7 26

The document outlines the inspection and construction activities for the first phase of the Msalato International Airport project, detailing various tasks scheduled from July 26 to July 28, 2025. Key activities include concrete casting, excavation, and inspections across multiple locations, including runways, access roads, and sewerage manholes. Each entry specifies the chainage, work description, and inspection times, highlighting the project's progress and compliance with construction standards.

Uploaded by

Mesafint lisanu
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
41 views2 pages

7 26

The document outlines the inspection and construction activities for the first phase of the Msalato International Airport project, detailing various tasks scheduled from July 26 to July 28, 2025. Key activities include concrete casting, excavation, and inspections across multiple locations, including runways, access roads, and sewerage manholes. Each entry specifies the chainage, work description, and inspection times, highlighting the project's progress and compliance with construction standards.

Uploaded by

Mesafint lisanu
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd

PROJECT:CONSTRUCTION OF MSALATO INTERNATIONAL AIRPORT - PHASE ONE, LOT 1; PACKAGE 1: INFRASTRUCTURE

Submitted Date:25/7/2025
DATE OF TIME OF
S/N LOCATION CHAINAGE WORK DESCRIPTION REMARK
INSPECTION INSPECTION
1 temporary access roads Inspection of weekly dusting suppression 26/7/2025 8:00AM 30783

2 runway No.2-26,2-27 Casting concrete of base cane for runway edge light 27/7/2025 8:00AM 30784

3 WW2 (Sewerage Manhole) CH. KM 7+469.72-8+710.55(W2-188~W3-9) Casting concrete of blinding (32Nos) 27/7/2025 8:00AM 30785

4 access road 1 CH. KM 0+360-0+480 LHS offset 1m to RHS offset 3.5m Inspection and testing of Wearing course AC20 27/7/2025 8:00AM 30786

5 access road 1 CH. KM 0+480-1+250 RHS offset 1-5.5m Inspection and testing of Wearing course AC20 27/7/2025 8:00AM 30787

6 access road 1 CH. KM 1+250-1+425 LHS offset 1-5.5m Inspection and testing of Wearing course AC20 27/7/2025 8:00AM 30788

7 access road 1 CH. KM 1+440-1+500 RHS offset 1-5.5m Inspection and testing of Wearing course AC20 27/7/2025 8:00AM 30789

8 WW2 (Sewerage Manhole) CH. KM 7+109.72-7+269.72(W2-179~183) Inspection of formwork and reinforcement of TYPE "A" Sewerage Manhole (A1) (5Nos) 27/7/2025 8:00AM 30790

9 WW2 (Sewerage Manhole) CH. KM 7+109.72-7+269.72(W2-179~183) Casting concrete of base slab and wall (A1)(5Nos) 27/7/2025 8:30AM 30791

10 AGL manhole (RW46-51) CH. KM 1+635.52-1+935.52 Curing of AGL Manhole (6Nos) 27/7/2025 8:00AM 30792

11 AGL manhole (RW1-22) CH. KM 0+000-0+332.72 Excavation of AGL Manhole (20Nos) 27/7/2025 8:00AM 30793

12 AGL manhole (RW1-22) CH. KM 0+000-0+332.72 Inspection and FDT of AGL Manhole foundation (20Nos) 27/7/2025 8:30AM 30794

13 AGL manhole (RW1-22) CH. KM 0+000-0+332.72 Checking level of AGL Manhole foundation (20Nos) 27/7/2025 9:00AM 30795

14 AGL manhole (RW13-22) CH. KM 0+182.50-0+332.72 Construction formwork of AGL Manhole (10Nos) 28/7/2025 8:00AM 30796

15 AGL manhole (RW13-22) CH. KM 0+182.50-0+332.72 Checking level of AGL Manhole formwork top level (10Nos) 28/7/2025 8:30AM 30797

16 AGL manhole (RW13-22) CH. KM 0+182.50-0+332.72 Casting Concrete of AGL Manhole (10Nos) 28/7/2025 9:00AM 30798

17 WW2 (Sewerage Manhole) CH. KM 7+309.72-7+469.72(W2-184~188) Inspection of formwork and reinforcement of TYPE "A" Sewerage Manhole (A1) (5Nos) 27/7/2025 8:00AM 30799

18 WW2 (Sewerage Manhole) CH. KM 7+309.72-7+469.72(W2-184~188) Casting concrete of base slab and wall (A1)(5Nos) 27/7/2025 8:30AM 30800

19 WW2 (Sewerage Manhole) CH. KM 7+509.72-7+669.72(W2-189~193) Inspection of formwork and reinforcement of TYPE "A" Sewerage Manhole (A1) (5Nos) 28/7/2025 8:00AM 30801

20 WW2 (Sewerage Manhole) CH. KM 7+509.72-7+669.72(W2-189~193) Casting concrete of base slab and wall (A1)(5Nos) 28/7/2025 8:30AM 30802

