The document provides a detailed estimate for civil works related to a construction project in Duwakot, Bhaktapur, including site clearance, excavation, backfilling, and various construction materials and labor costs. The total estimated cost for the civil works is 1,062,629.84, with additional costs for sanitary and electrical work bringing the grand total to 1,317,661.00. Each section outlines specific tasks, units, quantities, rates, and amounts for clarity in budgeting and planning.

Uploaded by

Milan Karki
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
98 views4 pages

Estimate Laxmi Aunt

The document provides a detailed estimate for civil works related to a construction project in Duwakot, Bhaktapur, including site clearance, excavation, backfilling, and various construction materials and labor costs. The total estimated cost for the civil works is 1,062,629.84, with additional costs for sanitary and electrical work bringing the grand total to 1,317,661.00. Each section outlines specific tasks, units, quantities, rates, and amounts for clarity in budgeting and planning.

Uploaded by

Milan Karki
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

ESTIMATION OF STRUCTURE

Duwakot, Bhaktapur

DETAILED ESTIMATE

S.N. DESCRIPTION OF WORK UNIT NO: LENGTH BREADTH` HEIGHT QTY REMARKS
CIVIL WORKS
A SITE CLEARANCE WORKS
Site clearence with thick bush & small plant
cutting , removing of roots, cut of heaps of soil,
1 sqm 64.01
including construction site line and levelling
work
1.00 64.01 64.01

B EXCAVATION
Earthwork in excavation in ordinary soils in
2 foundation including 10m hauling distance and cum 3.08
1.5 m lift all complete
Wall along lengthside cuft 2.00 53.00 0.50 1.50 79.50
Wall along widthside cuft 3.00 13.00 0.50 1.50 29.25

C BACK FILLING
Earth Back filling in 150 mm thick layer,
3 watering, ramming including supply of filling cum 2.16
materials within 6 km distance all complete.
70% of Excavation 2.16

D BRICK SOILING
Supply & Filling/Soling of flat brick soling with
4 sqm 64.01
line and levelled work in foundation .
sqft 1.00 53.00 13.00 689.00

E PCC WORK
Plain cement Concrete (PCC) in 1:2:4 ratio for
foundations, flooring and walls with approved
quality of cement, sand and crushed stone
5 cum 4.88
aggregate including supplying mixing
laying,compacting , curing etc all complete in
approval of site engineer.
cuft 1.00 53.00 13.00 0.25 172.25

F STEEL WORK
Mild steel works 250 including straightening,
6 cleaning, cutting, binding & fixing in position MT
with welding
ISNB50 M 3.00 11.99 35.96

I CONCRETE BLOCK WORKS


IN SUPERSTRUCTURE
Good quality concrete Block in 1:4 C/S mortar
in Foundation in perfect line level finish
7 including wetting the blocks, racking the joints cum 103.05
and curing the work for at least 7 days all
complete.
Wall along long direction cuft 1.00 53.00 13.00 172.25
Wall along short direction cuft 3.00 13.00 13.00 507.00
Partition Wall cuft 1.00 13.00 5.00 65.00
Compound Wall cuft 1.00 73.00 5.00 365.00

J DOOR WINDOW WORKS


Supplying an glass ( Frame 50x80 mm , Sash 58*
8 sqm 37.90
36 mm ) UPVC Panels all complete.
Ground floor sqft 1.00 51.00 8.00 408.00
DETAILED ESTIMATE

S.N. DESCRIPTION OF WORK UNIT NO: LENGTH BREADTH` HEIGHT QTY REMARKS
K PLASTER WORK
20 mm thick cement sand plaster in (1:4) ratio on
9 sqm 227.89
wall. (External Plaster)
Wall along long direction sqft 2.00 53.00 13.00 689.00
Wall along short direction sqft 6.00 13.00 13.00 1014.00
Partition Wall sqft 2.00 13.00 5.00 130.00
Compound Wall sqft 2.00 73.00 5.00 730.00
Deduction
Window sqft (2.00) 4.00 4.00 (32.00)
DOOR sqft (2.00) 2.50 6.00 (30.00)
Window sqft (2.00) 4.00 6.00 (48.00)

