Tender Nhidcl
Tender Nhidcl
Name of the Work: Maintenance and Repair of Balance Length 6.450 Km (from Ch. 78+200
to Ch. 84+650) of NH-44A vaghmun to Simlung section at Risk and Cost
of the EPC Contractor on item rate basis & work order basis in F.Y 2024-
25 (2nd Call).
BID DOCUMENT
VOLUME-I
August, 2024
Page 1 of 98
CONTENTS
Volume – I
TITLE
Page 2 of 98
(SECTION-I)
NOTICE INVITING TENDER
(E-TENDERING MODE ONLY)
Page 3 of 98
Regional Office – Agartala of
National Highways & Infrastructure Development Corporation Limited
Notice Inviting Emergent e-Tender
(National Competitive Bidding through e-Tendering mode only)
1. National Highways and Infrastructure Development Corporation Ltd. (hereinafter called “the
Employer”) invites sealed bids in single stage two cover system i.e., the Technical and
Financial Bids on percentage rate basis for the following works from the experienced
Road/Bridge Contractors/firms/organizations excluding those firms who have been declared
as non-performing by MoRT&H/NHAI/NHIDCL or the firms those are blacklisted/debarred
for specified period by MoRT&H/NHAI/NHIDCL:
Eligibility
Criteria
Estimated Eligibility Criteria
Average
Civil Cost Bids as Completed
Length Time of annual
Sr. Name of work/Contract Put to Security work of similar
(km) Completion turnover
No. Package Tender (Rs. In nature during last
(months) for last 5
(Rs. In Lakhs) 5 Years (Rs. In
Years
Lakhs) Lakhs)
(Rs. In
Lakhs)
Maintenance and
Repair of Balance
Length 6.450 Km
(from Ch. 78+200 to
At least one
Ch. 84+650) of NH- similar Completed
44A vaghmun to works not less
1 7.04
Simlung section at 6.45
351.81 6 351.81 than the amount
Risk and Cost of the equal to 40% of
the total value of
EPC Contractor on
contract (Rs.
item rate basis & 140.72 Lakhs)
work order basis in
F.Y 2024-25 (2nd
Call).
Cost of Bid Documents: Rs. 10,000/- + 18% GST (Non-Refundable). The bidder
must make online payment of tender document fee i.e.,
Rs. 11,800/- , through the RTGS/NEFT/Demand Draft (in
favour of Executive Director, Regional Office-Agartala,
Tripura) in Establishment Account of ED (P), RO
Agartala: -
Particulars Details
Name of Beneficiary National Highways & Infrastructure
Development Corporation Limited
Establishment Account
Beneficiary Bank 79901010002270
Account No.
Beneficiary Bank Branch IFSC – CNRB0017990
Page 4 of 98
Beneficiary Bank Branch Agartala-II Branch
Name
Beneficiary Bank Canara Bank, Agartala-II Branch,
Address Durga Bari Road, 1st floor above
RMS office, Agartala, Tripura:
799001
S. No Description Period
1 Date of issue of NIT 25.08.2024
2 Date of issue of Sale of Tender Documents 25.08.2024
3 Date of close of sale of Tender Documents (through online) 04.09.2024 (up to 1500 Hrs)
4 Last Date of receipt of pre-bid queries 28.08.2024
5 Date of Pre-Bid meeting 29.08.2024
6 Date of uploading of reply to the pre-bid queries 30.08.2024
The works shall be carried out as per site condition. The work may be required to be fully executed or
partially executed as per site condition and direction of Engineer in charge and the project work will
be foreclosed on fixing of appointed date of the upgradation work. Therefore, no claim whatsoever
from any of the selected bidders on this account shall be entertained in this regard.
Date: 25.08.2024
Page 7 of 98
(SECTION-II)
INSTRUCTIONS TO BIDDERS
& APPENDIX TO BID
Page 8 of 98
Section II: Instructions to Bidders
Table of Clauses
Clause Clause
A. General D. Submission of Bids
1 Scope of Bid 19 Sealing and marking of Bids
Page 9 of 98
Section II
1.1 The Employer (i.e., Managing Director, National Highways & Infrastructure
Development Corporation ltd.) invites bids for “as described in these documents and
referred to as “the works”. The name and identification number of the works is provided
in the Notice Inviting Tender.
1.2 The successful bidder will be expected to complete the works by the intended
completion date specified in the Contract data.
1.3 Throughout these Bidding Documents, the terms “bid” and “tender” and their
derivatives (bidder/tender, bid/tender, bidding/tendering, etc.) are synonymous.
1.4 The project work will be foreclosed on fixing of appointed date of the upgradation work,
therefore, no claim whatsoever from any of the selected bidders on this account shall be
entertained in this regard.
2. Source of Funds
2.1 The expenditure on this project will be met by National Highways & Infrastructure
Development Corporation ltd (NHIDCL).
3 Eligible Bidders
3.1 This Invitation for Bids is open to all bidders meeting the qualification requirements
prescribed in this document.
3.2 Bidders shall not be under a declaration of ineligibility for corrupt and fraudulent
practices by the Central Government, the State Government or any public undertaking,
autonomous body, authority by whatever name called under the Central or the State
Government.
3.3 Deleted
f) Scanned copy of audit reports on the financial standing of the Bidder, and a
certificate from Chartered Accountant as a proof of turnover for the last five years;
g) Scanned document in support of evidence access to line (s) of credit and availability
of other financial resource facilities (40 % of Contract value), certified by bankers
(not more than 3 months old).
h) Scanned undertaking that the bidder will be able to invest minimum cash up to 25
% of contract value of work, during implementation of work.
i) Deleted
j) Scanned copy of information regarding any litigation or arbitration during the last
five years in which the Bidder is involved, the parties concerned, the disputed
amount, and the present status;
k) Deleted
l) the proposed methodology and programme of construction, backed with equipment
planning and deployment, duly supported with broad calculations and quality
control procedures proposed to be adopted, justifying their capability of execution
and completion of the work as per technical specifications within the stipulated
period of completion as per milestones (for all contracts over Rs.5 Crore).
4.3 Bids from joint ventures, consortiums, combination or any sort of arrangement
between two or more than two entities are not allowed.
4.4 A. To qualify for award of the contract, each bidder in its name should have the
following; -
a) Achieved an average annual financial turnover (in all classes of civil engineering
construction works only) equal to the amount indicated in NIT during last five years
ending 31st March of the previous financial year (to be considered as 31.03.2023),
duly certified by Chartered Accountant.
Page 11 of 98
b) satisfactorily completed (not less than 90% of contract value), as a prime contractor
(or as a officially nominated subcontractor, provided further that all other
qualification criteria are satisfied) similar works during last five years ending last
day of month previous to the one in which bids are invited, at least one contract of
Road/ or Bridge works /Airport runway of 40% of the estimated cost put to tender.
The works may have been executed by the Applicant as Prime Contractor or as a member
of JV or Sub Contractor. As Sub-Contractor, he should have acquired the experience of
execution of all major items of works under the proposed contract. In case a project has
been executed by a Joint Venture, weightage towards experience of the project would be
given to each joint venture in proportion to their participation in the Joint Venture.
Substantially Completed Works means those works which are at-least 90% completed as
on the date of submission and continuing satisfactorily. For these, a Certificate from the
employer shall be submitted along with the application incorporating clearly the name of
the work, Contract value, billing amount, date of commencement of works, satisfactory
performance of the Contractor and any other relevant information.
c) The bidder should have completed similar nature* of work in any government
organization in last five financial years]
*Similar Nature means, the bidder must have any of the following work: -
S. No Items
1 Road Works
(Following escalation factor shall be used to bring the value of such completed works at
the level of current financial year i.e., 2024-25)
4.4 B.
a) Each bidder must upload the scanned copies of following documents along with the
submission of online bidding:
i. An affidavit on a Stamp Paper, duly attested from the Notary Public, that the
information furnished with the bid documents is correct in all respects; and
ii. Such other certificates as defined in Section- III.
iii. Failure to submit the certificates/documents as specified above shall make the
bid non-responsive.
b) Each bidder must demonstrate:
Page 12 of 98
i. Evidence of availability (either owned or leased or rented) of the key
equipment’s for this work as stated in the Appendix to ITB.
ii. Availability for this work of personnel with qualification & experience as stated
in the Appendix to ITB.
c) Deleted.
d) Deleted.
4.4 C. Deleted
4.5 Contractors' experience and resources shall not be taken into account in determining the
bidder's compliance with the qualifying criteria.
4.6 Bidders who meet the minimum qualification criteria will be qualified only if their
available bid capacity is more than the total bid value. The available bid capacity will be
calculated as under:
Assessed Available Bid capacity = (A*N*2 - B)
Where,
A = Maximum value of civil engineering works executed in any one year during the last
five years (escalation factor as specified in this section shall be used to bring the
maximum value of civil engineering works to the level of current financial year i.e.,
2024-25) taking into account the completed as well as works in progress.
N = Number of years prescribed for completion of the works for which bid is invited.
B = Value (escalation factor as specified in this section shall be used to bring the value to
the level of current financial year i.e., 2024-25) of existing commitments and on-going
works to be completed during the next 0.50 year (period of completion of the works for
which bid is invited)
4.7 Even though the bidders meet the above qualifying criteria, they are subject to be
disqualified if they have:
i. Made misleading or false representations in the forms, statements, affidavits and
attachments submitted in proof of the qualification requirements; and/or
ii. Record of poor performance such as abandoning the works, not properly
completing the contract, inordinate delays in completion, litigation history, or
financial failures etc. or debarring from MoRT&H/NHAI/NHIDCL/State PWD
work etc.
iii. Tampered the bid document in any manner.
5 One Bid per Bidder
5.1 Each Bidder shall submit only one Bid for a particular package. A Bidder who submits
more than one Bid for the same package will cause be disqualified.
6 Cost of Bidding
6.1 The Bidder shall bear all costs associated with the preparation and submission of his
Bid, and the Employer will, in no case, be responsible or liable for those costs.
7 Site Visit
7.1 The Bidder, at his own cost, responsibility and risk, is encouraged to visit, examine and
Page 13 of 98
familiarize himself with the Site of Works and its surroundings including source of earth,
water, road aggregates etc. and obtain all information that may be necessary for preparing
the Bid and entering into a contract for construction of the Works. The costs of visiting
the Site shall be at the Bidder's own expense. He may contact the regional office,
Agartala of NHIDCL in this regard.
Page 14 of 98
Section II
Instructions to Bidders (ITB)
Page 15 of 98
on any matter that may be raised at that stage.
9.1.2 The bidder is requested to submit any questions in writing or by
cable/email so as to reach the Employer not later than one week before the
meeting.
9.1.3 Minutes of the meeting, including the text of the questions rose (without
identifying the source of the enquiry) and the responses given will be
transmitted without delay on website. Any modifications of the bid
documents listed in Clause 8.1, which may become necessary as a result of
the pre-bid meeting or which are required in the opinion of the Employer
shall be made by the Employer exclusively through the issue of an
Addendum pursuant to Clause 10 and not through the minutes of the pre-
bid meeting.
9.1.4 Deleted
Page 16 of 98
Section II
Instructions to Bidders (ITB)
C. Preparation of Bids
11 Language of Bid
11.1 All documents relating to the Bid shall be in English.
12 Documents Comprising the Bid
12.1 The e-bid submitted by the bidder shall be in two separate parts.
Part-I - This shall be named Technical Bid and shall comprise of information submitted
in section-III.
Part-II - It shall be named Financial Bid and shall comprise of Priced bill of quantities.
Documents to be submitted in physical form may reach the office of “Executive
Director (P), NHIDCL, Regional Office-Agartala, National Highways & Infrastructure
Development Corporation Limited, Regional Office, 3rd floor, UD Bhawan, Near Ravindra
Bhawan, Sakuntala, Agartala, Tripura” or at the address “General Manager (P), NHIDCL,
PMU-Dharmanagar, 2nd floor to SBI (Bazaar Branch), Thana Road, Dharmanagar, North
Tripura District, Tripura-799250” on or before bid due date and it should be pledged in the
name of Executive Director, Regional Office-Agartala, Tripura.
12.2 Though, the scanned copies of following documents are required to be uploaded
during submission of e-bid on the e-tendering portal, as per clause 12.1 above, however,
following original documents in physical form may be submitted in a sealed envelope on or
before bid due date at the address mentioned above duly super scribed “Name of Work, Bid
due date and time”. Name and address of the bidder should also be indicated on the envelope.
a) Original copy of payment of proof of Bid Security
b) Original copy of proof of payment of Bid Document Fee
c) Deleted
d) Written Power of Attorney of the signatory (whose digital signature certificate is
used during e-tender submission) of the bidder to commit the bid
e) Affidavit (A-1) duly notarized (format enclosed).
12.3 The following documents, which are not submitted with the bid, will be deemed to
be part of the bid.
Section Particulars
1. Notice Inviting Tender
2. Instruction to the bidders
3. Conditions of Contract
4. Contract Data
5. Technical Specifications
Page 17 of 98
13 Bid Prices
13.1 The Contract shall be for the whole Works, as described in Clause 1.1 based on the
priced Bill of Quantities submitted by the Bidder.
13.2 The bidder shall quote bid prices on appropriate format enclosed as part of tender
document on e-tender portal i.e., https://eprocure.gov.in. The items for which no rate or
price is entered by the Bidder will be required to be executed free of cost and shall be
deemed covered under the other rates and prices in the Bill of Quantities quoted.
13.3 All duties, taxes including GST, royalties and other levies payable by the Contractor
under the Contract, or for any other cause, shall be included in the rates, prices, and total
Bid price submitted by the Bidder. The rates have been taken based on latest SOR i.e.,
inclusive 18% GST, However the GST will be paid as per Standard Norms &
Guidelines.
13.4 The rates and prices quoted by the Bidder shall be fixed for the duration of the Contract
and shall not be subject to adjustment.
14 Currencies of Bid and Payment
14.1 The unit rates and the prices shall be quoted by the bidder entirely in Indian Rupees. All
payments shall be made in Indian Rupees.
15 Bid Validity
15.1 Bids shall remain valid for a period of 120 days after the deadline date for bid
submission specified in Clause 20. A bid valid for a shorter period shall be rejected by
the Employer as non-responsive.