21 ULV pipeline MIA-ZA-MH08~MIA-ZA-MH20 Excavation of ULV pipeline trench 27/7/2025 8:00AM 30803

22 Contractor's camp Precasting 1Nos 600mm reinforcement Concrete pipe (C30) 27/7/2025 8:00AM 30804

23 Contractor's camp Precasting BN kerbstones (125Nos) 27/7/2025 8:30AM 30805

24 Contractor's camp Precasting 1Nos 600mm reinforcement Concrete pipe (C30) 28/7/2025 8:00AM 30806

25 Contractor's camp Precasting BN kerbstones (125Nos) 28/7/2025 8:30AM 30807

26 external perimeter road 1 CH. KM 4+566.91(box culvert) Setting out of box culvert 27/7/2025 8:00AM 30808

27 external perimeter road 1 CH. KM 4+566.91(box culvert) Construction of excavation for box culvert 27/7/2025 8:30AM 30809

28 ATC inner road 1-4 Inspection and FDT of 1st layer filling 27/7/2025 8:00AM 30810

29 Green area part 13 Construction of formation level 27/7/2025 8:00AM 30811

30 Power Station inner road 1 CH. KM 0+000-0+198 Construction of 3rd layer filling 27/7/2025 8:00AM 30812

31 Power Station inner road 2 CH. KM 0+000-0+092.40 Construction of 3rd layer filling 27/7/2025 8:00AM 30813

32 passenger terminal apron ditch (R.C.D) CH. KM 0+196.84-0+220.16 Construction formwork and Fixing Reinforcement of base slab 27/7/2025 8:00AM 30814

33 passenger terminal apron ditch (R.C.D) CH. KM 0+196.84-0+220.16 Inspection of formwork and reinforcement of ditch wall and base slab 27/7/2025 8:30AM 30815

34 passenger terminal apron ditch (R.C.D) CH. KM 0+196.84-0+220.16 Checking level of formwork for ditch wall and base slab 27/7/2025 9:00AM 30816

35 passenger terminal apron ditch (R.C.D) CH. KM 0+196.84-0+220.16 Casting concrete of ditch wall and base slab 27/7/2025 9:30AM 30817

36 passenger terminal apron ditch (R.C.D) CH. KM 0+450-0+500 Construction of 1st layer backfilling on both sides 27/7/2025 8:00AM 30818

37 passenger terminal apron ditch (R.C.D) CH. KM 0+450-0+500 Inspection and FDT of 1st layer backfilling on both sides 27/7/2025 8:30AM 30819

38 passenger terminal apron ditch (R.C.D) CH. KM 0+450-0+500 Construction of 2nd layer backfilling on both sides 27/7/2025 9:00AM 30820

39 passenger terminal apron ditch (R.C.D) CH. KM 0+450-0+500 Inspection and FDT of 2nd layer backfilling on both sides 27/7/2025 9:30AM 30821

40 passenger terminal apron ditch (R.C.D) CH. KM 0+450-0+500 Construction of 3rd layer backfilling on both sides 27/7/2025 10:00AM 30822

41 passenger terminal apron ditch (R.C.D) CH. KM 0+450-0+500 Inspection and FDT of 3rd layer backfilling on both sides 27/7/2025 10:30AM 30823

42 passenger terminal apron ditch (R.C.D) CH. KM 0+450-0+500 Construction of 4th layer backfilling on both sides 27/7/2025 2:00PM 30824

43 passenger terminal apron ditch (R.C.D) CH. KM 0+450-0+500 Inspection and FDT of 4th layer backfilling on both sides 27/7/2025 2:30PM 30825

44 passenger terminal apron ditch (R.C.D) CH. KM 0+450-0+500 Construction of 5th layer backfilling on both sides 27/7/2025 3:00PM 30826

45 passenger terminal apron ditch (R.C.D) CH. KM 0+450-0+500 Inspection and FDT of 5th layer backfilling on both sides 27/7/2025 3:30PM 30827

46 perimeter security road LHS CH19-S1 CH. KM 0+060-0+110 Inspection of completed Stone Pitching before grouting 27/7/2025 8:00AM 30828

47 perimeter security road LHS CH19-S1 CH. KM 0+060-0+110 Checking level after Stone Pitching 27/7/2025 8:30AM 30829

48 perimeter security road LHS CH19-S1 CH. KM 0+470-0+590 Inspection of completed Stone Pitching before grouting 27/7/2025 8:00AM 30830

49 perimeter security road LHS CH19-S1 CH. KM 0+470-0+590 Checking level after Stone Pitching 27/7/2025 8:30AM 30831

