Name of Project : LOT II:EXPANSION OF BAC DOCUMENTS STORAGE
Location : DA-RFO 02, TUGUEGARAO CITY, CAGAYAN
Contractor : Intra Coast Construction and General Services
STATEMENT OF WORK ACCOMPLISHED
AS OF AUGUST 5, 2022
% of Accomplishment Total Project Accomplishment Total Project Cost Accomplishm
Unit Cost Total Cost Percentage
Item No. Description Unit Quantity (Ph P) (Ph P) on Total Cost This
Previous This Period To Date Previous Period To Date Previous This Period
I. GENERAL REQUIREMENTS lot 1.00 48,310.50 48,310.50 2.29 0.00 41.49 41.49 0.00 0.95 0.95 0.00 20,044.03
II. DEMOLITION WORKS lot 1.00 19,324.20 19,324.20 0.92 0.00 100.00 100.00 0.00 0.92 0.92 0.00 19,324.20
III. EARTHWORKS cu.m 67.14 870.49 58,445.01 2.77 0.00 47.00 47.00 0.00 1.30 1.30 0.00 27,469.15
IV. REINFORCING STEEL WORKS kg 7,162.34 77.11 552,304.00 26.21 0.00 68.77 68.77 0.00 18.02 18.02 0.00 379,819.46
V. CONCRETE WORKS cu.m 44.32 4,201.12 186,193.50 8.84 0.00 52.09 52.09 0.00 4.60 4.60 0.00 96,988.19
VI. MASONRY WORKS sq.mt. 200.28 1,493.97 299,212.53 14.20 0.00 34.64 34.64 0.00 4.92 4.92 0.00 103,647.22
VII. FORMWORKS AND SCAFFOLDS lot 1.00 81,608.51 81,608.51 3.87 0.00 49.95 49.95 0.00 1.93 1.93 0.00 40,763.45
VIII. CEILING WORKS sq.m 91.12 1,086.24 98,978.17 4.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
IX. PAINTING WORKS sq.m 590.49 219.05 129,347.74 6.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
X. TILE WORKS sq.m 90.99 1,339.57 121,887.40 5.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
XI. METAL WORKS lot 1.00 139,385.94 139,385.94 6.61 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
XII. TINSMITRY WORKS lot 56.00 2,317.41 129,775.05 6.16 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
XIII. DOORS AND WINDOWS lot 1.00 65,609.04 65,609.04 3.11 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
XIV. RAILING lot 1.00 33,484.01 33,484.01 1.59 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
XV. PLUMBING lot 1.00 6,710.81 6,710.81 0.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
XVI. ELECTRICAL lot 1.00 136,703.01 136,703.01 6.49 0.00 2.34 2.34 0.00 0.15 0.15 0.00 3,198.85
Total 2,107,279.42 100.00 - 32.80 32.80 0.00 691,254.56
Original Contract Value
Total Cost of Change Order 1 -
New Contract Value
Percent Change in Original Contract Value
Original No. of Days Contracted Period
No. of Days Extension/Reduction of Contract Time Allowed this Change -
Total Days of Contract Time to Date
Prepared by: Checked/Reviewed by: Recommending Approval Approved By;
FRANCIS B. GUMABAY RUBEN B. CUBERO, JR. ROSE MARY G. AQUINO NARCISO A. EDILLO, Ma.Ed.
Architect I Chief, GSO OIC-RTD, Research and Regulatory Regional Executive Director
KATHRINE BACUNOT ALLANJAY JOEL PASCUA JAYSON CASTRO
JENNYDINE GRANDE GENERWIN ARELLANO JHUNE URABA
KYLA MAE PAMITTAN
On-The-Job-Trainees
Total Project Cost Accomplishment
To Date
20,044.03
19,324.20
27,469.15
379,819.46
96,988.19
103,647.22
40,763.45
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
3,198.85
691,254.56