Resource Optimization in Project Management
Resource Optimization in Project Management
Page 1
C. Modeling D. A and C are answers
10. Which one of the following is component of linear programming model?
A. Setting of decision variables C. Setting of objective
B. Setting of constraints D. Setting of a non-negative variables E. All of the above
11. In LP model, which one of the following is expressed in the form of inequalities?
A. Objective function B. Constraints variables E. None
C. Decision D. All of the above
12. Which one of the following is wrong about linear programming
A. It is used to find the minimum or maximum value of the objective function
B. It is a mathematical modeling technique used to determine optimal allocation of resources
C. It consists of linear objective function and linear constraints
D. It is expressed with a first degree function
E. None of the above
13. Which one of the following is not the application area of operational research
A. Scheduling B. Supply chain management C. Optimization D. None of the above
14. In a linear programming problem, which one of the following is correct for graphical method?
A. A point in the feasible region is a solution to the problem
B. One of the corner points of the feasible region is the optimum solution
C. Any point in the positive quadrant does not satisfy the non-negativity constraint
D. The lines corresponding to different values of objective functions are parallel?
15. In a linear programming problem, which one of the following is correct for transportation problem?
A. If the of cell occupied in a m x n transportation problem, is less than (m+n-1) then the problem is said to
be non-degenerate.
B. If the of cell occupied in a m x n transportation problem, is equal to (m+n-1) then the problem is said to
be degenerate.
C. If the of cell occupied in a m x n transportation problem, is equal to (m+n-1) then the optimal
solution is reached.
D. None of the above
16. In a linear programming problem, an assignment problem is not characterized by
A. Each worker (or resource) can be assigned to only one job (or task)
B. The objective is typically to minimize the total cost or maximize the total benefit of assigning jobs to
workers
C. Each worker can only be assigned to one job, and each job can only be assigned to one worker.
D. The decision variables are usually binary (either 0 or 1), indicating whether a specific job is assigned to
a specific worker.
E. None of the above
17. An optimal solution of an assignment problem can be obtained only if
A. Each row & column has only one zero element
B. Each row & column has at least one zero element
Page 2
C. The data is arrangement in a square matrix
D. None of the above
18. In applying Vogel's approximation method to a profit maximization problem, row and column penalties are
determined by:
A. Finding the largest unit cost in each row or column.
B. Finding the smallest unit cost in each row or column.
C. Finding the sum of the unit costs in each row or column.
D. Finding the difference between the two lowest unit costs in each row and column.
E. Finding the difference between the two highest unit costs in each row and column
A linear programming model to maximize profit is given below. Based on the model, answer questions from
19 to 20.
Max Z = 60x +18y
Subject to constraints
2x+y ≤ 100
x+y ≤ 80
x ≥0 and y ≥0
19. The maximum profit of the company is
A. 3000 Birr B.4500 Birr C. 5000 Birr D. 4000 Birr E. None of the above
20. The amount product (x,y) that generate maximum profit for the company is
A. (0, 50) B. (50, 0) C. (50, 30) D. (30, 50) E. None of the above
Page 3
21. Which of the following is not a phase of project management?
a) Project planning b) Project scheduling c) Project controlling d) Project
being
22. Who introduced the bar charts?
a) Williams henry b) Henry Gantt c) Jane Gantt d) Joseph
henry
23. The difference between the maximum time available and the actual time needed to perform
an activity is known as _________
a) Free float b) Independent float c) Total float d) Half float
24. In the plinth area method, the cost of construction is computed by the multiplication of
________
a) Plinth length and rate b) Plinth breadth and rate c) Plinth area and plinth
area rate
d) Plinth volume and plinth length rate
25. For the preparation of approximate estimates, cubical contents method is more accurate than
the unit base method and plinth area method.
a) True b) False
26. Which one of the following represents an activity
a) excavation for foundation
b) curing of concrete
c) setting of question paper
d) preparation of breakfast
e) all the above.
27. Which of the following does not represent an activity?
A. Site located B. Foundation is being dug C. The office area is
being cleaned D. The invitations are being sent
28. In time-cost optimization of a project, crashing is done.
(A) On all the activities
(B) On all the activities lying on the critical path
(C) Only on activities lying on the original critical path and having flatter costslopes
(D) On original critical activities and those that become critical at any stage of crashing
