0% found this document useful (0 votes)
83 views2 pages

Swa Bac

This document provides a status update on the expansion of the BAC documents storage project in Tuguegarao City, Cagayan, as of August 5, 2022. It details the 16 items of work required and their progress percentages. Overall, 32.8% of the project has been completed, with a total cost accomplished of 691,254.56 pesos out of the original contract value of over 2 million pesos. Several items, including ceiling, painting, tile, metal, and tinsmitry works, have not yet begun.

Uploaded by

Carjez Love
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
83 views2 pages

Swa Bac

This document provides a status update on the expansion of the BAC documents storage project in Tuguegarao City, Cagayan, as of August 5, 2022. It details the 16 items of work required and their progress percentages. Overall, 32.8% of the project has been completed, with a total cost accomplished of 691,254.56 pesos out of the original contract value of over 2 million pesos. Several items, including ceiling, painting, tile, metal, and tinsmitry works, have not yet begun.

Uploaded by

Carjez Love
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd

Name of Project : LOT II:EXPANSION OF BAC DOCUMENTS STORAGE

Location : DA-RFO 02, TUGUEGARAO CITY, CAGAYAN


Contractor : Intra Coast Construction and General Services
STATEMENT OF WORK ACCOMPLISHED
AS OF AUGUST 5, 2022

% of Accomplishment Total Project Accomplishment Total Project Cost Accomplishm


Unit Cost Total Cost Percentage
Item No. Description Unit Quantity (Ph P) (Ph P) on Total Cost This
Previous This Period To Date Previous Period To Date Previous This Period

I. GENERAL REQUIREMENTS lot 1.00 48,310.50 48,310.50 2.29 0.00 41.49 41.49 0.00 0.95 0.95 0.00 20,044.03

II. DEMOLITION WORKS lot 1.00 19,324.20 19,324.20 0.92 0.00 100.00 100.00 0.00 0.92 0.92 0.00 19,324.20

III. EARTHWORKS cu.m 67.14 870.49 58,445.01 2.77 0.00 47.00 47.00 0.00 1.30 1.30 0.00 27,469.15

IV. REINFORCING STEEL WORKS kg 7,162.34 77.11 552,304.00 26.21 0.00 68.77 68.77 0.00 18.02 18.02 0.00 379,819.46

V. CONCRETE WORKS cu.m 44.32 4,201.12 186,193.50 8.84 0.00 52.09 52.09 0.00 4.60 4.60 0.00 96,988.19

VI. MASONRY WORKS sq.mt. 200.28 1,493.97 299,212.53 14.20 0.00 34.64 34.64 0.00 4.92 4.92 0.00 103,647.22

VII. FORMWORKS AND SCAFFOLDS lot 1.00 81,608.51 81,608.51 3.87 0.00 49.95 49.95 0.00 1.93 1.93 0.00 40,763.45

VIII. CEILING WORKS sq.m 91.12 1,086.24 98,978.17 4.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

IX. PAINTING WORKS sq.m 590.49 219.05 129,347.74 6.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

X. TILE WORKS sq.m 90.99 1,339.57 121,887.40 5.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

XI. METAL WORKS lot 1.00 139,385.94 139,385.94 6.61 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

XII. TINSMITRY WORKS lot 56.00 2,317.41 129,775.05 6.16 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

XIII. DOORS AND WINDOWS lot 1.00 65,609.04 65,609.04 3.11 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

XIV. RAILING lot 1.00 33,484.01 33,484.01 1.59 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

XV. PLUMBING lot 1.00 6,710.81 6,710.81 0.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

XVI. ELECTRICAL lot 1.00 136,703.01 136,703.01 6.49 0.00 2.34 2.34 0.00 0.15 0.15 0.00 3,198.85
Total 2,107,279.42 100.00 - 32.80 32.80 0.00 691,254.56
Original Contract Value
Total Cost of Change Order 1 -
New Contract Value
Percent Change in Original Contract Value
Original No. of Days Contracted Period
No. of Days Extension/Reduction of Contract Time Allowed this Change -
Total Days of Contract Time to Date

Prepared by: Checked/Reviewed by: Recommending Approval Approved By;

FRANCIS B. GUMABAY RUBEN B. CUBERO, JR. ROSE MARY G. AQUINO NARCISO A. EDILLO, Ma.Ed.
Architect I Chief, GSO OIC-RTD, Research and Regulatory Regional Executive Director

KATHRINE BACUNOT ALLANJAY JOEL PASCUA JAYSON CASTRO


JENNYDINE GRANDE GENERWIN ARELLANO JHUNE URABA
KYLA MAE PAMITTAN
On-The-Job-Trainees
Total Project Cost Accomplishment

To Date

20,044.03

19,324.20

27,469.15

379,819.46

96,988.19

103,647.22

40,763.45

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

3,198.85
691,254.56

You might also like