JICA Clock Tower Construction Planning
JICA Clock Tower Construction Planning
Concrete - Beam & Column m3 74.0 61.6 96.8 61.6 74.0 367.9
Concrete - Pilecap m3 76.1 73.5 73.5 73.5 76.1 372.8
Reinforcement - Pier tf 18.0 16.2 20.4 16.2 18.0 88.9
Steel - Pier tf 0.0 0.0 0.0 0.0 0.0 0.0
Foundation
(1) General
The construction plan consists of two major project components of the civil works, namely, i)
new construction of the flyover, and ii) widening of the existing road including new construction
of the pedestrian bridge and re-setting of traffic signal.
Major components of the project are new construction of the bridge section (flyover) of about 3.4
km and road section including two types of civil works, namely, i) widening of the existing road
with total length of about 3.7 km, and ii) new construction of the pedestrian bridges and
Re-setting of the traffic signal.
Major components of the project and approximate work quantities are listed in Table 7.5.1.
7-56
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
The main construction work of this Project is flyover construction, which is the first of its kind in
Kampala City.
Construction work of flyover involves large-scale civil engineering works mainly with steel
material and requires bridge construction equipment. The equipment and materials are expected
to be supplied from other countries such as neighboring Kenya or South Africa.
Foundation works
The construction method of foundation works can be divided into three steps, namely:
7-57
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
Crawler Crane
Crawler Crane
CCP Pile
Substructure
The RC-Portal Type Pier will be constructed with temporary support as shown in Figure 7.5.2. It
is planned to traverse the existing arterial road which is required to be open to traffic flow even
under construction.
Superstructure
Truck Crane
PC-I girders are fabricated in the factories (pre-cast). One girder will be fabricated with the
proper length of segments in the factory and thereafter will be transported and connected to the
other girder on site.
7-58
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
After the girder is lifted up on the piers, the girder will be shifted in a lateral direction and will be
set in the right position. Consequently, the next girder will be erected in the same manner.
There are many road construction works in Uganda at the moment. Therefore, construction
equipment and materials to be used for construction are available including onshore
procurement.
However, general control and supervision are necessary because the works have to be done not as
isolated components but in parallel and in combination with the other component, which is the
bridge construction.
Base course also should be compacted by road roller macadam (12 ton
7-59
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
7-60
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
Step-2 Footing
After the aggregate bed has been compacted, concrete placing for the concrete
footing will follow in several lifts.
Step-3 Column
The RC-type Column is designed to traverse the existing arterial road which is
required to be open to traffic flow even under construction.
Re-setting of traffic signal is carried out in parallel with the road construction (i.e., Step-2 – Road
construction work). The re-setting of traffic signal work is shown as follows:
7-61
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
(1) General
As the project roads are very busy trunk roads in Kampala City, the construction works have to
be carried out without interrupting daily traffic. This will be done under well-designed method of
traffic management system organized by the contractor and MoWT in affiliation with KCC and
traffic police to secure the safety of vehicles and pedestrians as well as those of project
personnel.
The project roads are mostly 7.0 m wide, 2-lane roads which require traffic management during
the construction works. These works shall be done under one side construction method without
interrupting traffic for both directions. This method requires traffic control by contractor with
the assistance of traffic police. Since the weekday daytime traffic is large, major construction
works are required to be carried out at night and during weekends.
Project 3.7
Shoprite Jct Traffic
Improvement
Luwum Street
Nasser Road
The tentative implementation schedule of the Project is prepared taking into account the ICB
procedure. The project includes four sub-projects:
7-62
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
Flyover sub-projects:
Roads sub-projects:
9 Project 2.4 Mukwano Road Widening including Mukwano Roundabout & Nsambya
Junction Capacity Improvement, and
9 Project 3.7 Shoprite Junction Traffic Improvement
Mukwano Road Widening including roundabout and Nsambya Junction shall be scheduled to
start. Midway of its construction, the Shoprite traffic improvement shall commence. The main
objective is to allow continuity of traffic flow, i.e., as one section of the component is under
construction, the other can be utilized by the public.
The construction period for this sub-project is scheduled to last about 26 months: 12 months for
Mukwano Road widening and 20 months for Shoprite traffic improvement.
2. Transportation 3,221 t 6
4. Foundation 4,522 m 15
5. Substructure 12,013 m3 24
6. Superstructure 1,675 m 27
1. Excavation 3,260 m3 5
2. Concreting 3,150 m3 5
4. Surfacing 2,810 m3 1
5. Miscellaneous 1 L/S 1
Project 1.2 Jinja - Yusuf Lule and Mukwano - Jinja,Nile
Procurement 3,661 t 12
Transportation 3,661 t 6
Foundation 2,475 m 8
Avenue Ramp
Substructure 9,526 m3 19
Superstructure 1,687 m 27
2. Concrete 860 m3 2
4. Surfacing 560 m3 1
5. Miscellaneous 1 L/S 1
1. Excavation 5,010 m3 5
Improvement
2. Concrete 6,110 m3 4
4. Surfacing 5,570 m3 3
5. Miscellaneous 1 L/S 2
1. Excavation 2,000 m3 3
2. Concrete 3,272 m3 4
Improvement
4. Surfacing 3,926 m3 9
6. Miscellaneous 1 L/S 2
: Rainy season
7-63
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
Road maintenance activities, which are required after completion of the project, are generally
divided into two categories, i.e., routine maintenance work and periodic maintenance work. Each
maintenance work consists of the following items:
- Operation cost: Costs for electricity for street lighting, signal operation, etc,
- Clearing cost: Costs for clearing the road and bridge surfaces, drainage facilities,
traffic sign boards, traffic devices, trimming/cutting of trees/grass, etc.
- Repairing cost: Costs for pavement repair including pot hole patching and crack
sealing for AC pavement, re-painting road markings, repair of sign
boards, safety devices and traffic control facilities, repair/seal of
concrete cracks of bridge decks, handrail, girders, abutment and piers,
replacement deck drainage pipe, etc.
ii) Periodic Maintenance includes the following:
- Overlay for AC pavement (every 5 years)
- Repainting of steel girder and replacement of expansion joint of bridge which includes
reconstruction of water proofing of pavement surface, minor repair of damaged deck
girder, etc. (every 15 years)
Taking the above activities into account, the maintenance cost for the Jinja Flyover, Clock Tower
Flyover, Mukwano Road Widening and Shoprite & Clock Tower Traffic Improvement projects
were estimated as shown in Table 7.6.1.
The above cost estimate was developed based on the assumption shown in the following Table
7.6.2:
7-64
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
Currently all Pre-FS roads will be under administration of the KCC as other national roads which
are located in the city centre. The number of engineers of KCC in civil engineering sectors is a
few and their capacity is very limited. The budget of KCC for road and bridge is also very small
(refer to Section 3.2.1). Therefore, the road and bridge maintenance by KCC would not be
possible or very limited as other infrastructures. However, the GOU has planned to move the
administration of national roads and other urban trunk roads located in the city centre from KCC
to UNRA in a few years.
The GOU established UNRA in 2006 as one of the products of the road sector reforms and it
became fully operational on 1st July 2008. The UNRA is responsible for both development and
maintenance of national roads. Since the salary scale of UNRA staff is more than 5 – 7 times
higher than that of MoWT and KCC, their motivation is high and UNRA can employ the staffs
who have better capacity. In addition, EU has conducted capacity building of UNRA, including
planning and implementation of maintenance projects.
As to the maintenance budget, the GOU established Uganda Road Fund (URF) in 2008 and it has
a duty to finance the implementation of the Annual Road Maintenance Programs that are carried
out by UNRA and the other designated road agencies responsible for district, urban and
community access roads. Since the current URF is approximately US$ 100 million, it will be
sufficient to cover the maintenance cost required for the Pre-FS flyovers.
The Study Team understands that as capacity of UNRA is insufficient for steel structures
(bridges) maintenance, development of the maintenance capacity should be incorporated in the
project at the implementation stage. The Study Team also recommends that introduction of a
performance-based maintenance and management contract (PMMC) would be appropriate for the
flyover maintenance reducing life cycle costs, increasing in maintenance efficiency and reducing
the government burden.
7-65
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
8.1 INTRODUCTION
Road traffic safety is a great concern in GKMA. As part of the Study on Greater Kampala Road
Network and Transport Improvement, a road traffic safety study is conducted to improve road
traffic safety situation in GKMA.
The economic growth of Uganda has been steady since the early 1990s. While the demand for
passengers and goods transport has increased together with the growth of the economy, the road
system in GKMA is being built or improved with domestic funding as well as aid funds from
donor organizations. In recent years, income growth and improvement of transport infrastructure
have both contributed to a rapid increase in the number of motorized vehicles. As traffic volume
expanded, traffic-related problems also increased, i.e., traffic conflicts and bottlenecks became
evident and traffic accidents began to rise. On the other hand, the level of understanding and
compliance to traffic safety requirements remains very low among the public. Also, authorities
have not been always aware of their critical role in restoring traffic safety and order.
Thus, traffic accident has become a major social problem and consequently, traffic safety is now
regarded as one of the most urgent policy issues of the Government of Uganda (GOU).
The study area of the Road Traffic Safety Study follows the study area described in Chapter 1.3.2.
The related local government authorities as stakeholders of the Road Traffic Safety Study are as
follows:
The Road Traffic Safety Study focuses on the road sector, as well as on road-railway crossing.
8-1
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
The population in GKMA has increased from 2,047,000 in 2003 to 2,503,000 in 2008, with an
annual growth rate of 4.1% more than that of total national population, and reached 8.5% of the
total national population in 2008 as shown in Tables 8.2.1 and 8.2.2. Moreover, considerable
number of squatters seems to live in GKMA.
Uganda achieved annual GDP growth of around 8% from 2000 to 2008. However, GDP growth
fell to 6.2% in 2003 and 5.8% in 2004. Thereafter, GDP growth rose up again. GDP per capita,
however, is still at a low level but has increased to 626,895 Shillings (= US$ 303, US$ 1 = UShs
2,070) in 2008 as shown in Table 8.2.3.
Table 8.2.3 Gross Domestic Product and Per Capita GDP in Uganda
(Unit of GDP: Bln Shs)
GDP GDP Real Annual Per Capita GDP Per Capita GDP Real Annual
Year
(Current Price) (Constant Prices) Growth Rate (%) (Current Price) (Constant Prices) Growth Rate (%)
2000 10,030 10,297 - 437,251 448,860 -
2001 11,132 11,199 8.8 469,976 472,816 5.3
2002 11,990 11,990 7.1 490,190 490,190 3.7
2003 13,843 12,728 6.2 548,137 503,980 2.8
2004 15,271 13,467 5.8 585,622 516,420 2.5
2005 17,878 14,814 10.0 663,971 550,193 6.5
2006 20,166 15,859 7.1 725,343 570,410 3.7
2007 23,351 17,156 8.2 813,425 597,638 4.8
2008 28,340 18,582 8.3 956,081 626,895 4.9
Note: constant price are for 2002
8-2
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
1) Registered Vehicles
The estimated number of vehicles rapidly increased with high annual growth rates of 13%-23%
in recent years. Meanwhile, high annual growth rates of 17%-44% for newly registered vehicles
were recorded over the same period as shown in Table 8.2.4.
As for the annual growth of newly registered vehicles, station wagon and motorcycle record
constant high growth rates of over 30% in recent years. Alternatively, the annual growth rate of
cars is rather smaller than the average annual growth rate of newly registered vehicles as shown
in Table 8.2.5. Most of the newly registered vehicles are imported used cars except for
motorcycles.
8-3
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
The number of cars and motorcycles has increased from 59,800 and 89,200 in 2004 to 90,900
and 236,500 in 2008, respectively. In 2008, the vehicle ownership rates are 7.9 automobiles and
8.0 motorcycles per 1,000 persons as shown in Table 8.2.6.
The number of motorcycles in Uganda has rapidly increased. The share of motorcycles accounts
for over 50% of total number of vehicles in Uganda in 2008 as shown in Figure 8.2.1. Boda-boda
shares a dominant proportion of the total number of motorcycles.
100%
90%
80%
Others
70% Agric Tractors
60% Motor Cycles
Cars
50%
Mini Buses
40% Buses
30% Pick-up vans & 4-Wheel Drives
Trucks
20%
10%
0%
2004 2005 2006 2007 2008
Source: MOWT
Figure 8.2.1 Vehicle Share by Vehicle Type
Road transport shares a dominant proportion of the total transport demand in GKMA. Transport
demand of people and goods in GKMA is absolutely increasing. Minibuses/taxis, bus and
motorcycle share about 43% of total vehicle-km as commercial passenger transport while light
goods vehicles and trucks share about 35% as goods transport. Share of private passenger
transport is about 22% of total vehicle-km. Motorcycles share about 50% of commercial
passenger transport demand as shown in Table 8.2.7.
8-4
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
About 49% of total motorcycle vehicle-km is estimated as total vehicle-km on less traffic roads
as shown in Table 8.2.8. It seems that minibus and motorcycle consider roominess and flexible
access of vehicles in choosing their roads. Trunk roads with high traffic demand are mainly
covered by minibuses while collector streets with low traffic demand are covered by motorcycles
(Boda-boda).
Table 8.2.8 Estimated Total Annual Traffic by Surface Type and Traffic Range (2003)
Length Motorised Traffic Totals (million vehicle-kms)
Traffic Range in ADT
(km) exc. MC MC Inc. MC MC Share (%)
0 - 2,499 1,835 668.3 170.2 838.5 20.3
2,500 - 4,999 572 653.8 129.8 783.6 16.6
Paved 5,000 - 9,999 143 346.4 28.2 374.6 7.5
Roads 10,000 - 19,999 74 346.1 38.2 384.3 9.9
20,000 and over 22 179.4 13.7 193.1 7.1
Total 2,646 2,194.0 380.1 2,574.1 14.8
0 - 2,499 7,895 729.8 373.7 1,103.5 33.9
Unpaved 2,500 - 4,999 73 27.5 50.6 78.1 64.8
Roads 5,000 and over
Total 7,968 757.3 424.3 1,181.6 35.9
0 - 2,499 9,730 1,398 544 1,942.0 28.0
2,500 - 4,999 645 681 180 861.7 20.9
5,000 - 9,999 143 346 28 374.6 7.5
All Roads
10,000 - 19,999 74 346 38 384.3 9.9
20,000 and over 22 179 14 193.1 7.1
Total 10,614 2,951.3 804.4 3,755.7 21.4
Source: Consultancy Services for Preparation of National Transport Master Plan,
Interim Report 3 (February 2004), Tahal Consulting Engineers
Most of main radial routes from Kampala have large traffic volumes. The range of average
annual growth rates from 2001 to 2008 is from 6.6% to 16.6% except for unpaved road sections
as shown in Table 8.2.9. Outstanding growth is recorded on radial routes heading to northwest
direction such as Nansana-Busunju-Lwamata route and Busega-Mubende-Kabarole route due to
recent housing developments.
8-5
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
Table 8.2.9 Traffic Growth on Main Radial Routes from Kampala (2001/2008)
Length Daily Traffic in Veh-kms ('000) Growth Rate
Route
(km) 2001 2008 (%)
Kibuye - Entebbe Airport 36.9 383.3 733.6 9.7
Kibuye - Masaka - Lyantonde 198 822.8 1291.2 6.6
Busega - Mubende - Kabarole Brd 177.9 166.2 431.3 14.6
Nansana - Busunju - Lwamata 96.3 94.9 278 16.6
Kalerwe - Lwero - Kafu Bridge 178.5 361.7 569.8 6.7
Kalerwe - Gayaza - Kalagi 34.5 129.6 279.5 11.6
Gayaza - Zirobwe* 31.5 53.8 56.6 0.7
Mukono - Kayunga 33.8 65.4 102.1 6.6
Kayunga - Galiraya* 77.5 75.5 60.1 -3.2
Nakawa - Mukono - Njeru 71.4 455.1 923.6 10.6
Total 936.3 2,608.3 4,725.8 8.9
Note: * Unpaved sections
Source: Traffic Census on National Road Links in Central Uganda, Draft Final
Report (April 2008), Prome Consultants
Traffic accidents:
Traffic accidents refer to collisions between vehicles; between vehicles and pedestrians;
between vehicles and animals; or between vehicles and fixed obstacles.
Accident Severity:
Fatal accident: is defined as one in which death occurs on the scene of the accident
and/or within a given period of time as a result of injuries sustained in the accident.
Minor accident: is one in which a person is treated for minor injuries and released to go
home thereafter. It can also be an accident with damage only where no persons are
injured at all.
Juvenile: (As per the children statute 1997) is a person below 18 years of age.
Adult: A person aged 18 years and above as per the Constitution of Uganda.
8-6
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
25,000
20,000
15,000
No.