inthe order of ascending cost slope
Answer: Option D
29. Which of the following does not represent an activity?
(A) Site located
(B) Foundation is being dug
(C) The office area is being cleaned
(D) The invitations are being sent
Answer: Option A
30. In resources levelling
(A) Total duration of project is reduced
(B) Total duration of project is increased
(C) Uniform demand of resources is achieved
(D) Cost of project is controlled
Answer: Option C
31. Sensitivity analysis is a study of
(A) Comparison of profit and loss
(B) Comparison of assets and liabilities
(C) Change in output due to change in input
(D) Economics of cost and benefits of the project
Answer: Option C
32. Preliminary project report for a road project must contain
(A) The detailed estimated cost based on detailed design
(B) The several alternatives of the project that have been considered
(C) The soil survey, traffic survey, concept design and approximate cost
(D) The contract documents for inviting tenders
Answer: Option C
33. For which of the following materials, the output of power shovels for a fixed shovel size will be
maximum
(A) Moist loam
(B) Good common earth
(C) Well blasted rock
(D) Wet sticky clay
Answer: Option A
34. In PERT analysis, the time estimates of activities and probability of their occurrence follow
(A) Normal distribution curve
(B) Poisson's distribution curve
(C) Beta distribution curve
(D) None of the above
Answer: Option C
35. Free float is mainly used to
(A) Identify the activities which can be delayed without affecting the total float of
preceding activity
(B) Identify the activities, which can be delayed without affecting the total float of
succeeding activity
(C) Establish priorities
(D) Identify the activities which can be delayed without affecting the total float of either
the preceding or succeeding activities
Answer: Option B
36. Grader is used mainly for
(A) Trimming and finishing
(B) Shaping and trimming
(C) Finishing and shaping
(D) Finishing, shaping and trimming
Answer: Option
37. Which of the following surfaces will give highest rolling resistance for a rubber tyred vehicle?
(A) Concrete
(B) Loose sand
(C) Asphalt
(D) Firm earth
Answer: Option B
38. Which of the following earth moving machines has the shortest cycle time?
(A) Drag line
(B) Hoe
(C) Clam shell
(D) Dipper shovel
Answer: Option D
39. Updating may result in
(A) Change of critical path
(B) Decrease of project completion time
(C) Increase of project completion time
(D) All of the above
Answer: Option D
40. The time by which a particular activity can be delayed without affecting the preceding and
succeeding activities is known as
(A) Total float
(B) Free float
(C) Interfering float
(D) Independent float
Answer: Option D
41. During the construction period, price variation clause in contracts caters to
(A) Increase in rates of only important materials
(B) Variation in cost in materials element, labour element and petrol-oil-lubricant element
(C) Variation in total cost of the project on an ad hocbasis
(D) Rate of inflation
Answer: Option B
42. Critical path method
(A) Is an improvement upon bar chart method
(B) Provides a realistic approach to daily problems
(C) Avoids delays which are very common in bar charts
(D) All the above
Answer: Option D
43. At a work site, statistical quality control of concrete means
(A) Measurement of risks to eliminate failures
(B) Applying the theory' of probability to sample testing or inspection
(C) Reduction in wastage of inspection costs
(D) Reduction in costs for the removal of defects
Answer: Option B
44. For the network shown in the given figure, the expected time for the activity
(A) 1-2 is 4
(B) 2-3 is 7
(C) 3-4 is 8
(D) All the above
Answer: Option D
45. A critical ratio scheduling
(A) Determines the status of each activity
(B) Adjusts automatically changes in activity progress
(C) Is a dynamic system
(D) None of these
Answer: Option D
46. For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5,
17 and 8 days respectively, The expected time is
(A) 8 days
(B) 9 days
(C) 10 days
(D) 15 days Answer:
Option B
47. Pick up the correct statement from the following:
(A) Optimistic time estimate refers to activities
(B) Pessimistic time estimate refers toactivities
(C) Most likely time estimate refers to activities
(D) All the above
Answer: Option D
48. In the time-cost optimisation, using CPM method for network analysis, the crashing of the
activities along the critical path is done starting with the activity having
(A) Longest duration
(B) Highest cost slope
(C) Least cost slope
(D) Shortest duration
Answer: Option C
49. A golden rule for the procurement of construction stones, suggests
(A) 100% at the site
(B) 67% at the site and 33% under procurement
(C) 50% at the site and 50% under procurement
(D) 33% at the site and 67% under procurement
Answer: Option B
50. The time with which direct cost does not reduce with the increase in time is known as
(A) Crash time
(B) Normal time
(C) Optimistic time
(D) Standard time
Answer: Option B
51. Pick up the correct statement from the following with regards to C.P.M. network analysis of
projects
(A) The latest occurrence time of the node of which the activity arrow terminates minus the
duration of the activity, is called latest start time
(B) The latest occurrence time for the node at which the activity arrow terminates, is
called latest finish time
