PROJECT:CONSTRUCTION OF MSALATO INTERNATIONAL AIRPORT - PHASE ONE, LOT 1; PACKAGE 1: INFRASTRUCTURE
Submitted Date:25/7/2025
DATE OF TIME OF
S/N LOCATION CHAINAGE WORK DESCRIPTION REMARK
INSPECTION INSPECTION
1 temporary access roads Inspection of weekly dusting suppression 26/7/2025 8:00AM 30783
2 runway No.2-26,2-27 Casting concrete of base cane for runway edge light 27/7/2025 8:00AM 30784
3 WW2 (Sewerage Manhole) CH. KM 7+469.72-8+710.55(W2-188~W3-9) Casting concrete of blinding (32Nos) 27/7/2025 8:00AM 30785
4 access road 1 CH. KM 0+360-0+480 LHS offset 1m to RHS offset 3.5m Inspection and testing of Wearing course AC20 27/7/2025 8:00AM 30786
5 access road 1 CH. KM 0+480-1+250 RHS offset 1-5.5m Inspection and testing of Wearing course AC20 27/7/2025 8:00AM 30787
6 access road 1 CH. KM 1+250-1+425 LHS offset 1-5.5m Inspection and testing of Wearing course AC20 27/7/2025 8:00AM 30788
7 access road 1 CH. KM 1+440-1+500 RHS offset 1-5.5m Inspection and testing of Wearing course AC20 27/7/2025 8:00AM 30789
8 WW2 (Sewerage Manhole) CH. KM 7+109.72-7+269.72(W2-179~183) Inspection of formwork and reinforcement of TYPE "A" Sewerage Manhole (A1) (5Nos) 27/7/2025 8:00AM 30790
9 WW2 (Sewerage Manhole) CH. KM 7+109.72-7+269.72(W2-179~183) Casting concrete of base slab and wall (A1)(5Nos) 27/7/2025 8:30AM 30791
10 AGL manhole (RW46-51) CH. KM 1+635.52-1+935.52 Curing of AGL Manhole (6Nos) 27/7/2025 8:00AM 30792
11 AGL manhole (RW1-22) CH. KM 0+000-0+332.72 Excavation of AGL Manhole (20Nos) 27/7/2025 8:00AM 30793
12 AGL manhole (RW1-22) CH. KM 0+000-0+332.72 Inspection and FDT of AGL Manhole foundation (20Nos) 27/7/2025 8:30AM 30794
13 AGL manhole (RW1-22) CH. KM 0+000-0+332.72 Checking level of AGL Manhole foundation (20Nos) 27/7/2025 9:00AM 30795
14 AGL manhole (RW13-22) CH. KM 0+182.50-0+332.72 Construction formwork of AGL Manhole (10Nos) 28/7/2025 8:00AM 30796
15 AGL manhole (RW13-22) CH. KM 0+182.50-0+332.72 Checking level of AGL Manhole formwork top level (10Nos) 28/7/2025 8:30AM 30797
16 AGL manhole (RW13-22) CH. KM 0+182.50-0+332.72 Casting Concrete of AGL Manhole (10Nos) 28/7/2025 9:00AM 30798
17 WW2 (Sewerage Manhole) CH. KM 7+309.72-7+469.72(W2-184~188) Inspection of formwork and reinforcement of TYPE "A" Sewerage Manhole (A1) (5Nos) 27/7/2025 8:00AM 30799
18 WW2 (Sewerage Manhole) CH. KM 7+309.72-7+469.72(W2-184~188) Casting concrete of base slab and wall (A1)(5Nos) 27/7/2025 8:30AM 30800
19 WW2 (Sewerage Manhole) CH. KM 7+509.72-7+669.72(W2-189~193) Inspection of formwork and reinforcement of TYPE "A" Sewerage Manhole (A1) (5Nos) 28/7/2025 8:00AM 30801
20 WW2 (Sewerage Manhole) CH. KM 7+509.72-7+669.72(W2-189~193) Casting concrete of base slab and wall (A1)(5Nos) 28/7/2025 8:30AM 30802
21 ULV pipeline MIA-ZA-MH08~MIA-ZA-MH20 Excavation of ULV pipeline trench 27/7/2025 8:00AM 30803
22 Contractor's camp Precasting 1Nos 600mm reinforcement Concrete pipe (C30) 27/7/2025 8:00AM 30804
23 Contractor's camp Precasting BN kerbstones (125Nos) 27/7/2025 8:30AM 30805
24 Contractor's camp Precasting 1Nos 600mm reinforcement Concrete pipe (C30) 28/7/2025 8:00AM 30806
25 Contractor's camp Precasting BN kerbstones (125Nos) 28/7/2025 8:30AM 30807
26 external perimeter road 1 CH. KM 4+566.91(box culvert) Setting out of box culvert 27/7/2025 8:00AM 30808
