Toilet 1 Payment 1st
Toilet 1 Payment 1st
Item Actuaal
Description Unit Aggreem Rate
No. BOQ
ent Qty
B. Sub Structure.
1. Excavation and Earth Work
Clear the site to remove the top soil to
an average depth of 20cm. The site
clearance shall include cutting and
uprooting of trees on the site (site
1.1 clearance 2m away building on every m2 45.26 45.26 12.00
Bulk excavation under the built up area
and under pavement around the building
1.2 to redused level to a depth of 30cm m3 6.68 6.68 83.00
starting from natural ground level
Excavation of soft rock for latrine pit to a
1.3 depth not exceeding 150 cm, starting m3 19.85 19.85 284.00
from reduced ground level (G.L),(P.Q)
Ditto over 150cm, but not exceeding 300
1.4 m3 19.85 19.85 422.00
cm price shall include excavation of soft
Ditto
rock over 150cm, but not exceeding 300
cm price shall include excavation of Hard
1.5 Rock m3 26.46 26.46 663.00
Ditto over 300cm price shall include
1.6 m3 11.91 11.91 773.00
excavation of soft rock
Steel reinforcement
a/ In R.C. according
elevation column to drawing
& top tie
/0190, cut, bent
beam at roof leveland placed in position. m3 1.43 - 2,912.00
The unit price shall include cutting,
4.2 bending and placing in position. -
Ø 8 mm plain bars kg 192.28 - 52.00
Ø12 mm deformed bars kg 216.85 - 51.00
Ø14 mm deformed bars kg 48.00 - 53.00
Provide, cut and fix in position sawn
zigba wood formwork or equivalent for
4.3 tie beam m2 13.92 - 188.00
Total Carried to Summary -
15x20x40 cm concrete
5. Hollow hollowBlock
Concrete block -
(Class B ) walling bedded in cement
5.1 mortar 1:3. m2
80.68 - 355.00
Ditto, but 10cm thick H.C.B. wall (Class
5.2 B) m2 16.30 - 296.00
Total Carried to Summary -
6. Roofing -
G-32 galvanized corrugated iron sheet
roofing fixed to 5x7 cm zigba purlins at
c/c 90 cm and Ø 8-10 cm eucalyptus
trusses. Each truss shall be firmly fixed
with Ø6mm plain bars to concrete tie
beam and column, all cone according to
roof truss drawing.
6.1 m2 48.75 - 435.00
11.1 -
A) dia 20 mm
ml 36.00 - 185.00
Supply and fix gate valves of approved
standards complete with unions, clastie
water proofing and hand wheels of
normal quality -
A) dia 20 mm pcs 4.00 - 338.00
11.2 Sanitary Fixtures and Fittings -
Supply and fix hand wash basin made of
white vitreous china equipped with
concealed bracket mad of grey malleable
cast iron white painted compete with
plug. Chains, Stands and traps. Size
(500x400)mm.