(C) Earliest occurrence time of the event from which the activity arrow' originates, is
called earliest start time of the activity
(D) All the above
Answer: Option D
52. Interfering float is the difference between
(A) Total float and free float
(B) Total float and independent float
(C) Free float and independent float
(D) None of the above
Answer: Option A
53. While filling the tender for any work, the contractor considers
(A) Site survey
(B) Availability of construction materials
(C) Availability of labour
(D) All the above
Answer: Option D
54. An excavator costs Birr 20,00,000 and has an estimated life of 8 years. It has no salvage value at
the end of 8 years. The book value of the excavator at the end of 3 years using general double
declining balance method is
(A) Birr 8,43,750
(B) Birr 8,75,000
(C) Birr 10,50,000
(D) Birr 11,56,250
Answer: Option A
55. Pick up the incorrect statement from the following:
(A) The various functions under each activity, are shown by one bar on Bar Charts
(B) Bar chart establishes the interdependency of one event on another
(C) Only approximate percentage of the completed work is reported
(D) None of these
Answer: Option B
56. A wheeled tractor hauling unit is working on firm earth. The total loaded weight distribution of
this unit is:
Drive wheels: 25000 kg Scraper
wheels: 10000 kg
If the coefficient of traction for wheeled tractor on firm earth is 0.5, the rimpull which this tractor can
exert without slipping is
(A) 10000 kg
(B) 12500 kg
(C) 22500 kg
(D) 5000 kg
Answer: Option B
57. If the expected time of completion of a project is 60 weeks with a standard deviation of 5 weeks,
the probability of completing the project in 50 weeks and 65 weeks respectively will be
(A) 2.3% and 84.1%
(B) 97.7% and 84.1%
(C) 97.7 % and 15.9%
(D) 15.9% and 97.7%
Answer: Option A
58. Power stations are generally treated as
(A) Light construction
(B) Heavy construction
(C) Industrial construction
(D) Electrical construction
Answer: Option C
59. For a given size of bucket, the ideal output of a dragline will be least in
(A) Moist loam
(B) Sand and gravel
(C) Good common earth
(D) Wet sticky clay
Answer: Option D
60. Bar charts are suitable for
(A) Minor works
(B) Major works
(C) Large projects
(D) All the Above
Answer: Option A
61. The time corresponding to minimum total project cost is
(A) Crash time
(B) Normal time
(C) Optimistic time
(D) Between normal time and crash time
Answer: Option D
62. Construction team means
(A) An engineer
(B) An architect
(C) An owner
(D) All the above
Answer: Option D
63. Select the incorrect statement.
(A) Start float and finish float are always equal.
(B) Total float can be either start float or finish float.
(C) Start float and finish float need not be equal.
(D) Start float and finish float are the differences between activity times and not event times.
Answer: Option C
64. The artificial activity which indicates that an activity following it, cannot be started unless the
preceding activity is complete, is known as
(A) Event
(B) Free float
(C) Dummy
(D) Constraint
Answer: Option C
65. PERT technique of network analysis is mainly useful for
(A) Small projects
(B) Large and complex projects
(C) Research and development projects
(D) Deterministic activities
Answer: Option C
66. Pick up the correct statement from the following:
(A) The float may be positive, zero or negative
(B) If the float is positive and the activity is delayed by a period equal to its total float,
the completion of project is not delayed
(C) If the float of an activity is negative, delay in its performance is bound to delay
the completion of project
(D) All the above
Answer: Option D
67. The independent float affects only
(A) Preceding activities
(B) Succeeding activities
(C) The particular activity involved
(D) None of the above
Answer: Option C
68. Site order book is used for recording
(A) Instructions by the executive engineers
(B) Construction measurements
(C) Issue of store equipments
(D) Names of the casual labour
Answer: Option A
69. The time by which activity completion time can be delayed without affecting the start of
succeeding activities, is known as
(A) Duration
(B) Total float
(C) Free float
(D) Interfering float
Answer: Option C
70. The part of a derrick crane include
(i) Mast
(ii) Boom
(iii) Bull wheel
(iv) Jack
Of these statements
(A) (i), (ii) and (iv) are correct
(B) (ii), (iii) and (iv) are correct
(C) (i), (iii) and (iv) are correct
(D) (i), (ii) and (iii) are correct
Answer: Option D
71. If the gross vehicle weight of a truck is 30 tonne and rolling resistance is 30 kg/tonne, then the
tractive effort required to keep the truck moving at a uniform speed is
(A) 30 kg
(B) 300 kg
(C) 900 kg
(D) 1000 kg
Answer: Option C
72. Works costing less than Birr 20,000 are treated as
(A) Any project
(B) Major projects
(C) Minor projects
(D) All the above
Answer: Option C
73. A machine costs Birr 20000 and its useful life is 8 years. The money is borrowed at 8% interest
per annum. The capital recovery factor at 8% interest per annum for 8 years is 0.174. The annual
equipment cost of the machine will be
(A) Birr 1740
(B) Birr 3480
(C) Birr 5220
(D) Birr 6960
Answer: Option B
74. Railway projects are treated as
(A) Light construction
(B) Heavy construction
(C) Industrial construction
(D) None of these
Answer: Option B
75. Consider the following statements:
In the critical path method of construction planning, Free Float can be.