15.2 In exceptional circumstances, prior to expiry of the original time limit, the Employer
may request that the bidders may extend the period of validity for a specified additional
period. The request and the bidders’ responses shall be made in writing or by cable. A
bidder may refuse the request without forfeiting his bid security. A bidder agreeing to
the request will not be required or permitted to modify his bid, but will be required to
extend the validity of his bid security for a period of the extension, and in compliance
with Clause 16 in all respects.
16 Earnest Money / Bid Security/ Forfeiture/ Debarment
The Bidder shall furnish, as part of the Bid, Earnest Money/Bid Security, in the amount as
specified in the NIT. Demand Draft must be in favor of Executive Director, Regional Office-
Agartala, Tripura. The bidder can also make online payment of bid security through
RTGS/NEFT in the following Project Account of ED (P).
The Earnest Money/ Bid Security shall, at the Bidder’s option, be in the form of e-Bank
Guarantee/Demand Draft/Bankers Cheque/RTGS/ NEFT/FDR only (any other form will not be
acceptable) of any scheduled commercial bank approved by RBI having a net worth of not less
than Rs. 500 crore as per the latest annual report of the bank and must be in the name of the
Employer. In case of foreign bank (issued by a branch in India) the net worth in respect of the
Indian operations shall only be taken into account. It shall be valid for 45 days beyond the
validity of the bid. Any bid having bid security for lesser value and shorter validity period shall
be treated as non-responsive. Any Bid not accompanied by Bid Security shall also be treated as
NON-RESPONSIVE.
Page 18 of 98
S. Particulars Details
No.
5 Beneficiary Bank Address Canara Bank, Agartala-II Branch, Durga Bari Road,
1st floor above RMS office, Agartala, Tripura: 799001
B. The acceptance of the guarantees shall also be subject to the following conditions: -
i. The capital adequacy of the Bank shall not be less than the norms prescribed by RBI
(presently 9, with effect from 31st March, 2003,).
ii. The bank guarantee issued by a Cooperative Bank shall not be accepted.
16.3 Any bid not accompanied by an acceptable bid security shall be rejected by the
Employer as non -responsive.
16.4 Bid securities of the unsuccessful bidders should be returned to them at the earliest after
expiry of the final bid validity and latest on or before the 30th day after the award of the
contract.
16.5 The Bid Security of the successful Bidder will be discharged when the Bidder has signed
the Agreement and furnished the required Performance Security.
16.6 The Bid Security/ Earnest Money will be forfeited:
i. if the Bidder withdraws the Bid after its submission during the period of Bid validity;
ii. if the Bidder does not accept the correction of the bid price, pursuant to Clause 27; or
iii. in the case of a successful Bidder, if the Bidder fails within the specified time limit to
a) Sign the Agreement; and/or
b) Furnish the required Performance Security.
Page 19 of 98
16.7 To be decided by Employer/Engineer in charge
17 Alternative Proposals by Bidders
17.1 Bidder shall submit offers that fully comply with the requirement of the Bidding
Documents. Conditional offer or alternate offer will not be considered further in the
process of evaluation and the bid will be declared non-responsive.
18 Format and Signing of Bid
18.1 The Bidder shall submit e-bid comprising of the documents as described in Clause 12 of
the ITB.
18.2 DELETED.
18.3 DELETED.
18.4 The documents to be submitted in the physical form on or before bid due date as per
NIT. Documents as mentioned here shall contain no overwriting, alterations or
additions, except those to comply with instructions, issued by the employer or as
necessary to correct errors made by the bidder, in which case such corrections shall be
made by scoring out the cancelled portion, writing the correction and signing and dating
it along with the stamp by the person or persons signing the Bid.
Page 20 of 98
Section II
Instructions to Bidders (ITB)
D. Submission of Bids
19 Marking of Bids
19.1 The documents to be submitted in physical form as per clause 12.2 of ITB may be
submitted in a sealed Envelope super scribed as “Documents in Physical Form” at the
top left corner.
19.2 DELETED.
19.3 DELETED.
19.4 DELETED.
19.5 DELETED.
20 Deadline for Submission of Bids
Complete e-Bid to be uploaded on NHIDCL e-tender portal before due date & time. The
Envelope containing “Documents in Physical Form” may also be received by the Employer
at the address mentioned in Sl. no 7 of NIT on or before bid due date. In the event of the
specified date for the submission of documents in Physical form being declared a holiday for
the Employer, the same will be received up to the specified time on the next working day.
20.1 The Employer may extend the deadline for submission of bids by issuing an amendment
in accordance with Clause 10, in which case all rights and obligations of the Employer
and the bidders previously subject to the original deadline will then be subject to the new
deadline.
21 Late Submission of Document in Physical Form:
21.1 Documents which are to be physically submitted shall be submitted on or before bid due
date at specified time.
22 Modification and Withdrawal of Bids
22.1 Bidders may modify or withdraw their e-bids as directed on the e-tendering portal,
before the Bid Due Date and time as prescribed in Clause 20.
22.2 DELETED.
22.3 No bid may be modified after the deadline for online submission of bids.
22.4 Withdrawal or modification of a Bid between the deadline for submission of bids and
the expiration of the original period of bid validity specified in Clause 15.1 above or as
extended pursuant to Clause 15.2 shall result in the forfeiture of the Bid security
pursuant to Clause 16.
22.5 Bidders may modify the prices of their bids before deadline of online submission of bid.
Page 21 of 98
Section II
Instructions to Bidders (ITB)
E. Bid Opening and Evaluation
23 Bid Opening
Bid opening shall be carried out in two stages. Firstly, 'Technical Bid' of all the bids received
(except those received late) shall be opened on the date and time mentioned in Notice
Inviting Tender (NIT). 'Financial Bid' of those bidders whose technical bid has been
determined to be substantially responsive shall be opened on a subsequent date through
online process of e-tendering, which will be notified to such bidders.
23.1 The Employer will open the "Technical Bid" of all the bids received (except those
received late), in the presence of the bidders/bidders’ representatives who choose to
attend at the time, date and place specified in the NIT. In the event of the specified date
for the submission of bids being declared a holiday for the Employer, the Bids will be
opened at the appointed time and location on the next working day.
23.1.1 DELETED
23.1.2 DELETED
23.2 In all cases, the amount of Bid Security, forms and validity shall be announced.
Thereafter, the Employer at the opening as the Employer may consider appropriate, will
announce the bidders' names and such other details.
23.3 The Employer will prepare minutes of the Bid opening, including the information
disclosed to those present in accordance with Clause 23.1.
23.4
(i) Subject to confirmation of the bid security by the issuing Bank, the bids
accompanied with valid bid security, bid document fee, Tender Processing fee
will be taken up for evaluation with respect to the information furnished in Part I
of the Qualification Information and other bid.
(ii) As soon as possible, the Evaluation Committee will finalize the list of responsive
bidders whose financial bids are eligible for consideration. However, to assist in
the examination, evaluation of technical bids, the Employer may at his discretion,
ask any bidder for clarification of his bid, however, no additional documents in
support of clarification will be entertained.
23.5 The Employer shall inform the bidders, whose technical bids are found responsive, of
the date, time and place of opening of the financial bids. The bidders so informed, or
their representative, may attend the meeting of opening of financial bids.
23.6 At the time of the opening of the ‘Financial Bid’, the names of the bidders whose bids
were found responsive in accordance with clause 23.5 will be announced. The financial
bids of only these bidders will be opened. The responsive bidders’ names, the Bid prices,
the total amount of each bid, pursuant to clause 22 and such other details as the
Employer may consider appropriate will be announced by the Employer at the time of
bid opening. Any Bid price, which is not read out and recorded, will not be taken into
account in Bid Evaluation.
23.7 The Employer shall prepare the minutes of the opening of the Financial Bids.
Page 22 of 98
24 Process to be Confidential
24.1 Information relating to the examination, clarification, evaluation, and comparison of
bids and recommendations for the award of a contract shall not be disclosed to bidders
or any other person not officially concerned with such process until the award to the
successful Bidder has been announced. Any attempt by a Bidder to influence the
Employer’s processing of bids or award decisions may result in the rejection of his Bid
25 Clarification of Bids and Contacting the Employer
25.1. To assist in the examination, evaluation, and comparison of Bids, the Employer may, at
his discretion, ask any Bidder for clarification of his Bid, including breakdowns of unit
rates. The request for clarification and the response shall be in writing or by cable, but
no change in the price or substance of the Bid shall be sought, offered, or permitted.
25.2. Subject to sub-clause 25.1, no Bidder shall contact the Employer on any matter relating
to his bid from the time of the bid opening to the time the contract is awarded.
25.3. Any effort by the Bidder to influence the Employer in the Employer's bid evaluation,
bid comparison or contract award decisions may result in the rejection of the Bidders'
bid.
26 Examination of Bids and Determination of Responsiveness
26.1 During the detailed evaluation of “Technical Bids”, the Employer will determine
whether each Bid
a) meets the eligibility criteria defined in Clauses 3 and 4 of ITB;
b) the required documents in physical form submitted by the bidder as well as the
documents uploaded by the bidder are in order; and
c) is substantially responsive to the requirements of the Bidding Documents. During
the detailed evaluation of the “Financial Bids”, the responsiveness of the bids will
be further determined with respect to the remaining bid conditions, i.e., priced bill
of quantities, technical specifications etc.
26.2 DELETED.
26.3 DELETED.
27 DELETED.
28 Evaluation and Comparison of Financial Bids
28.1 The Employer will evaluate and compare only the bids determined to be substantially
responsive in accordance with Clause 26.
28.2 DELETED
28.3 If the Bid of the successful Bidder is seriously unbalanced in relation to the
Engineer’s/Employer's estimate of the cost of work to be performed under the contract,
the Employer may require the Bidder to produce detailed price analyses for any or all
items of the Bill of Quantities, to demonstrate the internal consistency of those prices
with the construction methods and schedule proposed. After evaluation of the price
analyses, the Employer may require that the amount of the performance security set forth
in Clause 33 be increased and an additional performance security set forth in Clause 33
Page 23 of 98
may be obtained at the expense of the successful Bidder to a level sufficient to protect the
Employer against financial loss in the event of default of the successful Bidder under the
Contract.
28.4 A bid, which contains several items in the Bill of Quantities which are unrealistically
priced low and which cannot be substantiated satisfactorily by the bidder, may be rejected
as non-responsive.
29 Price Preference
29.1 There will be no price preference to any bidder.
Page 24 of 98
Section II
Instructions to Bidders (ITB)
F. Award of Contract
30 Award Criteria
30.1 Subject to Clause 32, the Employer will award the Contract to the Bidder whose Bid has
been determined to be substantially responsive to the bidding documents and who has
offered the lowest evaluated Bid Price.
31 Employer’s Right to Accept any Bid and to Reject any or all Bids
31.1 Notwithstanding Clause 30, the Employer reserves the right to accept or reject any Bid,
and to cancel the bidding process and reject all bids, at any time prior to the award of
Contract, without thereby incurring any liability to the affected Bidder or bidders or any
obligation to inform the affected Bidder or bidders of the grounds for the Employer’s
action.
32 Notification of Award and Signing of Agreement.
32.1 The bidder whose Bid has been accepted will be notified of the award by the Employer
prior to expiration of the Bid validity period by cable, telex or facsimile confirmed by
registered letter. This letter (hereinafter and in the Part I General Conditions of Contract
called the “Letter of Acceptance”) will state the sum that the Employer will pay to the
Contractor in consideration of the execution, completion and maintenance of the Works,
by the Contractor as prescribed by the Contract (hereinafter and in the Contract called
the “Contract Price”).
32.2 The notification of award (LOA) will constitute the formation of the Contract, subject
only to the furnishing of a performance security in accordance with the provisions of
Clause 33.
32.3 The Agreement will incorporate all agreements between the Employer and the
successful Bidder. It will be signed by the Employer and the successful Bidder after the
performance security is furnished.
32.4 Upon furnishing by the successful Bidder of the Performance Security, the Employer
will promptly notify the other Bidders that their Bids have been unsuccessful.
33 Performance Security
33.1 Within 10 (ten) days after receipt of the Letter of Acceptance, the successful Bidder
shall deliver to the Employer a Performance Security of 3 (three) percent of the
Contract Price, valid for the period of 28 days after the expiry of defect liability period
plus additional security for unbalanced Bids in accordance with Clause 28.3 of ITB and
sign the contract. For unbalanced bids, an additional performance security shall be
provided to the employer for an amount calculated as under: (a) If the Bid Price offered
by the Selected Bidder is lower than 20% of the estimated Project Cost, then the
Additional Performance Security shall be calculated @20% of the difference in the (i)
Estimated Project Cost (as mentioned in RFP)-20% of the Estimated Project Cost and
(ii) the Bid Price offered by the selected Bidder. (b) Maximum limit of additional
performance security shall be limited to 3% of the Bid price offered by the setected
bidder. (c) This Additional Performance Security shall be treated as part of the
Performance Security.
Page 25 of 98
33.2 The validity shall account for additional 3 months time to account for BG verification,
signing of contract and start date.
33.3 The performance security shall be in the form of a Bank Guarantee in the name of the
Employer, from a Bank as applicable in case of bid security defined in Appendix to ITB.
33.4 Failure of the successful bidder to comply with the requirement of sub-clause 33.1 shall
constitute sufficient ground for cancellation of the award and forfeiture of the bid
security and debarment for a period as specified in clause 16.7.
34 Advances - Deleted
35 Corrupt or Fraudulent Practices
The Employer will reject a proposal for award if it determines that the Bidder recommended
for award has engaged in corrupt or fraudulent practices in competing for the contract in
question and will declare the firm ineligible, either indefinitely or for a stated period of time,
to be awarded a contract with NHIDCL and any other agencies, if it at any time determines
that the firm has engaged in corrupt or fraudulent practices in competing for the contractor,
or in execution.
The Employer requires the bidders/Contractors to strictly observe the laws against fraud and
corruption enforced in India, namely, Prevention of Corruption Act, 1988.
Appendix to ITB
Instructions to Bidders
Clause Reference
(1.1) The Employer is RO-Agartala, 3rd floor, UD bhawan, Near
Ravindra Bhawan, Sakuntala, Agartala, Tripura
(1.1) Maintenance and Repair of Balance Length 6.450 Km (from
Ch. 78+200 to Ch. 84+650) of NH-44A vaghmun to Simlung
section at Risk and Cost of the EPC Contractor on item rate
basis & work order basis in F.Y 2024-25(2nd Call).