10,000
5,000
0
1990 1995 2000 2005 2006 2007 2008
Year
8-7
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
8
7.5
7.2
7 6.9
6.6
6.4
6 6.1
No./10,000 pop.
5 5.0
4.5 4.6 4.6
4.4
4 4.0
1 1.0
0.8 0.7 0.8 0.8 0.8
0
1995 2000 2005 2006 2007 2008
Year
800.0
700.0 709.1
600.0
572.5
533.0
No./10,000 veh.
500.0
440.0 436.6
400.0 384.7 367.4
300.0 292.6
200.0
100.0
72.9 68.7 73.3
52.9
0.0
2005 2006 2007 2008
Year
According to the Global Road Safety Partnership (GRSP) statistics, nearly 1 million people are
killed and more than 10 million people are injured in road traffic accidents in the world every
year. More than 75% of these occur in developing and transitional countries.
According to the traffic accident data of African countries (refer to Figure 8.2.5), the level of
traffic safety in Uganda is very low.
8-8
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
In terms of fatalities as against the rate of population, Uganda’s figure is 8.0 per 10,000 persons.
In terms of fatalities as against motorized vehicles including motorcycle, Uganda’s figure is 65
per 10,000 vehicles. It ranked the worst as shown in Figures 8.2.5 and 8.2.6. In comparison,
fatalities in Japan are 0.45 per 10,000 persons and 0.63 per 10,000 motorized vehicles in 2007.
35
30
25
20
15
10
0
i
e
r
ia
e
bia
ia
da
nd
C
aw
a
la
o
s
ca
a
bw
qu
ib
u
an
ll e
an
th
ric
DR
go
il a
an
i
al
as
rit
m
bi
so
ba
uw
he
nz
An
Af
az
Za
M
Ug
Na
am
ag
au
Le
m
Ta
yc
Sw
ts
h
ad
M
Zi
oz
ut
Bo
Se
M
So
M
Source: WHO
Figure 8.2.5 Road Accident Fatalities per 100,000 Population in SADC countries
70
60
50
40
30
20
10
0
i
e
r
ia
e
bia
da
nd
ia
C
aw
us
la
s
ca
a
bw
qu
ib
an
ll e
an
ric
DR
go
il a
an
m
iti
al
as
m
bi
ba
uw
he
nz
An
Af
r
az
Za
Ug
Na
am
ag
au
Ta
yc
Sw
ts
h
ad
M
Zi
oz
ut
Bo
Se
M
So
Source: WHO
Figure 8.2.6 Road Accident Fatalities per 10,000 Vehicles in SADC countries
i) Monthly Fluctuation
Figure 8.2.7 shows the monthly fluctuation of traffic accidents which occurred in
[Link] shown in this figure, December has the highest number of fatalities. January
and February have lower levels of accident in comparison with other months which
have almost equivalent level of accident indicators.
8-9
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
600
500
400
No.
300
200
100
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Month
450
400
350
300
250
No.
200
150
100
50
0
0:00
1:00
2:00
3:00
4:00
5:00
6:00
7:00
8:00
9:00
10:00
11:00
12:00
13:00
14:00
15:00
16:00
17:00
18:00
19:00
20:00
21:00
22:00
23:00
Time
As shown in this figure, in 2008, the fatal accidents accounted for about 12% of the
8-10
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
total accidents and serious and minor accidents accounted for 53% and 14% of the total,
respectively. Proportion of the serious accidents has been increasing since 2007.
100%
90%
80%
70%
60%
50%
40%
30%
20%
10%
0%
1990 1995 2000 2005 2006 2007 2008
Year
Note: Number of serious and minor injuries was combined before 2005.
Source: Traffic Accident Report, Uganda Police Force
Figure 8.2.9 Traffic Accidents by Accident Type (1990-2008)
v) Vehicle Type
Figure 8.2.10 shows the composition of traffic accident victims by road user category.
In terms of fatal accidents, 38% of traffic accident victims were pedestrians, 32% were
passengers and 13% were motorcyclists. As regards serious injury accidents, 30% of
traffic accident victims were pedestrians, 36% were passengers and 18% were
motorcyclists.
100%
90%
3,288 733
80% 934
70%
400
1,106 Pedestrians
60%
286 Pedal Cyclist
361
50% 1,910 Motor Cyclist
331 Passengers
40%
Driver
30%
1,139
3,954
20% 804
10%
133 660 202
0%
Fatal Serious Slight
vi) Ownership
Table 8.2.11 shows the composition of ownership of vehicles involved in road traffic
accidents. Almost 90% of road accidents are caused by private owned vehicles. Public
transport vehicles such as minibus and boda-boda were counted as private owned
vehicles.
8-11
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
8-12
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
7000
6000
5000
4000 Minor
No.
Serious
3000 Fatal
2000
1000
ds cles
t O es
nt
us
s
rs
Ve s
rs
k
s
les
s
s
s
cle
le
le
uc
ium nibu
bu
cle
ar
ile
pla
to
icl
nib
ic
hic
yc
c
Tr
M t go mni
hi
hi
ac
cy
ra
h
eh
He Om
lc
or
g
ve
ve
ve
i-T
Tr
En uel
rin
v
O
or
ot
da
ium ds
e
ee
d
ot
m
vy
M
F
os
od
Pe
gh
l le
o
oo
Se
M
gi n
a
p
o
Li
ro
ed
g
ur
&
nt
M
y
l-p
gh
av
Co
er
Li
a
ed
He
Du
ail
n
ria
Tr
st
de
Pe
Source: Uganda Police Traffic Department
Figure 8.2.11 Traffic Accidents by Vehicle Class (2009 Bi-annual)
Table 8.2.13 Accident Statistics on the Four Main Highways of Kampala (2008)
Highway Fatal Serious Slight Total Length (km) Acc/km
Entebbe 60 188 242 490 37 13.2
Jinja 132 363 562 1057 80 13.2
Masaka 157 272 233 662 130 5.1
Guru 145 239 219 603 332 1.8
Total 494 1062 1256 2812 579 Average:
4.9
Source: Road Safety Management Capacity Review in Uganda, Draft Final Report, Dec
2009, Consia
Composition of relevant organizations and their responsibilities on traffic safety are shown in
Figure 8.2.12.
8-13
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
Comprehensive
License
Policy Engineering Enforcement Education Propaganda Emergency
Inspection
Institution
UTODA
NAFEBO
NRSC is responsible for coordinating traffic safety efforts and reporting the entire country’s
traffic safety situation to the Government.
The functions and responsibilities of MoWT are to set strategies and policy directions, and,
through its statutory agencies, to ensure the operations and regulatory functions and duties are
being carried out.
The Uganda National Road Authority (UNRA) is responsible for managing, monitoring and
investing in transport infrastructures of its sub-sectors. The UNRA was established in 2007 as a
subordinate agency to the MoWT responsible for national road administration from planning
through construction and maintenance.
TLB is responsible for regulating operations of public service vehicles (PSV), commercial buses
8-14
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
MOE is responsible for educating and disseminating traffic laws and regulations in schools and
universities.
MOH is responsible for giving emergency treatment, supporting and curing injuries caused by
traffic accidents.
ICC –U is a non - governmental, non - profit organization that was incorporated in May 1996. It
was established in response to the escalating burden of injury in Uganda. The ICC-U addresses
injury in its broadest scope, in a scientific, sustainable, collaborative and political manner with
the guiding principles of equity and integrity.
UPF is responsible for managing and monitoring road traffic accidents and enforcing road traffic
rules and regulations. UPF consists of following departments:
UNBS is a standards-setting body. It has set several standards regarding road safety.
KCC is responsible for traffic management and road infrastructure in Kampala City.
Entebbe Municipal Council is responsible for traffic management and road infrastructure in
Entebbe Municipality.
Mukono Town Council is responsible for traffic management and road infrastructure in Mukono
Town.
Kira Town Council is responsible for traffic management and road infrastructure in Kira Town.
8-15
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
Wakiso Town Council is responsible for traffic management and road infrastructure in Wakiso
Town.
Several NGOs participated in road traffic safety development sector in Uganda. Arrive Alive
Uganda was launched in 2007 as a coalition of private companies aiming to contribute reduction
of road traffic accidents and support or oppose legislative action related to road traffic safety in
Uganda. ICC-U is a research center that conducts injury surveillance, research and advocacy.
URCS is an organization providing humanitarian support for victims of various accidents
including traffic accidents with ambulances and quality first aid kits.
RSDP was prepared in 1996 by GOU with the assistance of development partners (WB/IDA,
ADB, EU/EDF) as a 10-year road sub-sector rolling program to maintain and improve road
network including road traffic safety measures (Table 8.2.14).
Roads Development Program (RDP) is one of the road improvement projects under RSDP
founded by IDA. It has implemented several traffic safety related projects as follows:
This study was carried out under RSDP and its objective is to formulate a 3-year Road Safety
Action Plan and 5-year Road Safety Improvement Program in the following road safety areas:
8-16
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
GOU approved the 3-year Road Safety Action Plan and 5-year Road Safety Improvement
Program. Governmental departments, private sector, NGOs and other concerned organizations
started to implement the 3-year Road Safety Action Plan and 5-year Road Safety Improvement
Program under supervision and coordination of NRSC. Proposed traffic safety measures are
shown in Table 8.2.15.
Table 8.2.15 Proposed Measures by “Road Safety Audit and Improvement Study”
Sub-sector Organization/Implementation/ Infrastructure/Equipment/Activity/
Institution/Budget Human Resource
General Institution - Development of the Highway Code -
- Revised sections of the MoWT’s Road - Training staff and developing regulations
Infrastructure/Traffic Design Manual (A new traffic sign system - Implementation of physical road safety
Management together with a Traffic Signs Manual, New improvement at 12 out of the 58 black spots
manual on Safety at Road works) identified
Transport Operation - - Driver training curriculum
- Training program for driving instructors
Enforcement - - Provision of road safety enforcement
equipment to the Uganda Police
Education and - - Materials for road safety education in
Information primary schools
Campaign/Propaganda
- F/S on the establishment of a public
emergency ambulance system for Kampala
Medical Emergency District, improving the local trauma research -
and surveillance capacity of the Injury
Control Center of Mulago Referral Hospital;
updating and expanding the national trauma
care training program and setting up a
trauma surveillance system
Source: TSDP Project Appraisal Document (PAD) , WB
National Road Safety Action Plan Phase 1 was formulated under RDP by SweRoad together with
TRL. The action plan includes:
8-17
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
TSDP is the successor project to the Fourth Road Development Program (RDPP-4) planned as
one of the programs under RSDP. It is intended to support RSDP-3 aimed at improving the
sector performance through contributing jointly with other development partners in a sector-wide
approach.
TSDP consists of following five components (2011-2013) according to its project information
document:
Proposed projects and costs for the “Enhanced Road Safety” component are shown in Table
8.2.16. “Study for Road Safety Management Capacity Review in Uganda” financed by GRSF has
been conducted to prepare the proposed projects since 2009.
Road Safety Management Capacity Review in Uganda (hereinafter referred to as “RSMCR”) was
commenced in October 2009 with the objectives below. The final report is scheduled to be
submitted in March 2010.
- Review safety management capacity in Uganda in accordance with the guidelines set out in
the World Bank Transport Note TN-1; and
- Reach consensus with the government and development partners on a road safety policy and
strategy and short-term measures (action plan) by the year 2020 to overcome revealed
capacity weakness for inclusion in a forthcoming investment project, in accordance with the
World Bank guidelines.
8-18
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
RSMCR sets a target for road traffic accident reduction which is to reduce road traffic accident
fatalities to a maximum level of 1,400 fatalities by the year 2020 through the action plan.
Ten strategic objectives with corresponding projects are proposed as shown in Table 8.2.17.
Total cost of the short-term activities amounting to US$ 10.2 million is envisaged to be funded
solely by WB or co-funded with EU.
Cost
No. Projects
‘000 US$
2 Establish Road Safety Unit in UNRA (including TA and training) 300
Provide capacity building (TA and training) to Uganda Traffic Police 300
Establish Traffic Planning and Road Safety Unit in Kampala City Council (including
300
S TA and training)
Build capacity within the proposed MTRA as it will be responsible for vehicle
500
Build capacity inspection and driver testing
among road Establish general training program for road safety institutions 200
safety institutions Provide TA on road safety research
M Provide TA on vehicle inspection
Review the capacity of road safety institutions
Implement recommendations of the capacity review undertaken
L
Develop a long-term capacity plan for road safety institutions
Cost
No. Projects
‘000 US$
3 Enact legislation for driver training and testing already developed -
Review the current legislative framework for road safety and establish the legislative
100
S gaps in the Traffic and Road Safety Act 1998
Ensure necessary road safety amendments are undertaken. -
Establish legal Harmonize the regional and international traffic regulations with that of Uganda -
and regulatory
framework Monitor and evaluate the implementation of the regulations
M Review the road safety legislation and regulations and align penalties with relevant road safety risks
and strengthen the legislation accordingly
L Monitor and review the legislative setting in relation to evidence-based accident risks.
8-19
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
Cost
No. Projects
‘000 US$
4 Secure a sustainable road safety funding from Road Fund -
Establish an independent vote for road safety within the consolidated funds under the
S -
MTEF
Establish Explore other funding sources like driver testing and licensing -
sustainable Review the funding mechanisms and framework for resource allocation
financing Cooperate with development partners and international organizations to support road safety
mechanisms M
programs in the country
Cooperate with the private sector and NGOs for support and resources for road safety promotion
L Review the funding mechanisms for road safety at local government level
Cost
No. Projects
‘000 US$
Establish accident information system (crash database) and analysis tools
5 800
providing reliable and timely statistical information about road traffic accidents
S
Develop accident cost model 50
Carry out systematic accident black spot identification 100
Establish mechanisms for promoting road safety research at major universities in Uganda
Carry out a record linkage study to assess the level of underreporting
Develop a road M Carry out annual road safety performance reviews and publish annual road safety reports
safety research,
(NRSA)
monitoring and
evaluation Include road safety performance indicators in the Joint Assessment Framework.
framework Evaluate all major road safety initiatives in order to assess their outcome and impact on road
safety, and develop catalogue of interventions and their accident reducing effect
L Establish a road safety Research and Development Fund to promote and support innovations
and the participation of local research professionals
Disseminate road safety research information in a systematic manner
Cost
No. Projects
‘000 US$
Develop both targeted and mass road safety campaigns on traffic regulations and
6 600
accident risks
Develop and regularly circulate comprehensive public information and
S 400
communication on road safety
Coordinate existing and planned promotional programs by stakeholders including
Education, -
school promotion programs
promotion and
campaigns Review the mass campaign effectiveness and suggest ways of improving them
M
Review the information being disseminated with purpose of improving promotion programs
Roll out school curricula on road safety knowledge, skills and behavior countrywide
L
Review and revise education and promotion activities, and develop a new awareness program
Cost
No. Projects
‘000 US$
7 Implement the outputs of previous projects on driver training and testing 200
S Develop and consolidate the electronic driver licensing system -
Develop the curriculum for motorcycle, PSV and HGV training program 200
To improve
Interface driver permit data between the service provider with police, MoWT and NRSA
driver training
and testing M Introduce defensive driving courses for all public transport operators and heavy goods vehicle
drivers
L Evaluate driver training and testing interventions, and revise the curriculum accordingly
8-20
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
Cost
No. Projects
‘000 US$
Embrace the International Road Assessment Program (IRAP) for national road
8 -
network (UNRA)
S Implement speed management projects (demonstration projects) along the Northern 350
Corridor (3,000)
Prepare road safety plan for Kampala City 450
To develop a Emphasize road safety audits on all road maintenance and rehabilitation programs, and make
safe and well road safety audits on all new projects mandatory
managed road M
Evaluate effects of demonstration sites
network Review the IRAP methodology
Evaluate road safety engineering interventions, and revise design and operations procedures
L accordingly
Roll out design standards developed from demonstration projects
Cost
No. Projects
‘000 US$
Privatize vehicle inspection: MoWT to finalize the awarding of contract for vehicle
9 -
S inspection to service provider
Review and enhance inspection of PSVs and trucks 400
Revitalize the annual compulsory inspection of all vehicles above the age of five years
To improve M
vehicle fleet Certify and monitor private vehicle inspection operators
Review vehicle inspection schemes and procedures, and develop a long-term vehicle fleet
L
management strategy
Cost
No. Projects
‘000 US$
10 Review and implement the government rescue plan study 350
S
Develop national trauma care plan (including TA) 250
To establish Increase collaboration with NGOs on victim care and first aid training
rescue service Implement trauma care plan: Establish and/or upgrade trauma care centers along road corridors
and victim care M with high accident rates
framework Train target groups (police and taxi drivers) on first aid
L Promote and enhance research in injury prevention
Note: S: short-term (1-3 years), M: medium-term (4-6 years), L: long-term (7-9 years)
Source: Road Safety Management Capacity Review in Uganda, Final Draft Report, March 2010, Consia
6) Other Donors
GOJ/JICA granted assistance to improve several congested intersections and roads in GKMA.