no 2.00 - 5,487.00
11.3 Soil Waste and Vent Pipes -
Supply and lay rigid sewage pipe (PVC)
of approved standard including the
necessary fittings such as bends, Y,T
with a slope as indicated on the drawing
with a firm bed of sand 100mm above
and under the pipe. Unit price shall
include excavation of trench, supply and
spread of granular material back filling
-
A) dia 50mm ml 10.00 - 651.00
543.12 543.12
554.44 554.27
5,637.40 5,635.98
8,376.70 8,374.59
17,542.98 17,542.98
9,204.11 9,204.11
1,363.53 1,363.53
6,189.94 6,189.94
3,052.14 3,052.14
52,464.36 52,460.67
78,862.35 78,862.35
3,084.00 3,084.00
6,553.50 6,553.50
2,220.48 2,220.48
90,720.33 90,720.33
12,964.22 12,964.22
-
714.40 714.40
4,184.88 4,184.88
-
1,664.00 1,664.00
3,536.00 3,536.00
20,306.81 20,306.81
43,370.31 43,370.31
-
-
4,164.16 -
-
9,998.56 -
11,059.35 -
2,544.00 -
2,616.96 -
30,383.03 -
-
28,641.40 -
4,824.80 -
33,466.20 -
-
21,206.25 -
1,575.00 -
2,632.50 -
2,832.00 -
5,460.00 -
5,964.00 -
8,750.00 -
48,419.75 -
-
-
20,403.00 -
5,169.00 -
25,572.00 -
-
12,440.00 -
365.00 -
4,084.08 -
32,481.00 -
49,370.08 -
-
19,179.50 -
29,920.00 -
49,099.50 -
-
- -
1,084.00 -
522.00 -
-
3,008.00 -
4,614.00 -
-
-
6,660.00 -
-
1,352.00 -
-
6,366.00 -
10,974.00 -
-
- -
6,510.00 -
1,465.00 -
33,327.00 -
TIM DIMEN QUATY DESCRIPTION TIM DIMEN
A.SUB STRUCTURE
1.EXCAVATION
385.15
a/ edges of floor slab
QUATY DESCRIPTION
18.06 m2
2. Masonry works
2.1 70 cm thick trachytic or
equivalent stone masonry
35.40 m3
26.55 m3
61.95 m3
2.2,50 cm thick stone masonry
hand wash
2.40 m3
5.10 m 3
2.4, Construct stone masonry
ramp with cement mortar
1.73 m3
a/ edges of floor slab
3.80 m2
b/ formwork for the slab
22.26 m 2
3.3,Steel reinforcement
according to drawing
Ø8 mm deformed bars
32.00 kg
Ø12 mm deformed bars
68.00 kg
Ø14 mm deformed bars
385.15 kg
-25
TOSH For Reinforcement
No of
Of sub-structure
No Location Shape ɸ(mm) Length No of multipl Member Total No length for diameter
(m) Bars es s of Bars 6.00 8.00 10.00 12.00 14.00
8.00 4.15 30.00 1.00 1.00 30.00 32.00 68.00
xx 12.00 7.25 22.00 1.00 1.00 22.00 159.50
Floor
Slab yy 14.00 5.25 30.00 1.00 1.00 30.00 157.50
Total length(m) 32.00 - 68.00 317.00
Weight per meter (kg/m) 0.22 0.39 0.62 0.89 1.21
Total weight (Kg) - 32.00 - 68.00 383.15
Project: - construction of displa one stop Shop toilet MAIN CONTRACT WITH TOT
Client: - Bishoftu city Administration SUPPLIMENTARY CONTRACT
Consultance: - Staff Engineers VAT 15%
Contractor Benti ,Mekdes and their friends Gc TOTAL SUM
AS PER THE ATTACHED STATEMENT, THE VALUE OF WORK EXECUTED AND/OR MATERIAL ON SITE
Total
We certify that the contractor is now entitiled to the sum of Birr 179,470.66(one hundered seventy nine thausand fo
Prepared By Certified By
______________ __________________
Supervisor Process Owner
irst payment
o: one
Date: January - 21-2020
Amount in Birr
TRACT WITH TOT 1,342,340.23
NTARY CONTRACT
201,351.03
1,543,691.26
OR MATERIAL ON SITE
Amount
373,102.62
55,965.39
429,068.01
21,453.40
0.00
128,720.40
150,173.80
Approved B`
______________
Construction office
463107.379
PAYMENT CERTIFICATE NO:first payment
FOR MEASUREMENT No: one
Project: - construction of displa one stop Shop toilet MAIN CONTRACT WITH TOT
Client: - Bishoftu city Administration SUPPLIMENTARY CONTRACT
Consultance: - Staff Engineers VAT 15%
Contractor Benti ,Mekdes and their friends Gc TOTAL SUM
AS PER THE ATTACHED STATEMENT, THE VALUE OF WORK EXECUTED AND/OR MATERIAL ON SITE
Total
We certify that the contractor is now entitiled to the sum of Birr 179,470.66(one hundered seventy nine thausand fo
Prepared By Certified By
______________ __________________
Supervisor Process Owner
irst payment
o: one
Date: January - 21-2020
Amount in Birr
TRACT WITH TOT 1,342,340.23
NTARY CONTRACT
201,351.03
1,543,691.26
OR MATERIAL ON SITE
Amount
373,102.62
55,965.39
429,068.01
21,453.40
0.00
128,720.40
150,173.80
Approved B`
______________
Construction office
463107.379
Project: Toilet for one step shopping
Client : Bishoftu Town municipality
Bill of quantity and spesification
SUMMARY
Item No. Description Contract Amount
previous Excuted Amount
A. SUB-STRUCTURE
1 EXCAVATION & EARTH WORKS 52,464.36 52,460.67
- 90,720.33
-
- 186,551.31
- -
35,129.59 35,129.59
28,780.20 28,780.20
46,779.75 46,779.75
29,044.94 29,044.94
- -
19,179.50 19,179.50
- -
- -
158,913.98 158,913.98
158,913.98 345,465.29
317,827.96 690,930.58
47,674.19 103,639.59
365,502.15 794,570.17
Project: Toilet for one step shopping center
Client : Bishoftu City municipality
Bill of quantity and spesification
Item
Description Unit Aggreeme
No.
