PE Design On
PE Design On
This document shall address the typical works for KM6 level 3 MDC iVE - PB Project.
This method statement will serve as guideline to carry out and complete the fabrication
and installation work for steel structure in construction activity. The detail of this
proposal includes type of Plants and machinery, sequence/area of works, inspection
(Quality Control) and Safety.
The Construction standard above is shown as following IMCS Specification:-
IMCS Description
Section 05_50_00_00(05500) Metal Fabrications
Section 03_15_10_00(03151) Anchor Bolts and Inserts
Section 05_12_00_00(05120) Structural Steel Framing
Section 09_91_13_00(09915) Painting Building
Section 01_81_13_00(01913) Sustainable Design Requirements.
2.0 Resources
2.1 Materials
All materials used on site must be approved type and they are as follows: -
iii. Client shall be informed of the date and time of installation works.
iv. The EHS officer shall determine the condition permissive for the
operation before proceeding with work.
v. All installation activities shall follow the approved installation
procedures and any change made prior to or during the operation
shall be agreed upon by at relevant parties.
3.3 Receiving
i. All equipment/tool delivery to site shall be informed in advance to
Kinetics management team.
ii. All materials receive at the site shall be visually inspect by site
supervisor/ engineer for any damage after unloading. Any damage
shall be taken immediately, if possible to avoid any delay of erection.
iii. Inspection for delivery on site shall be carry out the inspection
together with KINETIC QAQC & Client Representative for proper
checking before used it.
3.4 Handling
i. Person in charge or site supervisor to closely monitor the workers
involved in dismantle and installation work to ensure compliance with
safety and quality requirement onsite.
ii. Work shall be done in proper manner to prevent damage equipment
as well as the surrounding work area.
iii. Personnel handling the materials must wear gloves.
iv. Transfer the items collected to the designated demolish area.
v. Work in pairs to transfer material or heavy items.
3.5 Storage
i. The materials deliver on site shall be place at storage area. The
materials shall be group, barricade and put proper barrier ownership
tag if necessary
ii. Materials are to be store in stillages and on pallets as appropriate in
a manner that prevent damage.
iii. Structure shall be supported by wood to avoid from any
starches/unlevel.
iv. Housekeeping at the end of the day.
I. Site clearing.
II. Barricade work area complete with signage and polytent.
III. Perform pre-post checklist and get the approval from EHS and Intel
PM.
No Activity Sequence
1 a) To inform related Project Manager, System Owner and KINETICS EHS
management before start work for the day.
b) To obtain the entire relevant valid EHS document before start work.
c) To assign all the workers, stuff to attend safety induction before start work.
d) Get the valid permit for the workers and machinery to enter the site.
4 To brief the workers on the job sequence and streamline their job for hazard
avoidance prior work starts.
5
Work Sequences
c) All respective parties shall be visit site for taking actual measurement of all
the steel structural measurement and dimension before fabrication to be
carried out (Filter).
e) Qualified welder shall carry out welding works and welder performance
qualification shall be submit to KSM.
f) Visual inspection will have carried out and upon request by consultant the
testing shall be carried out testing using Ultrasonic testing and magnetic
particle inspection.
Cutting
Each steel structure will be properly cut into size (to be follow with Final
Approved Design/Drawing) by Qualified and Approved Steel Fabricator using a
Good Machinery/Equipment.
Jointing
Bolt Positioning
Each bolt position at the steel structure shall be marked properly and
accordingly and shall be double check before drilling process by [Link] of
bolt position will be carried out using a suitable tool(s). Holes shall be 1/16 inch
larger than the nominal bolt diameter, Holes for cast-in-place column base
anchor bolts shall be a minimum of 5/16 inch larger than the nominal bolt
diameter and fitted with plate washers unless otherwise shown on the Drawings
cured using a suitable method accordingly before received sand blasting layer.
Steel painting
Surface Preparation
completely dry and free from burrs, weld spatter, flux, loose scale, dirt, oil,
a) SSPC-SP2 method use impact hand tools to remove stratified rust (Rust
Scale)
b) Use hand wire brushing, hand abrading, hand scraping or other non impact
methods to remove all loose mil scale, all loose or non adherent rust and all
lost paint.
c) SSPC-SP3 is power tool cleaning, which is a method of surface preparation
on steel surfaces with the use of power assisted hand [Link] use power
tools or blast cleaning as a substitute cleaning method (Brush grinder)
General Note(s)
Pre-coat Checks
a) All visible oil grease and soil shall be removed with an approved materials the
cleaned area shall than be washed in clean chloride free potable water and
allowed to dry.
Paint Mixing
b) For single packaged ready mixed materials remove a portion of liquid from
the top of the container and transfer to a clean container. Mix the remaining
portion with a clean broad strong [Link] a lifting whirling motion to
thoroughly incorporate the heavier liquid that has settled to the bottom
replace the removed portion a little at a time mixing thoroughly each time a
portion is added until the entire contents are of a uniform consistency a
boxing procedure (pouring back and forth several times to clean containers)
will assist in thorough mixing.