The improvement included traffic safety facilities development such as traffic lights, guard block,
and street lights.
- “Road Black Spot Mapping in Uganda” which is intended to guide road users on where
accidents are more likely to occur on road sections in collaboration with Disability
Prevention and Rehabilitation Section, MOH.
- Road Safety Campaign in collaboration with MOH
EU granted a mixed long-term and short-term TA assistance including traffic safety to UNRA.
8-21
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
7) Taking into consideration the activities conducted in Uganda over the past decade, the general
trend of traffic safety in Uganda is that since the rate of traffic accidents is rapidly increasing
and the inner nature of accidents is becoming more and more serious, the required traffic
safety activities should be comprehensive and implemented in a more professional and
effective manner.
NTMP set out a framework for development of the transport sector over the next 15
years (2008-2023). It proposed traffic management and safety measures development
plan including three major safety improvement projects as listed in Table 8.2.18.
Institutional Framework:
Goals and objectives of the institutional arrangement were proposed by NTMP based
on principles of “liberalization”, “decentralization”, and “capacity building” as follows:
・ Put in place effective institutional frameworks for policy making, higher level
planning, funding and regulation of the transport sector;
・ Enhance and sustain the coordinated delivery capacity of public sector transport
actors; and
In line with above goals and objectives, the following institutions related to road traffic
safety are proposed as succession and new organizations:
The regulatory functions of TLB, Civil Aviation Authority (CAA), and Uganda
Railways Corporation (URC) are assumed to be transferred to the prospective new
institution of MTRA. MTRA is expected to ensure effective regulation of the country’s
transport sector with responsibility for licensing, economic regulation, safety and
environmental issues, and legal services pertaining to rail, waterway, and public road
passenger and freight transport sector operations.
In order to develop the capacity needed to address deteriorating traffic safety concerns
in Uganda, the functions of NRSC will be transferred to NRSA, which is expected to
have adequate resources to enforce a comprehensive safety policy framework. GOU
8-22
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
- Poor planning and/or deviation from planned activities and operations related to
policies, technical construction standards and the use of resources
- Inadequate and irregular resources for funding without clear disbursement criteria
Estimated initial costs for the new institutions over the five years by NTMP are shown
in Table 8.2.19.
Legal Framework:
NTMP proposed legal reforms in the existing transport legal framework necessary to
enable establishment of prospective organizations as shown in Table 8.2.20.
Table 8.2.20 Proposed Legal Reforms for Organizational Change in Traffic Safety by NTMP
Prospective Existing Act of Incorporation for Existing Legal Reform
Organizations Organizations Institutions
MTRA TLB, CAA, URC Traffic and Road Safety Act, 1998 Necessary
NRSA NRSC
MATA / MATE - - Not Necessary
Source: NTMP (May 2009), MoWT
8-23
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
- Improvement and signalization of junctions and upgrading road links that are under
capacity;
- Restriction of heavy vehicles from specific city center locations during day time;
- Reorganizing traffic flow patterns, like banning right turning movements where
necessary;
- Provide convenient taxi loading and unloading stops, and ban stopping at
undesignated locations;
- Reinforce speed limits with physical speed control measures, especially on through
roads in trading centers and towns. The most effective speed control measure in
Uganda is the use of humps. However, the design of humps is not standardized;
- Safe night driving depends on the night visibility of pavement markings. High
priority should be given to the application of markings with high night visibility;
- The serious safety issues associated with boda bodas must be addressed by a
combination of measures, including regulation, sensitization/education and law
enforcement; and
8-24
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
The RSIAP was proposed by MoWT as urgent national road safety improvement action
plan for the period from January 2009 to June 2009 to ensure minimization of road
traffic accident rates as shown in Table 8.2.21. The RSIAP focuses on reduction of
accident risk factors associated with public transport vehicle, impaired driving and
raising awareness of stakeholders on key aspects of road safety.
Arrive Alive Uganda prepared Uganda Road Safety Action Plan from 2006 to 2008
which introduced comprehensive approach. The Uganda Road Safety Action Plan
clearly stipulated resolution areas, monitored status and responsible organization for
each project. Outline of the Uganda Road Safety Action Plan is shown in Table 8.2.22.
8-25
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
Several traffic safety activities are implemented at each traffic safety sub-sector as
8-26
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
shown in Table 8.2.23. The activities are implemented by various traffic safety
stakeholders and involvement of the traffic safety stakeholders in the traffic safety
activities has been accelerated.
Traffic and Road Safety Act was commenced on 11 September 1998. This is the second law on
transportation and road safety in Uganda. The Traffic and Road Safety Act has been amended to
meet transitional change of the motoring society as follows:
8-27
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
- Traffic and Road Safety (Motor Vehicle Inspectors on the side of the road) Regulations, under
preparation
- Traffic and Road Safety (Driving Tests) Regulations, under preparation
- Traffic and Road Safety (Driver Examiners) Regulations, under preparation
- Traffic and Road Safety (Traffic Signs) Regulations, under preparation
- Traffic and Road Safety (Mobile Phones) Regulations, under preparation
- Traffic and Road Safety (Seat Belts) Regulations, under preparation
Successful implementation of the law and the regulations will contribute remarkably in ensuring
traffic order and safety. This, however, is not expected to be easy since there are various
regulations that require very careful implementation planning.
There are two major important tasks that should be undertaken for the successful implementation,
namely:
Even though several road traffic safety action plans are formulated in the past in Uganda, most of
the measures proposed in the action plans were not put in practice. This was mainly caused by
lack of funding and resource allocation.
Traffic safety expenditure for implementation of comprehensive traffic safety activities, both
public and private, is divided into the following six major categories:
・ Traffic Safety Agencies (Routine administrative and traffic safety activities expenditure)
Annual budget of NRSC is only 150 million Shillings.
・ Engineering (e.g., road safety audit, safe road plan and design, safe road construction, black
spot improvement, traffic management improvement, etc.). This expenditure takes a dominant
part of the whole budget for traffic safety.
・ Enforcement
・ Emergency
The following financial resources are generally utilized for traffic safety activities. The
application of these financial resources for the traffic safety activities has not been fully
implemented in Uganda:
・ National and local government budget (e.g., UNRA 913,922 million Shillings (2009/2010
draft estimates including donor fund), KCC (Works) 5,570 million Shillings (2009-2010 budget
8-28
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
cash flow))
・ Traffic fine (3,157 million Shillings (Express Penalty Scheme returns in 2008))
・ Insurance firms
Formulation of systematic traffic safety measures as well as its implementation has not been fully
realized and traffic accident situation is getting more serious due to the rapid expansion of the
motorization in GKMA. Traffic safety issues being subjected to policy consideration and
strategic planning will be identified based on the analysis of the present situation and shall be
categorized into specific themes. Three fundamental elements of traffic accident, namely: person,
vehicle and road environments, will be taken into consideration to identify policy issues.
Road traffic safety institutional capacity building, which includes human and financial resources
development, is essential besides the development of effective road traffic safety measures.
Therefore, the strategic plan is required to focus on both aspects of traffic safety, namely,
formulation and implementation of effective countermeasures and institutional development.
Figure 8.2.13 shows the issue identification flow.
Present Institutional
Setup Practical Experience in
other developed countries
Intersectoral and sectoral traffic safety problems were examined to identify policy and planning
issues based on present traffic safety situation in Uganda including accident analysis, traffic
safety measures, and traffic safety institution which are discussed in the foregoing sections.
Identified major problems and issues are summarized in Tables 8.2.24 and 8.2.25 respectively.
8-29
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
Table 8.2.24 Summary of the Current Traffic Safety Situation and Problems
Infrastructure/Traffic Driver/Vehicle Enforcement Education/Awarene Medical Emergency
Management ss Campaign
• Weak traffic safety initiative of responsible governmental agencies especially NRSC (policy making, coordination, traffic safety
awareness, traffic safety measures implementation)
• Lack of coordinating framework among traffic safety stakeholders (legislation and mandatory, etc.)
• Legal fatigue of Traffic and Road Safety Act due to rapid motorization and diversification of life style
Intersectoral • Lack of national traffic safety fundamental plan including implementation, monitoring and evaluation system
Situation and • Poor political support to traffic safety policy due to lack of awareness and consciousness on traffic safety and vested interest
Problems security
• Poor planning and implementing capacity of traffic safety measures in the responsible governmental agencies (inconsistent,
inappropriate)
• Limitation of human and financial resources
• Lack of integrated traffic safety database and its communication system (accident data, driver’s data, vehicle data, road and
traffic data, etc.)
• Lack of traffic safety research and development institute
• Lack of continuous monitoring and evaluation on the traffic safety activities
・ No independent ・ Delay of new driving ・ Insufficient ・ Inadequate ・ Undeveloped
traffic safety section test system legislation for newly consistent medical
in MoWT, UNRA introduction emerging traffic school emergency
and KCC ・ Slow transition to offence and toughen education system in the
・ Lack of computerized driving regulation and opportunity for hospitals and its
comprehensive license system penalty for flagrant children (low deployment
traffic safety ・ Lack of licensed violations (drunk school ・ No standards of
strategic plan in driver management driving, etc.) enrollment crash rescue and
engineering sector system (periodic ・ Inconsistency of ratio) evacuation
・ Lack of traffic safety renewal, etc.) enforcement ・ Lack of policy ・ Insufficient
Sectoral Institutional budget in UNRA ・ Lack of regulation (e.g., direction and training system for
Problems and KCC communication speed governors) mandate on emergency
・ New systems are system between ・ Lack of effective traffic safety medical
introduced but not computerized driving traffic regulation and school technology and
in full operation in license database and law enforcement education first-aid technique
UNRA (Road Safety related agencies plans ・ Lack of ・ Inadequate
Audit, Design such as police, ・ Lack of capacity on consistent financial
standards, etc.) courts and revenue traffic regulation and traffic safety compensation
・ Unclear regulation authority law enforcement education system for
of PSV’s passage ・ Suspension of due to inadequate system from accident victims
and parking compulsory vehicle police training nursery to due to insurance
inspection system system university system
due to lack of vehicle ・ Lack of human ・ Lack of
inspection capacity power for traffic involvement
on both human control and and
resource and enforcement institutionalizati
equipment ・ Defaulting of the on of
・ Incomplete vehicle Express Penalty community
registration system Regulations traffic safety
(owner record, owner ・ Lack of licensed ・ Unclear
inhabitancy, etc.) and driver management responsibility
communication system (violation among
system among record, etc.) concerned
related agencies ・ Lack of guidelines parties on
and standards for traffic safety
traffic control awareness
・ Corruption by site campaign and
enforcer publication
・ Non-completion of activities
the traffic accident
and enforcement
database and
communication
system
8-30
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
8-31
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
8-32
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
8-33
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
Key policy issues are identified based on identified subsector issues, and are categorized into
focus areas based on the three fundamental elements and respective responsible sectors as shown
in Table 8.2.26.
Table 8.2.26 Identification of Key Traffic Safety Policy Issues (Focus Areas)
Pre-Accident Policy Issue Post-Accident Policy
Issue
Person Vehicle Road Traffic
Environment
MoWT/UNRA/KCC 1
(Engineering) ・ Safety Road
Development
・ Effective Traffic
Management
TLB/UNBS 2a 2b
(Driver License/Vehicle ・ Driver’s License ・ Vehicle Inspection
Inspection) System System
・ Driver Education
and Management
Uganda Police Force 3 3
(Enforcement) ・ Traffic Law ・ Vehicle Registration ・ Traffic Control and ・ Accident
Enforcement System Regulation Investigation
MOES 4a
(Education) ・ School Traffic
Safety Education
NRSC (NRSA) 4b
(Awareness Campaign) ・ Awareness
Campaign/Publicity
MOH 5
(Emergency) ・ Medical Emergency
System
・ Accident Insurance
System
NRSC (NRSA) 6a Institutional Strengthening (Lead Agency Function, Laws and Regulations, etc.)
(Inter-sectional 6b Research and Development (Database, Communication System, Training System, etc.)
Themes) 6c Resource Development (Human and Finance Resource)
1 Safety Road Environment Development
2 Safety Driving and Vehicle Safety Development
a Safety Driving
b Vehicle Safety
3 Traffic Control and Enforcement Development
4 Traffic Safety Education and Awareness Campaign Development
a Traffic Safety Education
b Traffic Safety Awareness Campaign
5 Medical Emergency and Accident Victim Support System
6 Institution and Resource Development
a Administration
b Research and Development
c Resource Development
Source: JICA Study Team
Sectoral planning issues are examined within the ten identified key policy areas considering
implementation as shown in Table 8.2.27. The current traffic accident situation, existing policies
on traffic safety and experiences in other developed countries are taken into consideration.
8-34
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
8-35
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
An accurate accident costing is necessary to provide the government appropriate basis for policy
making, planning, prioritizing and investing for traffic safety. Thus, examination of appropriate
accident costing method should be established based on existing practical measures such as the
human capital method and the gross output method.
Motorization rate in Uganda has rapidly increased and the losses due to road traffic accidents are
not small in terms of the national economy. In general, from 1% to 5% of a country’s GDP is lost
to traffic accident.
ESCAP introduces simplified formula to roughly estimate ratio of economic loss to GDP as
follows:
It can be said that losses are roughly 3% in poorer developing countries and become less than 1%
for developed economies according to the formula. (Source: Road Safety in Asia and the Pacific – ESCAP
document No. E/ESCAP/MCT/SGO/9, Busan, Korea, September 2006)
As a result of the estimate, the losses due to road traffic accidents in Uganda in 2008 are roughly
2.90% of GDP.
8-36
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
8.3.1 INTRODUCTION
The purpose of the strategic plan is to formulate long-term strategies which can reduce the
number of road traffic accidents with consideration of future socio-economic situation. Moreover,
the following two areas are needed to properly address the essential elements of road traffic
safety:
1) Development of countermeasures which can mitigate road traffic accidents at present as well
as in anticipation of the highly-motorized traffic society in the future.
An overall target and sub-sector targets shall be established. Possible strategies will be developed
afterwards to achieve these set targets.
Countermeasures on Institutional
Sub-sectors Improvement
In order to show a strong policy for this strategic plan study, a numerical target will be proposed
to make it possible to estimate the socio-economic benefit of the measures.
The following two targets will be proposed for the road traffic safety strategic plan:
8-37
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
1) To reduce the number of fatalities into half (based on 2007 figures) by the year 2023 referring
to the Declaration of the 4th African Road Safety Conference held in 2007 in Accra, which
requires a half reduction in road traffic accident fatalities by 2015. This target corresponds to
three other considerations:
• the fatalities rate per 100,000 population should be less than 5.0%;
• the fatalities rate per 10,000 vehicles should be less than 36.5%; and
• a reduction of 4.2% in traffic accidents per year against previous year, in terms of number
of fatalities.
2) To strengthen the capability and functions of the organizations involved in road traffic safety,
and to develop new organizations and rules/regulations necessary to ensure sustainability of
traffic safety measures.
Basic strategies will be discussed in two areas, namely, Basic Planning Policies and
Implementation Strategies.
1) Five areas are identified for implementation of effective and efficient traffic safety measures
based on road traffic accident elements and political demarcation of government.
3) Sustainable human and financial resource development is the most important challenge of the
strategic study. Responsible organizations in government need to establish necessary
sections/committees for traffic safety development in their respective organizations. For
financial resource development, a new mechanism with private sector involvement was
examined during this strategic plan period. It is also important to fully and effectively utilize
ODA projects.
Implementation Strategies
8-38
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
Six focus areas to reduce traffic accident efficiently are selected as follows:
Sectoral strategy and target for each sub-sector are prepared based on the overall basic strategy,
target, critical issues, etc. of the strategic road traffic safety plan discussed in the preceding
sections.
Targets are set based on the present critical issues and problems facing traffic safety, and
ongoing policy of the GOU. The development process of sectoral road traffic safety strategic
plan is illustrated in Figure 8.3.2.
8-39
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
Action Program
Sector Target
Three major elements of traffic safety (person, vehicle and road environment) are aimed to
improve in this sector to establish comprehensive traffic safety policy. Traffic safety facilities in
Uganda have not been adequately developed to respond to the currently increasing number of
traffic accidents which result in high socioeconomic losses for the country. On the other hand,
road network development has been implemented in accordance with the government’s
economic development policy. More consideration for road safety should be prioritized by the
government to minimize losses of economic development.
Therefore, based on this situation, the sector goal is towards system development for a safe road
traffic environment to minimize traffic accident risk.