Package No.: NHIDCL/RO-Agt/W/T/Manu-Simlung (Pkg-
IV)(NH-44A)/312-Part(1)]
(4.4) Name of the Equipment Quantity
B) (b) (i) Tipper/Trucks 1
Hydraulic Excavator 1
Motor Grader 1
Excavator 1.0 cum bucket capacity 1
Vibratory Roller 1
Dozer 180 HP @ 60 cum per hr 1
Hot Mix plant (40-60 TPH) -
Paver finisher 1
Front end Loader 1
Smooth Wheeled Roller 1
Vibratory Roller 1
Bitumen pressure distributer @ 1750 -
sqm per hr
Air Compressor 1
Water Tanker 1
Generator set (63/100/250 KVA) 1
Any other equipment required for carrying out work as per
Ministry’s specification.
Note: The bidder must upload scanned copy of the documentary
evidence in support of his owning/leased/ rented of the above
Page 26 of 98
equipments. In case the bidder proposes to hire or take the above
equipment on lease, he should, along with the lease/rent agreement,
attach the proof of ownership of these equipment’s with the
company/ entity from whom the equipment’s are proposed to be
hired on lease/ rent.
(4.4) The Number of Technical personnel, Qualifications and
(B) (b) (ii) Experience will be as follows:
The Technical Personnel are:
SL. No. Personnel Qualification Particular No. of Persons
Experience
(minimum
requirement)
5 years on highway
B.E (Civil) or equivalent
1 Project Manager constructions / 1
+ 10 Years Exp.
maintenance work.
B.E (Civil) + 3Years 2 years on highway
2 Site Engineer Exp. Or Diploma + 5 constructions / 1
Years Exp. maintenance work.
B.E. Civil+3Years Exp. 2 years on highway
3 Quantity Surveyor Or constructions / 1
Dip.Civil. +5Years Exp. maintenance work.
Total 3
Note: The detailed signed and scanned CVs of the Key Technical
Personnel at S. No. 1 signed by the key personnel himself, must be
uploaded along with the bid. The name and educational qualification
of other personnel should be given. Non-compliance of the above or
non-furnishing of the CV as above or conditional deployment of any
of the above personnel or proposal to employ lesser number of
personnel than above shall make the bid non-responsive and
financial bid shall not be opened.
Page 27 of 98
SECTION III
QUALIFCATION INFORMATION
(To be Filled by Bidder)
Page 28 of 98
SECTION III
QUALIFCATION INFORMATION
The information to be filled in by the Bidder in this section & document submitted in physical
form will be used for the purposes of post qualification as provided for in Clause 4 of the
Instructions to Bidders. This information will not be incorporated in the Contract.
1. For Individual Bidders
1.1
a) Year of Constitution
c) Place of registration:
__________________________
__________________________
1.2 Power of attorney of signatory of Bid [Upload scanned copy & also supply Original
copy in envelop of physical form]
1.3 Total value of Civil Engineering construction work performed in the last Five years (in
Rs. _______ Lakhs) refer ITB Clause 4.4 A (a)
(Upload scanned copies of certificate from Chartered Accountant)
2023-2024 -----------
2022-2023 -----------
2021-2022 -------------
2020-2021-------------
2019-2020-------------
Total ----------------
1.4 (a) Work performed as prime contractor; work performed in the past as a nominated
sub- contractor provided further that all other qualification criteria are satisfied (in the
same name) of a similar nature during the last five years as per ITB Clause 4.4A(b).
Page 29 of 98
Remarks
Value of Date of Actual
Descrip Stipulated explaining
Project Name of the Contract Contract issue of date of
tion of period reasons
Name Employer * No. (Rs. work completio
work completion for delay
Crore) order n
& work
1 2 3 4 5 6 7 8 9
* Upload certificate(s) from the Employer (to be given by an officer at the rank of Executive
Engineer or equivalent & also supply original or certified copy)
1.4 (b) Information on Bid Capacity (works for which bids have been submitted and accepted
and works which are yet to be completed) as on the date 7 days before the last date for bid
submission (as per Cl 4.6 of the ITB).
Page 30 of 98
(on letter head of bidder)
* Upload certificate (s) from the Engineer(s)-in-Charge of the rank of Executive Engineer or
equivalent & also supply original or certified copy of certificate.
(ii) Details of works for which bid submitted and accepted (i.e., where contract signing is
pending)
Value of
Work During
Date of issue
Place Name & Value Stipulated Completion
Description of of Letter of
& Address Of Given in period for period of
works Acceptance
State Employer LOA completion work for
(LOA) *
which bids
are invited
1 2 3 4 5 6 7
(iii) Bid Capacity (Bidder shall calculate, mention his bid capacity and enclose the supporting
calculation)
A = Rs. …………lakh (enclose the details)
N = ………………years
B = Rs. …………lakh (enclose the details)
Page 31 of 98
1.5 Availability of Key Equipment essential for carrying out the Works [Ref. Clause 4.4(B)
(b) (i)]. The Bidder should list all the information requested below.
Note: The bidder must upload the documentary evidence in support of his owning/leased/
rented of the above equipment’s. In case the bidder proposes to hire or take the above
equipment on lease, he should, along with the lease/rent agreement, attach the proof of
ownership of these equipment’s with the company/ entity from whom the equipment’s
are proposed to be hired on lease/ rent. The bidder shall submit an undertaking as per
Performa Appendix 1.7 (ITB, Section -2) of the bid document.
1.6 Qualification and Experience of Key Personnel required for administration and
execution of the Contract [Ref. Clause 4.4 (B) (b) (ii)]. Upload biographical data for
technical personnel (Refer also to Cl. 4.2 (e) of Instruction to Bidders).
Page 32 of 98
Total Experience in
Sl. Professional the proposed
Position Name Qualification
No. Experience position
(Years) (Years)
1. Project
Manager
2. Site Engineer
3 Quantity
Surveyor
Note: The detailed and signed CVs of the Key Technical Personnel at S. No. 1 signed by the
key personnel himself must be uploaded along with the bid. The name and educational
qualification of other personnel should be given.
2. Bidders should upload the scanned copy of the following affidavits/ undertakings as per
formats enclosed hereinafter & also send original copy of Affidavit/Undertakings:
(i) Affidavit (it should be on stamp paper attested by Notary Public)
(ii) Undertaking regarding minimum investment of cash towards working capital.
(iii) Undertaking that the Bids shall remain valid for the period specified in Clause 15.1.
Page 33 of 98
SAMPLE FORMAT FOR EVIDENCE OF ACCESS TO OR
AVAILABILITY OF CREDIT FACILITIES
(Clause 4.1(i) of ITB)
BANK CERTIFICATE
If the contact for the work, namely …………………………..is awarded to the above firm, we
shall be able to provide overdraft/credit facilities to the extent of Rs………………. to meet their
working capital requirements for executing the above contract during the contract period.
-------------------------
(Signature)
Name of Bank Senior Bank Manager
Address of the Bank
Page 34 of 98
AFFIDAVIT (A-1)
1. I, the undersigned, do hereby certify that all the statements made in the enclosed attachments
are true and correct.
2. The undersigned also hereby certifies that neither our firm
M/s___________________________________________ has abandoned any work on
MoRTH/NHAI/PWD/NHIDCL nor any contract awarded to us for such works have been
rescinded, during last five years prior to the date of this bid.
3. The undersigned hereby authorize(s) and request(s) any bank, person, firm or corporation to
furnish pertinent information deemed necessary and requested by
MoRTH/NHAI/PWD/NHIDCL to verify this statement or regarding my (our) competence
and general reputation.
4. The undersigned understands and agrees that further qualifying information may be
requested, and agrees to furnish any such information at the request of the
MoRTH/NHAI/PWD/NHIDCL and within the prescribed time.
______________________________
______________________________
______________________________
Name of Firm
______________________________
DATE
Page 35 of 98
(To be notarized by Notary)
UNDERTAKING
_____________________________________
(Signed by an Authorized Representative of the Firm)
_____________________
Name of the Representative
__________________________
Name of Firm
______________________
DATE
Page 36 of 98
(To be notarized by Notary)
UNDERTAKING
______________________________
______________________________
______________________________
Name of Firm
______________________________
DATE
Page 37 of 98
(On the letter head of the bidder)
Undertaking
________________________________________
(Signed by an Authorized Representative of the Firm)
_______________________
Name of the Representative
______________________
Name of Firm
(Seal of the company)
______________________
Date
Page 38 of 98
(SECTION-IV)
Page 39 of 98
FORM OF E-BANK GUARANTEE FOR PERFORMANCE SECURITY
Contract Package No: NHIDCL/RO-Agt/W/T/Manu-Simlung(Pkg-IV)(NH-44A)/312-Part(1)]
To
AND WHEREAS it has been stipulated by you in the said contract that the Contractor shall
furnish you with a Bank Guarantee for the sum specified therein as security for compliance with
his obligations in accordance with the Contract;
AND WHEREAS we have agreed to give the Contractor such a Bank Guarantee:
NOW THEREOF we hereby affirm that we are the guarantor and responsible to you on behalf of
the Contractor, up to a total of Rs……………… (amount of guarantee)
(Rupees……………………………………. (in words), and we undertake to pay you, upon your
first written demand and without cavil or argument, any sum or sums within the limits
of………………. (Amount of guarantee) as aforesaid without your needing to prove or to show
grounds or reasons for your demand for the sum specified therein.
We hereby waive the necessity of your demanding the said debt from the Contractor before
presenting us with the demand.
We further agree that no change or addition to or other modification of the terms of the contract
or of the works to be performed there under or of any of the contract documents which may be
made between you and the Contractor shall in any way release us from any liability under this
guarantee, and we hereby waive notice of any such change, addition or modification.
This guarantee shall be valid upto the date of expiry of the project completion period.
This guarantee shall also be operatable at our …………. ….. branch at Agartala, from whom,
confirmation regarding the issue of this guarantee or extension/ renewal thereof shall be made
available on demand. In the contingency of this guarantee being invoked and payment there
under claimed, the said branch shall accept such invocation letter and make payment of amounts
so demanded under the said invocation.
Notwithstanding anything contained herein before, our liability under this guarantee is restricted
to Rs. ________________ (Rs. _________in words) and the guarantee shall remain valid
till___________________. Unless a claim or a demand in writing is served upon us on or
before____________ all our liability under this guarantee shall cease.
Bank Guarantee has been sent to authority’s bank through SFMS gateway as per the details below: -
Page 40 of 98
S.No. Particulars Details
Signature and seal of the Guarantor with Name, Designation, Employee Code Number &
Telephone Number………………………………………………………
Date………………………….
1…………………………………………………………………………………………
(Name, Address & Occupation)
2…………………………………………………………………………………………
(Name, Address & Occupation)
An amount shall be inserted by the Guarantor, representing the percentage of the Contract Price
specified in the Contract including additional security for unbalance bids, if any and
denominated in Indian Rupees.
Page 41 of 98
FORM OF LETTER OF APPLICATION
To,
DESCRIPTION OF WORKS: Maintenance and Repair of Balance Length 6.450 Km (from Ch.
78+200 to Ch. 84+650) of NH-44A vaghmun to Simlung section
at Risk and Cost of the EPC Contractor on item rate basis &
work order basis in F.Y 2024-25 (2nd Call).
Dear Sir,
It is certified that the information furnished in this document is true and correct. The
proposal is unconditional and unqualified. We undersigned accept that NHIDCL reserves the
right to reject any or all application without assigning any reason.
Thanking you,
Yours faithfully,
M/s_________________________________
Page 42 of 98
FORM OF LETTER OF ACCEPTANCE
To
M/s………………………….
Sir,
Based on your bid submitted on ………….. in compliance of bidding document of NHIDCL for
execution of the work of ………………………………………………. , it is hereby notified that your bid
for a contract price of Rs…………… (Rupees in words………) has been accepted for and on behalf of
NHIDCL
You are hereby requested to furnish Performance Security plus additional security in the form
detailed in para. 33.2 of ITB for an amount equivalent to Rs…………… (Rupees in words………)
within 10 days as per provisions of clause 33.1 of ITB of the bid document and sign the contract
agreement failing which the actions as stipulated in clause-.33.3 of ITB shall be taken.
Thanking you,
Yours faithfully,
(………………..)
Page 43 of 98
FORM OF AGREEMENT
AGREEMENT
This agreement made the ______________day of _________________________
2024_____________________ between the National Highways & Infrastructure Development
Corporation Ltd. (hereinafter called “the Employer” of the one part and _________________ (here in
after called “the Contractor”) of the other part.
AND WHEREAS the Employer invited bids from eligible bidders of the execution of certain
works, viz “Maintenance and Repair of Balance Length 6.450 Km (from Ch. 78+200 to Ch.
84+650) of NH-44A vaghmun to Simlung section at Risk and Cost of the EPC Contractor
on item rate basis & work order basis in F.Y 2024-25(2nd Call).
Package No.: NHIDCL/RO-Agt/W/T/Manu-Simlung(Pkg-IV)(NH-44A)/312-Part(1)] AND
WHEREAS pursuant to the bid submitted by the Contractor, vide letter dated -------------- (here
in after referred to as the “BID” or “ÖFFER”) for the execution of works, the Employer by his
letter of acceptance dated ------------------ accepted the offer submitted by the Contractor for the
execution and completion of such works and the remedying of any defects thereon, on terms and
conditions in accordance with the documents listed in para 2 below.
AND WHEREAS the Contractor by a deed of undertaking dated --------------- has agreed
to abide by all the terms of the bid, including but not limited to the amount quoted for the
execution of Contract, as stated in the bid, and also to comply with such terms and conditions as
may be required from time to time.
AND WHEREAS pursuant to the bid submitted by the Contractor vide letter dated
----------------- (hereinafter referred to as the “the Offer”), the employer has by his letter of
acceptance no.------------------------------------------------------ accepted the offer submitted by the
Contractor for the execution and completion of such works and the remedying of any defects
therein, on terms and conditions in accordance in the conditions of particular application and
condition included hereinafter;
AND WHEREAS the contractor has agreed to undertake such works and has furnished a
performance security pursuant to clause 33 of the instructions to bidders (Section-I).
