5.2 Methods of Demolition

The document outlines various engineered demolition methods, including mechanical techniques such as hydraulic crushers, wrecking balls, and pusher arms, as well as piecemeal demolition by hand. It emphasizes safety precautions, operational guidelines, and the importance of skilled personnel during demolition processes. Additionally, it details the sequence of demolition and specific criteria for each method to ensure effective and safe operations.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
201 views7 pages

5.2 Methods of Demolition

The document outlines various engineered demolition methods, including mechanical techniques such as hydraulic crushers, wrecking balls, and pusher arms, as well as piecemeal demolition by hand. It emphasizes safety precautions, operational guidelines, and the importance of skilled personnel during demolition processes. Additionally, it details the sequence of demolition and specific criteria for each method to ensure effective and safe operations.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

ROHINI COLLEGE OF ENGINEERING & TECHNOLOGY

5.6 ENGINEERED DEMOLITION METHODS

Mechanical method by

* Hydraulic crusher with Long Boom arm * Other Methods like

* Non Explosive Demolition Agent * Explosive Demolition

* Saw cutting * Cutting and Lifting

* Water jet * Wrecking Ball


* Pusher Arm * Wire Rope Pulling * Clam Shell

Piecemeal Demolition (Demolition by Hand):

For demolitions of reinforced concrete buildings by hand, tools such as electric,


pneumatic breakers, jack hammers etc are commonly being used.

Oxy-acetylene torch could be used to cut the reinforcements.

The reinforcements shall remain until all the concrete connecting to or supported by the
reinforcement is broken away or when its supports are no longer required.

Cantilever canopies, balconies and exterior walls are critical elements in building
demolition. In congested areas, these features could critically impact on the safety of the
public.

Demolition of these features shall be performed with extreme caution.

If rope or tie wires are used to pull down the structural elements, the pulling wire must be
at least 4 times stronger than the anticipated pulling force.

In addition, workers shall be shielded from the rope or tie wires. The rope or ties wire
shall be checked at least twice per day.

CE3013 ADVANCED CONSTRUCTION TECHNIQUES


ROHINI COLLEGE OF ENGINEERING & TECHNOLOGY
Lifting appliances may be necessary to hold larger structural members during
cutting and for lowering severed structural members and other debris.
a) Mechanical Demolition

Mechanical demolition generally involves the use of large machinery with


attachment to dismantle the building from outside.

The common mechanical methods include the use of a Hydraulic crusher with long
Boom arm, Wrecking Ball, pusher arm, wire rope, clam shell etc…

These methods shall only be applied to isolated buildings on relatively flat ground.

If it is attached to another structure, the two properties should be separated by the use of
hand methods before the main demolition process begins.

The concerns and good practices of the mechanical demolition generally included the
following;

1) The machine shall be operated on smooth and firm ground;

2) It shall also have adequate counter-weight to prevent overturning during the


operation;
3) The equipment and accessories such as attachments and rope shall be inspected
frequently and shall be repaired or whenever necessary;

4) The impact of the collapsed structural sections on the floor or ground shall be
checked to prevent the potential overloading of the suspended floor, vibration and
disturbance to adjacent properties and damage to underground utilities.

5) The site shall have full time security to prevent unauthorized personnel entering
the site. No person shall stay within the working area of the machine and the building
while the machine is operating.

6) Sufficient water spray or other anti-dust precautions shall be provided to minimize


air pollution by dust;

7) The cab of the machine shall be equipped with impact proofed glass and its

CE3013 ADVANCED CONSTRUCTION TECHNIQUES


ROHINI COLLEGE OF ENGINEERING & TECHNOLOGY
construction shall be robust enough to protect the operator from flying debris;

8) A spot person shall be on site full time to provide guidance and assistance to the
operator in the demolition process.
Demolition Sequence

In general, the following sequence shall apply:


a) Prior to demolition of internal floors, all cantilevered slabs and beams, canopies, and
verandahs shall first be demolished

b) The structural elements, in general, shall be demolished in the following sequence:

- Slabs;

- Secondary beams; then

- Main beams

c) Mechanical plant shall descend from the floor with temporary access ramp, or be
lowered to the next day floor by lifting machinery or by other appropriate means;

d) When a mechanical plant has just descended from the floor above, the slabs and
beams, in two consecutive floors may be demolished by the mechanical plant
simultaneously. The mechanical plant may work on structural elements on the same
floor and breaking up the slabs on the floor above;

e) The wall panel, including beams and columns shall be demolished by gradually
breaking down the concrete or by pulling them down in a controlled manner;

A. Hydraulic crusher with Long Boom arm

The crusher attachment breaks the concrete and the reinforcement by the hydraulic
thrust through the long boom arm system. The hydraulic crusher can be operated from
the ground outside the building. This method is also suitable for dangerous buildings,
silos and other industrial facilities. For environmental reason, it should be used wherever
practicable because of its quietness.

Application Criteria

The operation shall have a minimum clear space of 1/2 the building height as a

CE3013 ADVANCED CONSTRUCTION TECHNIQUES


ROHINI COLLEGE OF ENGINEERING & TECHNOLOGY
safety zone for the falling debris; The equipment shall be inspected and maintained
periodically to make sure the equipment is in good and safe condition.