In line with the basic strategies discussed in the previous section, six strategies for the
engineering sector are reformulated:
(i) To improve physical road conditions (road structure and geometric) to provide safe and
comfortable driving environment;
(ii) To improve traffic control and management devices to provide safety guidance to the
drivers and road users;
(iii) To develop effective measures in line with road functions and traffic conditions
(accidents and demand);
(iv) To promote comprehensive traffic safety measures (black spot, residential areas, etc).
(v) To improve institutions (organization, rules and regulations, R&D, database, etc.) to
ensure sustainable road safety environmental development; and
8-40
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
The benefit from black spot improvement is not only limited to alleviating traffic
accident at a specific location; instead, it is expected to also provide further practical
guidelines for other black spot improvement as discussed below.
In general, accidents have been shown to be not completely randomly distributed but to
be clustered at certain locations on any road. Also, an accident study would often show
common patterns of traffic accidents. Thus, implementation of appropriate road
improvement measures developed based on results of black spot accident analyses
could prevent or mitigate similar occurrences in the future. Black spots are locations
where many of the traffic accidents occur. Thus, prioritizing treatment of these sites
would expectedly provide the highest return in terms of number of traffic accidents
avoided. Moreover, cost-effective countermeasures such as use of road signs, markings
to channel traffic through complex intersections and safe waiting areas for turning
vehicles would provide significant traffic accident alleviation. Therefore, the black spot
improvement system has to be conducted immediately as it is expected to effectively
reduce traffic accidents and is highly cost-effective as well as to accumulate and utilize
experiences and feedbacks.
(c) Training and technical upgrading system for the black spot improvement engineers
8-41
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
(c) Training and technical upgrading system for black spot improvement engineers
Also as reported from the United States, conduct of RSAs and implementation of their
recommended safety improvements in design is estimated to typically cost 5% of
overall engineering design fees. In general, design cost is 7% to 10% of the
construction cost of a road development project. When RSA is estimated at 5% of the
design cost, it is 0.35% to 0.50% of the construction cost. Therefore, if RSA is carried
out appropriately, the cost effectiveness would be quite high. So considering the huge
amount of investment in road development in the future, savings may instead be
allocated to the improvement of damaged sections. Then, the operation and
maintenance cost which accounts for a large part of road sector budget can then be
saved to enhance new road construction in the future. Based on the above discussion,
the RSA system should therefore be enhanced and implemented appropriately as soon
as possible. By doing so, improvement in cost-effectiveness of road sector development
and the reduction in traffic casualties can be expected.
8-42
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
Instruction and guidelines on adoption of basic traffic safety facilities in Uganda are
indicated in road design standards. However, since many traffic accidents occur due to
illegal overtaking, conformity to design standards and guidelines therefore is not an
absolute measure for traffic accident alleviation.
Since design standards are developed based not only on vehicle movement
characteristics but also on assumed driving behaviors, effectiveness of road safety
facilities become compromised by wrongful driving behaviors and inadequate traffic
enforcement.
In consideration of lessons learned from the past transition of the design standard and
guidelines in Uganda, simply adopting international design standards from developed
countries has not resulted in levels of safety that are achieved in the developed
countries because such standards are generally accompanied by effective enforcement,
driver training and safety education and promotion. In addition, traffic conditions and
types of traffic on the roads of Uganda are very different from those of the developed
countries.
Therefore, it is necessary to review and revise accordingly the design standards and
guidelines for more safety-conscious road and road safety facilities design based on the
abovementioned factors, as well as based on accident analysis and assessment of
relevance between the accident and road facilities.
(b) Enhancement of traffic control to respond to local characteristics and the road
8-43
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
function
(c) Promotion of smooth and comfortable road traffic and road accident prevention
measures on general roads
• Development of road facilities and traffic control facilities to enhance smooth traffic
(e) Review of design standard considering motorcycle traffic, bicycle and pedestrians
(f) Review of design standard considering variety of financial sources of urban and
local governments and traffic safety level
(b) Enhancement of traffic control in accordance with local characteristics and road
function
(c) Promotion of smooth and comfortable road traffic and road accident prevention
measures on general roads
Crossing facilities have not been installed except for those in junctions with traffic
lights. Thus, pedestrians have to cross the roads under very dangerous situations.
8-44
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
While bicycles are still considered to be an important mode of transport for daily
activities, bicycle lanes are still not properly designated on roads which often cause
traffic bottleneck and accidents.
(b) To separate car traffic from light vehicles and to develop facilities for light vehicles
(b) Separation of car traffic and development of facilities for light vehicles
8-45
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
Major issues of urban traffic safety in Uganda are mixed traffic with motorcycle traffic,
insufficient development of traffic control systems such as traffic lights and traffic signs,
frequent illegal parking on sidewalks and carriageways, undesirable driving and
walking behaviors, and lack of traffic enforcement and institutional framework
development. Therefore, timely implementation of comprehensive traffic safety
measures to meet both rapidly increasing rate of urbanization and motorization is
essential. Traffic demand management activities such as encouraging modal shift from
private to public transportation will be key countermeasures to address these urban
traffic problems.
(c) Development of parking space and strengthening of enforcement for illegal parking
(c) Development of parking space and strengthening of enforcement for illegal parking
8-46
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
organization which will be exclusively responsible for traffic safety mitigation shall be
proposed.
To increase efficiency and capacity of the traffic safety improvement system, the
following support mechanisms shall be developed:
• Post auditing monitoring to follow up the results and establish the responsible agency
(b) Follow-up on the results of post monitoring of the black spot improvement
(d) Utilization of database supporting the auditing, development of the supporting tools
and establishment of the responsible agency
8-47
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
Sector Target
Recent increment of motorization rate and various purpose vehicles has been made road traffic
situation in Uganda complicated. Meanwhile, vehicles and drivers in Uganda has not been
manage properly to maintain appropriate quality for contributing safe traffic society due to lack
of institution. It is therefore necessary to develop strict and comprehensive driver and vehicle
management system to enhance the social responsibility of the road users and operators.
In line with the basic strategies discussed in the previous section, five strategies for the Safe
Driving and Vehicle Safety sector are reformulated:
8-48
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
Periodic Driver Training System: Periodic training for drivers should be introduced in
consideration of revisions on the road traffic law and emerging road environment.
Training for Lecturer & Examiner System: Skills and knowledge upgrading system for
instructors should be introduced.
Management System for PSV and Commercial Driver: Serious traffic accidents were
caused by PSV and commercial vehicles. It is therefore necessary to develop
appropriate countermeasures.
8-49
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
8-50
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
(4) Effective and Efficient Traffic Control and Enforcement (Enforcement Sector)
Sector Target
Smooth and safety traffic flow can be achieved by proper knowledge and ability of each road
users. In this regard, traffic police needs to play important role as traffic regulator and traffic
enforcer for inappropriate road users and vehicles. Fundamental activities of the traffic police are
guiding and instructing traffic regulation to maintain road traffic order toward more effective
traffic controls. In order to ensure the effectiveness and efficiency of guiding and instructing for
traffic regulation and enforcement, human resource development program is prioritized with
focus on the violations that are causing these traffic accidents, which were identified from the
traffic accident analysis.
Planning Strategy
In line with the basic strategies discussed in the previous section, three strategies for the Safe
Enforcement sector are reformulated:
(i) To develop coordinated traffic regulation planning and implementation system among
concerned agencies
(ii) To promote efficient and effective traffic law enforcement activities
(iii) To develop human resource in combination with applications of modern science and
technology
2) Development Strategy for the Priority Program
(i) Traffic Safety Guidance for Young and Vulnerable Road Users Program
Objectives of the Program
Based on traffic accident analysis, focus was given to high risk road user group and
locations to guide and/or to educate them. Each sub-program has a specific target, i.e.,
sub-program (a) is focused on motorcycle taxi riders and pedestrians; sub-program (b)
is focused on driving at black spots and black sections; sub-program (c) is focused on
driving during peak hour; and sub-program (d) is focused on young drivers.
(b) On-site traffic safety guidance at black spots and black sections
8-51
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
(b) Presentation and exchange of views among the participants on the current situation
of traffic safety guidance and enforcement activities
(c) Presentation and exchange of views among the participants on the current issues on
traffic facilities and traffic management related to traffic safety guidance and
enforcement
(iv) Recording and Evaluation of Traffic Safety Guidance and Enforcement Activities
Program
8-52
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
(v) Human Resource Development on Traffic Safety Guidance and Enforcement Program
Objectives of the Program
Efficient and effective human resource development for traffic safety guidance and
enforcement is most crucial issues in enforcement sector in Uganda. Therefore,
development of consecutive and gradual human resource development program and its
proper implementation is essential to develop policemen’s ability on traffic guidance
and enforcement.
(vi) Preparation and Development of Equipment for Traffic Safety Guidance and
Enforcement Program
8-53
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
• Accident investigation
(5) Enhancement of Traffic Safety Education and Awareness Campaign (Education Sector)
Sector Target
Since three factors of the traffic accident are person, vehicle, and road environment and person is
dominant factor on the traffic accident, education and publication to enhance traffic safety
awareness is most important issues on traffic safety. Despite enhancement of traffic safety
awareness for all road users is ambitious, conscientious effort with appropriate policy and
efficient participation and cooperation of every concerned agency is essential.
In line with the basic strategies discussed in the previous section, four strategies for the education
sector are reformulated:
8-54
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
(b) Traffic safety zone (safe routes to/from home-school for all school levels)
8-55
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
(f) Guideline on the management and evaluation of school traffic safety education
Sector Target
The objectives of the sector are to develop efficient and enhanced post-accident system focusing
on road accident casualties to reduce death and injury severity.
8-56
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
In line with the basic strategies discussed in the previous section, three strategies for the medical
emergency sector are reformulated:
• Develop emergency call system to cover GKMA based on public health and private
systems
8-57
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
(iii) Capacity Development for Disaster and Mass Casualty Accident Program
Objectives of the Program
Share of the PSV vehicles in passenger traffic is huge, and public transport is
promoting in Kampala city. This therefore increases the risk of mass casualty accidents.
The health sector and local authorities at all levels should therefore be more concerned
on the issue of mass casualty accident.
Development of institution, financial resource, and human resource is essential element to ensure
the sustainability of the traffic safety policy and to continue effective and efficient
countermeasures. Institutional development program for the respective elements are proposed as
follows:
8-58
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
Establishment of national road safety authority as substitute for present responsible organization
to upgrade responsibility and function of road traffic safety is essential for sustainable traffic
safety development in Uganda.
Key implementation strategy to achieve traffic safety development policy by NRSA is to ensure
4Cs (communication, cooperation, coordination, and corroboration) among the agencies and
organizations involved in traffic safety projects and activities. Moreover, following functions of
the lead agency shall be fulfilled properly:
(a) Advise Government on road safety policy including the drafting of regulations, guidelines
and policies
(b) Develop in conjunction with stakeholders, a comprehensive National Road Safety Action
Plan that will be published and updated regularly
(c) Monitor and report on the progress of the National Road Safety Action Plan
(d) Develop sustainable road safety funding sources and road safety training program for
persons involved in delivering road safety
(e) Serve as a central road safety body and co-ordinate activities between government
departments, private sector, academic and professional institutes, NGOs, and
community based organizations
(f) Improve the road traffic collision database, collection of accidents statistics and analysis
and their dissemination
(g) Take the lead responsibility for road safety education and publicity and work in
collaboration with others to improve road user behavior
(h) Promote and conduct research to ensure road safety policy is based on the best local data
available and lesions learned from elsewhere
(i) Support the establishment and operation of the District Road Safety Committees (DRSCs)
and improve communication between district and national level organizations
(j) Promote the informed participation of civil society, including private sector, in reducing
death and injury on Uganda’s roads
(k) Set standards for road safety equipment and ensure their compliance
2) Authorization of Traffic Safety Strategic Plan
Most important issue of traffic safety policy development is to develop the comprehensive
measures, ensure its sustainability, and develop a smooth and effective dissemination mechanism.
Many government agencies shall be further involved in traffic safety development. Thus, the
functions and responsibilities of these agencies and organizations and the mechanism for policy
development should be clarified and finally legalized.
Policy guidelines for the Five-Year Action Program are introduced in Japan as a series of action
programs since 1970 based on the Traffic Safety Policies Act. This institutional system shall be
taken into account in traffic safety institution in Uganda.
8-59
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
Key role of NRSA is to be responsible for intersectoral issues on traffic safety policies and
measures. Establishment of Traffic Safety and Development Center in NRSA is proposed as an
organization solely responsible for the intersectoral issues to ensure efficiency and effectiveness
of the traffic safety policy with following proposed framework:
Appropriate site investigation and recording of traffic accidents and traffic violations contributes
to examine not only traffic safety countermeasures, but also traffic safety policy effectively and
efficiently. Important element on data collection of the investigation and recording is that the
data should be evidence to provide a clear picture of accident and violations, as well as the
drivers’ personal histories and information.
Therefore, traffic safety database system should be designed to provide adequate and clear for
examination of countermeasures on each road traffic safety sub-sectors (engineering,
enforcement, education) and three elements (person, vehicle, road environment).
Another key role of NRSA is to develop sustainable traffic safety financial resource.
• Road Fund
• Violation fees
• Insurance premium from insurance companies,
• Gasoline tax,
• Other transport tax
• Private sector’s donations and social contributions
2) Promising Traffic Safety Financial Resource Development
8-60
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
budget allocation plan for road traffic safety is not included. Dominant budget
allocation for road development and improvement is explicable based on present road
condition in Uganda. However, safety conscious measure shall be taken into account on
road development to alleviate economic losses by the traffic accident. As discussed in
chapter 8.2.3 (4), economic loss by the traffic accident is estimated about 2.9% of GDP.
• Others
Continuous upgrading of skills, knowledge and technical expertise on traffic safety sector shall
be required to meet changing motorization situation in Uganda. To ensure sustainable traffic
safety human resource development, the strategies that will be proposed are as follows:
(i) Development of traffic safety training system for staffs in concerned agencies
(ii) Capacity development supported by ODA projects
(iii) Promotion of research and development in the traffic safety sector
8-61
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
8.4.1 INTRODUCTION
Action Plan (2011-2015) involves the first phase implementation period of the proposed traffic
safety measures in the Strategic Plan. This Action Plan is important to ensure smooth and
successful implementation of the proposed measures.
Basic Principle No. 1: The “4Es” approaches should guide the planning and implementation of
measures indicated in this Action Plan. Participation of whole traffic safety concerned agencies is
essential conditions for the success of this Action Plan.
Basic Principle No. 2: The Action Plan should be integrated with related existing policies and
plans of the government.
Basic Principle No. 3: The proposed traffic safety measures should be ensured under a strong
leadership and with adequate financial and human resources.
• To improve the knowledge, creating traffic safety awareness for road users.
