Specialty Fats Project R15
Specialty Fats Project R15
Chipita S.A
Project Charter
Technical
15-04-2012
Rev. 15
Table of Contents
1. Background
1.1. Business Vision
1.2. Our Mission
1.3. Goals
1.4. Business Plan
1.5. Scope
1.6. Project Phases / Time Frame
1.7. Future Expansions
1.8. Capital Estimations
2. Project Team Structure
2.1. Project Steering Team
2.2. Project Management Team
2.3. Spin Off Teams
2.4. Consultation & Technical Support
2.5. Suppliers & Contractors
3. Project Plan
3.1. Approach
3.2. CPS
3.3. Financial Plan & Cost Tracking
3.4. Quality Plan
3.4.1. Product Quality Plan
3.4.2. Process Quality Plan
3.4.3. Project Quality Plan
4. Project Considerations
4.1. Risks / Challenges
4.2. Issues
4.3. Assumptions
4.4. Constraints
5. Appendix
5.1. Supporting Documents
1. Project Background:
To establish a successful and professional International food industries company that supply
B2B bakeries and food service customers with:
High Quality & Customized Specialty Fats.
Technical Solution Support
Customer Service Support (Product development & Logistic).
To build a complete plant with full in house capabilities to supply fats to discriminating
customers who demands the highest degree of quality, services and technical solutions.
Expandable capacity : 60K MT / Year production capability in first year expandable to 100K MT / year.
Flexibility : High degree of batch preparing flexibility (5MT / batch)
Sophistication : specialized recipe formulation for top quality product
Top design : Compliance to International Industrial Standards and Food Safety Requirements.
1.5. Scope
The project now will be executed in one phase and it will include all the facilities required for full in-
house capabilities.
Estimates Remarks
$M M SR
Land & Buildings 6.9 26
Tea Factory Land 5,200 m 2 (Adjacent to Salama) 0.5 2
Area Qualification 0.3 1
Oils Processing Building 3.2 12 Base on Ref 5 building cost
Packaging Building 2.1 8 2 levels for production + 1 Lvel utility
Raw Materials WH 0.8 3
Cold Stors 0.5 1.7
Cold Stors 0.5 1.7 Based on budgetary offer
Tanks 8.1 30.4
Raw Oils Tanks (Plant 5 x 300T & Harbour 10 x 1000T) 3.8 14.23 Based on budgetary offer
intermediate Tanks (40 x 40 T) SS 304 2.5 9.56 Based on budgetary offer
Finished Oil Tanks (10 x 40T) SS 304 0.64 2.39 Based on budgetary offer
Tanks Insulations (50 Tanks) 0.16 0.60
Agitators & Instuments 0.97 3.65
Plants & Equipmets 19.7 74
Margaine Line (40KMT) 6.7 25 Based on budgetary offer (Split 2B confirmed)
Shortening & CBS Line (20KMT) 2.4 9 Based on budgetary offer
Oils Processing Units 10.7 40 Reviwed with Pavlos
E / M works 1.7 6.5
Mechanical Works 0.80 3 Base on Ref 5 building cost
Electrical Works 0.67 2.5 Base on Ref 5 building cost
Fire Protections System & Water Tank 0.27 1
Utlities 4.8 18
Power Stations 0.67 2.5 3 x 1000kW stations
Air Compressors 0.13 0.5
Boilers 0.80 3 2 x 8T / Hr boilers
Chillers & AC 0.27 1
Stand By Power Generation 0.40 1.5 1500 kVA
Water Treatment Unit 0.27 1
Hydrogen Production unit 2.27 8.5 Based on budgetary offer
Infrastructure: 1.4 5.3 ?? To be confirmed
Roads & Drainage 0.21 0.8
Waste Water Treatment 0.53 2
offices, Restrooms & Workshops 0.13 0.5
Training Center 0.27 1
Lab Equipments 0.27 1
Others 2.8 10.5
Equipment Storage & Handling 0.07 0.25
Insurance 0.03 0.1
Design & Supervision 1.07 4
Project Mangement Fees (internal) 0.27 1.00
Trainings & Travel 0.13 0.5
Testing Materials 0.03 0.1
Custom Clearance 0.05 0.2
Equipment Rentals 0.01 0.05
Commissioning Fees 0.08 0.3
Provision 1.07 4
Total 46.0 172.4
Note: the refinery is to be equipped to refine blends and tropical oils only. Liquid oils is assumed to be supplied by Afia
(mainly Sunflower)
Project - Technical Team Structure:
1.9. Project Steering Team:
1. Walid Salah
2. Kyriakos
3. Ehab Sami Faidi
4. Omar Bayazeid
5. Mazen Badawood
6. Zalmi Fazeel
7. Matouk Moarfi
8. Amr Gadallah
9. Kostas Pikros
10. Jamal Malik
11. Saleh Faghih
Note:
Different spin off teams will be formed as required at different stages of the project to
handle one of the following requirements:
Full plan and cost tracking sheet will be prepared after the CAPEX approval
3.2. Issues
Power Supply
Waste Water Disposal
Water Supply
3.3. Constraints
3.4. Assumptions
Power Station feeding the Industrial City is already built, however, the main power cabling
and connection is still not done. This might take few months
Waste water drainage system is not yet started; according to MODON officials, the contract
is already awarded and the drainage system might not be ready before 2 years.
Water supply is not available. We assume supply by tankers as currently done in AIC (SAR 10 -12 / CM)
Source Energy, an independent energy supplier recommended by MODON is promising to start
operation by April 2013. They promise to supply Electrical Power, Steam, cold and Chilled Water.
Provision need to be made from our side to arrange for electrical supply (through our own generators
or renting from outside) and also for waste water disposal.
7 x 1,000 m3 (new)
3 x 500 m3 (from existing tanks)
Basic Agreement:
Note:
Share existing pipe lines (2 lines) to unload from ships to tanks with of 150 – 220 Ton / Hr. The following should be
considered:
These lines should be equipped with heating tracing lines to avoid solidification of hard oils.
Special cares to avoid oils mixing.
Future demands might require increasing unloading speed by increasing branching pipe lines to existing tanks. New
tanks piping should consider higher pipe sizes from the beginning.
4. Attachments
4.1. Laboratory Requirements (prepared by Zaheer)
Totally four rooms are required for Laboratory, Chemical stores and Office. The proposed dimensions are as
follows:
Analytical Laboratory 6 x 12 Meters with laboratory furniture, stools & Fume hood facility.
Manpower: Three Shift Chemists, One Microbiologist and One Laboratory Assistant.
Note:
Manpower Requirement
[Link] Designation Number
JV Production Head Count
1 Plant Manager 1
2 Production Manager 1
3 Quality Manager 1
4 Shift Supervisor 3
5 Skilled Operator 15
6 Utility 6
7 QC 3
Total 30