nt Qty
B. Sub Structure.
1. Excavation and Earth Work
Clear the site to remove the top soil to an average
depth of 20cm. The site clearance shall include cutting
and uprooting of trees on the site (site clearance 2m
away building on every side
1.1 m2 45.26
Bulk excavation under the built up area and under
pavement around the building to redused level to a
depth of 30cm starting from natural ground level
1.2 m3 6.68
Excavation of soft rock for latrine pit to a depth not
exceeding 150 cm, starting from reduced ground level
(G.L),(P.Q)
1.3 m3 19.85
Ditto over 150cm, but not exceeding 300 cm price
shall include excavation of soft rock
1.4 m3 19.85
Ditto over 150cm, but not exceeding 300 cm price
shall include excavation of Hard Rock
1.5 m3 26.46
Ditto over 300cm price shall include excavation of soft
rock
1.6 m3 11.91
1.8 m3 93.79
25 cm thick basaltic or equivalent stone hard core, well
rolled, consolidated and blinded with crushed stone.
1.9 m2 18.06
Total Carried to Summary
2. Masonry Work
An average of 70 cm thick trachytic or equivalent
stone masonry foundation wall below NGL, bedded in
cement mortar 1:3 for pit
2.1 m3 61.95
50 cm thick hard tracytic stone masonry wall for hand
wash
2.2 m3 2.40
50cm above NGL, bedded and jointed in cement
mortar 1:3 and external side roughly dressed and left
for pointing.
2.3 m3 5.10
Construct stone masonry ramp with cement mortar of
1:3 and slope 10% . price includes 5cm cement screed
on its surface and pointing the sides of masonry.
2.4 m3 1.73
Total Carried to Summary
3. Concrete Work
20 cm thick concrete ground floor slab, concrete
quality C-25, 360 kg cement/ m3 of concrete, evenly
spread and leveled.
3.1 m3 4.45
Provide, cut and fix in position sawn zigba formwork or
3.2 equivalent, to
a/ edges of floor slab, width not exceeding 20 cm.
m2 3.80
b/ formwork for the slab ( soffit)
m2 22.26
Steel reinforcement according to drawing/0190, cut
bent and placed in position. Unit price shall include
cutting, bending and placing in position and tying wire.
3.3
Ø 8 mm deformed bars
kg 32.00
Ø12 mm deformed bars kg 68.00
Ø14 mm deformed bars kg 383.15
Total Carried to Summary
B. Super Structure.
4. Concrete work
Reinforced concrete class C-25, filled into formwork
4.1 and vibrated around reinforcement rods.