NOW THIS AGREEMENT WITNESSETH as follows:
1 In this agreement works and expressions shall have the same meanings as are respectively
assigned to them in the conditions of contract hereinafter referred to;
2 The following documents shall be deemed to form and be read and constructed as part of this
agreement viz.
a) The Contract Agreement,
b) Letter of Acceptance,
c) Notice to proceed with the works,
d) Contractor's Bid,
e) Contract Data,
f) Conditions of Contract including Special Conditions of Contract
g) Technical Specifications,
h) Drawings, if any
i) Scope of work
j) Bill of Quantities
k) Any other document listed in the Contract Data.
5 the employer hereby covenants to pay the contractor in consideration of the execution and
completion of the works and the remedying of defects therein the contract price or such other
sum as may become payable under the provisions of the contract at the times and in the
manner prescribed by the contract.
IN WITNESS WHEREOF the parties here to have caused this agreement to be executed the
day and year first before written, signed, sealed and delivered by the said Employer through
his Authorized Representative and the said Contractor through his Power of Attorney holder
in the presence of:
2. Name: 2. Name:
Signature: Signature:
Address: Address:
Page 45 of 98
(SECTION-V)
Page 46 of 98
Table of Clauses
Sl.No. Sl.No.
A. General D. Cost Control
1 Definitions 35 Bill of Quantities
2 Interpretation 36 Variations
3 Language and Law 37 Payments for Variations
4 Engineer’s Decisions 38 Cash Flow Forecasts
5 Delegation 39 Payment Certificates
6 Communications 40 Payments
7 Subcontracting 41 Compensation events
8 Other Contractors 42 Tax and currencies for payment
9 Personnel 43 Price adjustment
10 Employer’s and Contractor’s Risks 44 Security Deposit/ Retention Money
11 Employer’s Risks 45 Liquidated damages
12 Contactor’s Risks 46 Advance Payment
13 Insurance 47 Securities
14 Site Investigation Reports 48 Cost of Repairs
15 Queries about the Contract Data E. Finishing the Contract
16 Contractor to Construct the works and do 49 Completion
maintenance
17 The works to be Completed by the 50 Taking Over
Intended Completion Date
18 Approval by the Engineer 51 Final Account
19 Safety 52 Operating and maintenance manual
20 Discoveries 53 Termination
21 Possession of the Site 54 Payment upon Termination
22 Access to the Site 55 Property
23 Instructions 56 Release from performance
24 Deleted F. Special Conditions of Contract
25 Arbitration 57 Labour
26 Deleted 58 Compliance with Labour Regulation
B. Time Control 59 Drawings and Photographs of the works
27 Programme 60 The Apprenticeship Act, 1961
28 Extension of Completion Date
29 Delays Ordered by the Engineer
30 Management Meetings
C. Quality Control
31 Indentifying Defects
32 Tests
33 Correction of Defects
34 Uncorrected Defects
Page 47 of 98
Section V
CONDITIONS OF CONTRACT
Part I General Conditions of Contract (GCC) and Contract Data
A. General
1. Definitions
1.1 Terms which are defined in the Contract Data are not defined in the Conditions of Contract
but keep their defined meanings. Capital initials are used to identify defined terms.
Bill of Quantities means the priced and completed Bill of Quantities forming part of the Bid.
The Completion Date is the date of completion of the Works as certified by the Engineer, in
accordance with Clause 49.1.
The Contract is the Contract between the Employer and the Contractor to execute, complete,
and maintain the Works. It consists of the documents listed in Clause 2.3.
The Contract Data defines the documents and other information, which comprise the Contract.
The Contractor is a person or corporate body whose Bid to carry out the Works has been
accepted by the Employer.
The Contractor's Bid is the completed bidding document submitted by the Contractor to the
Employer and includes technical and financial bids.
The Contract Price is the price stated in the Letter of Acceptance and thereafter as adjusted in
accordance with the provisions of the Contract.
A Defect is any part of the Works not completed in accordance with the Contract.
The Defects Liability Certificate is the certificate issued by Engineer, after the Defect Liability
Period has ended and upon correction of Defects by the Contractor.
The Defects Liability Period is 06 months calculated from the Completion Date.
Drawings include calculations and other information provided or approved by the Engineer for
the execution of the Contract.
The Employer is the party as defined in the Contract Data, who employs the Contractor to carry
out the Works. The Employer may delegate any or all of its functions to a person or body
nominated by him for specified functions.
Page 48 of 98
The Engineer is the person named in the Contract Data (or any other competent person
appointed by the Employer and notified to the Contractor, to act in replacement of the Engineer)
who is responsible for supervising the execution of the Works and administering the Contract.
Equipment is the Contractor's machinery and vehicles brought temporarily to the Site to
construct the Works.
The Initial Contract Price is the Contract Price listed in the Employer's Letter of Acceptance.
The Intended Completion Date is the date on which it is intended that the Contractor shall
complete the Works. The Intended Completion Date is specified in the Contract Data. The
Intended Completion Date may be revised only by the Engineer by issuing an extension of time
after the approval from Employer.
Materials are all supplies, including consumables, used by the Contractor for incorporation in
the Works.
Plant is any integral part of the Works that shall have a mechanical, electrical, electronic,
chemical, or biological function.
Site Investigation Reports are those that were included in the bidding documents and are
factual interpretative reports about the surface and subsurface conditions at the Site.
Specification means the Specification of the Works included in the Contract and any
modification or addition made or approved by the Engineer.
The Start Date is given in the Contract Data. It is the date when the Contractor shall commence
execution of the Works. It does not necessarily coincide with any of the Site Possession Dates.
A Sub-Contractor is a person or corporate body who has a Contract with the Contractor to carry
out a part of the work in the Contract, which includes work on the Site.
Temporary Works are works designed, constructed, installed, and removed by the Contractor
that are needed for construction or installation of the Works.
A Variation is an instruction given by the Engineer after the approval from NHIDCL, which
varies the Works.
The Works are what the Contract requires the Contractor to construct, install, maintain, and
handover to the Employer, as defined in the Contract Data.
2. Interpretation
2.1 In interpreting these Conditions of Contract, singular also means plural, male also means
female or neuter, and the other way around. Headings have no significance. Words have their
normal meaning under the language of the Contract unless specifically defined. The Engineer
will provide instructions clarifying queries about these Conditions of Contract.
Page 49 of 98
2.2 If sectional completion is specified in the Contract Data, references in the Conditions of
Contract to the Works, the Completion Date, and the Intended Completion Date apply to any
Section of the Works (other than references to the Completion Date and Intended Completion
Date for the whole of the Works).
2.3 The documents forming the Contract shall be interpreted in the following order of
priority.
(a) Agreement,
(b) Letter of Acceptance
(c) Contractor's Bid,
(d) Contract Data,
(e) Conditions of Contract
(f) Technical Specifications,
(g) Drawings, if any
(h) Implementation Manual
(i) Scope of Work
(j) Bill of Quantities, and
(k) Any other document listed in the Contract Data.
3.1 The language of the Contract and the law governing the Contract are stated in the Contract
Data.
4. Engineer's Decisions
4.1 Except where otherwise specifically stated, the Engineer will decide contractual matters
between the Employer and the Contractor in the role representing the Employer.
5. Delegation
5.1 The Engineer, duly informing the Employer, may delegate any of his duties and
responsibilities to other people except to the Adjudicator, after notifying the Contractor, and may
cancel any delegation after notifying the Contractor.
6. Communications
6.1 Communications between parties that are referred to in the Conditions shall be effective only
when in writing. A notice shall be effective only when it is delivered.
7. Subcontracting
7.1 The Contractor may subcontract any portion of work, up to a limit specified in Contract
Data, with the prior approval of the Employer in writing. Subcontracting shall not alter the
Contractor's obligations.
7.2 The Contractor shall not be required to obtain any consent from the Employer for:
Page 50 of 98
a. the sub-contracting of any part of the Works for which the Sub-Contractor is named in
the Contract;
b. the provision of labour or labour component.
c. the purchase of Materials which are in accordance with the standards specified in the
Contract.
7.3 Beyond what has been stated in clauses 7.1 and 7.2, if the Contractor proposes sub-
contracting of any part of the work during execution of the Works, because of some unforeseen
circumstances to enable him to complete the Works as per terms of the Contract, the Employer
will consider the following before according approval:
a) The Contractor shall not sub-contract the Works more than the limit specified in Contract
Data.
b) The Contractor shall not sub-contract any part of the Work without prior consent of the
Employer. Any such consent shall not relieve the Contractor from any liability or
obligation under the Contract and he shall be responsible for the acts, defaults and
neglects of any of his sub-Contractor, his agents or workmen as fully as if they were the
acts, defaults or neglects of the Contractor, his agents and workmen.
7.3 The Engineer should satisfy himself before recommending to the Employer whether
a) the circumstances warrant such sub-contracting; and
b) the sub-Contractor so proposed for the Work possess the experience, qualifications and
equipment necessary for the job proposed to be entrusted to him in proportion to the
quantum of Works to be sub-contracted.
8. Other Contractors
8.1 The Contractor shall cooperate and share the Site with other Contractors, public authorities,
utilities, and the Employer between the dates given in the Schedule of Other Contractors, as
referred to in the Contract Data. The Contractor shall also provide facilities and services for them
as described in the Schedule. The Employer may modify the Schedule of Other Contractors, and
shall notify the Contractor of any such modification.
9. Personnel
9.1 The Contractor shall employ the technical personnel named in the Contract Data or other
technical persons approved by the Engineer. The Engineer will approve any proposed
replacement of technical personnel only if their relevant qualifications and experience are
substantially equal to or better than those of the personnel stated in the Contract Data. If the
personnel stated in the contract data are not deployed on site by the contractor, it will be treated
as a breach of contract and action will be taken as per clause 53.
9.2 If the Engineer asks the Contractor to remove a person who is a member of the
Contractor's staff or work force, stating the reasons, the Contractor shall ensure that the person
leaves the Site within seven days and has no further connection with the Works in the Contract.
10.1 The Employer carries the risks which this Contract states are Employer's risks, and the
Contractor carries the risks which this Contract states are Contractor's risks.
Page 51 of 98
11. Employer's Risks
11.1 The Employer is responsible for the excepted risks which are (a) in so far as they directly
affect the execution of the Works in the Employer’s country, the risks of war, hostilities,
invasion, act of foreign enemies, rebellion, revolution, insurrection or military or usurped power,
civil war, riot commotion or disorder (unless restricted to the
Contractor’s employees), natural calamities and contamination from any nuclear fuel or nuclear
waste or radioactive toxic explosive, or (b) a cause due solely to the design of the Works, other
than the Contractor’s design.
12.1 All risks of loss of or damage to physical property and of personal injury and death, which
arise during and in consequence of the performance of the Contract other than the excepted risks,
referred to in clause 11.1, are the responsibility of the Contractor.
13. Insurance
13.1 The Contractor at his cost shall provide, in the joint names of the Employer and the
Contractor, insurance cover from the Start Date to the end of defect liability period for events (a)
to (d), in the amounts and deductibles stated in the Contract Data for the following events which
are due to the Contractor's risks:
13.2 Insurance policies and certificates for insurance shall be delivered by the Contractor to
the Engineer for the Engineer's approval before the Start Date. All such insurance shall provide
for compensation to be payable in Indian Rupees to rectify the loss or damage incurred.
13.3 If the Contractor does not provide any of the policies and certificates required, the
Employer may effect the insurance which the Contractor should have provided and recover the
premiums the Employer has paid from payments otherwise due to the Contractor or, if no
payment is due, the payment of the premiums shall be debt due.
13.4 Alterations to the terms of insurance shall not be made without the approval of the
Engineer.
13.4 Both parties shall comply with any conditions of the insurance policies.
14.1 The Contractor, in preparing the Bid, may rely on any Site Investigation Reports referred to
in the Contract Data, supplemented by any other information available to him, before submitting
the bid.
Page 52 of 98
15. Queries about the Contract Data
16.1 The Contractor shall construct, install and maintain the Works in accordance with the
documents forming part of the contract.
17.1 The Contractor may commence execution of the Works on the Start Date and shall carry out
the Works in accordance with the Programme submitted by the Contractor, as updated with the
approval of the Engineer, and complete them by the Intended Completion Date.
18.1 The Contractor shall submit Specifications and Drawings showing the proposed Temporary
Works to the Engineer, who is to approve them if they comply with specifications and drawings.
18.3 The Engineer's approval shall not alter the Contractor's responsibility for design of the
Temporary Works.
18.4 The Contractor shall obtain approval of third parties to the design of the Temporary
Works, where required.
18.5 All Drawings prepared by the Contractor for the execution of the temporary or permanent
Works, are subject to prior approval by the Engineer before their use.
19. Safety
19.1 The Contractor shall be responsible for the safety of all activities on the Site.
20. Discoveries
21.1 The Employer shall give complete possession of the Site to the Contractor on the date of
signing of agreement.
22.1 The Contractor shall allow access to the Site and to any place where work in connection
with the Contract is being carried out, or is intended to be carried out to the engineer and any
person/persons/agency authorized by:
Page 53 of 98
a. The Engineer
b. The Employer
23. Instructions
23.1 The Contractor shall carry out all instructions of the Engineer, which comply with the
applicable laws where the Site is located.
23.2 The Contractor shall permit the Employer to inspect the Contractor's accounts and records
relating to the performance of the Contractor and to have them audited by Auditors appointed by
the Employer if so required by the Employer.
24. Deleted
25. ARBITRATION
(a) In case of Dispute or difference arising between the Employer and a domestic contractor
relating to any matter arising out of or connected with this agreement, such disputes or
difference shall be settled in accordance with the Arbitration and Conciliation Act, 1996.
The arbitral tribunal shall consist of 3 arbitrators one each to be appointed by the Employer
and the Contractor. The third Arbitrator shall be chosen by the two Arbitrators so appointed
by the Parties and shall act as presiding arbitrator. In case of failure of the two arbitrators
appointed by the parties to reach upon a consensus within a period of 30 days from the
appointment of the arbitrator appointed subsequently, the Presiding Arbitrator shall be
appointed by the Secretary General of Indian Road Congress.
(b) If one of the parties fails to appoint its arbitrator in pursuance of sub-clause (a) and (b)
above within 30 days after receipt of the notice of the appointment of its arbitrator by the
other party, then the Secretary General of Indian Road Congress shall appoint the arbitrator.