L PAINT WORKS
Supplying and applying Two coat weather proof
painting with one coat primer of approved
10 Sq.m 227.89
color in building as per specifications and
instruction of the site engineer.(Berger)
Same as external plaster sqft 227.89 227.89

M Roofing Work
Supplying and providing of 0.5mm thick CGI
11 sqm 1.00 53.00 18.00 88.63
Roofing Sheet all complete.
Providing and fitting of gutter pipe with necessary
12 fitting and accessories all complete as directed by the R.m 1.00 53.00 16.15
site engineer.

N Iron Works
Providing and fixing of Rolling Shutter of 80
mm wide and 1.25 mm thick MS laths of mild
13 steel sheet machine rolled with necessary Unit 4.00 4.00
fittings all complete as directed by the site
engineer
ESTIMATION OF STRUCTURE
Duwakot, Bhaktapur

SUMMARY OF COST

S.N Description Unit Quantity Rate Amount Remark


CIVIL WORKS
Site clearence with thick bush & small
plant cutting , removing of roots, cut of
1 sqm 64.01 135.00 8,641.38
heaps of soil, including construction site
line and levelling work
Earthwork in excavation in ordinary soils
in foundation including 10m hauling
2 cum 3.08 750.00 2,309.59
distance and 1.5 m lift all complete

Earth Back filling in 150 mm thick layer,


watering, ramming including supply of
3 cum 2.16 1,100.00 2,371.18
filling materials within 6 km distance all
complete.
Supply & Filling/Soling of flat brick
4 soling with line and levelled work in sqm 17.60 700.00 12,316.93
foundation .
Plain cement Concrete (PCC) in 1:2:4
ratio for foundations, flooring and walls
with approved quality of cement, sand
5 and crushed stone aggregate including cum 4.88 10,000.00 48,775.77
supplying mixing laying,compacting ,
curing etc all complete in approval of site
engineer.
Assembling and erecting of specified
steel sections confirmed to IS 800-2007
in place with tying down bolts, nuts
revits and application of 2 coats of
6 KG 35.96 200.00 7,192.67
redoxide primer, treating of weld
surfaces for smooth finishes etc as per
specifications,drawings and instructions
by Engineer incharge.
Good quality concrete Block in 1:4 C/S
mortar in Foundation in perfect line level
7 finish including wetting the blocks, sqm 103.05 1,900.00 195,800.12
racking the joints and curing the work
for at least 7 days all complete.
Supplying an glass ( Frame 50x80 mm ,
8 Sash 58* 36 mm ) UPVC Panels all sqm 37.90 7,500.00 284,283.30
complete.
20 mm thick cement sand plaster in (1:4)
9 sqm 227.89 475.00 108,248.30
ratio on wall. (External Plaster)
Supplying and applying Two coat
weather proof painting with one coat
10 primer of approved color in building as Sq.m 227.89 375.00 85,459.18
per specifications and instruction of the
site engineer.(Berger)
Providing and fixing of Rolling Shutter
of 80 mm wide and 1.25 mm thick MS
11 laths of mild steel sheet machine rolled Unit 4.00 45,000.00 180,000.00
with necessary fittings all complete as
directed by the site engineer
Supplying and providing of 0.5mm thick
12 Sq.m 88.63 1,400.00 124,081.30
CGI Roofing Sheet all complete.
ESTIMATION OF STRUCTURE
Duwakot, Bhaktapur

SUMMARY OF COST

S.N Description Unit Quantity Rate Amount Remark


Providing and fitting of gutter pipe with
necessary fitting and accessories all
13 R.m 16.15 195.00 3,150.11
complete as directed by the site engineer.

Sub Total Civil work 1,062,629.84


Sanitary Work 127,515.58
Electrical Work 127,515.58
Grand Total 1,317,661.00