Kebutuhan Unit

The document estimates the ore hauling unit requirements for a mine over the course of a month. It provides data on inventory levels, working hours, haul distance, hauling equipment specifications, and cycle times to calculate the production rate and required number of units for each hauling equipment type. The estimates show that 12 units of Hino FM 260 JD trucks would be required to haul the 10,000 tons of ore over the month.

Uploaded by

Rachmat Risejet
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

ESTIMASI KEBUTUHAN UNIT ORE HAULING

Inventory Ton/Month 10.000 Day PORT DIST ( M )


Working Hours 64 8 STP 15.000
Haul Distance meter 15.000

Data Satuan Dump Truck


Hino FM 260 JD Scania IVECCO NISSAN Dump Truck PS
& FOTTON PS
Jumlah Unit Unit 1 1 1 1 1
Efisiensi Kerja Asumsi 80% 80% 80% 80% 80%
Faktor Koreksi 80% 80% 80% 80% 80%
Kapasitas Vessel Ton 15 17 20 18 11
Jarak meter 15.000 15.000 15.000 15.000 15.000
Kecepatan Load m/Jam 25000 25000 25.000 25.000 25.000
Kecepatan Empty m/Jam 30000 35000 30.000 30.000 30.000
Cycle Time Load Jam 0,60 0,60 0,60 0,60 0,60
Menit 36,0 36 36 36 36
Cycle Time Empty Jam 0,50 0,43 0,50 0,50 0,50
Menit 29,00 24,86 29 29 29
Spot Time Detik 30 30 30 30 30
Dumping Time Detik 30 30 30 30 30
Undumping Time Detik 15 15 15 15 15
Cycle Time Detik 75 75 75 75 75
Menit 1,25 1,25 1,25 1,25 1,25
Total Cycle Time Menit 66,25 62,11 66,25 66,25 66,25
Produksi/Unit Ton/Hour 13,04 15,77 17,39 15,65 9,56
Total Produksi Ton/Hour 156,50 157,66 156,50 156,50 162,58
Kebutuhan 11,98 9,91 8,99 9,98 16,34
Unit
Alat 12 10 9 10 17