Painting
e) The representative of the paint manufacturer should visit the site at regular
intervals to provide technical support and shall submit a periodic report to
subcontractor /contractor confirming that painting is being carried out in
accordance with the requirements and quality of work is acceptable. An
adhesion test may be carried out if necessary.
f) The specific paint systems that shall be used are identified in the project
specifications. Application of all coating systems shall be in accordance with
the manufacturer’s instructions MSDS data sheets and project
requirements.
General Note(s)
a) After the I-beam is being install and positioning, 2 layer of finish coat shall
be
b) apply on the i-beam by using Nippon Paint (Nippon Paint 9000 Gloss Finish
- Lavender Grey-1307).
c) Allow minimum 8 hour for curing before apply finish coat.
d) Total 2 layer of finish coat shall be at least Around 30 - 35 µm per coat.
Shall carry out inspection together with Kinetics QAQC for the primer coat
thickness test.
a) The paint coats shall be applied as per project specifications and product
manufacturer’s recommendations /data sheets.
b) No mixing of different manufacturers coating in any system is permitted.
Only approved paint manufacturer products shall be applied.
c) Paint shall be applied by one or a combination of the following methods.
i- Brushing
a) Steel member will be inspect at factory for MRI, all steel structure will paint
on spot after fabrication at factory, materials will deliver and direct install on
site step by step and part by part. The complete fabrications steel member
(Pipe bridge) as provide in approve shop drawing.
b) Skill worker to mark the bolt location on the RC steel structure and beam by
laser or measurement tape to confirm the setting out point is accurate.
c) Bolt will install after RC beam, skill worker to drill the RC steel structure
after confirmation setting out with QAQC and plant bolt for steel structure
with approval epoxy chemical (Hilti RE-500).
e) Always check the alignment and tighten for bolt and nut to prevent from
rocking.
f) Site worker must always double check the position, alignment and
installation based on approval shop drawing
g) Bolt will plant to concreted roof beam by Hilti RE-500 after setting out
confirm by QAQC KSM, scissor lift or boom lift will be used for external area
installation.
h) Touch up to all damage surface with approved paint materials after steel
structure complete install to position.
Inspection of Member
b) Make sure each member is placed in its proper position in the structure and
that fillers, shims, and washers required for the type of connection are
properly used.
f) After finished the painting work, all steel member shall be checked that the
small area is painted.
a) All materials shall be place on designated area near the location for
assembly and erection.
b) Surface steel structural member shall be clean by air blowing on ground
prior for lifting works.
c) Provide dunnage underneath to avoid materials on direct contact with soil
and protect from dirt.
d) After pre-assembly check if the bolts are already snug tight condition by
using torque wrench. Mark the as applicable.
e) Lifting of painted structural shall be done with nonabrasive chocker.
f) The crane is responsible for loading or unloading structural members shall
be assigned separately prior to erection works.
g) Position the cranes on designated area. Crane 1 shall be responsible for
the pre-assembly of column and girders in ground level and assisting crane
2 for erecting frame assembly. Crane 2 shall be responsible for the erection
of frame assembly from ground level to its designated location and assisting
erection girders connection frames. Crane 3 or Boom lift shall be
responsible for the erection of girders connection to erected frames, tie
beam and bracings.
h) The ground where the crane will be position shall be stabilized. Clearance
or the crane access way shall establish and maintained the duration of
works.
Bolt Tightening
The Pipe Bridge are modified by cutting the RHS steel member to follow the
dimension as mentioned in approval drawing (to be follow with Final Approved
Design/Drawing) by using Oxy Cutting processes.
Welding works
a) The welding for RHS steel members to follow the new dimension shall be
performed in accordance.
b) Welder shall have valid qualification which have been certified by means of job
clearance card performance qualification of contract welder and certification
review and registration of project welder.
c)
Touch-up application
4. BOOM LIFT
a) Inspect the boom lift before use. Inspect any of the hydraulic hoses and
fittings for leaks. Check the air pressure in the tires.
b) Start the boom lift with no person in the basket. Operate the control panel
from the ground, checking to see that every function is in good working
order. Switch the active input to platform so you can operate the boom lift
from the basket.
c) Strap on a safety harness. When in the basket, latch the attachment of your
safety harness onto the proper attachment in the basket.
d) Examine the area around you and check for any potential hazards, such as
downed power lines, loose soil or any other obstacles. Also be sure you
steer clear of power lines as an overhead hazard.
e) Steer your boom lift into the target area, again making sure you steer clear
of any sudden hazards. Adjust the angles and height of your boom arms
accordingly. If working in a rather tight area, retracting arms in the reverse
order in which extended is an easy way to get out.
f) Perform the work required and lower the boom lift to its locked position.
Bring the arms low enough to the point where can safely exit the basket.
Shut down the boom lift at the ground.
6. DEMOBILIZATION
On the accomplishment of lifting operations, the crane's boom will be lower and
telescoped to the save length. The hydraulic outriggers will be shortened to save
length, outrigger plate/ timbers will be kept secure to the crane. Other lifting
equipment will be removed safely and stored properly. The crane and trailer/lorry
will be escorted to leave the site by traffic controller to the exit guardhouse.