8-62
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
(v) Traffic Safety Project Monitoring and Maintenance Program 0 0 0.5 0.1 0.1 0.5
Core Agency Coordinating Cost (million USD)
Activities Completed by
Involved Agency 2011 2012 2013 2014 2015 2023
(1) Capacity development on planning and implementation of traffic safety environment improvement
(a) Monitoring and evaluation system for safety planning 2023 NRSA 0.1 0.1 0.5
(b) Establishment of a monitoring and evaluation unit of road
2013 NRSA 0.5
safety plan
Total 0 0 0.5 0.1 0.1 0.5
8-63
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
8-64
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
(i) Traffic Safety Guidance for Young and Vulnerable Road Users Program
Table 8.4.13 Action Plan for Traffic Safety Guidance for Young and Vulnerable Road Users Program
Core Agency Coordinating Cost (million USD)
Activities Completed by
Inv olved Agency 2011 2012 2013 2014 2015 2023
(a)On-street traffic safety guidance to motorcy cle tax i and
2020 POLICE UTODA 0.2 0.2 0.2 0.2
pedestrians
(b)On-site traffic safety guidance on how to drive at black- POLICE
2020 UTODA 0.1 0.1 0.1 0.1
spots and black-sections
(c)Intensified traffic safety guidance for y oung drivers 2023 POLICE 0.2 0.2 0.2 0.2
Total 0 0 0.5 0.5 0.5 0.5
8-65
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
(iv) Recording and Evaluation of Traffic Safety Guidance and Enforcement Activities
Program
Table 8.4.16 Action Plan for Recording and Evaluation of Traffic Safety Guidance and Enforcement
Activities Program
Core Agency Coordinating Cost (million USD)
Activities Completed by
Inv olv ed Agency 2011 2012 2013 2014 2015 2023
(a)Recording of traffic guidance and enforcement activ ities 2013 POLICE 0.3 0.3
(b)Ev aluation of the activ ities 2013 POLICE 0.1
(c)Activ ity planning based on the ev aluation 2014 POLICE 0.1
Total 0 0.3 0.4 0.1 0 0
(v) Human Resource Development on Traffic Safety Guidance and Enforcement Program
Table 8.4.17 Action Plan for Human Resource Development on Traffic Safety Guidance and
Enforcement Program
Core Agency Coordinating Cost (million USD)
Activities Completed by
Involved Agency 2011 2012 2013 2014 2015 2023
(a)Examination of human resource development policy on
2012 POLICE NRSA 0.1
traffic safety guidance and enforcement
(b)Development of training system for sustainable human POLICE
resource 2013 NRSA 0.2
development
(c)Beginners' training 2015 POLICE 0.2 0.2
(d)Intermediate leaders' training 2015 POLICE 0.2 0.2
(e)Advance training 2015 POLICE 0.2 0.2
Total 0 0.1 0.2 0.6 0.6 0
(vi) Preparation and Development of Equipment for Traffic Safety Guidance and
Enforcement Program
Table 8.4.18 Action Plan for Preparation and Development of Equipment for Traffic Safety Guidance
and Enforcement Program
Core Agency Coordinating Cost (million USD)
Activities Completed by
Involved Agency 2011 2012 2013 2014 2015 2023
(a)Equipment procurement plan for traffic safety guidance and
2012 POLICE 0.1
enforcement
(b)Implementation of procurement plan 2014 POLICE 0.5 0.5
Total 0 0.1 0.5 0.5 0 0
8-66
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
8-67
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
(iii) Capacity Development for Disaster and Mass Casualty Accident Program
Table 8.4.26 Action Plan for Capacity Development for Disaster and Mass Casualty Accident Program
Core Agency Coordinating Cost (million USD)
Activities Completed by
Involved Agency 2011 2012 2013 2014 2015 2023
(a)Strengthening emergency capacity of the hospitals 2015 MOH 0.5 0.5 0.5 0.5
(b) Development of satellite hospitals along black 2023 MOH 10
(c)Organization of a disaster medical assistance team 2013 MOH 0.2 0.2
Total 0 0.7 0.7 0.5 0.5 10
Table 8.4.27 Action Plan for Traffic Safety Institutions Development Program
Year 2011 2012 2013 2014-2015
National Road • Detailed design of the • Implementation by the • Establishment of • Start of full-scale
Safety Authority structure and its legal provisional organization permanent organization activities
procedure • Human resource • Preparation of • Monitoring and
• Establishment of development Five-Year Action Plan evaluation of the
provisional organization Five-Year Action
• Human resource Plan
development
1.2 1.0 0.3 0.3
Traffic Safety • Detailed design of the • Human resource • Establishment of • Start of full scale
Research and structure development for the permanent organization activities
Development • Establishment of center • Research and analysis • Data collection and
Center provisional organization for Five-Year Action analysis of Five-Year
• Human resource Plan Action Plan
development for the • Completion of traffic
center safety database
0.3 0.3 - -
Traffic Safety • Preparatory period • Legal procedure • Start of activities
Foundation • Review of the
organizational setup
1.5 - -
Total 1.9 2.6 0.3 0.3
(million USD)
8-68
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
(1) Smooth economic development has brought rapid increase in the rate of motorization.
As of 2008, a total of 470,000 vehicles are registered across the country, 50% of which
are motorcycles.
(2) The road traffic accidents increased rapidly from 1990 to 2007, with an annual increase
rate of 7.8%. During this 17-year period, the number of fatalities has increased 3.6
times. The numbers of accidents, fatalities and injuries have reached 20,413, 2,807 and
14,073, respectively, which increased economic losses to approximately 2.9% of the
GDP. Fatality rate still remains at a critical level of 52.9 per 10,000 motorized vehicles.
(3) Causes of the traffic accidents are intricately intertwined between physical situation and
human errors as well as mixed traffic and reckless driving behaviors. Many traffic
accidents have occurred on the main trunk roads, of which 38% of total fatalities are
pedestrians. The major causes of accidents are careless driving and reckless driving.
(4) The GOU has undertaken numerous countermeasures as well as enlisted the support,
assistance and cooperation of international donors to alleviate one of the most pressing
social problems in the country at present, which is traffic safety. While some of the
countermeasures are implemented in the country, there are still further needs to develop
safe driving behaviors among traffic participants in the country.
(5) Urgent traffic safety issues have been addressed by the different sectors, such as black
spot improvements for the engineering sector, dissemination of school traffic safety
education for the education sector, and development of the 119 system for the
emergency sector. However, these efforts are still on the pilot stages and only in very
limited areas.
(6) Traffic Safety Strategic Plan and its Action Plan have been developed. The Strategic
Plan is aimed at developing traffic safety development policies and strategies toward
2023 while the Action Plan will be the implementation program of the proposed
Strategic Plan policies and strategies for the next five years (2011-2015).
(7) The proposed Action Plan is an integration of different sectoral programs into a
comprehensive program, namely: Transport Engineering, Transport Operation, Traffic
Enforcement, Traffic Safety Education Development, Medical Emergency and
Institutional Improvement.
The proposed Strategic Plan will be a basic policy and guideline for the government. The
Strategic Plan and Action Plan include the comprehensive measures, and the following are some
of the major recommendations to facilitate key institutional setup of the strategic traffic safety
plan:
8-69
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
Background
This project is proposed to take above traffic safety principles into practical traffic safety
activities as integrated project of following action programs for coordination and human
resource development:
Project Objective
Objectives (Output)
・ To improve abilities of traffic policemen of Kampala Traffic Police Division for traffic
enforcement.
・ To improve abilities of officers of KCC for traffic management and road facilities.
8-70
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
Implementation Structure
Implementation Plan:
Background
Two action plans named “(iii) Vehicle Registration System Development Program” and “(iv)
Vehicle Inspection System Development Program” are proposed as driver and vehicle sector
development program based on the following sector planning strategy on “Enhancement of
Safe Driving and Safety Vehicles”:
(ii) To develop driving standard and vehicle standard to clarify social responsibilities of
drivers and vehicle owners
(iv) To develop integrated vehicle management system (vehicle registration, vehicle
inspection) to create safe and sustainable traffic safety society
This project is proposed as initial setup stage for above mentioned action plan programs to
provide practical planning suggestion for smooth implementation of the action plan programs
towards development of new vehicle registration and inspection system with improvement
following current problems:
8-71
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
Objectives
Implementation Plan
(3) Project for the Study on Development of Traffic Control Device Integration and Traffic
Surveillance System
Background
An action plan named “(iii) Highway Traffic Safety Facility Enhancement Program, (3), c)
Traffic signal and control system development” is proposed as engineering sector development
program based on the following sector planning strategy on “Development of Safe Road
Traffic Environment”:
(ii) To improve traffic control and management devices to provide safety guidance to the
drivers and road users;
This project is proposed as a pilot scheme for the above mentioned action plan to transfer
8-72
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
planning, design, and operational technology on the integrated traffic surveillance system. In
addition to that, it is intended to make the road improvement projects which include traffic
signals installation more effective towards achievement of following issues:
・ Capacity expansion of existing independent traffic lights to meet future traffic demand
・ Area traffic control and its surveillance system is necessary to meet motorization
development
Objectives
・ Pilot project for advanced and coordinated traffic lights operation (KCC, UPF)
・ Development of strategy for introduction of area traffic surveillance system based on the
result of the pilot project (KCC, UPF)
Implementation Plan
・ Traffic safety specialist (traffic engineer, electric engineer, enforcement specialist, etc.)
8-73
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
In this section, the major findings acquired from the traffic survey conducted in January 2010 are
enumerated.
1) Traffic Volume
The traffic volume of minibus and motorcycles by the traffic count is shown in the following
table.
Table 9.1.1 Traffic Count Result Table 9.1.2 Traffic Count Result
(Minibus) (Motorcycle)
Survey Other Composition No. of
Road Name Minibus Total Survey Point Road Name
Point Vehicle of Minibus Motorcycle
No.1-1 Port Bell 1,748 9,145 10,893 16.0% No.1-1 Port Bell 4,470
No.1-2 Jinja 8,129 15,568 23,697 34.3% No.1-2 Jinja 8,019
No.1-3 Kira 4,433 15,632 20,065 22.1% No.1-3 Kira 6,103
No.1-4 Gayaza 3,954 6,546 10,500 37.7% No.1-4 Gayaza 7,865
No.1-5 Bombo 3,547 8,963 12,510 28.4% No.1-5 Bombo 9,418
No.1-6 Sir. Apollo Kaggwa 2,616 5,550 8,166 32.0% No.1-6 Sir. Apollo Kaggwa 7,911
No.1-7 Makerere Hill 3,005 17,640 20,645 14.6% No.1-7 Makerere Hill 13,627
No.1-8 Hoima 6,344 5,013 11,357 55.9% No.1-8 Hoima 10,121
No.1-9 Masaka 5,144 6,814 11,958 43.0% No.1-9 Masaka 6,606
No.1-10 Natete 2,262 10,073 12,335 18.3% No.1-10 Natete 8,000
No.1-11 Entebbe 9,150 19,640 28,790 31.8% No.1-11 Entebbe 12,725
No.1-12 Gaba 4,187 11,211 15,398 27.2% No.1-12 Gaba 13,220
Note: Motorcycle is excluded
Source: JICA Study Team
Since most minibuses are deemed to be matatsu (minibus), the movement of matatsu is surmised
by minibus here. The total traffic volume counted is highest on Entebbe Road, second highest on
Jinja Road and third highest on Makerere Hill Road. Meanwhile, minibus volume is highest on
Entebbe Road, second highest on Jinja Road and third highest on Hoima Road. Comparing north,
south, east and west, the total traffic and minibus traffic are less in the west direction. On Hoima
Road, minibus occupies more than 50% of total traffic (Table 9.1.1).
In case of boda-boda, it is more difficult to distinguish boda-boda from private motorcycle. But
most of motorcycles are speculated to be boda-boda, either formal or informal. Volume of
motorcycle varies more irregularly and influenced by traffic congestion on the road and activity
around the survey point (Table 9.1.2). In some survey points, motorcycle volume is close to the
volume of other vehicles. It is evident that the effect of motorcycles is not ignored for the road
capacity. Figure 9.1.1 shows the total traffic volume and minibus volume.
9-1
Final Report
9-2
The Study on Greater Kampala Road Network and Transport Improvement
Based on the O-D table of minibus captured at road side interview, the desired line of minibus
vehicle is shown in the following figure. The concentration in the Kampala City center (zone 1)
is dominant. Among the incoming movements toward the city center, the movement from
Kampala City (zone 2 – zone 5) is very large. Outside the Kampala City area, traffic from
adjacent zones such as Kira (zone 14), Kyandondo (zone 15), Nangabo (zone 16) and Nabuweru
(zone 17) is also large. Except for the adjacent zones, movement from Entebbe (zone 9) is
conspicuous.
9-3
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
1) Minibus Passenger
a) Trip Purpose
b) Trip Length
c) Frequency of Trip
9-4
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
d) Fare
- Average Fare
Average fare of minibus trip for all purposes is UShs1,242. For school, home, business and office
purposes, average fare is UUShs2000-3000. For shopping, average fare is lower.
Minibus fare for passengers traveling under 30 minutes is UShs 700-800. The fare increases to
UShs 1,000 for 30-60 minutes travel.
- Fare and Income Table 9.1.3 Monthly Income and Minibus Fare
2) Boda-Boda Passenger
a) Trip Purpose
9-5
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
b) Trip Length
Trip length (time) distribution of boda-boda passenger is shown in the following figure. Travel
time of boda-boda passenger is most frequently between 10-20 minutes and decreases from 20
minutes. Most of the trips are completed within 60 minutes.
The average time is approximately 21 minutes. boda-boda is used for short distances including
walking distances since some parts of Kampala are in the hilly areas.
c) Frequency of Trip
In total, more than 50% of passengers use boda-boda once or twice everyday. As for the
frequency by trip purpose, passengers use boda-boda more than once every day for office,
business, home and school purposes. For shopping, social and hospital purposes, less than 20%
of passengers use boda-boda
everyday.
d) Fare
- Average Fare
9-6
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
Boda-boda fare for passengers traveling under 30 minutes is 700-800 Shs. The fare increases to
UShs 1,000 for 30-60 minutes travel.
1) Minibus Driver
b) Working Hour, Trip Frequency and Daily Collection Source: JICA Study Team
Average working hour of minibus drivers is 16.1 hour/day Figure 9.1.13 Type of Minibus
Drivers – Employed or Independent
and trip frequency is 5.0 times/day. Average travel time
for one trip (from origin to destination) is 3.22 hours.
Average daily collection of minibus fee is approximately UShs 86,000 (USD 44*).
9-7
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
2) Boda-Boda Driver
b) Daily Collection
Source: JICA Study Team
Average daily collection of boda-boda fee is Figure 9.1.16 Type of Boda-Boda
approximately UShs21,000 (USD 11*). Drivers – Employed or Independent
9-8
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
This order is not different by trip purpose. Source: JICA Study Team
However, time shows a larger portion on
Figure 9.1.18 Minibus Passengers’ Demand
office and business trips.
9-9
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
Based on the traffic flow and its tendency, the Study Team pointed out the following issues which
should be solved for the operation of public transport:
1) Bus
• Buses are a high capacity collective mode of transport for medium and long distance journey
with well established boarding points, routes, intermediate stops and timetable。
• The traffic congestion in the bus terminals within the CBD hampers the operation of buses.
• Even more, large inter-urban buses accelerate the congestion in the central area.
• Inter-urban bus terminals inside the city center are too small and many passengers are waiting
outdoor for a long time.
- Relocation of inter-urban bus terminals outside the city center will contribute in decreasing the
traffic congestion in the city center.
- Connection with other modes such as Bus Rapid Transit (BRT) and minibus will be
convenient for inter-urban bus passengers.
2) Minibus
3) Boda-Boda
9-10
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
The results of the questionnaire about the passenger’s demand for minibus show that 45% of the
answers are for cheaper fare, 21% for speeding up the travel, 12% for safe driving and 9% for
comfortable vehicle.
The fare for public service vehicles in the existing system is not fixed. Also, the association of
minibus operators and drivers is a strong political body which controls the fare by itself. In order
to create orderly minibus system with fixed route, fixed fare and timetable, it is necessary to
review the existing tendering system. One of the measures is to divide the minibus control into
route (road) and to assign the control body for each route. The control body shall be selected by
open tendering.
The second answer is to speed up the public transport. In order to solve this request, there are two
ideas. One idea is to expand the road traffic capacity to meet the increasing traffic demand. The
other is to control the traffic demand and give priority to public transport system. The idea of the
GKMA relates to the second idea. The BRT System is proposed to be introduced on the main
radial arterial roads in Kampala.
The third and fourth answers need the education, control and enforcement of safe driving and
vehicle inspection for the drivers and owners of the minibuses. These items should be included in
the review of the licensing system of the public service vehicles.
9-11
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
Based on the present conditions and present issues derived from Clauses 9.1 and 9.2, the strategy
for the long-term and medium-term public transport improvement is articulated.
The following are the policies to solve the present issues of each public transport mode:
1) Minibus
z Conversion of minibus to the BRT and large bus on routes where demand is concentrated
z Clarification of operating route and operating area of minibus
z Orderly operation with fixed fare, fixed bus stop and timetable
z Review of licensing system and registration system
z Establishment of new minibus terminal at the proper locations outside CBD
2) Large Bus
z Relocation and collection of inter-urban bus terminals with sufficient size outside the city
center
3) Boda-Boda
z Clarification of role as the auxiliary mode for BRT, large bus and minibus
z Exclusion of informal boda-boda by licensing system and sticker
z Prohibition of operation on BRT route and restriction of operating route
z Review of licensing system to control and improve the driving
The relation of the present issues and the above policies is shown in the following chart.
9-12
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
Minibus
Large-size bus
9-13
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
Boda-Boda
Driving manner of Boda-Boda is rough Clarification of role as the auxiliary
and Boda-Boda hampers other traffic mode for BRT, large bus and Minibus
by irregular driving.
Exclusion of informal boda-boda by
Motorcycle volume including Boda- licensing system and sticker
Boda is increasing and occupies large
portion of traffic. Prohibition of operation on BRT route
and restriction of operating route
Many accidents and heavy injuries of
Boda-Boda passengers occur. Review of licensing system to control
and improve the driving
In this public transport plan, long-term and medium-term target years are defined as 2023 and
2018, respectively.