1. Greater than Total Float.
2. Greater than Independent Float
3. Equal to Total Float.
4. Less than Independent Float. Of these statements
(A) 1 and 4 are correct
(B) 2 and 3 are correct
(C) 1 and 4 are correct
(D) 1 and 2 are correct
Answer: Option B
76. Pick up the correct statement from the following:
(A) The duration between the earliest start time of the preceding event and latest finish time of
the succeeding event, is called 'float'
(B) The duration of time by which an activity can be delayed without affecting the
succeeding activity, is called free float
(C) The difference between total float and free float, is called interfering float
(D) All the above
Answer: Option D
77. The original cost of equipment is Birr 10,000. Its salvage value at the end of its total useful life of
five years is Birr 1,000. Its book value at the end of two years of its useful life (as per straight line
method of evaluation of depreciation) will be
(A) Birr 8,800
(B) Birr 7,600
(C) Birr 6,400
(D) Birr 5,000
Answer: Option C
78. For completion of a project, the critical path of the network represents
(A) Minimum time
(B) Maximum time
(C) Maximum cost
(D) Minimum cost
Answer: Option A
79. The maximum rimpull in the first gear of a tractor while towing a load is 6300 kg. The tractor
weighs 12.5 tonnes and is operating along a 2 percent upgrade and the rolling resistance is 45
kg/tonne. Pull available for towing the load is
(A) 3425 kg
(B) 5515 kg
(C) 4350 kg
(D) 2975 kg
Answer: Option B
80. Which one of the following represents an event?
(A) Concrete cured
(B) Fixing of door
(C) Plastering of walls
(D) Selecting sites
Answer: Option A
81. The rated loads of lifting cranes, as percentage of tipping load at specified radius, for crawler-
mounted and pneumatic tyre-mounted machines would be respectively
(A) 80 and 90
(B) 90 and 80
(C) 85 and 75
(D) 75 and 83
Answer: Option D
82. PERT is
(A) An analytic in concept
(B) Limited of event oriented diagrams
(C) Used for research and development projects
(D) All the above
Answer: Option D
83. Optimistic time, most likely time and pessimistic times for the activities of a network in the given
figure are written above their arrows. If the contractual obligation time for the project is 75, the
latest occurrence time for the event 2, is
(A) 20
(B) 25
(C) 35
(D) 15
Answer: Option B
84. An earth moving equipment costs Rs. 5,00,000 and has an estimated life of 10 years and a salvage
value of Rs. 50,000. What uniform annual amount must be set aside at the end of each of the 10
years for replacement if the interest rate is 8% per annum and if the sinking fund factor at 8% per
annum interest rate for 10 years is 0.069?
(A) Rs. 31050
(B) Rs. 34500
(C) Rs. 37950
(D) Rs. 50000
Answer: Option A
85. Output of a bulldozer is
(i) Increased if drawbar HP of the tractor is increased for a given hauling distance
(ii) Decreased if drawbar HP of the tractor is increased for a given hauling distance
(iii) Increased if the hauling distance is increased for a given drawbar HP of the tractor
(iv) Decreased if the hauling distance is increased for a given drawbar HP of thetractor
Of these statement
(A) (i) and (iii) are correct
(B) (i) and (iv) are correct
(C) (ii) and (iii) are correct
(D) (ii) and (iv) are correct
Answer: Option B
86. For the execution of a project, a contractor is
(A) A person
(B) A firm
(C) An agency
(D) All the above
Answer: Option D
87. The constraints in case of resource smoothening operation would be
(A) Resources
(B) Project duration time
(C) Both resources and project duration time
(D) None of the above
Answer: Option B
88. The time which results in the leasi, possible construction cost of an activity, is known as
(A) Normal time
(B) Slow time
(C) Crash time
(D) Standard time
Answer: Option B
89. The direct cost of a project with respect to normal time is
(A) minimum
(B) Maximum
(C) Zero
(D) Infinite Answer:
Option A
90. The object of technical planning, is
(A) Preparation of specifications
(B) Preparation of estimates
(C) Initiating the procurement action of resources
(D) All the above
Answer: Option D
91. If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then
its expected time and variance are respectively
(A) 3.5 and 5/6
(B) 5 and 25/36
(C) 3.5 and 25/36
(D) 4 and 5/6 Answer:
Option C
92. Various activities of a project, are shown on bar charts by
(A) Vertical lines
(B) Horizontal lines
(C) Dots
(D) Crosses Answer:
Option B
93. Select the correct statement.
(A) Activity arrows in a CPM network are drawn to scale
(B) The tail of an arrow represents the finish of an activity
(C) Arrow bead represents the start of an activity
(D) None of the above
Answer: Option D
94. If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest
finish time, then the following relation holds good
(A) EF = ES + D
(B) LS = LF - D
(C) LF = LS + D
(D) All the above
Answer: Option D
95. Total float for any activity is defined as the difference between
(A) Its latest finish time and earliest start time for its successor activity
(B) Its latest start time and earliest start time
(C) Its latest start time and earliest finish time
(D) Its earliest finish time and earliest start time for its successor activity
Answer: Option B
96. Pick up the incorrect statement from the following:
(A) The activity is the time consuming part of a project
(B) The beginning and end of a job, are called events
(C) The activity which consumes maximum time, is called a node
(D) Logically and sequentially connected activities and events form a network
Answer: Option C
97. Assertion (A): Activity 57 is critical.
Reason (R): Earliest finish time and latest finish time for events 57 are same Select
the correct answer.
