Universal Ambient Light
Installation Tutorial
Universal Ambient Light Installation Tutorial
1. Installation Precautions
1-1. Pay attention to the following during the installation process:
1-2. The dismantled trim panels and other components need to be placed so as not
to scratch the dashboard or the interior of the car
1-3. The wire skin or other debris left by the wiring, please clean up in time and do
not leave it in the car
1-4 .The wiring part inside the vehicle must be well insulated and fixed to prevent
short circuit from causing other faults
1-5. Avoid the line affecting the steering wheel shaft, accelerator, pedal and other
active control components of the car
1-6. Check and count the corresponding product accessories before loading
1-7.The main control box directly takes the 12V power supply to test the LED strip
and other lamp accessories
1-8. Switch whether the three basic colors of red, green and yellow are lack of color
and breakpoint
1-9. After inspection, there is no problem before loading, and the light bar cannot be
violently bent
1-10. The installation of the light bar is not tested, and the problem of the light bar in
the installation is not guaranteed.
1-11. The light bar can be cut. If the color of the tail is inconsistent or the color of the
whole strip is out of sync after cutting, you can continue to trim about 2 mm.
1-12. Be sure to install the wiring harness and control box when the vehicle is turned
off, so as not to damage the machine or other accessories in the state of hot
swapping
1-13. The installation position of lamps (contour light bar/handle/storage
box/footwell lamp, etc.) should be installed according to the actual situation. The
installation position of lamps in this document is only for reference
2. Product functional testing
2-1. Control: physical button control, applet control, APP control
2-2. The main control box is connected to electricity: the power ground (GND) is
connected to the ground wire or the ground wire; the power supply +12V is
connected to the body ACC
2-3. Power connection of the auxiliary control box: the power ground (GND) is
connected to the ground wire or the ground wire; the power supply +12V is
connected to the body ACC or the normal power 12V
2-4. Count the accessories and install the main control box first
2-5.Main control controller wiring and wiring
3. Main control box installation
3-1. First find the car power fuse box, find the ACC12V fuse (ACC12V is the power
supply that will become 0V after the car key is removed or the OFF gear), connect the
power +12V of the main control box wiring harness here; connect the main control
box wiring harness " Power ground (GND)” is connected to ground or ground wire;
connect to the main control box and place it in a suitable place to fix it (note, do not
place the main control box at the air outlet of the air conditioner, so as not to affect
the music rhythm effect)
3-2.Installation of the central control outline light (connected to "Zone 1/Central
control outline light"): First remove the relevant central control decorative strips with
the rocker, for the wiring of the central control outline light, and install the light strip
into the central control gap. If it is very tight, cut off the hot melt adhesive on the
reverse side, then put it into the light bar, and fix it with screws. The installation
position of each model is different, and the actual position shall prevail.
3-3.Footwell lamp installation (connected to "2 zone/footwell"): Footwell lamp
wiring
Move the wire to the four foot socket lights and fix them in place
4.Sub-control box installation
4-1.Remove the door frame decorative strip and door lock screw, unplug the socket
in the door frame, and take off the door frame
4-2.The outline light bar is pierced from the door frame and installed
in the door gap. The construction is based on the door gap situation to
avoid violent extrusion and explosion of the lamp beads.
4-3.The handle light and the storage box light need to be installed by opening the
hole. The opening position of the handle light is generally upward, and the position
should be hidden to see the light and not see the light. The storage box can also be
opened upward or side to back.
4-4. Find the normal power 12V (or ACC12V), and connect the power +12V
of the wiring harness of the sub-control box here; find the ground wire,
and connect the "power ground (GND)" of the wiring harness of the
sub-control box here; after completing the wiring assembly , Do not rush
to lock the door frame, you should first perform a basic power-on test
(whether the control is normal, whether the color of the light bar is the
same, whether the lights are synchronized)
Note: The four gates should be unified, that is, the four gates take
"normal power 12V" or the four gates take "ACC12V"
5. Optional speaker installation
5-1. Find the position of the door panel horn and align it well (it is
forbidden to stick the horn on the horn to avoid abnormal noise).
5-2. Find the position and fix it with hot melt glue
Common problems and solutions
Fault possible causes Solution
phenomenon
Main box light 1.The power supply 1. Check whether the power
is off line is not connected supply is strong 12V, and
or wrongly connected measure whether there is 12V
(should be connected (9~16V) between PIN1 (GND) and
to 12V strong PIN2 (power)
electricity) 2. Change grounding to wiring
2. If the ground wire grounding
is grounded, the Plug in the lamp head connector
grounding may be bad and replace the lamp
3.The lamp head is not
plugged in or the lamp
is damaged
Sub box light 1. The power supply 1. Check whether the power
is off line is not connected supply is strong 12V, and
or wrongly connected measure whether there is 12V
(should be connected (9~16V) between PIN1 (GND) and
to 12V strong PIN2 (power)
electricity) 2. Change grounding to wiring
2. If the ground wire grounding
is grounded, the 3. Plug in the lamp head
grounding may be bad connector and replace the lamp
3. The lamp head is not Manually pair the ambient light
plugged in or the lamp again (see "Keys, Mini Programs
is damaged Operation Instructions")
The secondary box is
not paired (automatic
pairing failed)
When ACC is Inconsistent door The four gates should be
OFF, the door connection unified, that is, the four gates
lights are take "normal power 12V" or the
turned off four gates take "ACC12V"
asynchronously
Physical The button connector Plug in the button connector;
buttons cannot is not plugged in check whether the button circuit
be controlled properly; the line is is off. For the specific use of
disconnected the button, see "Button and Mini
Program Operation Instructions"
Abnormal color Wire harness gets Check wiring; replace with new
and brightness stuck during light bar/light head
of lamps installation
resulting in short or
open circuit; light
bar/light head
damaged
The mini The applet/APP has Delete the applet/APP and scan
program/APP been updated; the main the code again to enter; replace
cannot find the box is damaged; the the main box; contact the
ambient light problem of new mobile after-sales staff
(main box) phone adaptation
In close The main box Method 1: After the first car is
proximity, mistakenly used the paired and installed, do not
when two or auxiliary box next to turn off the ACC or keep the
more vehicles it as the auxiliary ambient light on, then pair the
are installed box of the car door second car, and so on.
at the same Method 2: After the first car
time, the pairing and installation is
pairing completed, unplug the car
affects each battery electrode, and then pair
other the second car, and so on.
Method 3: After the first
vehicle is paired and installed,
disconnect the power supply of
the main/secondary box, and then
pair the second vehicle, and so
on.
Method 4: Keep the distance
between vehicles at least 40
meters before pairing