Kochi Water Metro Terminal Construction Methodology

This document provides a method statement for integrated shore protection work and underground sump construction for the Kochi Water Metro Project. It details the scope of work, reference documents, required machinery, materials, work methodology, responsibilities and quality assurance measures for sheet pile installation and underground sump construction.

Uploaded by

JITHESH K G GVR
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
118 views7 pages

Kochi Water Metro Terminal Construction Methodology

This document provides a method statement for integrated shore protection work and underground sump construction for the Kochi Water Metro Project. It details the scope of work, reference documents, required machinery, materials, work methodology, responsibilities and quality assurance measures for sheet pile installation and underground sump construction.

Uploaded by

JITHESH K G GVR
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
  • Machineries & Equipment: Describes the machinery and equipment required for the project along with their specifications.
  • Scope: This section details the scope of the project including the specific tasks and exclusions.
  • Reference Documents: Lists the reference documents needed for executing the project, including technical specifications and standards.
  • Purpose: This section describes the purpose of the document, focusing on integrated shore protection work and U.G. sump construction.
  • Work Methodology: Details the methods and procedures for executing the construction activities effectively.
  • Quality Assurance: Discusses the measures and standards to ensure the quality of the construction work meets project specifications.
  • Responsibility: Outlines the responsibilities of key personnel involved in the project to ensure accountability and proper execution.
  • Safety, Health & Environment: Provides guidelines and safety measures to be followed to maintain health and safety standards during the project.

MARYMATHA INFRASTRUCTURE PRIVATE QUALITY MANAGEMENT SYSTEM

LIMITED
MIPL/KWM/MS/07
Construction of Terminals for Kochi Water
Page 1 of 7
Metro Project (Phase 1 Stage 1A)

Project Title: “Construction of Terminals at Vyttila, Eroor, Kakkanad (Phase 1 Stage 1A) for
Kochi Water Metro Project”.

METHOD STATEMENT FOR INTEGRATED SHORE


PROTECTION WORK AND UG SUMP

DISCIPLINE Civil Mechanical Electrical General


Contact Document control


MS for INTEGRATED SHORE
Work: MIPL/KWM/MS/07
PROTECTION WORK AND UG SUMP

Tel: Action Required


Email:
For information For Approval 
[email protected]

Preparation & Issue

Name Position Signature Date

Prepared by QC Incharge

Reviewed by Project Manager

Approved by VP

This submission is considered ready for review and complies with contract other than stated herewith.
Approved by
(KMRL/GC)

1
MARYMATHA INFRASTRUCTURE PRIVATE QUALITY MANAGEMENT SYSTEM
LIMITED
MIPL/KWM/MS/07
Construction of Terminals for Kochi Water
Page 2 of 7
Metro Project (Phase 1 Stage 1A)

CONTENTS

Sl No. Content Page no.

01 Purpose 3

02 Scope 3

03 Reference documents 3

04 Machineries & Equipment 4

05 Materials 4

06 Work Methodology 5

07 Responsibility 6

08 Quality Assurance 6

09 Safety, Health & Environment 7

2
MARYMATHA INFRASTRUCTURE PRIVATE QUALITY MANAGEMENT SYSTEM
LIMITED
MIPL/KWM/MS/07
Construction of Terminals for Kochi Water
Page 3 of 7
Metro Project (Phase 1 Stage 1A)

1. PURPOSE:

This methodology is proposed for providing permanent shore protection using sheet piles, at
Kakkanad for Kochi Water Metro Project (Phase 1 Stage 1A).

2. SCOPE:

The scope of work includes the following

 Sheetpile permanently installed for shoring protection.

 Rcc Capping above the sheet pile.

 Grade beam construction activities

 U.G sump construction activities

3. REFERENCE DOCUMENTS:

Following documents in totality or in part shall form the reference documents


1. Technical Specification

2. GFC Drawing

3. Relevant IS Codes

4. FQP

5. SHE manual

4. LIST OF MACHINERIES & EQUIPMENTS:


Sl.No Description Type/brand Capacity
1 Escort S15 15 T
2 Welding machine Rilon 3 phase 400amps
3 Compactor Vibromax VM 115 11.5 T
4 Truck/Trailer Bharat benz dumper 572 cft
5 Movax Sany 240 24 T

3
MARYMATHA INFRASTRUCTURE PRIVATE QUALITY MANAGEMENT SYSTEM
LIMITED
MIPL/KWM/MS/07
Construction of Terminals for Kochi Water
Page 4 of 7
Metro Project (Phase 1 Stage 1A)