a/ In R.C. elevation column & top tie beam at roof level m3 1.43
b/ in R.C ratto sitting slab above roof level atboth side m3 1.00
8.3 m3 3.57
Supply and lay 10cm thick storm water cast in-situ C-
25 rectangular concrete ditch of W=30cmx D=40cm
internal dimension with a minimum slope of 2% or
natural ground slope which ever is greater on and
including a firm bed of concrete. Price shall include
20cm thick stone masonry shoulder, 6mm rebar c/c 35
mesh , earth work and other necessary works as
shown on the detail drawing
8.4 ml 27.00
Total Carried to Summary:
9. Plastering and painting
Apply three coats of cement mortar plaster 1:3 to all
internal walls, External beams & columns,
9.1 m2 107.75
Apply quartz paint to external wall price includes
9.2 Primary cots . m2 110.00
Total Carried to Summary:
10. Eletrical Installation
10.1 Supply and install 10 Amp breaker with box pcs 1.00
11.1
A) dia 20 mm ml 36.00
Supply and fix gate valves of approved standards
complete with unions, clastie water proofing and hand
wheels of normal quality
A) dia 20 mm pcs 4.00
11.2 Sanitary Fixtures and Fittings
Supply and fix hand wash basin made of white vitreous
china equipped with concealed bracket mad of grey
malleable cast iron white painted compete with plug.
Chains, Stands and traps. Size (500x400)mm.
pcs 2.00
supply and fix Rotto water tanker that have 1000litters
cappacity no 2.00
11.3 Soil Waste and Vent Pipes
Supply and lay rigid sewage pipe (PVC) of approved
standard including the necessary fittings such as
bends, Y,T with a slope as indicated on the drawing
with a firm bed of sand 100mm above and under the
pipe. Unit price shall include excavation of trench,
supply and spread of granular material back filling
- - -
- -
32.00 - 32.00 52.00 1,664.00 1,664.00
68.00 - 68.00 52.00 3,536.00 3,536.00
383.15 - 383.15 53.00 20,306.81 20,306.81
43,370.31 43,370.31
-
-
-
1.70 1.70 1,723.00 5,169.00 -
25,572.00 -
-
- - - 622.00 12,440.00 -
- - - 73.00 365.00 -
- - - 1,144.00 4,084.08 -
- - - 1,203.00 32,481.00 -
- 49,370.08 -
-
- - - 272.00 29,920.00 -
- - - 49,099.50 -
- - - -
- - - - -
- - - 271.00 1,084.00 -
- - 261.00 522.00 -
- - - -
- - - 752.00 3,008.00 -
- - - 4,614.00 -
- - - -
- - - -
- - - 185.00 6,660.00 -
- - - -
- - - 338.00 1,352.00 -
- - - -
- - - 3,183.00 6,366.00 -
- - - 5,487.00 10,974.00 -
- - - -
- - - - -
- - - 651.00 6,510.00 -
- - - 293.00 1,465.00 -
- - - 33,327.00 -
currrent
Up to date
Excuted
Amount (Birr)
amount (birr)
- 543.12
- 554.27
- 5,635.98
- 8,374.59
- 17,542.98
- 9,204.11
- 1,363.53
- 6,189.94
- 3,052.14
- 52,460.67
-
- 78,862.35
- 3,084.00
- 6,553.50
- 2,220.48
- 90,720.33
-
- 12,964.22
- 714.40
- 4,184.88
-
- 1,664.00
- 3,536.00
- 20,306.81
43,370.31
-
-
6,115.20 6,115.20
2,795.52 2,795.52
9,998.56 9,998.56
11,059.35 11,059.35
2,544.00 2,544.00
2,616.96 2,616.96
35,129.59
-
23,955.40 23,955.40
4,824.80 4,824.80
28,780.20
21,206.25 21,206.25
1,575.00 1,575.00
2,632.50 2,632.50
2,592.00 2,592.00
3,990.00 3,990.00
5,964.00 5,964.00
8,820.00 8,820.00
46,779.75 46,779.75
-
26,115.84 26,115.84
-
2,929.10 2,929.10
29,044.94
-
- -
- -
- -
- -
-
-
19,179.50 19,179.50
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
TIM DIMEN QUATY DESCRIPTION
A.SUB STRUCTURE
4. Concrete Work
4.1,Reinforced concrete class C-
25In R.C. elevation column & top
a/
4 2.8 tie beam at roof level
0.2
0.2
0.2 0.76 m3 top tie beam
2.10 m 3
b/ In R.C. Rattoo sitting slab
&columnabove roof level at both
2 3 side
0.4
0.4
0.96 4.2, Steel reinforcement
according
192..28 Ø 8 mm deformed bars
192.28 kg
216.85 Ø12 mm deformed bars
216.85 kg
6 5.3
0.2 6.36
9 4.2
0.2 7.56
13.92 m2
5. Hollow Concrete Block
5.1, 20x20x40 cm concrete hollow
2 5.2 block
2 20.80
5 2.26
2 22.60
3.3
3.3
3.2 10.56
4 1
0.86 3.44
2 4.2
1.2 10.08
67.48 m2
5.2, Ditto, but 10cm thick H.C.B.