A certified copy of the order of the Secretary General of Indian Road Congress making such
an appointment shall be furnished to each of the parties.
(c) Arbitration proceedings shall be held at New Delhi, India, and the language of the
arbitration proceedings and that of all documents and communications between the parties
shall be English.
(d) The decision of the majority of arbitrators shall be final and binding upon both parties.
(e) The cost and expenses of Arbitration proceedings will be borne equally by both parties in
accordance with the following fee structure (the signing of the contract shall be the
acceptance of the fee structure given below by both the parties):
However, the expenses incurred by each party in connection with the preparation,
presentation, etc. of its proceedings shall be borne by each party itself.
(f) Performance under the contract shall continue during the arbitration proceedings and
payments due to the contractor by the employer shall not be withheld, unless they are the
subject matter of the arbitration proceedings.
26. Deleted
B. Time Control
27. Programme
27.1 The Engineer shall issue the indent of work in stages specifying the time limit for the same
as and when required. The Contractor shall submit to the Engineer for approval a programme
within the time stipulated in the Contract Data showing the general methods, arrangements,
order, and timing for all the activities in the Works, along with monthly cash flow forecasts.
27.2 An update of the Programme shall be a programme showing the actual progress achieved
on each activity and the effect of the progress achieved on the timing of the remaining Works,
including any changes to the sequence of the activities.
27.3 The Contractor shall submit to the Engineer for approval an updated Programme at
intervals. If the Contractor does not submit an updated Programme within this period, the
Engineer may withhold the amount stated in the Contract Data from the next payment certificate
and continue to withhold this amount until the next payment after the date on which the overdue
Programme has been submitted.
27.4 The Engineer's approval of the Programme shall not alter the Contractor's obligations.
The Contractor may revise the Programme and submit it to the Engineer again at any time. A
revised Programme shall show the effect of Variations and Compensation Events.
Page 55 of 98
28. Extension of the Intended Completion Date
28.1 The Engineer shall extend the Intended Completion Date only after the approval of
NHIDCL if a Compensation Event occurs or a Variation is issued which makes it impossible for
Completion to be achieved by the Intended Completion Date without the Contractor taking steps
to accelerate the remaining Works, which would cause the Contractor to incur additional cost.
28.2 The Engineer shall decide whether and by how much time to extend the Intended
Completion Date within 21 days of the Contractor asking the Engineer for a decision upon the
effect of a Compensation Event or Variation and submitting full supporting information. If the
Contractor has failed to cooperate in dealing with a delay, the delay by this failure shall not be
considered in assessing the new Indented Completion Date.
29.1 The Engineer may instruct the Contractor to delay the start or progress of any activity
within the Works. Delay/delays totaling more than 30 days will require prior written approval of
the Employer.
30.1 The Engineer may require the Contractor to attend a management meeting. The business
of a management meeting shall be to review the plans for the Works.
30.2 The Engineer shall record the business of management meetings and provide copies of
the record to those attending the meeting. The responsibility of the parties for actions to be taken
shall be decided by the Engineer either at the management meeting or after the management
meeting and stated in writing to all those who attended the meeting.
C. Quality Control
31.1 The Engineer shall check the Contractor's work and notify the Contractor of any Defects
that are found. Such checking shall not affect the Contractor's responsibilities. The Engineer may
instruct the Contractor to search for a Defect and to uncover and test any work that the Engineer
considers may have a Defect.
32. Tests
Page 56 of 98
32.2 If the Engineer instructs the Contractor to carry out a test not specified in the
Specification to check whether any work has a Defect and the test shows that it does, the
Contractor shall pay for the test and any samples.
33.1 The Defects Liability Period is 06 months calculated from the Completion Date. It is the
terms of contract that Construction of retaining wall shall be of very high standard,
requiring no major repairs for at least 6 (Six) months after the date of completion of
works.
33.2 If any defects including shrinkage, cracks, and other faults appear in the work within six
months of “Taking over” certificate, the Engineer shall give notice to the Contractor of
any defects before the end of the Defects Liability Period, which begins at Completion,
and is for twelve months thereafter. The Defects Liability shall be extended for as long as
defects remain to be corrected.
33.3 Every time notice of a defect is given; the Contractor shall correct the notified defect at
his own cost within the length of time specified by the Engineer’s notice. If the contractor is in
default the Engineer shall cause the same to be made good by other workmen and deduct the
expenses from any sums that may be due to the contractor.
34.1 If the Contractor has not corrected a Defect/completed the work, to the satisfaction of the
Engineer, within the time specified in the Engineer's notice, the Engineer will assess the cost of
having the Defect corrected/completed, and the Contractor will pay this amount.
D. Cost Control
35. Bill of Quantities
35.1 The Bill of Quantities shall contain items for the construction, installation, testing, and
commissioning and maintaining works to be done by the Contractor.
35.2 The Bill of Quantities is used to calculate the Contract Price. The Contractor is paid for
the quantity of the work done at the rates in the Bill of Quantities for each item for the work
executed.
35.3.1 If the final quantity of the work-done differs from the quantity in the Bill of Quantities
for the particular item by more than 25 percent provided the change exceeds 1% of initial
Contract Price, the Engineer shall adjust the rate to allow for the change. The Engineer shall
follow the guidelines of the Employer to determine the changed rate.
Page 57 of 98
35.3.2 The Engineer shall not adjust rates from changes in quantities if thereby the Initial
Contract Price is exceeded by more than 15 percent, except with the Prior approval of the
Employer. If requested by the Engineer, the Contractor shall provide the Engineer with a detailed
cost breakdown of any rate in the Bill of Quantities.
Deleted
36. Variations
36.1 The Engineer shall, having regard to the scope of the Works and the sanctioned estimated
cost, have power to order only after approval from NHIDCL / as per NHIDCL guidelines, in
writing, Variations within the scope of the Works he considers necessary or advisable during the
progress of the Works. Such Variations shall form part of the Contract and the Contractor shall
carry them out and include them in updated Programs produced by the Contractor. Oral orders of
the Engineer for Variations, unless followed by written confirmation, shall not be taken into
account.
37.1 If rates for Variation items are specified in the Bill of Quantities, the Contractor shall
carry out such work at the same rate. This shall apply for Variations only up to the limit
prescribed in the Clause 35. If the Variation exceeds this limit, the rate shall be derived under the
provisions of clause 37.2 and 37.3 for quantities (higher) exceeding the deviation limit.
37.2 For works where Schedule of Rates (SOR) of concerned circle of State’s Public Works
Department are available shall be applicable for determination of costs. If the rates for Variation
are not specified in the SOR, the Engineer shall derive the rate from similar items in the Bill of
Quantities.
37.3 If the rate for Variation item cannot be determined in the manner specified in Clause 37.1
or 37.2, the Contractor shall, within 14 days of the issue of order of Variation work, inform the
Engineer the rate which he proposes to claim, supported by analysis of the rates. The Engineer
shall assess the quotation and determine the rate based on prevailing market rates within one
month of the submission of the claim by the Contractor and approval from NHIDCL will be
taken. As far as possible, the rate analysis shall be based on the standard data book and the
current schedule of rates of the PWD (NH) division. The decision of the Employer on the rate
so determined shall be final and binding on the Contractor.
38.1 When the Programme is updated, the Contractor shall provide the Engineer with an
updated cash flow forecast.
39.1 The Contractor shall submit to the Engineer monthly statements of the value of the work
executed less the cumulative amount certified previously supported with detailed measurement
of the items of work executed.
39.2 The Engineer shall check the Contractor's monthly statement within 14 days and certify
Page 58 of 98
the amount to be paid to the Contractor after taking into account any credit or debit for the month
in question.
39.3 The value of work executed shall be determined, based on measurements by the
Engineer.
39.4 The value of work executed shall comprise the value of the quantities of the items in the
Bill of Quantities completed.
39.5 The value of work executed shall also include the valuation of Variations and
Compensation Events.
39.6 The Engineer / Employer may exclude any item certified in a previous certificate or
reduce the proportion of any item previously certified in any certificate in the light of later
information.
39.7 The final bill shall be submitted by the contractor within one month of the actual date of
completion of the work; otherwise, the Engineers certificate of the measurement and of the total
amount payable for work accordingly shall be final and payment made accordingly within a
period of sixty days as far as possible.
40. Payments
40.1 Payments shall be adjusted for deductions for advance payments, security deposit, other
recoveries in terms of the Contract and taxes at source, as applicable under the law. The
Employer shall pay the Contractor the amounts Engineer had certified within 14 days of the
date of each certificate.
40.2 The Authorized Representative of the Employer shall make the payment certified by the
Engineer.
40.3 Items of the Works for which no rate or price has been entered in the Bill of Quantities,
will not be paid for by the Employer and shall be deemed to be covered by other rates and
prices in the Contract.
41.2 If a Compensation Event would prevent the Works being completed before the Intended
Completion Date, the Intended Completion Date shall be extended. The Engineer shall decide
whether and by how much the Intended Completion Date shall be extended after the approval of
the employer.
41.3 The contractor shall not be entitled to compensation to the extent that the Employer’s
interests are adversely affected by the Contractor not having given early warning or not having
cooperated with the Engineer/Employer.
Page 59 of 98
42.2 All payments will be made in Indian Rupees.
43.1. Deleted
43.2. Deleted
44.1 The Employer shall retain security deposit of 6 % (six percent) of the amount from each
payment due to the Contractor until Completion of the whole of the Works, subject to the
condition that the maximum amount of Retention Money shall not exceed 5% (Five Percent) of
the Contract Price.
44.2 The security deposit/retention money and the performance security will be released to the
Contractor when the Defect Liability period is over, and the Engineer has certified that the
Defects, if any, notified by the Engineer to the Contractor before the end of this period have been
corrected.
44.3 If the contractor so desires then the Security Deposit/retention money can be released on
submission of unconditional Bank Guarantee at the following two stages: -
(a) At a point after the progress of work in financial term (gross value of work done) has
reached 50% of the contract amount.
(b) After the retention money has been deducted to the full value (5% of the Contract
Amount).
45.2 If the Intended Completion Date is extended after liquidated damages have been paid, the
Engineer shall correct any overpayment of liquidated damages by the Contractor by adjusting in
the next payment certificate. The contractor shall not be paid interest on the over payment of
liquidated damages.
47. Securities
47.1 Subject to further condition in contract data, the Performance Security equal to three
percent of the contract price and additional security for unbalanced bids shall be provided to the
Employer no later than the date specified in the Letter of Acceptance and shall be issued in the
form given in the Contract Data and by a prescribed bank. The Performance Security shall be
Page 60 of 98
valid until a date 28 days after the expiry of Defect Liability Period and the additional
performance security for unbalanced bids shall be valid until a date 28 days from the date of
issue of the certificate of completion. The validity shall account for additional 3 months’ time to
account for BG verification, signing of contract and start date.
For unbalanced bids, an additional performance security shall be provided to the employer for
an amount calculated as under: (a) If the Bid Price offered by the Selected Bidder is lower than
20% of the estimated Project Cost, then the Additional Performance Security shall be calculated
@20% of the difference in the (i) Estimated Project Cost (as mentioned in RFP)-20% of the
Estimated Project Cost and (ii) the Bid Price offered by the selected Bidder. (b) Maximum limit
of additional performance security shall be limited to 3% of the Bid price offered by the
setected bidder. (c) This Additional Performance Security shall be treated as part of the
Performance Security.
48.1 Loss or damage to the Works or Materials to be incorporated in the Works between the
Start Date and the end of the Defects Liability Period shall be remedied/ rectified by the
Contractor at their cost if the loss or damage arises from the Contractor's acts or omissions.
49. Completion
49.1 The Contractor shall request the Engineer to issue a certificate of Completion of the Works,
and the Engineer will do so upon deciding that the Works is completed.
50.1 The Employer shall take over the Site and the Works within seven days of the Engineer's
issuing a certificate of Completion.
51.1 The Contractor shall supply to the Engineer with a detailed account of the total amount that
the Contractor considers payable under the Contract before the end of the Defects Liability
Period. The Engineer shall issue a Defects Liability Certificate and certify any final payment that
is due to the Contractor within 56 days of receiving the Contractor's account if it is correct and
complete. If it is not, the Engineer shall issue within 56 days a schedule that states the scope of
the corrections or additions that are necessary. If the Final Account is still unsatisfactory after it
has been resubmitted, the Engineer shall decide on the amount payable to the Contractor and
issue a payment certificate within 56 days of receiving the Contractor’s revised account.
52.1 DELETED
52.2 DELETED
53. Termination
53.1 The Employer may terminate the Contract if the Contractor causes a fundamental breach
Page 61 of 98
of the Contract.
53.2 Fundamental breaches of Contract include, but shall not be limited to, the following:
a) the Contractor stops work for 28 days when no stoppage of work is shown on the current
Programme and the stoppage has not been authorized by the Engineer;
b) the Contractor is declared as bankrupt or goes into liquidation other than for approved
reconstitution or amalgamation;
c) the Engineer/Employer gives Notice that failure to correct a particular Defect is a
fundamental breach of Contract and the Contractor fails to correct it within a reasonable
period of time determined by the Engineer;
d) the Contractor does not maintain a Security, which is required;
e) the Contractor has delayed the completion of the Works by the number of days for which
the maximum amount of liquidated damages can be paid, as defined in clause 45;
f) the Contractor fails to provide insurance cover as required under clause 13;
g) if the Contractor, in the judgment of the Employer, has engaged in the corrupt or
fraudulent practice in competing for or in executing the Contract. For the purpose of this
clause, “corrupt practice” means offering, giving, receiving, or soliciting of anything of
value to influence the action of a public official in the procurement process or in Contract
execution. “Fraudulent Practice” means a misrepresentation of facts in order to influence
a procurement process or the execution of a contract to the detriment of the Employer and
includes collusive practice among Bidders (prior to or after bid submission) designed to
establish bid process at artificial non-competitive levels and to deprive the Employer of
the benefits of free and open competition.
if the Contractor has not completed at least thirty percent of the value of Work required to
be completed after half of the completion period has elapsed;
if the Contractor fails to set up a field laboratory with the prescribed equipment, within
the period specified; and
any other fundamental breach as specified in the Contract Data.