6 Diesel power generator Cummins 62.5kva


AQUARIUS MP-60 60 cum/hr
7 Batching plant
AQUARIUS MP-30 30cum/hr
10cum capacity – 4 Nos
8 Transit mixer Greaves 8cum capacity – 14 Nos
6 cum capacity- 02 nos
LEICA TS 06
9 Survey Instrument
Auto Level SOKKIA 1 no
10 Concrete Pump Aquarius 40cum/hr – 4Nos
Sany-36m 90cum/hr
11 Boom Placer
Putzmeister -36m 90cum/hr
12 Dewatering Pump As required 1 Hp

5.0 MATERIALS:

Sl.No Description Specification Remarks


1 Sheet Piles – Z section As per Spec
2 Reinforcement steel Fe 500D IS 1786
3 GSB MoRTH
4 Water IS 456
5 Concrete, if required as per the technical specifications
6 Welding rods Approved brands
6.0

WORK METHODOLOGY:

Preparatory Works

At present the shore is temporary protected by damaged R.R masonary. As

per the Gfc drawing the setting out will be done and if any loose rubble /placed in the setting

line that has to be remove properly for smooth erection.

Permanent Liner (Sheet Piles) Installation

Prefabricated Interlocking sheet pile of approximately 10mm thick and 12m

depth (or as per design requirement) will be driven using vibro hammer/Movax fixed on

Crane. The vertically of the sheet pile has to checked during driving process at regular

4
MARYMATHA INFRASTRUCTURE PRIVATE QUALITY MANAGEMENT SYSTEM
LIMITED
MIPL/KWM/MS/07
Construction of Terminals for Kochi Water
Page 5 of 7
Metro Project (Phase 1 Stage 1A)

interval. Consecutive sheet piles are driven by locking on the previous installed sheet pile

forming a continuous structural barrier. At top portion of the sheet pile encasing will be with

RCC coping beam of size recommended by designer. Also welding shall be done on sheet

pile joints up to water level.

U.G sump Construction

The activities involved temporary sheet piling or similar protection around the

U.G sump area to prevent the side collapsing and arresting the water seepage, Excavation,

dewatering, bottom PCC, reinforcement activity, shuttering and side supports, concreting

without construction joints and curing arrangements.

7.0 RESPONSIBILITY

 The Project Manager is wholly responsible for all the process

 The Planning Engineer is responsible for planning the works & monitoring the actual

progress with respect to the planned progress.

 The Site in charge will be responsible to ensure the proper sequence of works along

with appropriate preceding & succeeding activities and to confirm the resources

availability at site.

 The QA/QC Engineer is responsible to conduct the relevant field & laboratory tests,

and maintaining all such details in relevant records as per the ISO requirements. He

shall ensure that all tests (in house and third party) are conducted as per Quality test

plan.

 The HSE officer is responsible to examine the risk / hazard for this particular activity

and to prepare a plan to eliminate the risk/hazard and to protect the safe environment

& ensure workmen safety.

5
MARYMATHA INFRASTRUCTURE PRIVATE QUALITY MANAGEMENT SYSTEM
LIMITED
MIPL/KWM/MS/07
Construction of Terminals for Kochi Water
Page 6 of 7
Metro Project (Phase 1 Stage 1A)

 The Store in charge is responsible to procure the required materials as per the

engineer’s requirement and to keep the relevant records.

8.0 QUALITY ASSURANCE

 Sheet Piles shall be installed as accurately as possible according to drawings.

 Greater care shall be executed in respect of installation.

 If any deviation is observed the same shall be recorded and correct it as soon as

possible.

 Proper care shall be taken to ensure the correct implementation of the working

procedures described in this method statement.

9.0 SAFETY, HEALTH & ENVIRONMENT

 Working area shall be barricaded and display boards shall be provided.Lighting of 55

lux shall be provided in the working zone at night times.

 Only certified plant and machineries shall be put in operation.

 Operators shall have sufficient relevant experience and valid license to operate the

machineries.

 Safety stewards shall be engaged for monitoring to avoid unsafe conditions and

unsafe acts.

 All the staff and workmen shall be provided with personal protective equipment like

safety helmets, safety hand gloves, safety shoes, safety goggles, retro reflective

jackets and ear plugs as per the requirement.

 First aid box shall be made available at site office.

 Safety cones and flags shall be used to control the traffic.

6
MARYMATHA INFRASTRUCTURE PRIVATE QUALITY MANAGEMENT SYSTEM
LIMITED
MIPL/KWM/MS/07
Construction of Terminals for Kochi Water
Page 7 of 7
Metro Project (Phase 1 Stage 1A)

 No stranger shall be allowed in the vicinity of the working area.

 The crush zones of piling rig/cranes shall be barricaded for a distance of 1 m using

safety cones.

 The swinging area of the piling rig (especially during spoiling off) shall also be

barricaded for a distance of 2 m using safety cones.