FBI-10
Price : Rs. 2/-
KHADI & V.I. COMMISSION
PROJECT PROFILE FOR GRAMODYOG ROJGAR YOJNA
PROJECT PROFILE ON PRODUCTION OF LAC
The scheme has been made for those who are traditionally experienced in this line.
India is major producer of lac accounting for nearly 70-80% of the total world production.
Lac is considered to be important subsidiary ocupation for poor tribals in almost all the
major lac producing states of the country. There are four lac varieties produced and derive
their names from Hiindi months. Baisakhi and Agni are the two main commercial varieties
as they together contribute 85% of the annual lac production. The two common lac host
species namely (1) Ber and (2) Palas. It is gathered that each family on an average had 6
Ber and 23 trees.
1 Name of the Product : LAC
2 Project Cost :
a Capital Expenditure
Land :
Building Shed 1000 [Link] : Rs. 200000.00
Equipment : Rs. 150000.00
([Link] Working Table, Two head bottle
washing machine, Cap sealing M/c, Plastic
drums, Aluminium Vessles, [Link], laddles
small untensils, mug, cups, balance etc..
Total Capital Expenditure Rs. 350000.00
b Working Capital Rs. 164000.00
TOTAL PROJECT COST : Rs. 514000.00
3 Estimated Annual Production of LAC : ( Value in ‘000 )
[Link]. Particulars Quintals Rate Total Value
1 LAC 370.00 2600.00 986.00
TOTAL 370.00 2600.00 986.00
4 Raw Material : Rs. 350000.00
5 Lables and Packing Material : Rs. 100000.00
(85)
6 Wages (Skilled & Unskilled) : Rs. 90000.00
7 Salaries : Rs. 96000.00
8 Administrative Expenses : Rs. 60000.00
9 Overheads : Rs. 200000.00
10 Miscellaneous Expenses : Rs. 20000.00
11 Depreciation : Rs. 25000.00
12 Insurance : Rs. 3500.00
13 Interest (As per the PLR)
a. [Link] : Rs. 45500.00
b. [Link] : Rs. 21320.00
Total Interest Rs. 66820.00
14 Woring Capital Requirement :
Fixed Cost Rs. 225000.00
Variable Cost Rs. 761320.00
Requirement of WC per Cycle Rs. 164387.00
15 Cost Analysis
[Link]. Particulars Capacity Utilization(Rs in ‘000)
100% 60% 70% 80%
1 Fixed Cost 225.00 135.00 157.50 180.00
2 Variable Cost 761.00 456.60 532.70 608.08
3 Cost of Production 986.00 591.60 690.20 788.80
4 Projected Sales 1200.00 720.00 840.00 960.00
5 Gross Surplus 214.00 128.40 149.80 171.20
6 Expected Net Surplus 189.00 113.40 132.30 151.20
Note : 1. All figures mentioned above are only indicative and may vary from place to place.
2. If the investment on Building is replaced by Rental then
a. Total Cost of Project will be reduced.
b. Profitability will be increased.
c. Interest on [Link] be reduced.
(86)