50 perimeter security road LHS CH19-S1 CH. KM 0+060-0+110 Grouting for ditch 27/7/2025 9:00AM 30832
51 perimeter security road LHS CH19-S1 CH. KM 0+470-0+590 Grouting for ditch 27/7/2025 9:00AM 30833

52 WW2 (Sewerage Manhole) CH. KM 6+829.72-7+429.72(W2-173~187) Casting concrete of blinding (15Nos) 27/7/2025 8:00AM 30834

53 WW2 CH. KM 0+000-0+360 Laying 250mm UPVC pipe for sewerage pipeline 28/7/2025 8:00AM 30835

54 WW2 CH. KM 0+000-0+360 Checking level of pipe top for sewerage pipeline 28/7/2025 8:30AM 30836

55 WW2 CH. KM 0+000-0+360 Construction of 1st layer backfilling for sewerage pipeline 28/7/2025 9:00AM 30837

56 Fence AF-D CH. KM 5+700-5+950 Foundation excavation of post 27/7/2025 8:00AM 30838

57 Fence AF-D CH. KM 5+700-5+950 Inspection of completed foundation excavation of pos 27/7/2025 8:30AM 30839

58 Fence AF-D CH. KM 5+700-5+950 Casting concrete and intalling post 27/7/2025 9:00AM 30840

59 Fence AF-D CH. KM 6+520-7+070 Foundation excavation of post 27/7/2025 8:00AM 30841

60 Fence AF-D CH. KM 6+520-7+070 Inspection of completed foundation excavation of pos 27/7/2025 8:30AM 30842

61 Fence AF-D CH. KM 6+520-7+070 Casting concrete and intalling post 27/7/2025 9:00AM 30843

62 external perimeter road 1 LHS CH7-S1 CH. KM 0+000-0+340 Filling the expansion joints with bitumen sand 27/7/2025 8:00AM 30844

63 service access road 3 LHS CH8-S1 CH. KM 0+000-0+320.5 Filling the expansion joints with bitumen sand 28/7/2025 8:00AM 30845

64 service access road 3 RHS CH8-S2 CH. KM 0+000-0+320.5 Filling the expansion joints with bitumen sand 28/7/2025 8:00AM 30846

65 service access road 2 LHS CH8-S4 CH. KM 0+000-0+208.94 Filling the expansion joints with bitumen sand 28/7/2025 8:00AM 30847

66 service access road 3 RHS CH8-S3 CH. KM 0+000-0+204.86 Filling the expansion joints with bitumen sand 28/7/2025 8:00AM 30848

67 exit lane 4 CH. KM 0+000-0+235 LHS carriageway edge to shoulder edge Construction of Wearing course AC20 27/7/2025 8:00AM 30849

68 exit lane 3 CH. KM 0+000-0+107 LHS carriageway edge to shoulder edge Construction of Wearing course AC20 27/7/2025 8:00AM 30850

69 WW2 CH. KM 6+500-8+700 Establishment of benchmark (jointly ) 27/7/2025 8:00AM 30851

70 external perimeter road 1 CH. KM 2+700-2+850 RHS&LHS Construction of roadbed 27/7/2025 8:00AM 30852

71 external perimeter road 1 CH. KM 2+850-3+760 RHS&LHS Joint identification and assessment of potential termite spots 27/7/2025 8:00AM 30853

72 external perimeter road 1 CH. KM 2+850-3+760 RHS&LHS Excavation of potential termite mounds 27/7/2025 8:30AM 30854

73 external perimeter road 1 CH. KM 2+850-3+760 RHS&LHS Disposal of excavated material of termite mounds 27/7/2025 9:00AM 30855

74 external perimeter road 1 CH. KM 2+850-3+760 RHS&LHS Jointly taking measurement of excavated termite mounds 27/7/2025 9:30AM 30856

75 external perimeter road 1 CH. KM 4+540-5+313 RHS&LHS Joint identification and assessment of potential termite spots 27/7/2025 8:00AM 30857

76 external perimeter road 1 CH. KM 4+540-5+313 RHS&LHS Excavation of potential termite mounds 27/7/2025 8:30AM 30858

77 external perimeter road 1 CH. KM 4+540-5+313 RHS&LHS Disposal of excavated material of termite mounds 27/7/2025 9:00AM 30859

78 external perimeter road 1 CH. KM 4+540-5+313 RHS&LHS Jointly taking measurement of excavated termite mounds 27/7/2025 9:30AM 30860

79 external perimeter road 1 CH. KM 2+300-2+700 RHS&LHS Inspection and FDT of formation level 27/7/2025 8:00AM 30861

80 external perimeter road 1 CH. KM 2+300-2+700 RHS&LHS Checking level of formation level 27/7/2025 8:30AM 30862

81 perimeter security road CH. KM 13+660-14+140 RHS&LHS Construction of 3rd layer filling after removing unsuitable soil 27/7/2025 8:00AM 30863