In this study, the objectives of the public transport improvement are as follows:
z To provide a reliable and stable public transport service which meets the increasing volume
of passenger demand and diversification of needs of passengers
To cope with the increasing traffic demand and the worsening traffic congestion in GKMA,
enhancement of utilization of public transport is required more and more. To this end, public
transport should be improved and should be used by every social level of citizens. Through the
provision of reliable and stable public transport service which meets the increasing volume of
passenger demand and diversification of needs of passengers, utilization of public transport
should be promoted and thus, traffic condition in GKMA should be improved. Operation by fixed
time, fixed route and fixed fare is the most fundamental element for the reliable and stable
service.
z To harmonize with other road transport modes and to secure the safety of road traffic and
public transport
Road is the basic public infrastructure which various transport modes use. Public transport
should use the road properly as one of the users. Public transport should operate in harmony with
other traffic and should not hamper the road traffic. In this way, road safety and safety of
passengers can be secured. Therefore, the basic rule for the operation of public transport on road
should be established.
z To protect the interest of public transport industry properly and promote a sound evolution
of the public transport industry
Public transport industry is a kind of public entity working for the welfare of general public. In
order to protect the benefit of users by the provision of stable public transport, the public
transport industry should be managed stably based on the proper interest. Therefore, excessive
competition among industries shall be averted and competition shall be controlled. Through the
stable management of industry, sound evolution of public transport industry is ensured and the
beneficiary is protected.
9-14
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
For the establishment of the long-term and medium-term strategies for the public transport, the
following premises are given to each transport mode.
a) Introduction of BRT is the priority project in the transport sector of GKMA. Therefore, in
this study, the strategy of the public transport is established in harmony with the BRT project
and its implementation.
b) Since the number of passengers of minibus is very small and the transport efficiency is low,
the minibus shall be replaced gradually by large bus, medium bus and BRT as recommended
by NTMP/GKMA.
c) Bus is one of the public transport modes and it is necessary for it to be operated on fixed
route and fixed time. Therefore, operation method of present minibus without route and
timetable shall be gradually abolished.
d) The Transport Master Plan in GKMA (NTMP/GKMA) shows that the primary transport
mode in the target year is BRT. Therefore, the railway is not considered to function as a mass
transit system until the target year.
e) As for the Boda-Boda, the present operation is unsafe for passengers and hinders other traffic.
It is necessary to control the operation route or the operation area of Boda-Boda for a safe
and orderly operation.
a) BRT
- BRT will be introduced to enhance modal shift from passenger cars and minibuses to mass
transit by provision of rapid and comfortable transport mode on the arterial routes where
traffic demand is concentrated.
b) Large Bus
- Minibus will be replaced by large bus of approximately 50-60 passengers to improve the
transport efficiency and to alleviate traffic congestion.
- Large bus system will be introduced to prepare the BRT on the route where BRT will be
operated but not yet operating at present or to complement the BRT on the route where BRT
will not be operated.
- Large bus system will be administered by an integrated operating entity which will enable
the operation by fixed route, fixed schedule and fixed fare, as approved by the authority.
c) Medium Bus
- Since the existing minibuses are not efficient in terms of transport capacity and inferior in
terms of comfort of passengers, medium size buses with 25 to 30 passenger capacity will
replace the minibuses for the feeder routes of the BRT and large bus.
- Operation of medium bus will be limited to areas which the BRT and large buses will not
cover.
- Medium bus will be operated with fixed schedule and fixed fare, which are controlled by
the licensing authority.
9-15
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
d) Inter-urban Bus
- Inter-urban bus will be connected closely to the BRT and large bus to unite the whole
country to GKMA.
e) Boda-Boda
- The existing terminals will function as the terminals of the medium bus and minibus along
with the developed terminals for the BRT and large bus.
f) Terminal
- To facilitate passengers' mobility by connecting the BRT and large bus routes with other
transport modes, the terminals will be developed. These terminals will become the base
stations for operation of public service vehicles.
- Terminals will alleviate the concentration in the city center terminals by relocating them
outside the city center.
- Public transport will not hamper general traffic by developing terminals outside the road.
(4) Long-term Strategy
1) Basic Strategy
- In consideration of the progress of the BRT project, large bus is operated on the route in
which BRT is not introduced.
- Medium bus is operated in the area which BRT and large bus do not cover and replaces the
minibus.
- Necessary terminals for the operation of the BRT, large bus, inter-urban bus and medium
bus will be developed.
2) BRT
- BRT will be operated on the pilot route and the primary BRT routes.
3) Large Bus
a) Route
- Large bus will be operated on the secondary BRT route and on the major collector route
where BRT will not be operated and where passenger demand will be concentrated.
b) Operation System
- Large bus will be operated on a scheduled basis and on a fixed route approved by the
authority. Fare system of large bus will be set in conformity with the BRT.
c) Operation Body
- Large bus routes which connect to the BRT route will share the trackage with the BRT. In
this case, large bus will bear the track access charge.
- Body of large bus will correspond to the BRT standards.
- In order to control the operation of large buses in terms of schedule, route and fare, it is
necessary that large buses are operated by few enterprises which are established through
joint investments.
d) Institution
- Necessary institution will be arranged for the coordinated operation of BRT and large bus
with other public service vehicles and for the enhancement of introduction of BRT and large
9-16
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
bus.
4) Medium Bus
a) Route
- Replacement of minibus by medium bus and feeder system by medium bus will be
completed.
b) Operation System
- Total number of medium buses will be controlled to avoid excessive competition and to
keep the proper balance of supply and demand.
c) Institution
- Necessary institution will be arranged to realize controlled operation and to enhance the
introduction of medium bus.
5) Inter-urban Bus
- New inter-urban bus terminals will be developed and become the new town center outside
present urban area.
6) Boda-Boda
- Operation of Boda-Boda on the BRT and large bus routes will be prohibited. To coexist with
other vehicles on the road and to prevent accident, the driving method of Boda-Boda will be
restricted.
7) Terminal
- At the end of the large bus route located in the outer area, necessary bus terminals for the
transfer passengers will be developed. Terminals which are planned as the future BRT
terminals will be developed as the BRT terminals.
- Terminals for the medium bus will also be developed considering service area and service
route.
(5) Medium-term Strategy
1) Basic Strategy
- Among the BRT and large bus routes in the long-term strategy, the pilot route is selected
and operation of large bus will be commenced.
- Institutional framework for the introduction of BRT and large bus will be completed.
2) BRT
- BRT will be operated on the pilot route and development of BRT on primary route will be
commenced.
3) Large Bus
- For the introduction of large bus system, large bus pilot routes will be selected and
developed from the viewpoint of concentration of demand and extent of service area.
- Operation system of pilot routes will be the same as the system in the long-term with the
fixed route and fixed fare. Operation body will be the enterprise by joint investment.
4) Medium Bus
- Along the BRT and pilot large bus routes, medium bus will be introduced on the access
route for the BRT and large bus.
9-17
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
5) Inter-urban Bus
- New inter-urban bus terminals will be developed outside the present urban area.
6) Boda-Boda
- Operation of Boda-Boda on the BRT and pilot large bus routes will be prohibited and the
driving method of Boda-Boda will be restricted.
7) Terminal
- Terminals along the BRT and large bus pilot routes will be developed based on the
long-term strategy.
8) Institution
- Institutional framework for the introduction of BRT and large bus will be completed until
the target year of the medium-term.
The following table shows the development progress of public transport in each phase including
the long long-term (2030) which is the target year of the BRT.
Development objective and development strategy for public transport are shown in the following
table.
9-18
Table 9.3.2 Development Objective and Development Strategy for Public Transport
Final Report
Objective - Necessary terminals for the operation of BRT, large bus, inter-
urban bus and medium bus are developed.
BRT - Enhancement of modal shift from passenger cars and - Operation on pilot route and preparation for the introduction to - BRT will be operated on the pilot route and the primary BRT
minibuses to mass transit by provision of rapid and primary routes routes.
comfortable transport mode
Large Bus - Replacement of minibus to improve the transport - Large bus pilot routes will be selected and developed. - Large bus will be operated on the second primary BRT route
efficiency and to alleviate traffic congestion - Operation system of pilot routes will be the same as the system and on the major collector route where BRT will not be operated
- Introduction to prepare the BRT or to complement the in long-term. and to which passenger demand will concentrate.
BRT
- Intensive operation entities
Medium Bus - Replacement of minibus for the feeder routes of the - Along the BRT route and pilot large bus route, medium bus - Replacement of minibus by medium bus and feeder system by
9-19
BRT and the large bus will be introduced on the access route for the BRT and the large medium bus will be completed.
- Operation in the area where the BRT and large bus do bus
not cover
The Study on Greater Kampala Road Network and Transport Improvement
Inter-urban Bus - To unite the whole country to GKMA by connecting - New inter-urban bus terminals will be developed outside - New inter-urban bus terminals will be developed and become
with the BRT and the large bus closely present urban area. the new town center outside present urban area.
Boda-boda - Role as the supplemental transport mode by regulated - Operation of Boda-boda on the BRT route and pilot large bus - Operation of Boda-boda on the BRT route and large bus route
operating method and operating route route will be prohibited. The driving method of Boda-boda will will be prohibited. The driving method of Boda-boda will be
be restricted. restricted.
Terminal - To facilitate passengers' mobility by connecting the - Terminals along the BRT pilot route and large bus pilot route - At the end of the large bus route located in the outer area,
BRT and the large bus with other transport mode will be developed based on the long-term strategy. necessary bus terminals will be developed.
- To alleviate the concentration to city center terminals by - Terminals planned as the future BRT terminals will be
relocating to terminals outside the city center developed as the BRT terminals.
- Terminals for the medium bus will be also developed.
The BRT system has been selected by the GOU as one of the most effective countermeasures for
the decongestion of the traffic in the city. The proposed BRT system is characterized by a high
capacity, fast, comfortable and cost-effective urban transport mode through the provision of
segregated lane. The role of the BRT to cope with the existing issues is described as follows:
The major components of the proposed BRT are as follows. Detailed explanations of the
components are mentioned in Clause 4.4.4 of Chapter 4.
z Open route (Externalized) system and open bus stations with on-board revenue
collection
z Median operation and bilateral stations with passing lane at all main stations for
capacity/flexibility
z High capacity bus with high quality
z Variety of selection from single door bus to articulated bus is applicable
z Existing minibuses will play a role as feeder mode for the BRT, and Boda-Boda
will not operate along the BRT routes.
z Operation management and passenger information by low technology system
Through the evaluation of features of alternative routes, the following eight BRT routes have
been selected and given the order of priority. Detailed evaluation is expected to be conducted in
the Feasibility Study and Detailed Design in 2011.
¾ Route A1 (Pilot Route): Jinja Road to Kireka and Bombo Road to Bwaise,
¾ Route B1: Route A2 + Entebbe Road to Namasuba
¾ Route A2: Route B1 + Gayaza Road
¾ Route A3: Route A2 + Kira Road
¾ Route A4: Route A3 + Hoima Road
¾ Route B2: Route A4 + Masaka Road
¾ Route B3: Route B2 + Gaba Road
¾ Route B4: Route B3 + Port Bell Road
In order to clarify the presumption of progress of BRT development in the long-term and
medium-term in this study, the implementation priority, implementation cost and implementation
period have been analyzed. Presumed BRT routes to be developed in the long-term and
medium-term are shown in the following figures.
9-20
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
9-21
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
The presumed long-term BRT network in 2023 consists of arterial routes such as Bombo-Jinja
route (A1), Gayaza route (A2), Kira route (A3) and Entebbe route (B1). The remaining routes
will function as branch routes of the arterial routes and share the road space with the general
traffic until the designated runway will be constructed.
The presumed medium-term BRT network consists of Bombo-Jinja route (A1) and Entebbe route
(B1). The development of the BRT route will be limited due to budget, duration of land
acquisition and compensation, etc. The area which is not covered by the BRT will be covered by
the existing public transport means which shall be operated by fixed route, fixed time and fixed
fare through the new registration system of the public service vehicle licensing.
The following table shows the relation among the appraisal ranking, development step in Pre-FS
Study for BRT, and assumption in this study.
9-22
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
Based on the O-D table by vehicle type acquired from traffic survey conducted by the Study
Team, future public transport demand is forecasted by the following method. In order to conform
to the demand forecast by the BRT pre-feasibility studies, the total volume of public transport
demand in the future is made consistent with the BRT study. Detailed procedure of the traffic
demand forecast can be referred to in Chapter 5.4.
According to the demand forecast method in the previous section, passenger demand in the
long-term (2023) and medium-term (2018) are forecasted. The total volume of public transport
passengers are forecasted as shown in the following table. Growth rates per annum are 3.8% for
2010-2018 and 4.1% for 2018-2023. Growth rate will become higher in 2018-2023 due to the
progress of the BRT development.
9-23
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
1,750,000
1,500,000
1,250,000
942,000
508,400
1,000,000
BRT
0
2010 2018 2023
Source: JICA Study Team
Figure 9.5.2 Future Bus Passenger Demand
2) Desire Line
The following figure shows the present and future desire lines of public transport passenger. In
these figures, estimated future BRT passenger is excluded and traffic zones are combined with
the arterial road direction.
After introduction of the BRT, passenger demand decreases from city center towards Jinja Road
direction and Bombo Road direction in 2018. Also, demand decreases towards Gayaza Road
direction in 2023. As for the Entebbe Road direction, demand decreases compared with the
present. However, a still large demand for public transport, excluding BRT, remains.
9-24
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
In the long-term, the figure shows that public transport demand has large volume in Gaba Road,
Masaka Road and Hoima Road directions since these directions are not covered by the BRT.
According to the forecasted future O-D table of public transport passenger exclusive of BRT
passengers, traffic assignment is conducted. Assigned passenger is shown below in terms of the
width of lines.
9-25
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
9-26
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
• BRT route not developed but planned in the long-term (2030) will be serviced by large bus
system as the BRT tributary route, such as:
• Large bus system will be operated by fixed route, fixed schedule and fixed fare. But since
the large buses share the road with other traffic, it is difficult to keep the strict schedule.
Operation schedule should be adjusted not at the city center interchange but at the
terminals outside the city center.
Large bus network consisting of the aforesaid routes is shown in Table 9.6.1 and Figure 9.6.1.
9-27
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
9-28
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
Service areas of the BRT system and large bus system are shown in Figure 9.6.2. Many areas are
not covered by the BRT or the large bus network. These areas don't have the trunk roads and are
not appropriate for the operation of BRT and large bus. Medium bus will be introduced in these
areas and shall replace the present minibus.
• Minibuses will be replaced by medium buses gradually and until the end of the long-term,
all the minibuses shall be replaced by medium buses.
• Medium bus is prohibited to operate on the BRT and large bus routes. Licensing of
medium bus is area-based and operation area is limited to the area stated in the license.
Fixed fare, fixed route and fixed schedule shall also be stipulated during licensing.
• These conditions require the development of the terminals along the BRT and large bus
routes for the transfer to the BRT or large bus.
9-29
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
As development in the medium-term is the initial stage to accomplish the development of the
long-term network, fundamental condition will be arranged for the introduction of large bus
system. Therefore, a pilot route is selected from the long-term BRT network and large bus
network. The viewpoint for the selection of pilot routes is as follows:
• The BRT route in the medium-term is assumed in Figure 9.4.2. The routes developed in the
long-term but not yet developed in the medium-term will be supplemented by BRT
tributary route.
Munyonyo Route
Large bus network in the medium-term is shown in Figure 9.6.2.
9-30
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
As in the long-term, the areas not covered by the BRT system and large bus system will be
serviced by medium bus or minibus. These areas are shown in Figure 9.6.4.
• The following existing terminals will function as the terminals of the medium bus and
minibus along with the developed terminals for the BRT and large bus. Additional new
terminal is required and this is articulated in the next section.
9-31
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
9-32
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
Terminals facilitate passengers' mobility by connecting the BRT and large bus routes with that of
the other transport modes. The following intermodal mutual transfers are necessary as the
function of the terminal.
a) Integrated Terminal:
BRT / BRT tributary route / large bus, inter-urban bus, medium bus and passenger car
Integrated Terminal is composed of the terminals of BRT and inter-urban bus as its center. This
terminal is expected to become the core of the sub city center.
Kawampe Terminal (BRT route)
Kanyana Terminal (BRT route)
Kireka Terminal (BRT route)
Busega Terminal (Large bus route)
Nabweru Terminal (Large bus route)
c) BRT Terminal:
large bus
Large Bus Terminal functions for time adjustment and rotation of BRT
City Center Terminal
Luwafu Terminal
9-33
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
The type of terminals and the function of each terminal are shown in Table 9.6.4. Planned
location of terminals in the long-term is shown in Figure 9.6.5.
Since the terminals relating to BRT are not currently clear about their detailed conditions, the
terminal plan excludes terminals related to the BRT.
The terminal plan conducted in this study is also shown in Table 9.6.3 and the location of
terminals is shown in Figure 9.6.5.
