Method Statement for Reinforcement Steel Works
1. Introduction
1.1 Purpose: To outline the method for the installation and handling of reinforcement steel to
ensure compliance with design specifications, safety regulations, and quality standards.
1.2 Scope: This method statement covers all activities related to the handling, placing, and
securing of reinforcement steel for foundations, columns, slabs.
2. Responsibilities
2.1 Project Manager:
Ensure overall project compliance.
Provide resources and support.
2.2 Site Engineer:
Supervise reinforcement steel installation.
Verify compliance with design and specifications.
2.3 Safety Officer:
Monitor adherence to safety practices.
Conduct safety briefings and audits.
2.4 Reinforcement Steel Workers:
Follow procedures outlined in this method statement.
Report any issues or deviations.
3. Materials
3.1 Reinforcement Steel:
Approved Brand : TATA Tiscon , SAIL TMT
Grade: Fe500D
3.2 Accessories:
Binding Wire: Mild Steel Wire.
Supports: Chairs, Spacers Bars.
Cover Blocks: Concrete Cover Blocks.
4. Equipment
4.1 Tools:
Cutting Tools: Rebar cutters.
Bending Tools: Rebar benders, Manual or Hydraulic Bending Machines
4.2 Machinery:
Concrete Vibrators: For ensuring proper compaction around reinforcement.
5. Methodology
5.1 Preparation:
Review Drawings: Check reinforcement details, spacing, and cover requirements.
Site Inspection: Verify dimensions, formwork, and conditions.
5.2 Handling and Storage:
Storage: Store reinforcement With Proper cover don’t direct contact with soil to Avoid
Corrosion clean area to prevent damage.
Handling: Handle with care to prevent deformation.
5.3 Cutting and Bending:
Cutting: Measure and cut reinforcement bars according to the dimensions specified in
the drawings.
Bending: Use bending machines to shape reinforcement bars as per design requirements.
Ensure bends comply with specifications.
5.4 Installation:
Positioning: Place reinforcement steel as per the drawings, ensuring correct alignment
and spacing.
Securing: Use binding wire to tie reinforcement bars securely at intersections. Ensure
proper lapping and anchorage.
Supports and Spacers: Install supports and spacers to maintain correct cover and
alignment.
5.5 Inspection:
Pre-Pour Inspection: Check that all reinforcement is correctly placed and secured.
Ensure compliance with cover requirements.
5.6 Safety Measures:
PPE: Ensure all workers wear appropriate Personal Protective Equipment (PPE),
including gloves, helmets, and steel-toe boots.
6. Quality Control
6.1 Testing:
Material Testing: Conduct tests on reinforcement steel at site Basis Rolling Margin to
ensure Quality of Steel.
Visual Inspection: Regularly inspect reinforcement work for any defects.