27 external perimeter road 1 CH. KM 4+566.91(box culvert) Construction of excavation for box culvert 27/7/2025 8:30AM 30809
28 ATC inner road 1-4 Inspection and FDT of 1st layer filling 27/7/2025 8:00AM 30810
29 Green area part 13 Construction of formation level 27/7/2025 8:00AM 30811
30 Power Station inner road 1 CH. KM 0+000-0+198 Construction of 3rd layer filling 27/7/2025 8:00AM 30812
31 Power Station inner road 2 CH. KM 0+000-0+092.40 Construction of 3rd layer filling 27/7/2025 8:00AM 30813
32 passenger terminal apron ditch (R.C.D) CH. KM 0+196.84-0+220.16 Construction formwork and Fixing Reinforcement of base slab 27/7/2025 8:00AM 30814
33 passenger terminal apron ditch (R.C.D) CH. KM 0+196.84-0+220.16 Inspection of formwork and reinforcement of ditch wall and base slab 27/7/2025 8:30AM 30815
34 passenger terminal apron ditch (R.C.D) CH. KM 0+196.84-0+220.16 Checking level of formwork for ditch wall and base slab 27/7/2025 9:00AM 30816
35 passenger terminal apron ditch (R.C.D) CH. KM 0+196.84-0+220.16 Casting concrete of ditch wall and base slab 27/7/2025 9:30AM 30817
36 passenger terminal apron ditch (R.C.D) CH. KM 0+450-0+500 Construction of 1st layer backfilling on both sides 27/7/2025 8:00AM 30818
37 passenger terminal apron ditch (R.C.D) CH. KM 0+450-0+500 Inspection and FDT of 1st layer backfilling on both sides 27/7/2025 8:30AM 30819
38 passenger terminal apron ditch (R.C.D) CH. KM 0+450-0+500 Construction of 2nd layer backfilling on both sides 27/7/2025 9:00AM 30820
39 passenger terminal apron ditch (R.C.D) CH. KM 0+450-0+500 Inspection and FDT of 2nd layer backfilling on both sides 27/7/2025 9:30AM 30821
40 passenger terminal apron ditch (R.C.D) CH. KM 0+450-0+500 Construction of 3rd layer backfilling on both sides 27/7/2025 10:00AM 30822
41 passenger terminal apron ditch (R.C.D) CH. KM 0+450-0+500 Inspection and FDT of 3rd layer backfilling on both sides 27/7/2025 10:30AM 30823
42 passenger terminal apron ditch (R.C.D) CH. KM 0+450-0+500 Construction of 4th layer backfilling on both sides 27/7/2025 2:00PM 30824
43 passenger terminal apron ditch (R.C.D) CH. KM 0+450-0+500 Inspection and FDT of 4th layer backfilling on both sides 27/7/2025 2:30PM 30825
44 passenger terminal apron ditch (R.C.D) CH. KM 0+450-0+500 Construction of 5th layer backfilling on both sides 27/7/2025 3:00PM 30826
45 passenger terminal apron ditch (R.C.D) CH. KM 0+450-0+500 Inspection and FDT of 5th layer backfilling on both sides 27/7/2025 3:30PM 30827
46 perimeter security road LHS CH19-S1 CH. KM 0+060-0+110 Inspection of completed Stone Pitching before grouting 27/7/2025 8:00AM 30828
47 perimeter security road LHS CH19-S1 CH. KM 0+060-0+110 Checking level after Stone Pitching 27/7/2025 8:30AM 30829
48 perimeter security road LHS CH19-S1 CH. KM 0+470-0+590 Inspection of completed Stone Pitching before grouting 27/7/2025 8:00AM 30830
49 perimeter security road LHS CH19-S1 CH. KM 0+470-0+590 Checking level after Stone Pitching 27/7/2025 8:30AM 30831
50 perimeter security road LHS CH19-S1 CH. KM 0+060-0+110 Grouting for ditch 27/7/2025 9:00AM 30832
51 perimeter security road LHS CH19-S1 CH. KM 0+470-0+590 Grouting for ditch 27/7/2025 9:00AM 30833
52 WW2 (Sewerage Manhole) CH. KM 6+829.72-7+429.72(W2-173~187) Casting concrete of blinding (15Nos) 27/7/2025 8:00AM 30834
53 WW2 CH. KM 0+000-0+360 Laying 250mm UPVC pipe for sewerage pipeline 28/7/2025 8:00AM 30835