53.3 Notwithstanding the above, the Employer may terminate the Contract for convenience.
53.4 If the Contract is terminated, the Contractor shall stop work immediately, make the Site
safe and secure, and leave the Site as soon as reasonably possible but in no case later than 7 days.
54.2 Save and except Cl 35.3.3, if the Contract is terminated at the Employer's convenience,
the Engineer shall issue a certificate for the value of the work done, the reasonable cost of
removal of Equipment, repatriation of the Contractor's personnel employed solely on the Works,
and the Contractor's costs of protecting and securing the Works and less advance payments
outstanding on the date of the certificate, less other recoveries due in terms of the Contract, and
less taxes due to be deducted at source as per applicable law.
In case of termination on account of award of 2 laning work stated in Cl 35.3.3, the Engineer
Page 62 of 98
shall issue a certificate for the value of work done till termination, less advance payments
outstanding, less other recoveries due in terms of contract and less taxes due to be deducted at
source as per applicable law.
55. Property
55.1 All Materials on the Site, Plant, Equipment, Temporary Works, and Works shall be deemed
to be the property of the Employer for use for completing balance work if the Contract is
terminated because of the Contractor's default.
56.1 If the Contract is frustrated by the outbreak of war or by any other event entirely outside the
control of the Employer or the Contractor, the Engineer shall certify that the Contract has been
frustrated. The Contractor shall make the Site safe and stop work as quickly as possible after
receiving this certificate and shall be paid for all work carried out before receiving it and for any
work carried out afterwards to which a commitment was made.
57. Labour
57.1 The Contractor shall, make arrangements of his own cost and expenses for the
engagement of all staff and labour, local or others; for their payment, housing, feeding and
transport; and for compliance with various labour laws/ regulations.
57.2 The Contractor shall, as asked by the Engineer, deliver to the Engineer a return in detail,
in such form and at such intervals as the Engineer may prescribe, showing the staff and the
numbers of the several classes of labour from time to time employed by the Contractor on the
Site and such other information as the Engineer may require.
58.1 During the currency of the Contract, the Contractor and his sub-Contractors shall abide at
all times by all existing labour enactments and rules made there under, regulations, notifications
and bye laws of the State or Central Government or local authority and any other labour law
(including rules), regulations, bye laws that may be notified already or that may be notified under
any labour law in future either by the State or the Central Government or the local authority.
Salient features of some of the major labour laws that are applicable to construction industry are
given below. The Contractor shall keep the Employer indemnified in case any action is taken
against the Employer by the competent authority on account of contravention of any of the
provisions of any Act or rules made there under, regulations or notifications including
amendments. If the Employer is caused to pay or reimburse, such amounts as may be necessary
to cause or observe, or for non-observance of the provisions stipulated in the notifications/bye
laws/Acts/Rules/regulations including amendments, if any, on the part of the Contractor, the
Engineer/Employer shall have the right to deduct any money due to the Contractor including
from his performance security/ retention money. The Employer/Engineer shall also have right to
recover from the Contractor any sum required or estimated to be required for making good the
loss or damage suffered by the Employer. The employees of the Contractor and the Sub-
Contractor in no case shall be treated as the employees of the Employer at any point of time.
b) Payment of Gratuity Act 1972: - Gratuity is payable to an employee under the Act on
satisfaction of certain conditions on separation if an employee has completed the prescribed
minimum years (say, five years) of service or more or on death the rate of prescribed minimum
days‟ (say, 15 days) wages for every completed year of service. The Act is applicable to all
establishments employing the prescribed minimum number (say, 10) or more employees.
c) Employees P.F. and Miscellaneous Provision Act 1952: The Act Provides for monthly
contributions by the Employer plus workers at the rate prescribed (say, 10% or 8.33%). The
benefits payable under the Act are:
d) Maternity Benefit Act 1951: - The Act provides for leave and some other benefits to
women employees in case of confinement or miscarriage etc.
e) Contract Labour (Regulation & Abolition) Act 1970: - The Act provides for certain
welfare measures to be provided by the Contractor to contract labour and in case the Contractor
fails to provide, the same are required to be provided, by the Principal Employer by Law. The
principal Employer is required to take Certificate of Registration and the Contractor is required
to take license from the designated Officer. The Act is applicable to the establishments or
Contractor of Principal Employer if they employ prescribed minimum (say 20) or more contract
labour.
f) Minimum Wages Act 1948: - The Employer is to pay not less than the Minimum Wages
fixed by appropriate Government as per provisions of the Act if the employment is a scheduled
employment. Constructions of buildings, roads, runways are scheduled employment.
g) Payment of Wages Act 1936: - It lays down as to by what date the wages are to be paid,
when it will be paid and what deductions can be made from the wages of the workers.
h) Equal Remuneration Act 1979: - The Act provides for payment of equal wages for
work of equal nature to male and female workers and for not making discrimination against
female employees in the matters of transfers, training and promotions etc.
i) Payment of Bonus Act 1965: - The Act is applicable to all establishment employing
prescribed minimum (say, 20) or more workmen. The Act provides for payments of annual
bonus within the prescribed range of percentage of wages to employees drawing up to the
prescribed amount of wages, calculated in the prescribed manner. The Act does not apply to
certain establishments. The newly set-up establishments are exempted for five years in certain
circumstances. States may have different number of employment size.
j) Industrial Disputes Act 1947: - The Act lays down the machinery and procedure for
resolution of industrial disputes, in what situations a strike or lock-out becomes illegal and what
Page 64 of 98
are the requirements for laying off or retrenching the employees or closing down the
establishment.
l) Trade Unions Act 1926: - The Act lays down the procedure for registration of trade
unions of workmen and Employers. The Trade Unions registered under the Act have been given
certain immunities from civil and criminal liabilities.
m) Child Labour (Prohibition & Regulation) Act 1986: - The Act prohibits employment
of children below 14 years of age in certain occupations and processes and provides for
regulations of employment of children in all other occupations and processes. Employment of
child labour is prohibited in building and construction industry.
p) Factories Act 1948: - The Act lays down the procedure for approval of plans before setting
up a factory, health and safety provisions, welfare provisions, working hours, annual earned
leave and rendering information regarding accidents or dangerous occurrences to designated
authorities. It is applicable to premises employing the prescribed minimum (say, 10) persons
or more with aid of power or another prescribed minimum (say, 20) or more persons without
the aid of power engaged in manufacturing process.
59.1 The contractor shall do photography/videography of the site firstly before the start of the
work, secondly mid-way in the execution of different stages of work and lastly after the
completion of the work. No separate payment will be made to the contractor for this.
59.2 The Contractor shall not disclose details of Drawings furnished to him and works on
which he is engaged without the prior approval of the Engineer in writing. No photograph of the
Page 65 of 98
works or any part thereof or plant employed thereon, except those permitted under clause 59.1,
shall be taken or permitted to be taken by the Contractor or by any of his employees or any
employees of his sub-Contractors without the prior approval of the Engineer in writing. No
photographs/ Videography shall be published or otherwise circulated without the approval of the
Engineer in writing.
60.1 The Contractor shall duly comply with the provisions of the Apprenticeship Act1961 (III
of 1961), the rules made there under and the orders that may be issued from time to time under
the said Act and the said Rules and on his failure or neglect to do so he shall be subject to all
liabilities and penalties provided by the said Act and said Rules.
[CL.45.1]
Page 67 of 98
17. The standard form of Performance Security acceptable to the [CL.47.1]
Employer shall be an shall be an unconditional Bank Guarantee of
the type as presented in the Bidding Documents.
18. Other fundamental breach is that the contractor has failed to
complete 75% of value of indented work in any 3 indents issued by [CL.53.2]
the Engineer.
19. The percentage to apply to the value of work not completed
representing the Employer's additional cost for completing the work [CL.54.1]
shall be 20%.
Page 68 of 98
(SECTION-VI)
TECHNICAL SPECIFICATIONS
Page 69 of 98
TECHNICAL SPECIFICATIONS
7.1 PREAMBLE:
The Technical Specifications contained herein shall be read in conjunction with the other
Bidding Documents as specified.
The Technical Specifications in accordance with which the entire work described
hereinafter shall be executed and completed by the Contractor shall comprise of the
following:
5.2.2 In the absence of any definite provisions on any particular issue in the aforesaid
Specifications, reference may be made to the latest codes and specifications of IRC and
BIS in that order, Where even these are silent, the construction and completion of the
works shall conform to sound engineering practice as approved by the Engineer and, in
case of any dispute arising out of the interpretation of the above, the decision of the
Engineer shall be final and binding on the Contractor.
Page 70 of 98
PART - II
Clause 106 (a) Add the following sentence. “The trial run is to be carried out
laying the relevant pavement material and it is not to be part of the
permanent works. The trial is to be carried out on prior approval of
equipment by Engineer-in-Charge.”
“Before carrying out any survey work the Contractor shall submit to
the Engineer for the approval a programme and methodology for the
calibration of all optical and electronic survey equipment to be used
on site during construction of the works. The Contractor will
maintain calibration records for all such equipment in his site office,
available at all times for inspection by the Engineer.
Page 71 of 98
Clause 110 Public Utilities:
Existing services like water pipes, sewers, oil pipelines, cables, gas ducts
etc. Owned by various authorities including Public Undertaking an Local
Authorities shall be checked and located by the Contractor prior to
commencement of work.
The Contractor’s programme must take into account the period of notice
and duration of diversionary works of each body as existing at site. The
Contractor must also allow for any effect of these services and alterations
upon the Works and for arranging regular meetings with the various bodies
at the commencement of the Contract and throughout the period of the
Works in order to maintain the required co-ordination. During the
period of the Works, the contractor shall have no objection if the public
utility bodies and their decisions in the execution of their proposal in terms
of programme and construction. Provided that, in the opinion of the
Engineer, the Contractor has received reasonable notice thereof before the
relevant alterations are put in hand.
The Contractor shall preserve existing trees, plants and other vegetation
that are to remain within or adjacent to the works and shall use every
precaution necessary to prevent damage or injury thereto. On completion
of the Works, all areas disturbed by the Contractor’s construction
activities shall be restored in their original condition, or as may be
acceptable to the Engineer. The cost of this work shall be deemed to be
included in the rates generally.
Clause 111.5 Pollution from Hot Mix Plants and Batching Plants
The H.M.P. should be sited at least 500m away from the nearest abitation.
The H.M.P. shall be fitted with a dust extraction unit in order that the
exhaust gases comply with the requirements of the relevant current
Page 72 of 98
emission control legislation. “All operations at plants shall be undertaken
in accordance with all current rules and regulations protecting the
environment.”
A register of all herbicides and other toxic chemicals delivered to the site,
shall be kept and maintained up to date by the contractor. The register
shall include a name physical properties and characteristics, chemical
ingredients, health and safety hazard information, safe handling and
storage procedures, and emergency and first aid procedures for the
product.”
Clause 111.9 Add the following sentence at the end of the para.
All vehicles and machinery employed in the execution of the works shall be
regularly maintained to ensure that pollutant emission levels comply with
the relevant requirements of current pollution control legislation. During
routine servicing operations, the effectiveness of exhaust silencers must be
checked and if found to be defective must be replaced. Notwithstanding
this requirement, noise levels from any item of plant must comply with the
relevant legislation for levels of sound emission. Non compliant plant is to
be removed from site.
All works are to be carried out in such a fashion that the damage or
disruption to the flora and fauna is reduced to a minimum wherever
possible. Trees or shrubs will only be felled or removed that impinge
directly on the permanent works or necessary temporary works, after
seeking approval of the Engineer.
“The Contractor shall submit, for the Engineer’s approval, Traffic Control
Plan 5 days prior to commencement of the temporary / permanent works.”
Clause 112.2 Passage of Traffic along a part of the Existing Carriage way under
improvement:
Add “and no extra payment will be made except the treatment of shoulders
for earth work and granular sub-base as per Clause 112.2 above.” At the
end of first paragraph.
“At all times, the Contractor shall provide safe and convenient passage for
vehicles pedestrians and livestock to and from side roads and property
accesses connecting to the roadway. Work which affects the use of side
roads and existing accesses shall not be undertaken without providing
adequate prior provisions to the satisfaction of the Engineer.”
Clause 113 General Rules For the Measurement of Works for Payment:
“The rates in the Bill of Quantities are deemed to include the costs
of haulage from source of supply to the site for all materials
required for the Works.”
Add to Clause 114.2 (xvii). Cost of all provisions for executing the
work safely including all protective clothing, barriers, earplugs etc.
Page 76 of 98
Clause 121.3 Laboratory Equipment shall be provided as prescribed by the
Engineer relevant to items of work in BOQ.
Evenness
i) Theodolite 2 sets
ii) Precision automatic level 2 sets
iii) Precision staff 4 sets
iv) Camber templates 2 lane
a) Crown type cross-section 4 sets
b) Straight run cross-section 4 sets
Steel Tape
a) 3 m long 4 sets
b) 5 m long 4 sets
c) 10 m long 4 sets
d) 20 m long 4 sets
e) 30 m long 4 sets
Page 77 of 98
Clause 126: Supply of Video Cassettes
126.1 Description
The work consists of taking video films of important activities of the work as directed by the
Engineer during the currency of the project and editing them and converting them to a CD
(master CD+ 4 copies) film of playing time not less than 60 minutes and upto 180 minutes as
directed by the Engineer. It shall contain narration of the activities in English by competent
narrator. The editing of the film and the script for narration shall be as approved by the Engineer.
The CD shall be acceptable quality and the film shall be capable of producing colour pictures.
No separate payment shall be made and the work shall be treated as incidental.
Delete the last two sentences of last paragraph. And add, “The
earthwork shall be carried out as per the sequences stated in this
contract or as directed by engineer-in-charge”.
Page 78 of 98
Clause 304.3.7 Back filling
“No borrow area shall be made available by the Employer for this work.
The arrangement for the source of supply of the material for embankment
and sub grade as well as compliance to the different environmental
requirements in respect of excavation and borrow areas as stipulated, from
time to time, by the Ministry of Environment and Forest, Government of
India and the local bodies, as applicable shall be the sole responsibility of
the
Contractor.”
Paragraph 8 of this Clause given below Table 300-2 shall read as under:
Page 79 of 98
i) The Values of maximum dry density and optimum moisture content
obtained in accordance with IS 2720 (Part 8) for each fill material he
intends to use.
ii) The graphs showing values of density against moisture content from
which each of the values in (i) above of the maximum dry density and
optimum moisture content were determined.
iii) The dry density-moisture content-CBR relationship for each of the fill
materials be intends to use in the sub grade.”
