SITE PRACTICAL
RATE ANALYSIS OF BITUMEN MIX MATERIAL OF TANK PAD (TOTAL SCOPE-1220 MT)
A BITUMEN MIX MATERIAL
DATE TRIP/BATCH WT. in MT
5/7/2012 1 12
5/8/2012 1 20
5/9/2012 1 9
5/10/2012 2 33
5/11/2012 1 8
5/12/2012 2 31
1/14/1900 1 24
TOTAL 9 137
B COST AND AMOUNTS
B1 FUEL CONSUMPTION
TOTAL QTY. OF
DM-60 PLANT FUEL TRIP HOURS AVE. OF FUEL FUEL RATE AMTS
1 DG (125kv) DIESEL 9 6 16 864 48 41472
2 TANK BURNAL FOR HEATING L.D.O 9 6 18 972 45 43740
3 MIX. DRYER L.D.O 9 0.5 450 2025 45 91125
4 TOOL CLANING DIESEL DIESEL LS 50 50 48 2400
TOTAL 178737.00
B2 PLANT AND EQUIPMENTS
SL DESCRIPTION UNIT RATE USE
1 DG DAY 1350 7 9450
2 LOADER HOUR 1250 9 11250
3 PLANT DAY 24000 7 168000
4 DUMPER 1/2 DAY 8000 3.5 28000
5 BITUMEEN BROWSER 1/2 DAY 10000 3.5 35000
6 JEEP DAY 1000 7 7000
TOTAL 258700
B3 DATE LABOUR for laying RATE AMTS
5/6/2012 22 MDY
5/7/2012 10 MDY
5/8/2012 15 MDY
5/9/2012 63 MDY
5/10/2012 57 MDY
5/11/2012 16 MDY
5/12/2012 63 MDY
1/14/1900 23 MDY
TOTAL 269 MDY 400 107600
Note: Sand screening is being done by deparmental labour by CLIENT
TOTAL OF B B1+B2+B3 545037.00 RUPEES
TOTAL OF A 9 TRIP 137 MT
RATE PER TONNE BASIC 3978.37
10% OVER HEAD 397.84
TOTAL 4376.21
ADD 15% PROFIT 656.43
RATE PER TONNE 5032.64 RUPEES/MT
rachana rate analysis.xlsx Page 1