54 WW2 CH. KM 0+000-0+360 Checking level of pipe top for sewerage pipeline 28/7/2025 8:30AM 30836
55 WW2 CH. KM 0+000-0+360 Construction of 1st layer backfilling for sewerage pipeline 28/7/2025 9:00AM 30837
56 Fence AF-D CH. KM 5+700-5+950 Foundation excavation of post 27/7/2025 8:00AM 30838
57 Fence AF-D CH. KM 5+700-5+950 Inspection of completed foundation excavation of pos 27/7/2025 8:30AM 30839
58 Fence AF-D CH. KM 5+700-5+950 Casting concrete and intalling post 27/7/2025 9:00AM 30840
59 Fence AF-D CH. KM 6+520-7+070 Foundation excavation of post 27/7/2025 8:00AM 30841
60 Fence AF-D CH. KM 6+520-7+070 Inspection of completed foundation excavation of pos 27/7/2025 8:30AM 30842
61 Fence AF-D CH. KM 6+520-7+070 Casting concrete and intalling post 27/7/2025 9:00AM 30843
62 external perimeter road 1 LHS CH7-S1 CH. KM 0+000-0+340 Filling the expansion joints with bitumen sand 27/7/2025 8:00AM 30844
63 service access road 3 LHS CH8-S1 CH. KM 0+000-0+320.5 Filling the expansion joints with bitumen sand 28/7/2025 8:00AM 30845
64 service access road 3 RHS CH8-S2 CH. KM 0+000-0+320.5 Filling the expansion joints with bitumen sand 28/7/2025 8:00AM 30846
65 service access road 2 LHS CH8-S4 CH. KM 0+000-0+208.94 Filling the expansion joints with bitumen sand 28/7/2025 8:00AM 30847
66 service access road 3 RHS CH8-S3 CH. KM 0+000-0+204.86 Filling the expansion joints with bitumen sand 28/7/2025 8:00AM 30848
67 exit lane 4 CH. KM 0+000-0+235 LHS carriageway edge to shoulder edge Construction of Wearing course AC20 27/7/2025 8:00AM 30849
68 exit lane 3 CH. KM 0+000-0+107 LHS carriageway edge to shoulder edge Construction of Wearing course AC20 27/7/2025 8:00AM 30850
69 WW2 CH. KM 6+500-8+700 Establishment of benchmark (jointly ) 27/7/2025 8:00AM 30851
70 external perimeter road 1 CH. KM 2+700-2+850 RHS&LHS Construction of roadbed 27/7/2025 8:00AM 30852
71 external perimeter road 1 CH. KM 2+850-3+760 RHS&LHS Joint identification and assessment of potential termite spots 27/7/2025 8:00AM 30853
72 external perimeter road 1 CH. KM 2+850-3+760 RHS&LHS Excavation of potential termite mounds 27/7/2025 8:30AM 30854
73 external perimeter road 1 CH. KM 2+850-3+760 RHS&LHS Disposal of excavated material of termite mounds 27/7/2025 9:00AM 30855
74 external perimeter road 1 CH. KM 2+850-3+760 RHS&LHS Jointly taking measurement of excavated termite mounds 27/7/2025 9:30AM 30856
75 external perimeter road 1 CH. KM 4+540-5+313 RHS&LHS Joint identification and assessment of potential termite spots 27/7/2025 8:00AM 30857
76 external perimeter road 1 CH. KM 4+540-5+313 RHS&LHS Excavation of potential termite mounds 27/7/2025 8:30AM 30858
77 external perimeter road 1 CH. KM 4+540-5+313 RHS&LHS Disposal of excavated material of termite mounds 27/7/2025 9:00AM 30859
78 external perimeter road 1 CH. KM 4+540-5+313 RHS&LHS Jointly taking measurement of excavated termite mounds 27/7/2025 9:30AM 30860
79 external perimeter road 1 CH. KM 2+300-2+700 RHS&LHS Inspection and FDT of formation level 27/7/2025 8:00AM 30861
80 external perimeter road 1 CH. KM 2+300-2+700 RHS&LHS Checking level of formation level 27/7/2025 8:30AM 30862
81 perimeter security road CH. KM 13+660-14+140 RHS&LHS Construction of 3rd layer filling after removing unsuitable soil 27/7/2025 8:00AM 30863