Clause 305.3.5.2 In Paragraph 3, delete “IS: 2720 (Part 7) or “and “as the case may
be”.
“Only vibratory rollers of not less than 8 – 10 ton static weight with
plain or pad foot drum shall be used for compaction.”
“The earthwork for widening the existing road embankment and shoulders
shall be carried out in layers duly compacted. On completion of earth
work to the required height the triangular portion on the sloping face of
the layers shall be cut in such a manner that the specified slope is
achieved. This operation is incidental to work and no extra payment shall
be made for this.”
“In the case of high embankments, the Contractor shall use the material
from the approved borrow area.”
Clause 307.5 Add “(iii) application of top soil” after (ii). Delete “the contract unit rate
for application of top soil shall be as per clause 301.9.5”.
“The rate for concrete lined drains shall include bedding concrete and
jointing. The rate for lined surface drains shall include inlet sumps and
metal grates where specified.”
Page 81 of 98
The engineer shall identify the area where leveling and dressing is to be
carried out. The clearing and grubbing of rank vegetation and
undergrowth shall be carried out as per clause 201.1. If the stagnant water
is existing on the side, the same shall be pumped / bailed out. The area
shall be kept dry throughout the operation of leveling and dressing. The
leveling and dressing shall be carried out by excavating the high area and
filling the low area with the excavated material in proper slope. This
operation will be carried out manually/mechanically as per site conditions.
The measurement shall be made for the area to be leveled and dressed in
Sqm.
The contract unit rates for the items for leveling and dressing shall be
payment in full for carrying out the required operations including full
compensation for:
1. Cost of all labour, materials, tool, equipment and incidentals to complete
the work.
2. Clearing and grubbing the rank vegetation and undergrowth and their
disposal within 1000m.
3. Pumping and bailing out of water and keeping the area dry during
construction.
4. In all type of soils and saturated earth.
“The thickness of the loose layers shall be so regulated that the maximum
thickness of the layer after compaction does not exceed
150 mm.”
Page 82 of 98
Clause 401.7 Measurement for payment:
Page 83 of 98
Clause 501.8.3.1 Preparing Existing Granular Surface
Page 84 of 98
Clause 507.9 For DBM, Clause 508.9 for SDBC and Clause 509.9 for BC
These clauses stand amended to the extent that the rate shall cover the provision of bitumen in
the mix as per job mix formula. No variation in the rate for this item will be admissible on
account of quantity of bitumen used.
Clause 801
801.1 GENERAL
801.1 The colour, configuration, size and location of all traffic signs for highways (otherthan
Expressways for which the size of the signs, letters and their placement shall be as specified in
the drawings and relevant Specifications or as directed by the Engineer) and for other roads,
shall be in accordance with the Code of Practice for Road Signs, IRC:67:2010, or as shown on
the drawings. In the absence of any details or for any missing details (for example, chevron
signs etc.), the signs shall be provided in accordance with international standards and/or as
directed by the Engineer.
801.1.2 Unless otherwise specified, the signs shall be reflectorised as shown on the drawings or
as directed by the Engineer. They shall be of retro-reflectorised type and made of micro-
prismatic type reflective as per IRC:67:2010.
801.1.3 In general, cautionary and mandatory signs' shall be fabricated through process of screen
printing. In regard to informatory signs with inscriptions or cut letters of, coloured
retroreflective sheeting comprising un metalized microprismatic element material as per
IRC:67:2010 or durable transparent, coloured overlay film shall be used which must be bonded
well on the base sheeting, as directed by the Engineer.
801.2 Materials
The various materials and fabrication of the traffic signs shall conform to the following
requirements:
801.2.1 Concrete : Concrete shall be of the grade shown on the Contract drawing or otherwise
as directed by the Engineer.
801.2.2 Reinforcing steel: Reinforcing steel shall conform to the requirement of IS:1786unless
otherwise shown on the drawing.
801.2.3 Bolts, nuts, washers: High strength bolts shall conform to IS: 1367 whereas precision
bolts, nuts, etc., shall conform to IS:1364.
801.2.4 Plates and supports: Plates and support sections for the sign posts shall conform to
IS:226 and IS:2062 or any other relevant IS Specifications.
801.2.5. Substrate; Sign panels may be fabricated on aluminium sheet, aluminium composite
Page 85 of 98
panel, fibre glass sheeting, or sheet moulding compound. Aluminum sheets used for sign boards
shall be of smooth, hard and corrosion resistant aluminium alloy conforming to IS:736-Material
designation 24345 or 1900. Aluminium Composite Panel and other materials shall meet the
relevant ASTM (D903, E8, E393, E732)/BS/BIS requirements.
801.2.6 Shoulder mounted ground signs with a maximum side dimension not exceeding600mm
shall not be less than 1.5 mm thick with Aluminium and 3 mm thick with Aluminum Composite
Material. All other signs shall be at least 2 mm thick with Aluminium and 4 mm thick with
Aluminium Composite Material. The thickness of the sheet shall be related to the size ofthe sign
and its support and shall be such that it does not bend or deform under prevailing wind and other
loads. All overhead signs made with Aluminium Composite Material shall be minimum 4 mm
thick to withstand wind and other loads without deformation.
801.2.7 In respect of sign sizes not covered by IRC:67: 2010 the structural details(thickness,
etc.) shall be as per the approved drawings or as directed by the Engineer.
801.3.1 General requirements: The retro-reflective sheeting used on the sign shall consist of
the white or coloured sheeting having a smooth outer-surface which has the property of retro-
reflection over its entire surface. It shall be weather-resistant and show colour fastness. It shall
be new and unused and shall show no evidence of cracking, scaling, pitting, blistering, edge
lifting or curling and shall have negligible shrinkage or expansion. A certificate of having tested
the sheeting for co-efficient of retro-reflection, day/night time colour luminous, shrinkage,
flexibility, linear removal, adhesion, impact resistance, specular gloss and fungus resistance 3
years outdoor weathering and its having passed these tests shall be obtained from a Government
Laboratory, by the manufacturer of the sheeting. The retro- reflective sheeting shall be either of
Engineering Grade material with enclosed lens, High Intensity Grade with encapsulated lens or
Micro-prismatic Grade retro-reflective element material as given in Clause below
801.3.2 Micro Prismatic Grade Sheeting (Type XI) :Retro reflective sheeting typically
manufactured as a cube corner. The reflective sheeting shall be retro reflective sheeting made of
micro prismatic retro reflective material. The retro reflective surface, after cleaning with soap
and water and in dry condition shall have the minimum co-efficient of retro reflection
(determined in accordance with ASTM D 4956-09) as indicated in Table 800
Florescent
Observation Entrance Blue Brown Florescent Florescent
white Yellow Orange Green Red yellow
Angle Angle yellow Orange
-Green
0.1°B -4° 830 620 290 83 125 37 25 660 500 250
0.1°B +30° 325 245 115 33 50 15 10 260 200 100
0.2° -4° 580 435 200 58 87 26 17 460 350 175
0.2° +30° 220 165 77 22 33 10 7 180 130 66
0.5° -4° 420 315 150 42 63 19 13 340 250 125
0.5° +30° 150 110 53 15 23 7 5 120 90 45
1.0° -4° 120 90 42 12 18 5 4 96 72 36
1.0° +30° 45 34 16 5 7 2 1 36 27 14
Page 86 of 98
A Minimum Coefficient of Retro reflection (RA) (cd.lx-1.m-2).
B Values for 0.1o observation angles are supplementary requirements that shall apply only
when specified by the purchaser in the contract or order.
When totally wet, the sheeting shall show not less than 90 percent of the values, of retro
reflection indicated in above Table. At the end of 10 years, the sheeting shall retain at least 80
percent of its original retro-reflectance.
801.3.3 Messages / borders: The messages (legends, letters, numerals etc.) and borders shall
either be screen-printed or of cut-outs from durable transparent overlay or cut-out from same
type of reflective sheeting (excluding for black colour) for the cautionary/ mandatory signs.
Screen printing shall be processed and finished with materials and in a manner specified by the
sheeting manufacturer. For the information and other signs, the messages (legends, letters,
numerals etc.) and borders shall be cut-out from durable transparent overlay film or cut out from
same reflective sheeting only. Cut-outs shall be bonded with the sheeting in the manner specified
by the manufacturer. Both the screen printed areas and cut-out messages sheetings and cut-out
durable transparent overlay film shall be covered under the warranty period of the sheeting type,
issued by the sheeting manufacturer
801.3.4 For screen-printed transparent coloured areas on white sheeting, the coefficient of retro-
reflection shall not be less than 50 per cent of the values of corresponding colour in Tables 800
as applicable.
801.3.4.1 Cut-out messages and borders, wherever used, shall be made out of retro-reflective
sheeting (as per Clauses 801.3.2 as applicable), except those in black which shall be of non-
reflective sheeting.
801.3.5 Color: Unless otherwise specified, the general color scheme and properties shall
be as stipulated in ASTM 4956-09. The colors shall be durable and uniform in acceptable hue
when viewed in day light or under normal headlights at night and in inclement weather
conditions.
801.3.6 Adhesives: The sheeting shall have either a pressure-sensitive adhesive of the
aggressive-tack type requiring no heat, solvent or other preparation for adhesion to a smooth
clean surface, or a tack free adhesive activated by heat, applied in a heat-vacuum applicator, in a
manner recommended by the sheeting manufacturer. The adhesive shall be protected by an easily
removable liner (removable by peeling without soaking in water or other solvent) and shall be
suitable for the type of material of the base plate used for the sign. The adhesive shall form a
durable bond to smooth, corrosion and weather resistant surface of the base plate such that it
shall not be possible to remove the sheeting from the sign "base in one piece by use of sharp
instrument. In case of pressure-sensitive adhesive sheeting, the sheeting shall be applied in
accordance with the manufacturer's Specifications. Sheeting with adhesives requiring use of
solvents or other preparation for adhesive shall be applied strictly in accordance with the
manufacturer's instructions.
Page 87 of 98
801.3.7 Refurbishment: Where existing signs are specified for refurbishment, the
sheeting shall have a semi-rigid aluminum backing or materials as per Clause 801.2.5, pre-
coated with aggressive-tack type pressure sensitive adhesive. The adhesive shall be suitable for
the type of material used for the sign and should thoroughly bond with that material.
801.3.8.2 Complete sheets of the material shall be used on the signs except where it is
unavoidable; at splices, sheeting with pressure sensitive adhesives shall be overlapped not less
than 5 mm. Where screen printing with transparent colours is proposed, only butt jointing shall
be used. The material shall cover the sign surface evenly and shall be free from twists, cracks
and folds. Cut-outs to produce legends and borders shall be bonded with the sheeting in the
manner specified by the manufacturer.
801.3.9 Warranty and durability: The Contractor shall obtain from the manufacture a ten year
warranty for satisfactory field performance including stipulated retro-reflectance of the retro-
reflective sheeting of micro-prismatic sheeting, a seven-year warranty for high intensity grade
and a five year warranty for the sheeting of engineering grade and submit the-same to the
Engineer. In addition, a ten year, seven year and a five year warranty for satisfactory In-field
performance of the finished sign with retro-reflective sheeting of micro prismatic, high intensity
grade and engineering grade respectively, inclusive of the screen printed or cut out
letters/legends and their bonding to the retro-reflective sheeting shall be obtained from the
contractor/supplier and submitted to the Engineer. The Contractor/ supplier shall also furnish the
LOT numbers and certification that the signs and materials supplied against the assigned work
meets all the stipulated requirements and carry the stipulated warranty and that the
contractor/supplier is the authorized converter of the particular sheeting:
All signs shall be dated during fabrication with indelible markings to indicate the start of
warranty. The warranty shall also cover the replacement obligation by the sheeting manufacturer
as well as contractor for replacement/repair/restoration of the retro-reflective efficiency.
Page 88 of 98
A certificate in original shall be given by the sheeting manufacturer that its offered retro-
reflective sheeting has been tested for various parameters such as co-efficient of retro-reflection,
day/night time colour and luminance, shrinkage, flexibility, linear removal, adhesion, impact
resistance, specular gloss and fungus resistance and 3 year outdoor weathering; the tests shall be
carried out by a Government Laboratory in accordance with various ASTM procedures and the
results must show that the sheeting have passed the requirements for all the above mentioned
parameters. A copy of the test reports shall be attached with the certificate.
801.4 Installation
801.4.1 The traffic signs shall be mounted on support posts, which may be of Gl pipes
conforming to IS: 1239, Rectangular Hollow Section conforming to IS :4923 or Square Hollow
Section conforming to IS:3589. Sign posts, their foundations and sign mountings shall be so
constructed as to hold these in a proper and permanent position against the normal storm wind
loads or displacement by vandalism. Normally, signs with an area up to 0.9 sqm shall be
mounted on a single post, and for greater area two or more supports shall be provided. Post-
end(s) shall be firmly fixed to the ground by means of properly designed foundation. The work
of foundation shall conform to relevant Specifications as specified.
801.4.2 All components of signs (including its back side) and supports, other than the
reflective portion and G.I. posts shall be thoroughly de scaled, cleaned, primed and painted with
two coats of epoxy/ fibre glass/ powder coated paint, Any part of support post below ground
shall be painted with protective paint.
801.4.3 The signs shall be fixed to the posts by welding in the case of steel posts and by
bolts and washers of suitable size. After the nuts have been tightened, the tails of the bolts shall
be furred over with a hammer to prevent removal.
The measurement of standard cautionary, mandatory and information signs shall be in numbers
of different types of signs supplied and fixed, while for direction and place identification signs,
these shall be measured by area in square, metres.
801.6. Rate
The Contract unit rate shall be payment in full for the cost of making the road sign, including all
materials, installing it at the site furnishing of necessary test certificates, warranty and
incidentals to complete the work in accordance with these Specifications.
Page 89 of 98
Note : The warranty as specified in clause- 801.3.9 should be in the name of NHIDCL and
it must be deposited to the PD.