(A) A is correct but R is not correct
(B) R is correct but A is not correct
(C) Both A and R is correct
(D) Both A and R is incorrect
Answer: Option A
98. The main principle of an organisation, is
(A) Unity of command
(B) Effective control at all levels
(C) Delegation of authority
(D) All the above
Answer: Option D
99. If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the
expected time of completion of the project with 99.9% probability is
(A) 4 days
(B) 6 days
(C) 10 days
(D) 16 days Answer:
Option D
100. Pick up the correct statement from the following:
(A) Earliest expected time is denoted by TE
(B) Latest occurrence time is denoted by TL
(C) Contractual obligation time is denoted by Ts
(D) All the above
Answer: Option D
101. Consider the following operations:
1. Drilling
2. Blasting
3. Mucking
4. Placing steel
5. Placing concrete
The correct sequence of these operations in tunnel construction is
(A) 1, 2, 4, 3, 5
(B) 1, 3, 2, 4, 5
(C) 1, 2, 3, 4, 5
(D) 1, 3, 4, 2, 5
Answer: Option C
102. Pick up the incorrect statement from the following:
(A) The difference between the earliest start time and latest finish time of any activity, is the
maximum time available for the activity
(B) The difference between the maximum time available for the job and actual time it
consumes, is called total float
(C) The difference between the latest start time and earliest start time of an activity, is called
total float
(D) None of these
Answer: Option D
103. The basic action involved in sheep foot rolling is
(A) Kneading
(B) Pressing
(C) Tamping
(D) Vibration Answer:
Option A
104. Pick up the correct statement from the following:
(A) Programme Evaluation and Review Technique, is event oriented
(B) Programme Evaluation and Review Technique is not event oriented
(C) Critical Path Method is event oriented
(D) Critical Path method is event oriented
Answer: Option A
105. If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can
excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for
which the cost of excavation by machine will be equal to the cost of manual excavation is
(A) 500 cum
(B) 1000 cum
(C) 1500 cum
(D) 2000 cum
Answer: Option A
106. Time and progress chart of a construction, is also known as
(A) Bar chart
(B) Gantt chart
(C) Modified Mile stone chart
(D) All the above
Answer: Option D
107. Economic saving of time results by crashing
(A) Cheapest critical activity
(B) Cheapest noncritical activity
(C) Costliest critical activity
(D) Costliest noncritical activity
Answer: Option A
108. In the given figure, the network of a project represents
(A) 19
(B) 14
(C) 24
(D) None of these
Answer: Option A
121. Consider the following activities in a building construction:
1. Concreting of roof slabs
2. Brick-jelly lime concrete terracing
3. Erection of form work for slab
4. Construction of parapet wall in terrace
The correct sequence of these activities is
(A) 1, 3, 2, 4
(B) 3, 1, 4, 2
(C) 3, 1, 2, 4
(D) 1, 3, 4, 2
Answer: Option C
122. Military organisation is known as
(A) Line organisation
(B) Line and staff organisation
(C) Functional organisation
(D) None of these
Answer: Option A
123. Mobilization advance up to 10% of the cost of work is given to a contractor
(A) On commencement of work at site for payment of loan taken by him
(B) For the purchase of construction materials
(C) For the payment of advances to labour and other staff
(D) For all activities required to start the work at site on finalization of the contract
document Answer: Option D
124. Pick up the PERT event from the following:
(A) Digging of foundation started
(B) Digging of foundation completed
(C) Laying of concrete started
(D) All the above
Answer: Option D
125. A machine is purchased for Rs. 10,000,00 and has an estimated life of 10 years. The salvage
value at the end of 10 years is Rs. 1,50,000. The book value of the machine at the end of 5 years
using general straight line method of evaluation of depreciation is
(A) Rs. 4,75,000
(B) Rs. 5,75,000
(C) Rs. 6,50,000
(D) Rs. 8,50,000
Answer: Option B
126. Pick up the incorrect statement from the following:
(A) An activity of a project is denoted by an arrow on the net work
(B) The tail of the arrow indicates the start of the activity
(C) The head of the arrow indicates the end of the activity
(D) The arrows are drawn to scale from left to right
Answer: Option D
127. The process of incorporating changes and rescheduling or replanning is called
(A) Resource levelling
(B) Resource smoothening
(C) Updating
(D) Critical path scheduling
Answer: Option C
128. Completion of an activity on CPM network diagram, is generally known
(A) Event
(B) Node
(C) Connector
(D) All the above
Answer: Option D
129. Assertion A: For a given depth of cut, the output of a power shovel can be increased by
decreasing the angle of swing.
