Contract Ref:
LODHA Contractor Check list for Pre-pour
PARK logo Inspection
IR No.
Name of Contractor: Date:
Pre-pour check list
Element details: _______________________________________________________________________
Sr. Contr. Contr. Lodha Lodha
Activity
NO CM QC CM QA
A Reinforment bars
1 Approved drawings are available
2 Diameter of bars are as per approved drawing
3 Spacing/no. of bars are as per approved drawings
4 Cover to rebar is as required
5 Distribution of cover blocks is as per approved details.
6 Alignment of rebar is satisfactory.
7 Lap location is staggered and as per approved details.
8 Lap length is sufficient.
All dowel bars/couplers/addl. bars near openings are placed as
9
per approved details.
10 Coupler tightening is satisfactory.
11 Ensure continuity of earthing rebar.
12 Cleanliness is satisfactory
Approved to proceed with shuttering work (for vertical
13
elements)
B Shutter
1 Approved drawings are available
2 Materials used for shuttering work are as per approved details.
3 Dimensions of shutters are satisfactory
4 Cleanliness is satisfactory
5 Gaps in shutters are sealed properly.
6 Supports and bracings are as per approved details
7 Alignment of shutters are OK
8 Verticality of shutters are OK
9 Mould release agent is applied on the shutters.
10 Top level of concrete is marked on the shutters.
Contr. Lodha
C Services
MEP MEP
1 Electrical
2 Mechanical/Elevators
3 Plumbing
4 Only fixing of embedded items for concrete structure
Contract Ref:
LODHA Contractor Check list for Pre-pour
PARK logo Inspection
IR No.
Name of Contractor: Date:
5 Facade: inspection of completed works embedded item
6 Others
7 Builders openings are as per the approved details
D Safety requirements are OK
E Approved to proceed with the concrete pour
Comments
Contractor Surveyor Lodha Surveyor Lodha MEP
Contractor Contractor LODHA LODHA
CM QC CM QA
Name
Designation
Signature
Date and time