The excavator shall operate on firm ground that can support the machine during the
crusher operation; Except for special applications, each section of the structure shall be
demolished in a top down sequence to ensure stability of the structure;

Debris may be used to build up a platform for the excavator to extend the range of
reach. It is important that the debris is densely compacted to support the operation of the
excavator. The platform must be flat and the slope must be stable. The height of the build
up platform shall be limited to 3 m. The side slope of the temporary platform shall not be
steeper than 1:1 (horizontal to vertical) unless the condition allows a steeper slope. The
slope of access ramp for the machine shall be in accordance with the manufacturer‟s
recommendation. The width in both directions of the platform shall be at least one and
one-half the length of the machine to allow safe maneuver during the demolition
operation;

To minimize the dust impact, the structure shall be pre-soaked with water before
demolition. Water shall be continuously sprayed during the crushing operation;

Debris may fall out of the building during the demolition. The site shall be
completely fenced off. There shall be 24-hour guarded security to allow only authorized
personnel for site access. During the operation of the crusher there shall be no worker
within the machine operating area or inside the building;

The crusher operator shall possess the essential skills and significant experience in
the crusher operation. There shall be a spot person to assist in the operation and alert the
operator of any potential problem during the operation.

B. Wrecking Ball:

The wrecking ball application consists of a crane equipped with a steel ball. The
destruction of the building is by the impact energy of the steel ball suspended from the
crawler crane. The wrecking ball operates outside the building. This method is suitable

CE3013 ADVANCED CONSTRUCTION TECHNIQUES


ROHINI COLLEGE OF ENGINEERING & TECHNOLOGY
for dilapidated buildings, silos and other industrial facilities. However, the operation
requires substantial clear space. The application also demands high level skill operators
and well- maintained equipment.

Application Criteria

The recommended criteria for the use of wrecking ball are presented in the
following: Except for special application, the balling of each section of the structure shall
proceed from top to bottom. Care shall be taken to maintain the stability of the structure;
Recommended techniques for the wrecking ball operations include:

1) Vertical Drop – free falling of the wrecking ball onto the structure;

2) Swing in line – swinging of the ball in-line with the jib.

A second dragline will normally connect to the ball horizontally to control the ball
motion. The ball shall be swung into the building. The ball shall strike at the top of the
member so as to avoid the member from falling outside the building.

Slewing the jib is not recommended. The motion of the ball by slewing the jib is
difficult to control. It demands expert knowledge of the machine and structure as well as
operating skills to safely perform the task. Slewing can potentially induce a tremendous
amount of stress on the jib, as such, its use shall be avoided;

The jib or boom shall be operated with not less than 3 m above the portion of the
structure being demolished;

Clear space for operation between the crane and the structure being demolished
shall be 50% of the height of structure, the clear distance between the site boundary and
the building to be demolished shall not be less than 50% of the building height plus an
additional 6 m for the crane to maneuver, this criteria shall apply to all sides of the
building to be demolished by wrecking ball;

The demolition ball shall be connected with swivel type anti-spin device to prevent
twisting and tangling of the wire during operation;

The wire and boom of the machine used for balling shall have a rated capacity, at
the working radius, of at least 5 times the weight of the ball;

CE3013 ADVANCED CONSTRUCTION TECHNIQUES


ROHINI COLLEGE OF ENGINEERING & TECHNOLOGY
The strength of the wire shall be at least twice the tensile strength of the nominal
steel reinforcement of the floor slab and beams. The high strength wire allows the pullout
of the wrecking ball from potential traps;

To ensure that the crane is in good condition, the wire connecting to the ball, the
boom components and connecting pins shall be inspected twice daily.

A sufficient length of the wire shall be provided to allow the ball to drop to the
lowest working level plus an addition of 10% of the wire length and no less than 3
drums. For swing in-line method, there shall be sufficient length of the dragline wire to
allow the ball to fall in the event that the ball is entangled with the falling debris;

The operation shall not be performed adjacent to overhead power lines;

The site shall be entirely fenced off to forbid public access. A 24-hour security
guard shall be assigned to the site to enforce the access restriction; depending on the
relative location between the fence and the building, and fence shall be designed to
withstand accidental impact by the wrecking ball;

During the use of the demolition ball, expect for the crane operator and the spot
person, all other workers shall be kept away from the demolition ball‟s working radius.
Nobody shall stay inside the building;

To minimize the dust impact on the surrounding area, the structure to be


demolished shall be pre-soaked with water before demolition. Water spraying shall
continue on the structure during demolition;

Since the safety and success of the project depend highly on the operator and site
personnel, the operator must have proven experience and skill for operating the wrecking
ball to the satisfaction of the approval authority; and

A spot person shall be on site during the operation to assist the operator and to
ensure site safety. The spot person shall have extensive knowledge and experience in the
use of wrecking ball. The qualification and experience of the spot person shall be
equivalent to those of the wrecking ball operator.

CE3013 ADVANCED CONSTRUCTION TECHNIQUES


ROHINI COLLEGE OF ENGINEERING & TECHNOLOGY

C. Hydraulic Pusher Arm:

Articulated, hydraulically-powered pusher-arm machines are normally mounted on


a tracked or wheeled chassis, and have a toothed plate or hook for applying for applying
a horizontal force to a wall.

The machine should stand on a firm level base and apply force by a controlled movement
of the pusher arm.

Special conditions for pusher arm demolition are listed below:


1) The pusher arm shall be constructed of steel or equivalent material and shall have
adequate strength to operate on the building; a crane boom shall not be used;

2) Minimum safety distance of 0.5 times the height of the building element being
demolished shall be maintained between the machine and the building for pushing into
the building.

3) Minimum safety distance of 1.5 times the height of the building element being
demolished shall be maintained if structural elements are pulling out of the building;

4) The point of application of pushing shall not be less than 2/3 of the height and not
more than 600 mm below the top of the wall; and

5) The pusher arm method shall be limited to buildings less than 15 m high.

Chutes may be used to discharge debris into a vehicle or hopper.

Foundations would normally be grubbed up by excavation machines.