Reason R: If the angle of swing is decreased, the cycle time will be decreased. Select
the correct answer.
(A) Both A and R is true and R is the correct explanation of A
(B) Both A and R is true but R is not the correct explanation of A
(C) A is true but R is false
(D) A is false but R is true
Answer: Option A
130. The salient feature of functional organisation is
(A) Strict adherence to specifications
(B) Separation of planning and design part
(C) Each individual maintains functional efficiency
(D) All the above
Answer: Option D
131. A tractor shovel has a purchase price of Rs. 4.7 lacs and could save the organization an
amount of rupees one lac per year on operating costs. The salvage value after the amortization
period is 10% of the purchase price. The capital recovery period will be
(A) 3.7 years
(B) 4.23 years
(C) 5 years
(D) 7.87 years
Answer: Option B
132. The first method invented for planning projects, was
(A) Bar chart method
(B) Milestone chart
(C) Critical path method (CPM)
(D) Programme Evaluation and Review Technique (PER)
Answer: Option A
133. Which one of the following is not an excavating and moving type of equipment?
(A) Bulldozer
(B) Clam shell
(C) Scraper
(D) Dump truck
Answer: Option D
134. The main disadvantage of line organisation, is
(A) Rigid structure
(B) Extraordinary delay in communications
(C) Top level executions over work
(D) All the above
Answer: Option D
135. Batching refers to
(A) Controlling the total quantity at each batch
(B) Weighing accurately, the quantity of each material for a job before mixing
(C) Controlling the quantity of each material into each batch
(D) Adjusting the water to be added in each batch according to the moisture content of the
materials being mixed in the batch
Answer: Option C
136. While scheduling a project by C.P.M.
(A) A project is divided into various activities
(B) Required time for each activity is established
(C) Net work is drawn by connecting the activities and the events
(D) All the above
Answer: Option D
137. Slack time refers to
(A) An activity
(B) An event
(C) Both event and activity
(D) None of the above
Answer: Option B
138. Final technical authority of a project lies with
(A) Assistant Engineer
(B) Executive Engineer
(C) Superintending Engineer
(D) Chief Engineer
Answer: Option D
139. Whenever an activity has zero total float, then
(A) Free float of the activity must be zero but independent float need not be zero
(B) Independent float must be zero but free float need not be zero
(C) Free float and independent float both must be zero
(D) Free float and independent float both need not be zero
Answer: Option C
140. Mile Stone charts were invented in the year of
(A) 1910
(B) 1920
(C) 1930
(D) 1940
Answer: Option D
141. Which of the following is not a PERT event?
(A) Site investigation started
(B) Sessional work completed
(C) Bus starts from Jaipur
(D) Class is being attended
Answer: Option D
142. A construction schedule is prepared after collecting
(A) Number of operations
(B) Output of labour
(C) Output of machinery
(D) All the above
Answer: Option D
143. A tractor whose weight is 20 tonnes has a drawbar pull of 2500 kg, when operated on a level
road having a rolling resistance of 30 kg per tonne. If this tractor is operated on a level road
having a rolling resistance of 40 kg per tonne, then the drawbar pull of the tractor will
(A) Reduce by 200 kg
(B) Increase by 200 kg
(C) Increase by 250 kg
(D) Reduce by 250 kg
Answer: Option A
144. Pick up the correct statement from the following:
(A) The difference of latest occurrence time and earliest expected time, is calledslack
(B) The activities connecting the events having zero slack, lie on the critical path