802.1 General
802.1.1 Overhead signs may be used in lieu of, or as an adjunct to, kerb mounted signs
where the situation so warrants for proper information and guidance of the road users. The
following conditions may be considered while deciding about the provision of overhead signs:
Traffic volume at or near capacity
Complex interchange design
Three or more lanes in each direction
Restricted sight distance
Closely spaced interchanges
Multi.-lane exits
Large percentage of commercial vehicles
High speed traffic
804 Reflective Pavement Markers (Road Studs/Cat eyes)
804.1 General
The work cover the providing and mixing of reflective pavement marker (RPM) or
road stud, a device which is bonded to or anchored within the road surface for lane
marking and delineation for nighttime visibility. It reflects incident light in directions
close to the direction from which it came.
804.2 Material
804.2.1 Plastic body of RPM/road stud shall be moulded from ASA (Acrylic Styrene
Acrylonitrite) or HIPS (Hi-impact Polystyrene) or Acrylonitrite Butadiene
Styrene(ABS) or any other suitable material approved by the Engineer. The markers
shall support a load of 13635 kg tested in accordance with ASTM D 4280.
804.2.2 Reflective panels shall consist of number of lenses containing single or dual prismatic
cubes capable of providing total internal reflection of the light entering the lens face.
Lenses shall be molded of methyl merthcrylate conforming to ASTMD 788 or
equivalent.
804.3 Design
The slope or retro-reflecting surface shall preferably be 35+5 degree to base and the area
of each retro-reflecting surface shall not be less than 13.0 sqcm.
Each reflector or combination of reflectors on each face of the stud shall have a
Page 90 of 98
Coefficient of Luminous Intensity (C.I.L.) not less than that given in Table 800-12 or
Table 800-13 as appropriate.
Each Omni-directional stud shall have a minimum (C.I.L.) of not less than 2 mcd/lx
Note: 1) The entrance angle or 00U corresponds to the normal aspect of the reflectors when
the reflecting road stud is installed in horizontal road surface.
2) A stud that incorporates one or more corner cube reflectors shall be considered to be
included in category „A‟. A stud that incorporates one or more bi-convex reflectors
shall be considered to be included in category „B‟.
804.5 Tests
804.5.2 Under test conditions, a stud shall not be considered to fail the photometric
requirements if the measured C.I.L at any one position of measurement is less than
the values specified in Table 800-12 or 800-13 provided that
(i) the value is not less than 80% of the specified minimum, and
(ii) the average of the left and right measurements for the specific angle is greater
than the specified minimum.
The solar studs shall be made of Aluminum alloy and poly carbonate material which shall be
absolutely weather resistance and strong enough to support a load of 13635 kg tested in
accordance with ASTM D4280. Its colour may be white, red, yellow, green or blue or
combination as directed by the Engineer. Its water resistance shall meet the requirements of IP
65 in accordance with IS:12063:1987 Category 2 for protection against water ingress. The
dimentsions of solar studs shall not be less than 100 mm x 100 mm x 10 mm. It shall have super
bright LEDs so as to provide long visibility from a distance of more than 800m. Its flashing rate
shall not be less than 1 Hz. Its should be able to give the prescribed performance in the
temperature range of -400C to +550C. Its life shall be not less than 3 years.
Page 91 of 98
804.7 Fixing of Reflective Markers
804.7.1 Requirements
The enveloping profile of the head shall be smooth and the studs shall not present any sharp
edges in traffic. The reflective portions of the studs shall be free from crevice or ledges where
dirt might accumulate. All road studs shall be legibly market with the name, trademark or other
means of identification of the manufacturer. Marker height shall not exceed 20 mm. Marker
width shall not exceed 130 mm. The base of the marker shall be flat within 1.3 mm. If the
bottom of the marker is configured, the outermost faces of the configurations shall not deviate
more than 1.3 mm from a flat surface. All road studs shall be legibly marked with the name,
trade mark or other means of identification of the manufacturer.
804.7.2 Placement
The reflective marker shall be fixed to the road surface using the adhesives and the procedure
recommended by the manufacturer. No nails shall be used to affix the marker, as nails are
hazardous for the roads. Regardless of the type of adhesive used, the markers shall not be fixed
if the pavement is not surface dry and on new asphalt concrete surfacing until the surfacing has
been opened to traffic for al period of not less than 14 hours. The portions of the highway
surface, to which the marker is to be bonded by the adhesive, shall be free of dirt, curing
compound, grease, oil, moisture, loose or unsound layers, paint and any other material which
would adversely affect the bond of the adhesive. The adhesive shall be placed uniformly on the
cleaned pavement surface or on the bottom of the marker in a quantity sufficient to result in
complete coverage of the area of contact of the marker with no voids present and with a slight
excess after the marker has been lightly pressed in place. For epoxy installations, excess
adhesive around the edge of the marker, excess adhesive on the pavement and adhesive on the
exposed surfaces of the markers shall be immediately removed.
The contractor shall obtain from the manufacturer a two-year warranty for satisfactory field
performance including stipulated retro-reflectance of the reflecting panel and submit the same to
the Engineer, In addition, a two year warranty for satisfactory infield performance of the finished
road marker shall also be given by the contractor who carried out the work of fixing of reflective
road markers. In case the markers are displaced, damages, get worn out or lose their reflectivity
compared to stipulated standards, the contractor would be required to replace all such markers
within 15 days of the intimation from the Engineer at his own cost.
804.9 Rate
The contract unit rate for reflective road markers shall be payment in full compensation for
furnishing all labour, material, tools, equipment including incidental costs necessary for carrying
out the work at site conforming to the specifications complete as per approved drawings or as
directed by the Engineer.
Note : The warranty as specified in clause- 804.7.3 should be in the name of NHIDCL and
it must be deposited to the BO.
Page 92 of 98
SECTION 900 – QUALITY CONTROL FOR ROAD WORKS
Clause 901.10 For bitumen, cutback, emulsion, mild steel, cement and other
similar material where essential tests are to be carried out at the
manufacture‟s plant or at laboratories other than the site
laboratory, the cost of samples, sampling, testing, and furnishing of
the test certificates shall be borne by the Contractor. The frequency
of tests regarding bitumen, cutback and emulsion in respect of its
quality shall be as per the Table 900-4 of MOST Specification.
Page 93 of 98
INTEGRITY PACT
BETWEEN
NATI ONAL HIGHWAYS & INFRASTRUCTURE DEVELOPMENT CORPORATION LIM I TED
(NHIDCL) hereinafter referred to as "The Principal" (which expression, unless repugnant to
the context thereof, shall mean and include its legal representatives, heirs and
assigns)
AND
................................................hereinafter referred to as "The Bidder/Contractor" (which
expression, unless repugnant to the context thereof, shall mean and include its legal representatives,
heirs and assigns)
Preamble
The Principal intends to award, under laid down organizational procedures, contract(s) for (Name of
the contract) (herein after referred to as the 'Project'). The Principal necessarily requires full
compliance with all relevant laws of the land, rules, regulations, economic use of resources and of
fairness/transparency in its relations with its Bidder(s) and/or Contractor(s).
In order to achieve these goals, the Principal may appoint an Independent External Monitor (IEM), who
will monitor the tender process and the execution of the contract for compliance with the Integrity Pact
by all parties concerned, for all works covered in the Project.
Section1-CommitmentsofthePrincipal
(1) The Principal commits itself to take all measures necessary to prevent corruption and to
observe the following principles:-
a. No employee of the Principal, personally or through family members or through any other
channel, will in connection with the tender for or the execution of a contract, demand, take
a promise for or accept, for self or third person, any material or immaterial benefit, which
the person is not legally entitled to.
b. The Principal will, during the tender process treat all Contractor(s)/Bidder(s) with equity
and reason. The Principal will in particular, before and during the tender process, provide
to all Contractor(s)/Bidder(s) the same information and will not provide to any
Contractor( s )/Bidder( s), confidential/additional information through which the
Contractor(s)/Bidder(s) could obtain an advantage in relation to the tender process or the
contract execution.
c. The Principal will exclude from the process all known prejudiced persons .The Principal
shall obtain bids from only those parties who have been short-listed or pre qualified or
through a process of open advertisement/web publishing or any combination thereof.
(2) If the Principal obtains information on the conduct of any of its employees, Contractor(s)
and/or Bidder(s), which is a criminal offence under the IPC/PC Act, or if there be a substantive
suspicion in this regard, the Principal will inform the Chief Vigilance Officer and subject to its
discretion, can additionally initiate disciplinary actions.
(3) The Principal will enter in to agreements with identical conditions with all
Contractor(s)/Bidder(s) for the different Work Packages in the aforesaid Project.
( 4) The Principal will disqualify from the tender process all Contractor(s)/Bidder(s) in the range
of Rs.50 Crore and above, who do not sign this Pact or violate its provisions.
Page 94 of 98
Section 2: Commitments of the Bidder(s)/Contractor(s)
(1) The Bidder(s)/Contractor(s) commit(s) itself/themselves to take all measures necessary to
prevent corruption. He commits himself to observe the following principles during his
participation in the tender process and during the contract execution.
(a) The Bidder(s)/Contractor(s) will not, directly or through any other person or firm offer,
promise or give to any of the Principal's employees involved in the tender process or the
execution of the contract any material or other benefit which he/she is not legally entitled
to, in order to obtain in exchange any advantage, of any kind whatsoever, during the
tender process or during the execution of the contract.
(b) The Bidder(s)/ Contractor(s) will not enter with other Bidders in to any undisclosed
agreement or understanding, whether formal or in formal. This applies in particular to
prices, specifications, certifications, subsidiary contracts, submission or non-
submission of bids or any other actions to restrict competitiveness or to introduce
cartelization in the bidding process.
(c) The Bidder(s)/Contractor(s) will not use improperly, for purpose of competition or
personal gain, or pass on to others, any information or document provided by the
principal as part of the business relationship, regarding plans, technical proposals and
business details, including information contained or transmitted electronically.
(d) The Bidder(s)/Contractor(s) of foreign origin shall disclose the name and address of the
Agents/representatives in India, if any. Similarly, the Bidder(s)/Contractor(s) of
Indian Nationality shall furnish the name and address of the foreign principals, if any.
Further details as mentioned in the "Guidelines on Indian Agents of Foreign Suppliers"
shall be disclosed by the Bidder(s)/Contractor(s). Further, as mentioned in the
Guidelines all the payments made to the Indian agent/representative have to be in Indian
Rupees only. Copy of the "Guidelines on Indian Agents of Foreign Suppliers" is annexed
and marked as Annex-"A".
(e) The Bidder(s)/ Contractor(s) will, when submitting his bid, disclose any and all
payments he has made, is committed to or intends to make to agents, brokers or any
other intermediaries in connection with the award of the contract.
(2) The Bidder(s)/Contractor(s) will not instigate third persons to commit offences outlined
above or be an accessory to such offences.
Section 3: Disqualification from tender process and/or exclusion from future contracts.
(1) If the Bidder(s)/ Contractor(s),before awarding the Project or during execution has
committed a transgression by violating Section2 above or in any other form so as to put his
reliability or credibility in question, the Principal, at its sole discretion, is entitled to
disqualify the Bidder(s)/Contractor(s) from the tender process or terminate the contract, if
already awarded, for that reason, without prejudice to any other legal rights or remedies
available to the Principal under the relevant clauses of GCC/SCC of the
tender/contract.
(2) If the Contractor(s)/Bidder(s) has committed a transgression through a violation of
any of the terms under Section2 above or in any other form such as to put his reliability or
credibility into question, the Principal will also been titled to exclude such
Contractor(s)/Bidder(s) from future tenders/contract award processes. The imposition and
duration of the exclusion will be determined by the Principal, keeping in view the severity of
the transgression. The severity will be determined by the circumstances of the case, in
particular, the number of transgressions and/or the amount of the damage.
(3) Ifitisobservedafterpaymentoffinalbillbutbeforetheexpiryofvalidity of Integrity Pact that the
contractor has committed a transgression, through a violation of any of the terms under
Section 2 above or any other term(s) of this Pact, during the execution of contract, the
Page 95 of 98
Principal will be entitled to exclude the contractor from further tender/contract award
processes.
(4) The exclusion will be imposed for a minimum period of six (6) months and a maximum
period of three (3) years.
(5) If the Contractor(s)/Bidder(s) can prove that he has restored/recouped the
damage to the Principal caused by him and has installed a suitable corruption prevention
system, the Principal may, at its sole discretion, revoke or reduce the exclusion period before
the expiry of the period of such exclusion.
(5) The Principal will provide to the Monitor, sufficient information about all meetings
among the parties related to the Project, provided such meetings could have an impact on
the contractual relations between the Principal and the Contractor.
(6) As soon as the Monitor notes, or believes to note, a violation of this Pact, he will so
inform the Principal and request the Principal to discontinue and/or take corrective
action, or to take other relevant action (s). The Monitor can in this regard submit non-
binding recommendations. However, beyond this, the Monitor has no right to demand
from the parties that they act in a specific manner and/or refrain from action and/or
tolerate action.
(7) The Monitor will submit a written report to the MD, NHIDCL within 4 to 6 weeks from
the date of reference or intimation to it and, should the occasion arise, submit proposals
for corrective actions for the violation or the breaches of the provisions of the
agreement noticed by the Monitor.
(8) If the Monitor has reported to the MD, NHIDCL, of a substantiated suspicion of an
offence under relevant IPC/PC Act, and the MD, NHIDCL, has not, within the reasonable
time taken visible action to proceed against such offence or reported it to the Chief
Vigilance Officer, the Monitor may also transmit this information directly to the Chief
Vigilance Officer, NHIDCL / MD.
(9) The word 'Monitor' means Independent External Monitor and includes both singular
and plural forms.
Page 97 of 98
Section 9: Other provisions
(1) This Agreement is subject to Indian Law. Place of perf ormance and jurisdiction is the
Registered Office of the Principal, i.e. New Delhi.
(2) Changes and supplements as well as termination notices need to be made in writing.
(3) If the Bidder/Contractor is a partnership or a consortium, this Agreement must be
signed by all partners or consortium members.
(4) Should one or several provisions of this Agreement turn out to be invalid, the
remainder of this Agreement shall remain valid and binding. In such a case, the parties
will strive to come to an Agreement in accordance to their original intentions.
(5) Wherever he or his as indicated in the above sections, the same may be read as he/she or
his/her, as the case maybe.
Place- Place-
Date- Date-
Witness1:
Witness2:
Page 98 of 98