wall (Class B )
5 1.63
16.30 m2
TIM DIMEN QUATY
2 6.5
3.5 45.50
1 6.5
0.5 3.25
48.75
7 5
35.00
9 7.5 67.50
9 6 54.00
2 9.5 19.00
1 4.2
5
21.00
6 4.2 25.20
8 0.72
2 11.52
4 0.5
0.85
1.70
2 8.5
2 34.00
2 3.3
3.2 10.56
12 2.26
2 54.24
4 1
0.86
6 2.8
0.25 4.20
2 9.5
0.25 4.75
107.75
DESCRIPTION
6. Roofing
6.1, G-32roof cover
coping
m2
a/ Ø10-12 cm eucalyptus Higher/upper
member
ml
b/ Ø8-10 cm eucalyptus bracing & internal
ml
c/Ø 5x7 cm zigba purlins.
ml
6.2, Supply and fix 25 x 20cm facial board
ml
6.3,chipwood ceiling fixed to 4x5cm
m2
6.4, supply &fix 0.8mmthick finely cis sofit
price include 4*5cm zigba wood
ml
7. Metal work
7.1,All metal doors and windows shall be
fabricated from locally manufactured 38mm
LTZ frame
Type D 6 /D7,size 72 x 207cm
internal wall
partion wall
column
beam
m2
1951.04
0.112
0.672
0.4*0.4*2.8 0.448
0.448 0.896
0.896 0.112
0.448 0.448
0.112 1.344
0.672 0.12
0.72
TOSH For Reinforcement
No of
Of sub-structure
No LocationShape ɸ(mm) Length No of multipl Member Total No length for diameter
(m) Bars es s of Bars 6.00 8.00 10.00
10.00 4.15 22.00 1.00 1.00 22.00 91.30
Floor xx 14.00 7.25 22.00 1.00 1.00 22.00
Slab yy 14.00 5.25 30.00 1.00 1.00 30.00
Total length(m) - 91.30
Weight per meter (kg/m) 0.22 0.39 0.62
Total weight (Kg) - - 56.30
159.50
157.50
- 317.00
0.89 1.21
- 383.15
re
h for diameter
12.00 14.00
72.00
244.20
39.71
244.20 -
0.89 1.21
216.85 48.00
PAYMENT CERTIFICATE NO:Final Retention 2.5%
Project: - construction of display shop one stop Shop toilet MAIN CONTRACT WITH TOT
Client: - Bishoftu city Administration SUPPLIMENTARY CONTRAC
Consultance: - Staff Engineers VAT 15%
Contractor Benti ,Mekdes and their friends Gc TOTAL SUM
AS PER THE ATTACHED STATEMENT, THE VALUE OF WORK EXECUTED AND/OR MATERIAL ON S
Total 1,003,220.08
We certify that the contractor is now entitiled to the sum of Birr38,587.56(thirty eight thousand and five hundred
Prepared By Certified By
______________ __________________
Supervisor Process Owner
Final Retention 2.5%
Date: oct0ber12-2021
Amount in Birr
MAIN CONTRACT WITH TOT 1,342,340.23
SUPPLIMENTARY CONTRACT
201,351.03
TOTAL SUM 1,543,691.26
Amount
work measure 1,342,176.18
201,326.43
1,543,502.61
Retention2.5% 38,587.57
previous pay 1,003,220.08
epay (30%) 463,107.40
Total deductables 1,504,915.05
Approved By `
______________
Process Owner Construction office