(C) The critical path consumes the maximum time
(D) All the above
Answer: Option D
145. Frequency distribution curves
(A) Having a single lump, are called uninodal curves
(B) If symmetrical, are called normal curves
(C) If not symmetrical, are called skew curves
(D) All the above
Answer: Option D
146. Consider the following statements:
Wheeled tractors are replacing crawler tractors because
1. Wheeled tractors travel faster.
2. Crawler tractors are more expensive.
3. Track parts of a crawler wear out quickly.
4. Crawler tractors have stick control.
Of these statements
(A) 1, 3 and 4 are correct
(B) 2, 3 and 4 are correct
(C) 1, 2 and 3 are correct
(D) 1, 2 and 4 are correct
Answer: Option C
147. The difference between the time avail-to do a job and the time required to do the job, is known
as
(A) Event
(B) Float
(C) Duration
(D) Constraint
Answer: Option B
148. The grade resistance factor for an earth moving machine can be obtained by multiplying grade
percentage by a factor approximately equal to
(A) 2 kg/tonne
(B) 6 kg/tonne
(C) 9 kg/tonne
(D) 20 kg/tonne
Answer: Option C
149. A dummy activity
(A) Is artificially introduced
(B) Is represented by a dotted line
(C) Does not consume time
(D) All the above
Answer: Option D
150. The reduction in project time normally results in
(A) Decreasing the direct cost and increasing indirect cost
(B) Increasing the direct cost and decreasing the indirect cost
(C) Increasing the direct cost and indirect cost both
(D) Decreasing the direct cost and indirect cost both
Answer: Option B
151. Frederick W. Taylor introduced a system of working known as
(A) Line organisation
(B) Line and staff organisation
(C) Functional organisation
(D) Effective organisation
Answer: Option C
152. The area under the Beta distribution curve is divided into two equal parts by
(A) Most likely time
(B) Optimistic time
(C) Pessimistic time
(D) Expected time
Answer: Option D
153. CPM is
(A) Synthesising in concepts
(B) Is built of activities oriented programme
(C) Is based on time estimate
(D) All the above
Answer: Option D
154. A four wheel truck or whose operating weight is 12000 kg is pulled along a road having a
rising slope of 2% at a uniform speed. Assume grade resistance factor = 10 kg/tonne. The tension
in the tow cable is 720 kg. The rolling resistance of the road will be
(A) 20 kg/tonne
(B) 30 kg/tonne
(C) 40 kg/tonne
(D) 50 kg/tonne
Answer: Option C
155. The Overall in-charge of an organisation at the site responsible for the execution of the works,
is
(A) Executive Engineer
(B) Engineer
(C) Junior Engineer
(D) Assistant Engineer
Answer: Option B
156. Consider the following features/factors:
1. Projects are of the non-repetitive type
2. Time required need not be known
3. Time required is known precisely
4. Events have been established for planning
5. Emphasis is given to activities of project PERT is preferred for planning because of
(A)1, 2 and 4
(B)3, 4 and 5
(C)1, 3 and 4
(D)1, 2 and 5
Answer: Option A
157. The first stage of a construction, is
(A) Preparation of estimate
(B) Survey of the site
(C) Initiation of proposal
(D) Preparation of tender
Answer: Option C
158. Crash project duration is obtained by summing the
(A) Normal durations for all the activities
(B) Crash durations for all activities
(C) Crash durations for all the activities along the critical path obtained by taking into
account the normal duration for all the activities
(D) Crash durations for all the activities along the critical path obtained by taking into
account the crash duration for all the activities.
Answer: Option D
159. Pick up the correct statement from the following:
(A) Forward pass is used for calculating earliest expected time
(B) Backward pass is used for calculating the latest occurrence time
(C) Maximum value of earliest expected time is used if there is more than one value
ofany event
(D) All the above
Answer: Option D
160. Sinking fund is
(A) The fund for rebuilding a structure when its economic life is over
(B) Raised to meet maintenance costs
(C) The total sum to be paid to the municipal authorities by the tenants
(D) A part of the money kept in reserve for providing additional structures andstructural
modifications
Answer: Option A
161. If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the
expected time of the activity, is
(A) (a + m + b)/6
(B) (a + 2m + b)/6
(C) (a + 4m + b)/6
(D) (a + 5m + b)/6
Answer: Option C
162. Consider the following statements for a power shovel:
(i) Output can be increased by reducing the angle of swing for a given depth ofcut.
(ii) For a given angle of swing, output will be maximum at optimum depth of cut.
(iii) Output can be increased by keeping the depth of cut less than optimum depth,
(iv) Output can be increased by increasing the size of shovel. Of these statements
(A) (ii), (iii) and (iv) are correct
(B) (i), (ii) and (iv) are correct
(C) (i), (iii) and (iv) are correct
(D) (i) and (iv) are correct
Answer: Option B
163. If to, tp and tm are the optimistic, pessimistic and most likely time estimates of an activity
respectively, the expected time t of the activity will be
(A)
to + 3tm+ tp/3
(B)
to + 4tm+ tp/4
(C)
to + 4tm+ tp/5
(D)
to + 4tm+ tp/6
Answer: Option D
164. The most suitable type of equipment for compaction of cohesive soils is
(A) Smooth-wheeled rollers
(B) Vibratory rollers
(C) Sheep foot rollers
(D) Tampers Answer:
Option C
165. If the total float and duration of an activity are 5 and 10 days respectively, the particular
activity can be
(A) Started 5 days later
(B) Completed 5 days later
(C) Performed at slower rate in 15 days