9-34
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
9-35
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
Kampala City is facing growing traffic congestions within the urban area and city center. This
issue is caused by the following reasons:
z The trunk road network in Kampala consists of one center radial network system
except the Northern Bypass. Also, the width of the trunk roads remains
unchanged.
z The traffic demand concentrates in the city center and traffic volume is increasing
rapidly due to population growth and economic growth.
z Based on the above conditions, traffic congestion in the urban area and city center
became a serious obstruction to the socioeconomic development of Kampala as
the leading player of the national economic growth.
z Typical issue in the city center is the concentration of the minibuses, the citizen’s
most popular transport. The area of the minibus terminals is too small for the
demand and the waiting queue of minibus is one of the causes of traffic jam in the
center.
z The terminals of inter-urban buses, as the main transport means throughout the
country, are also located in the center and the penetration of large size buses into
the congested center accelerates the traffic jam.
Countermeasures are being undertaken except for the concentration of the inter-urban bus
transport in the bus terminals located in the city center.
The inter-urban buses which depart from the bus terminals are mainly operated by two major
associations and other companies. There are 115 companies in total operating 755 buses. The
operation plan for each bus route including departure time, bus stops and bus size is discussed
with each regional administration and authorized by the Transport Licensing Board (TLB) under
the MoWT. Everyday, 540 large size buses depart and arrive on 83 routes to all up-country areas.
9-36
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
a) Direct connection with intra urban public transport such as minibus to and from
any area within the city
b) Close location to the shops and service facilities to get services and commodities
for the passengers, as well as to sell agricultural products brought from
up-countries; many varieties of shops and markets located in the city center for the
requirement of passengers
Inter-
urban Bus
Terminals
Intra Urban
Transport
Market
Minibus and
Boda-boda
Movement of passengaers
Shops
Inter Urban Bus
(3) Necessity of Relocation of Inter-urban Bus Terminals through the Implementation of the
BRT Project
The BRT system is the essential countermeasure to strengthen the public transport system for the
decongestion of the increasing minibuses in the center.
The BRT system proposes the location of the BRT terminals outside the urban area. It is
necessary to connect the BRT terminals with other transport modes including the inter-urban bus
transport and thus, the existing inter-urban bus terminals at the city center shall be relocated close
to the proposed BRT terminals.
9-37
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
Inter-urban
Bus Terminals
Currently, the inter-urban buses from the bus terminals operate at an average of 540 trips per day
on 83 routes covering all areas in the country. as shown in Table 9.4 4. Most of bus operators
belong to two major inter-urban bus associations named Qualice Association and Uganda Bus
Association. Some operators are independent of those associates. Number of buses and
operations are shown in Table 9.7.1.
9-38
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
The existing relation between the number of departures and arrivals and the number of bus
berths/lay-bys is as follows:
¾ To the east direction through Jinja Road, average of 132 buses depart and arrive on 14
bus routes from the city center bus terminals. Average of 3.6 buses depart and arrive
every half hour during the 18 hours bus operation. If new east bound bus terminal is
relocated, at least four bus berths/lay-bys will be necessary depending on the bus
operation schedule.
¾ To the north direction through Bombo Road, average of 162 buses depart and arrive on
23 bus routes from the city center bus terminals. Average of four buses depart and
arrive every half hour during the 18 hours operation. If new north bound bus terminal
is relocated, minimum of four bus berths/lay-bys will be necessary.
¾ To the west direction through and Fort Portal Road, average of 10 buses depart and
arrive on 5 bus routes from the city center bus terminals. One bus depart and arrive
every half hour during the 18 hours operation. If new west bound bus terminal is
relocated, minimum of two bus berths/lay-bys will be necessary.
¾ To the south west direction through Masaka Road, average of 236 buses depart and
arrive on 42 bus routes from the city center bus terminals. Average of six buses depart
and arrive every half hour during the 18 hours operation. If a new west bound bus
terminal is relocated, minimum six bus berths/lay-bys will be necessary.
Based on the above, the operation frequency per hour is highest for the direction to the western
region, then to the northern region and followed by the direction to the eastern region.
The travel demand of the public transport from the GKMA will also increase in response to the
increasing population and increasing economic activity. Based on the estimated travel demand of
passenger transport in the Master Plan of the GKMA, a future travel demand of inter-urban
public transport has been estimated applying the estimated travel demand and the revised future
population of each region for the year 2023 as shown in Table 9.7.2.
The existing public transport for inter-urban travel consists of inter-urban large bus and minibus.
According to the traffic survey by the Study Team, 1,450 trips per day are through large buses
and 95,852 trips per day are by minibus. As a result, about 118,000 passengers per day comprise
the existing travel demand of inter-urban transport. The future travel demand will become about
300,000 passengers in 2023 with a growth ratio of 255% from 2010 to 2023.
Table 9.7.2 Future Travel Demand of Inter-urban Transport by Large Bus and Minibus
(in 2010, 2018 and 2023)
If the main transport means for inter-urban transport are not changed, the transport demand by
9-39
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
minibus will become the majority and the area and size of the inter-urban bus terminals will
require a huge area for the minibus transport.
On the other hand, the large size bus transport is efficient, comfortable and economical compared
with the minibus for the steadily growing demand. Therefore, it is recommended that the
government instruct the minibus operators to gradually change their vehicles into large buses.
The transition period from the minibus to large bus will be necessary. Almost half of the existing
minibus will remain unchanged in 2018 and the transition will be completed in 2023 as shown in
Table 9.7.2.
Table 9.7.3 also shows the estimated future transit demand by each access transport mode in
2023. Modal share of access mode is assumed as shown in the table.
Table 9.7.3 Future Access Demands by Transport Modes for Inter-urban Bus Terminals
Figure 9.7.4 shows the areas for both BRT and inter-urban bus terminals.
9-40
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
¾ The proposed location for the east bound IUBT is an open space near the intersection
between the Northern Bypass and Jinja Road.
¾ The proposed location for the north bound IUBT is either an open space at Kako area
along Bombo Road, 1.5 km north from the Northern Bypass or the open space at
Kanyana area along Gayaza Road, 1.5 km north from the Northern Bypass.
¾ The proposed location for the southwest bound IUBT is a wet land located near the
intersection of Masaka Road and the Northern Bypass.
¾ The proposed location for the west bound IUBT is an open space near Nabweru area
along Hoima Road.
(4) Proposed Functions of the New Inter-urban Bus Terminals
The functions required for the IUBT are not only for transport but also for the following service
facilities:
z IUBT: departure and arrival bus lay-by, bus road, ticket offices, passenger waiting
room, toilet, drivers and conductors office, shops, bus and car parking.
z BRT Terminal: departure and arrival bus lay-by, bus road, ticket offices, passenger
waiting room, toilet, drivers and conductors office, BRT bus and car parking, minibus
and boda-boda parking/terminal.
z Public Market: vegetable and meat market, general store, market office, toilet, truck
and car parking.
After preparation of the infrastructure, the proposed administration of the terminals, car parks
and bus parks as well as service shops will be conducted by the new private associations under a
contract with the government.
The proposed transit functions of the new IUBT shall require space for inter-urban bus, medium
bus, car/taxi and Boda-Boda as well as temporary parking during peak hours. The procedure for
the estimation of each terminal facility required is shown in Figure 9.7.6.
The peak hour rate for each transit demand is 4.5% of average daily traffic according to the
traffic survey by the Study Team. In order to estimate each terminal facility, the future traffic
9-41
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
demand of inter-urban bus transport and the modal share ratio by each access mode shall be
determined as shown in the above section.
Based on each transit demand by transport modes, the peak hour departing/arriving lay-by
demand by type of transport is assumed. The peak hour parking demand by type of modes is
assumed through the typical passenger capacity of each transit mode and the parking rate by
modes during peak hour as shown in Figure 9.7.6 and Table 9.7.4.
After the estimation of each lay-by and parking demand, unit lay-by by modes, unit parking
space and the layout plan of each bus terminal, the total terminal area shall be determined
following the procedure shown in Figure 9.7.6. Minimum bus turning radius of 12 m and
minimum road width of 6 m for circulation are applied.
Table 9.7.4 shows the future numbers of inter-urban bus, medium bus, car/taxi, Boda-Boda and
temporary parked vehicles as well as total rough area required for each facility. Figure 9.7.7
shows the typical lay-out plan of each inter-urban bus terminal which includes the minimum area
for shops, toilet, passenger waiting rooms, ticket office and terminal maintenance office.
9-42
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
200.0
boda boda
150.0 car/taxi
Medium
100.0
Bus
Large Bus
50.0
2023 IUB
demand
0.0
9-43
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
Public market is also one of the components of the terminals. There are two types of public
market, namely, standard type which has 100 shops and larger type which has 200 shops. The
minimum number of public market users will be determined from the size of the inter-urban bus
transport users. In case of Kiraka and Kawampe terminals, the urbanization in the nearby area is
already starting. Therefore, large type of public market is planned at Kireka, Kawampe and
Busega terminals based on the number of future terminal users and the urbanization of
surrounding area. The standard type of public market will be considered for the Nabweru
Terminal.
Proposed typical layout plan for each public market is shown in Figure 9.7.8.
9-44
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
The construction cost of each IUBT and public market is assumed as shown in Table 9.7.5. For
the assumption of the cost estimate, the development of the terminals shall be done by the
government and the properties of the terminals shall belong to the government. The operation
and maintenance of the terminals as well as the markets will be done by private associations.
The estimated construction cost for the major integrated IUBT such as the Kawampe and Kireka
terminals will be around UShs13 billion (USD 5.8 million). The cost for the Busega Terminal
will be UShs15 billion (USD 7 million). The cost for the Nabweru Terminal will be UShs7.5
billion (USD 3.4 million). The grand total will become UShs 48.6 billion (USD 22 million).
Table 9.7.5 Construction Cost Estimates for IUBTs and Public Market
Unit: Thousand
Source: JICA Study Team
The proposed implementation of the pilot BRT project will consist of the following items and
schedules:
The preparation of the detailed plan and financing for the pilot BRT terminals, which are the east
bound IUBT located near Kireka Stadium and the north bound IUBT located at Kako area along
Bombo Road, will be on schedule. The proposed areas for the north bound IUBT are located
9-45
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
either in the swamp area or the former farm land which require official approval for development
by the Environmental Authority.
Under these conditions, the proposed IUBT shall be implemented through the following process:
¾ Firstly, start the selection of the appropriate land and find financing agencies for the
feasibility study, detailed design and the implementation of the priority IUBT project
after the determination of the location of the pilot BRT terminals.
¾ Secondly, prepare the total development plan, feasibility study, selection of priority
project and environmental assessment for the approval of the authority,
¾ Thirdly, identify proposed land/areas for future governmental development and control or
restrict their land use plans.
¾ Fourthly, prepare the detailed design, cost estimate, bus operational plan and tender
documents and purchase the land for the IUBT.
¾ Tendering, evaluation, contracting and monitoring the project operation.
The financial resources for the IUBT project are proposed in Section 9.10.
9-46
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
In this section, based on the future public transport demand and bus network plan, the bus
operation plan is established and the financial condition of the operating entity is analyzed. The
extent of bus operation plan is as follows:
- The operation plan is established for large bus routes. BRT and BRT tributary routes are
excluded.
- The operation plan is analyzed in the beginning year of operation. Therefore, three routes are in
2023 and other three routes are in 2018.
In Section 9.5 of this chapter, future public transport demand is forecasted and the number of
passengers is distributed to the bus routes. The following table shows the future passenger
demand on large bus routes.
Peak hour passenger is estimated from the traffic survey result conducted by the Study Team.
Number of minibuses from the traffic count and average passenger from the roadside interview
are applied to acquire the hourly variation of passengers.
The rate of 12 hour minibus traffic volume to 24 hour traffic volume is 0.74 according to the
traffic survey. Hourly traffic variation of minibus during daytime is shown in the following figure.
Peak hour traffic volume in one direction is 6.0% of daytime traffic volume in both directions.
Therefore, peak hour demand of public passenger in one direction is 4.5% of all day passenger
demand in both directions. Also, the peak appears from 7:00 to 8:00 to the city center direction.
9-47
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
Future passenger demand is converted to peak hour demand in one direction by applying the
peak hour rate.
Considering road condition and flexibility of operation, passenger capacity of large bus is
determined to be 50-60. Loading factor or occupancy rate of large bus is set to be 0.85. Peak hour
operation of large bus is calculated from the average number of passengers which is 46.8. Total
number of operation of bus per day is estimated from the hourly variation of inbound and
outbound traffic. The following table shows the daily and peak hour operation of large bus.
Average operation speed on BRT route including stopping at bus stations is presumed at 25 km/hr.
It is presumed at 20 km/hr on ordinary roads referring to the traffic survey result. Travel time for
one way is calculated as follows:
9-48
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
According to the daily operation and operation distance, annual travel distance of each route is
shown in the following table:
When ten minutes layover for the time adjustment is added, the operation frequency by one bus
is calculated as the following table.
Based on the above table, peak vehicle requirement is calculated. Then, the necessary fleet is
estimated taking into account a spare of 10% for maintenance and breakdown.
9-49
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
In this section, effect of the shift from minibus to large bus is calculated and the effect to the road
is clarified. The calculation is done on all six routes.
Firstly, assuming passengers are carried by minibus, the total number of minibus and large bus
(both in pcu) are calculated by applying 10 passengers for a minibus and 46.8 passengers for a
large bus.
Table 9.8.9 Comparison of Number of Minibus and Large Bus on Large Bus Routes (2023)
(Assuming passengers are carried by minibus)
Total number pcu Total number Total number pcu Total number
of large bus Conversion of large bus in of minibus on Conversion of minibus in
on 6 routes factor pcu 6 routes factor pcu
5,573 2.40 13,375 26,054 1.15 29,962
Source: JICA Study Team
The decreased number of vehicles on bus routes and its effect to road traffic and road capacity
are shown in the following table.
Based on the calculation, it is noted that the introduction of large bus cannot change the traffic
condition drastically. But considering the congestion in GKMA, the introduction of large bus is
one of the necessary efforts to alleviate congestion.
In order to clarify the necessary measure for stable large bus operation that meets the passengers’
demand, financial analysis is conducted by two methods in this section.
- Financial analysis: Balance sheet of all six bus routes is estimated for a single year and
effective measures for improving the financial condition are proposed.
- Estimation of financial internal rate of return (IRR): Effectiveness of the proposed
measures is verified by estimation of financial IRR.
Based on the frequency and fleet by operation plan, financial analysis for the six large bus routes
is conducted. Base year of the analysis corresponds to the commencement year of the routes and
in this section, calculation is conducted for a single year.
9-50
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
Estimation of financial items described in the previous table is conducted following the operation
plan. Applied indices are surmised referring to the Final Report of BRT pre-feasibility studies
and the financial statements of public bus organizations in adjacent countries such as Rwanda
and Burundi. The following table shows the indices and methods for the estimation of the
financial items.
Table 9.8.12 Estimation Method for Financial Items
Operating Revenue
Operating Receipts 120 shillings per kilometer, base fare of 500 shillings, leakage of 10%
Operation Costs and Expenses
Variable costs
Fuel Consumption of 0.35 L/km for total running distance, fuel cost of
USD 1 /L
Tire USD 0.04 /km of total running distance
Spare parts USD 0.125/km of running distance
License and insurance USD 2,400 per year per vehicle including KCC trading license, TLB
PSV license and comprehensive insurance
Fixed costs
Driver 2 shifts for 16 hour operation and reserves for change, 500,000
shillings per month
Service staff Equivalent to number of drivers, 250,000 shillings per month
Maintenance staff 0.3 person per vehicle, 400,000 shillings per month
Office staff 0.6 person per vehicle, 350,000 shillings per month
Manager 1 person for a company, 750,000 shillings per month
Rent for bus depot 105 ㎡ per vehicle
Rent for office 10 ㎡ per office staff
Administrative costs Equivalent to fixed costs
Refund
Bus body USD 67,700 per vehicle including transport from Mombasa to
Kampala, 55 seats diesel bus, 2009 model
Import tax 49% of bus body
Loan 22% interest rate, 8 years of operation life
Income Tax 30% of income, interest for borrowed money is allowable
Source: JICA Study Team
Summary of the elements for the calculation is shown in the following table. The detailed
method is shown in the annex.
9-51
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
3) Balance Sheet
Two measures are considered for the improvement of financial condition of bus operation. One is
to ease the tax burden and the other is to increase the fare. Balance sheets of the following three
cases are calculated in consideration of these measures.
Case Condition
Base Case (Case 1) Current import tax, current minibus fare level
Case 2 Import tax exemption, current minibus fare level
Case 3 Import tax exemption, raising fare
9-52
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
Result of Calculation:
Profit rate varies among the large bus routes. Variation of profit rate is affected by the
operation efficiency (Table 9.8.7). Low efficiency route requires additional fleet
which becomes a burden for finance. As a whole, profit rates of all the bus routes are
too low to attract investors’ interest in the large bus business.
Result of Calculation:
The profit rates of all the bus routes are improved but are still low to attract investors’
interest in the large bus business.
