Daily Safety
Project Name:
Date Inspection :
Item Safety and Health Issues and Concerns
The combined painting and hot work activities
conducted at the workshop area could result in the
accumulation of fumes, volatile/gas, dust and fire
potentially posing a physical injury and health risk to
workers or posible of having fire incident in the
workplace.
1 Ineffective/improper placement of vacuum.
Performing painting activities without wearing a
respirator and eye googles
No deployment of fire extinguisher, insufficient
isolatation and signage.
2 Worker applying unsafe lift of heavy load by him self
3 uncluttered tubepile on walkways
4 Getting contact with spinning / moving parts
without using PPEs, such as hand gloves,
Lifting of materials without wearing of PPE (hard
5 hat, hand gloves)
using cutting tools without wearing PPE (hand
gloves,mask and ear plug)
6
hotwork activity without control measure (no fire
blanket and fire extinguisher)
Prepared by:
Acknowledge by:
Approved by:
Daily Safety and Health Observation
Attach Photo reference
PICTURE
PICTURE
PICTURE
PICTURE
h Observation Report
Action Required/Control Measures Resolution Date
1. Firefighting equipment should be provided
for hotwork activities prior to start the
hotwork operation.
2.A system of isolation (separation of hot
work from painting work) placement of
proper barriced in working area and put-up
safety signage that will remind personnel in
line with the hazard at the area. Indicate specific date
2.1 Provision of sufficient ventilation at the based on the
workshop and redesign the placement of commitment provided
vacuum, it should be place near the welding e,g October 21, 2023
operation.
3. Air circulation (in and out) to remove
fumes or provide industrial ventilation or
vacuum to minimize the emmision of welding
fumes.
4. Issuance of Permit to work
1. Used of engineering control such as push
cart.
[Link] method of lifting and weight limit to September 8, 2023
be lifted (23 kg)
3. training for manual handling
4. Buddy system must applied for manual
handling of bulk/heavy item.
1. The (responsible process owner) shall need
to have a temporary facility for materials
storage. 2. Remove/relocate the concerned
materials at the right storage area and give
safe access to personnel.
3. Place isolation barricade and put-up a
safety signage in strategic location to September 8, 2023
communicate safety awareness regarding
"Slip, Trip and fall hazard" and "DO NOT
Leave the working areas UNTIDY".
4. The Responsible process owner shall
submit corrective action taken on or before
the said resolution date.
1. Training on power tools handling is
beneficial (power tools are dangerous to the
hand of untrained users) September 8, 2023
2. Proper selection of PPE is important
3. Never use loose clothing
1. Using of electronic chain block instead of
manual block.
2. Third party inspection to equipment September 8, 2023
2. Use of PPE
1. Proper training for handling power tools.
2. Use of PPE (hand, mask and • Use ear
plugs/muffs) September 8, 2023
3. enclosed the hotwork area and provide fire
blacket and fire extinguisher
Responsible for corrective Action
The welder, fire watcher, supervisor in
charge and to monitor and validate by
safety officer.
Worker and job performer
Project in Charge Juan Dela Cruz
Worker and job performer, supervisor
Worker and job performer, supervisor
Worker and job performer, supervisor