(D) All the above
Answer: Option D
166. Rolling resistance of a wheel depends upon
(i) Vehicle load
(ii) Grade
(iii) Ground conditions Of
these statements
(A) Only (i) is correct
(B) (i) and (ii) are correct
(C) (i) and (iii) are correct
(D) (ii) and (iii) are correct
Answer: Option C
167. A Milestone chart
(A) Shows the interdependencies of various jobs
(B) Depicts the delay of jobs, if any
(C) Points outgoing ahead of schedule of jobs, if any
(D) None of these
Answer: Option D
168. Earliest finish of an activity is always
(A) Greater than earliest event time of the following node
(B) Less than earliest event time of the following node
(C) Less than or equal to earliest event time of the following node
(D) Greater than or equal to earliest event time of the following node
Answer: Option C
169. Critical path lies along the activities having total float
(A) Positive
(B) Negative
(C) Zero
(D) Same Answer:
Option C
170. If the scheduled completion time of a project is more than the earliest expected time for
completion of the project, then the probability of completion of the project within the scheduled
completion time will be
(A) 50 %
(B) Less than 50 %
(C) More than 50 %
(D) 100 %
Answer: Option C
171. The critical activity has
(A) Maximum float
(B) Minimum float
(C) Zero float
(D) None of these
Answer: Option C
172. For excavating utility trenches with precise control of depth, the excavation equipment used is
(A) Hoe
(B) Shovel
(C) Dragline
(D) None of the above
Answer: Option A
173. PERT analysis is based on
(A) Optimistic time
(B) Pessimistic time
(C) Most likely time
(D) All the above
Answer: Option D
174. The most popular type of organisation used for Civil Engineering Constructions, is
(A) Line organisation
(B) Line and staff organisation
(C) Functional organisation
(D) Effective organisation
Answer: Option A
175. The probability of completion of any activity within its expected time is
(A) 50 %
(B) 84.1 %
(C) 99.9 %
(D) 100 %
Answer: Option A
176. The performance of a specific task in CPM, is known
(A) Dummy
(B) Event
(C) Activity
(D) Contract Answer:
Option C
177. Pre-tender stage requires
(A) Acquisition of land
(B) Selection of site
(C) Fmalisation of alignment of work
(D) All the above
Answer: Option D
178. An event is indicated on the network by a number enclosed in
(A) A circle
(B) A square
(C) A triangle
(D) All the above
Answer: Option D
179. Select the incorrect statement.
(A) A critical path always begins at the very first event.
(B) A critical path always terminates at the last event.
(C) Critical activities control the project duration.
(D) Critical activity is the one for which free float is zero.
Answer: Option D
180. If t is the duration of an activity, t1 is the latest finish possible moment of its preceding
activity and t2 is the earliest start possible moment, the independent float of the activity is
(A)
(t1 - t2) - t
(B)
t - (t1 - t2)
(C)
(t1 + t2) - t
(D)
t + (t1 - t2)
Answer: Option A
181. Free float for any activity is defined as the difference between
(A) Its earliest finish time and earliest start time for its successor activity
(B) Its latest start time and earliest start time
(C) Its latest finish time and earliest start time for its successor activity
(D) Its earliest finish time and latest start time for its successoractivity
Answer: Option A
182. In CPM analysis,
(A) Emphasis is given to activities
(B) Uncertainties are not allowed
(C) Activities are represented by arrows
(D) All the above
Answer: Option D
183. The estimated time required to perform an activity, is known as
(A) Event
(B) Dummy
(C) Duration
(D) Float Answer:
Option C
184. Critical Path Net Work helps an engineer
(A) To concentrate his attention on critical activities
(B) To divert the resources from non-critical advanced activities to critical activities
(C) To be cautious for avoiding any delay in the critical activities to avoid delay of the
whole project
(D) All the above
Answer: Option D
185. A contractor has two option; (I): Invest his money in project A or (II): Invest his money in
project B. If he decides to invest in A, for every rupee invested, he is assured of doubling his
money in ten years. If he decides to invest in B, he is assured of making his money 1.5 times in 5
years. If the contractor values his money at 10% interest rate, he
(A) Should invest in neither of the two projects
(B) Could invest in either of the two projects
(C) Should invest in project A
(D) Should invest in project B
Answer: Option A
186. Henry Gantt developed Bar charts for planning and scheduling of projects in
(A) 1880
(B) 1900
(C) 1920
(D) 1940
Answer: Option B
187. If TL is the latest allowable event occurrence time, total activity slack(s), is equal to
(A) LST-EST
(B) LFT-EFT
(C) TL-EFT
(D) All the above
Answer: Option D
188. Modular co-ordination of construction means proper
(A) Planning
(B) Designing
(C) Execution
(D) All the above
Answer: Option D
189. Pick up the correct statement from the following:
(A) CPM analysis is activity oriented
(B) PERT analysis is event oriented
(C) In CPM, the time is related to cost
(D) All the above
Answer: Option D
190. The final selection of a construction site, is done by
(A) Departmental representative or user
(B) Local civil authority representative
(C) Representative of engineer authority
(D) All the above
Answer: Option D
191. The main advantage of line organisation is:
(A) Effective command and control
(B) Rigid discipline in the organisation
(C) Defined responsibilities at all levels
(D) All the above
Answer: Option D