9-53
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
Result of Calculation:
The profit rates of all the bus routes reach more than 15%. But even at this rate, large
bus business has some risk for the investors to invest. Therefore, additional assistance
by the government is necessary.
Through the analysis, it is clarified that large bus business cannot operate stably without
assistance from the government. The following measures are proposed:
a) Import tax exemption for the large bus body is at least a necessary measure for the bus entities.
b) In addition to import tax exemption, funds with low interest rate through government
financing are expected for the bus entities.
c) For the routes with low efficiency of bus operation, different fare system shall be introduced.
Following the conclusion of the financial analysis, financial IRR is analyzed to verify the
effectiveness of the proposed measures. To this end, Munyonyo Route (A) is selected for the
analysis.
1) Precondition
In the analysis, the following items are supposed to be the basic preconditions:
9-54
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
¾ Tax: Import tax exemption is the basic condition for the analysis.
¾ Traffic increase: Annual traffic increase rate from 2010 is 1.51% based on the traffic
demand forecast.
¾ Analysis period is eight years according to the operation life of large bus.
¾ Price index: According to the composite consumer price index from the Statistical
Abstract of Uganda Bureau of Statistics, annual price index is set to be 9.37%, which is
the average of all items from 2004 to 2008.
¾ Fare raising: 7.36% is applied as the annual large bus fare increase rate which is also
based on the transport and communication price index from the Statistical Abstract
The assumed cases for analysis are shown in the next table. Lending interest rate in Case 1 is
assumed at 22% based on the present lending rate. It is set to be 17% in Case 2, presuming the
establishment of the fund for the bus business as proposed in the previous section. In both Case 1
and Case 2, three cases with different levels of bus fare are examined. Case A involves the
present minibus level, Case B involves a 5% increase from the minibus level and Case C
involves a 10% increase from the minibus level.
2) Result of Calculation
The following table shows the result of financial IRR estimation. In Case 1-C and Case 2-C, IRR
rates exceed more than 10%. It is verified that both measures of reduction of interest rate and
raising fare are effective to improve the financial condition of bus operating entities.
9-55
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
The following tables show the financial balance in every year of the analysis period for the six
cases.
9-56
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
(3) Conclusions
According to the financial analysis and estimation of IRR, the following conclusions are derived:
a) Bus business cannot operate stably without assistance from the government.
- It is reasonable to raise the fare from the minibus level because large bus system provides
higher service level such as fixed time, fixed route and fixed fare.
- But it is also necessary to make efforts toward provision of refined and comfortable services
9-57
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
for passengers.
- Application of proper fare system is necessary to keep the profitability of bus routes where
passenger demand is less.
- It is necessary to gain additional income through various measures such as attaching
advertisements outside and inside bus body like those introduced in developed countries.
9-58
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
The required areas for facilities for large bus terminals and medium bus terminals are estimated
based on the same procedure in the estimation of IUBT facilities. Table 9.9.1 shows the future
transit passenger demand of the main transport and access transport. The number of lay-by and
parking facilities required for peak hour transport in each terminal is also shown in the table.
4.5% of the daily demand is applied for peak hour rate. Expected modal share of access transport
mode is also shown in Table 9.9.1.
As a result, Masanafu, Munyonyo and City Center terminals are to be small size terminals (Type
1) with a required area of 1,000m2, Kiwatule, Kigowa and Natete terminals are to be medium
size terminals (Type 2) with a required area of 2,000 m2, and Luafu terminal is to be a large size
terminal (Type 3) with a required area of 3,000m2 as shown in Table 9.9.1. Typical layout plan
for small and medium size terminals are shown in Figure 9.9.1.
9-59
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
9-60
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
The construction costs of the bus terminals have been estimated as shown in Table 9.9.2. The
required cost varies from UShs1.3 billion (USD 0.6 million) for small terminal of Type 1 (1,000
m2) to UShs 2.8 billion (USD 1.3 million) for medium size terminal of Type 3 (3,000 m2). The
total construction cost for the large and medium bus terminals will amount to UShs13.7 billion
shillings (USD 6.2 million).
The implementation period of each bus terminal will be determined taking into account the
implementation period of the large bus route and the medium bus route as shown in Section 9.6.
9-61
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
Bus lay-by is a basic facility for the stable operation of bus transport. Approximate interval of
lay-by will be around 400-500 m. The detailed location of each bus lay-by shall depend on the
detailed condition of the route. Typical size of bus lay-by is assumed from the amount of
passenger demand in each bus route as shown in Table 9.9.3.
Based on the preconditions described above, Table 9.9.4 shows the total number of typical bus
lay-by necessary for each bus route. The total construction cost is estimated to be UShs 6.5
billion (USD 3.0 million) excluding the Natete Road where the bus lay-bys are already improved.
Table 9.9.4 Total Number and Cost Required for Bus Lay-by Improvement Route
9-62
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
The total investment cost and schedule for public transport infrastructures including the IUBT
have been estimated as shown in Table 9.9.5. The total amount is about UShs 68.9 billion (USD
31.3 million). The total amount is divided into two phases, i.e., UShs 51.5 billion (USD 23.4
million) will be invested in the medium-term period from 2014 to 2018 and the UShs 17.4 billion
(USD 7.9 million) will be invested in the long term period by 2023.
Compared to the total amount of USD 1,380.4 million for the NTMP/GKMA from 2008 to 2023,
the expected total amount of bus infrastructures in the GKMA occupies 2.3% of the
NTMP/GKMA total amount. The investment in bus infrastructure plays the most important role
among the national transport items in terms of mass passenger transport for both inter-urban and
intra-urban transportation.
In this section, in order to compose the large bus network in harmony with the general traffic,
roads for the operation of large bus are evaluated and necessary measures to enhance smooth
operation of large buses are proposed. Necessary investment cost for the improvement is
included I NTMP/GKMA.
1) Target Roads
Target roads for evaluation and proposal are the roads on which large buses will be operated.
However, the roads which will be improved for the installation of the BRT network are excluded.
9-63
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
9-64
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
D1-1
Present traffic volume Heavy (Survey not conducted)
Great number of minibuses queuing to enter into small taxi park
Future traffic volume 2018 19,600-30,100
2023 17,800-31,600
Surface condition Partially deteriorated
Road width Total: 12-14 m
Carriageway: 5-7 m
Gradients Flat
Roadside land use Office, commercial
Old taxi park at the beginning point
View
Problem and issue - Future traffic volume exceeds the road capacity.
- Long queue of minibuses waiting to enter into taxi park.
Proposed improvements - Since this road is one of the trunk roads within the city center, improvement
of the road shall be analyzed in the context of the improvement of whole
network within the city center.
- Improvement of taxi park is proposed in the infrastructure plan for public
transport.
D1-2
Present traffic volume 11,958 vehicle/12hr. (Jan, 2010, JICA Study Team exclusive of motorcycle)
Future traffic volume 2018 19,300-29,100
2023 12,600-22,100
Surface condition Good
Road width Total: 12-15 m
Carriageway: 6-7 m
Gradients Steep almost all the way
Roadside land use Residential, office
View
9-65
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
D2-1
Present traffic volume Heavy (Survey not conducted)
Future traffic volume 2018 15,700
2023 20,900
Surface condition Good
Road width Total: 12-13 m
Carriageway: 5 m
Gradients Flat
Roadside land use Commercial
View
Problem and issue - Traffic jam at the crossing with the Entebbe Road.
- Kibue Junction near the crossing is one of the major congested points in
Kampala.
- No trunk road in the area between Entebbe Road and Gaba Road
- Future traffic demand exceeds capacity.
Proposed improvements - Improvement of Kibue Junction is proposed in this study.
- In the long-term, trunk road covering the area between Entebbe Road and
Gaba Road is required.
- Improvement method for the whole area shall be subject to further study.
Cross section to be
introduced
9-66
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
D2-2
Present traffic volume Heavy (Survey not conducted)
Future traffic volume 2018 11,500
2023 15,900
Surface condition Good
Road width Total: 10-12 m
Carriageway: 5-6 m
Gradients Small undulation
Roadside land use Residential
View
Problem and issue - No trunk road in the area between Entebbe Road and Gaba Road.
- Future traffic demand exceeds capacity.
Proposal for improvement - Road improvement method for the whole area shall be subject to further
study.
Cross section to be
introduced
9-67
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
D3
Present traffic volume Light (Survey not conducted)
Future traffic volume 2018 2,000
2023 3,400
Surface condition Good
Road width Total: 12-15 m
Carriageway: 5-7 m
Gradients Small undulation
Roadside land use Residential, farm
View
Problem and issue - Development along the road is foreseeable in the long term.
Proposed improvement - Improvement by two lanes is required.
Cross section to be
introduced
9-68
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
D4
Present traffic volume Light (Survey not conducted)
Future traffic volume 2018 8,400-10,800
2023 3,700-6,6000
Surface condition Partially deteriorated
Road width Total: 6-9 m
Carriageway: 4-5 m
Gradients Steep all the way
Roadside land use Residential, farm
View
Problem and issue - Land use along the road is sparse because of poor condition of service road.
- No trunk road is provided around the area.
Proposed improvements - Development of trunk road is required to enhance development of the town
along the road.
- Different route shall be selected to avoid steep hills.
- Development of two lane road is necessary.
Cross section to be
introduced
9-69
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
D5-1
Present traffic volume Heavy (Survey not conducted)
Future traffic volume 2018 15,000-18,600
2023 23,200-26,200
Surface condition Partially deteriorated
Road width Total: 13-15 m
Carriageway: 9-11 m
Gradients Partially gentle slope
Roadside land use Office, commercial
View
9-70
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
D5-2
Present traffic volume Heavy (Survey not conducted)
Future traffic volume 2018 13,600
2023 21,700
Surface condition Heavily deteriorated
Road width Total: 10-14 m
Carriageway: 6-8 m
Gradients Partially steep
Roadside land use Office, factory
View
9-71
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
D5-3
Present traffic volume Light (Survey not conducted)
Future traffic volume 2018 500
2023 5,800
Surface condition Deteriorated
Road width Total: 9-13 m
Carriageway:
Gradients Gentle slope
Roadside land use Residential
View
9-72
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
D6-1
Present traffic volume Heavy (Survey not conducted)
Future traffic volume 2018 12,800-18,800
2023 28,200-22,100
Surface condition Good
Road width Total: 10-15 m
Carriageway: 7-9 m
Gradients Steep
Roadside land use Generally residential, warehouse and factory at the beginning point
View
9-73
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
D6-2
Present traffic volume Light (Survey not conducted)
Future traffic volume 2018 1,000-2,900
2023 1,500-7,400
Surface condition Partially deteriorated
Road width Total: 10-14 m
Carriageway: 6-8 m
Gradients Gentle slope all the way
Roadside land use Generally residential
View
9-74
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
The following Table is a summary of the investment plan required to achieve the targets of the
Public Transport Plan.
(1) Organization
Currently, the TLB is the organization which licenses public service vehicle operation. The TLB
is required to reinforce and strengthen its functions and staffs for the introduction of large bus
and medium bus systems.
The BRT pre-feasibility studies proposed the Multi-sectoral Transport Regulatory Authority
(MTRA) and Metropolitan Area Transport Authority (MATA) as the control bodies for transport.
The ministry to control TLB will be reviewed if these institutions are realized.
2) Bus Fund
Establishment of fund is recommended to assist the bus operating entities. The government shall
finance the fund or introduce an international financing partner for the fund.
9-75
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
Operating industries of large buses will be led to organize a few unified operation entities from
the current large number of operators. Subsequently, it will become possible to adjust the
integrated timetable.
As for the maintenance of buses, operator should make a contract with bus supplier for bus
maintenance and the supplier shall appoint an adequate garage for repair and maintenance work.
In order to strengthen the organization in terms of licensing, and to induce investments for bus
operators, the authority and extent of governance of the public transport section in MoWT shall
be reinforced.
a) Large Bus
Basically, it is necessary to grant license to large buses on an individual route basis. In order to
provide the stable and steady service to passengers, the soundness of finance of the operating
industry will be evaluated and the fixed route, fixed fare and fixed schedule will be the
preconditions for licensing and will be obligatory. Supply of the number of buses will be
controlled in consideration of the demand along the route for the sake of avoidance of excessive
competition.
If two or more companies operate on a single route, the license authority will adjust the timetable.
Operating company will continue to operate at least five years to protect the beneficiary. License
will be renewed periodically but withdrawal without reason will not be approved. Moreover, the
company which caused heavy accident cannot continue to operate.
b) Medium Bus
Medium bus will replace the minibus gradually. The current licensing of the minibus will be
abolished in consideration of the progress of the introduction of the BRT and large bus and the
expansion of the service area of BRT and large bus.
The fixed route, fixed fare and fixed schedule will be the preconditions for licensing and will be
obligatory like in the large bus. Supply of the number of buses will be controlled in consideration
of the demand in the area for the sake of the avoidance of excessive competition. License will be
renewed periodically but withdrawal without reason will not be approved.
As articulated in Section 9.8, import tax exemption of bus body is requested for the reduction of
the burden of purchasing bus body. It will help in improving the financial condition of bus
operators.
3) Traffic Regulation
Basically, it is necessary to prohibit the running of minibus and Boda-Boda on the BRT and large
bus routes. But since enforcement of this regulation requires the approval of stakeholders, large
bus should follow the result of the BRT which will precede the introduction of large bus.
9-76
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
On common roads, the large bus should keep the regulation like other vehicles. However, when
the large bus tries to start from the bus stop, other vehicles should not interfere with the
confluence of the large bus.
Posts with sign board and timetable should be installed at the bus stops. Passengers should not
embark and disembark at places other than bus stops. Bus company should install the bus depot
outside the urban area to restrict the long parking time at the terminals.
(3) Stakeholders
The infrastructure of public transport such as the terminals and bus lay-bys should be part of the
road. The development and maintenance should be conducted as for the road because the
terminal and bus lay-by contribute toward the reduction of traffic congestion on the road.
Therefore, the resources for the development and maintenance of road will be invested to the
infrastructure for public transport. The authorities in charge of road will be responsible for the
development of infrastructure for public transport.
In this context, the road-related laws and regulations such as the Traffic and Road Safety Act
shall cover the terminal and bus lay-by.
The government needs to obtain assistance from donors to develop large scale bus terminal such
as the integrated terminal. Other small scale terminals will be developed by the government from
the budget for road development.
3) Market
Two methods are considered for the development of public market. One is to request the
assistance by the partners in the design and development. The other is to call for the investment
of private sector. In this case, the area surrounding the public market is developed simultaneously
for expanding commercial facilities. If the bus terminal and public market become the focus of
commercial activities, there will naturally be demand for commercial development in the
surrounding area. In spite of the fact that the investor cannot profit from public market, investor
can gain the profit from the sale of surrounding area.
The government shall select a corporation through proposal, give permission and assist the
corporation in the acquisition of land and necessary procedure.
The following are the proposals for the realization of public transport plan:
9-77
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
MoWT shall employ and request specialist from outside the government for direction in the
following aspects:
The investors of the bus fund compose the committee for the administration of the fund. The
committee will employ a specialist if necessary.
Direction for the bus operators will be conducted by the specialists employed by the government.
2) Development of Terminal
The government will clarify the responsible organization for the infrastructure of public transport,
and the government as a whole will approve and recognize the authority.
The government will request the foreign partner for technical assistance in the following sphere:
- Institution and regulations for the development and maintenance of public transport
infrastructure
- Introduction of instances of infrastructure development
- Demarcation of tasks between the government and the donor
- Assistance on the tasks of the government
The government shall request the partner for the implementation of the feasibility study for the
development of the infrastructure. In the feasibility study, the following items are scrutinized:
d) Implementation of development
Since the Study covered only formulation of conceptual model for the public transport plan, and
9-78
Final Report
The Study on Greater Kampala Road Network and Transport Improvement
in the Republic of Uganda November 2010
since the proposed locations of bus terminals are subject to the specific plan of BRT project,
environmental study such as IEE was not carried out for the public transport plan. Therefore, in
the feasibility study for the public transport plan proposed in the previous section, appropriate
environmental and social consideration should be conducted. The essential subjects to be
analyzed are the following two points.
Present minibus operators, drivers and passengers are the most affected PAPs by the reformation
of public transport system. Introduction of BRT will give an enormous impact to those PAPs.
Introduction of large Bus will also give a heavy impact to those people. Therefore the stake
holder meetings which will be conducted by the BRT Feasibility Study will give significant
lessons. Based on those lessons, environmental and social consideration shall be implemented in
the feasibility study proposed in the previous section.
This study proposed basic concept, function and distribution of terminals but exact location of
each terminal is not yet decided. In the proposed feasibility study which will decide the location
of terminals, necessary procedure for the environmental and social consideration shall be carried
out.
9-79