Diode - Hazard Study 5 Worksheet
Diode - Hazard Study 5 Worksheet
Installation Check
Use drop down lists for "Critical for Sart-up?" and "Action Status" columns.
Hazard study 5 worksheet Site and project data in the title box are automatically transferred from sheet 1 to other sheets.
NOTE (version 1 - 2010): Action numbers are generated automatically. Do not insert or delete rows or columns to preserve the automatic numbering.
Do not use "CUT AND PASTE" to move data from text cells. Use "COPY AND DELETE".
THB 11/18/2025
Air or water pollution exposures Air: Included in the Request EBC contractor to 2 Yes Long Implemented
environmental impact submit the drawings to the
approval assessment Water: investor, submit
Our factory has isolation acceptance drawings for
1.1.4 valves against the industrial environment impact.
area. The new system will
connect to the same output
with the old system.
Other site conditions requiring attention One side of the factory can be Follow up the effect on the 3 Tien Implemented
affected by the smoke of the surroundings after a period
1.1.5
chimney from the factory. of operation.
Soil protection in storage, materials handling & For the factory: There are
1.1.6
process areas spill-proof banks. For
tankfarm: There is anti-spill
Floor and tripping hazards - Unguarded openings in Thetank.location wasfactory
The whole designed
is to
floors. Pipe slots in the floor sealed. Holes for avoid these situations.
pipes, etc., which require toe rings. Toeboards ill-
fitting or incomplete. Handrails, security and
continuity. Variations in levels of adjoining floors.
Raised anchor bolts protruding from concrete floor.
Uncovered floor drains and gullies. Pipes and other
obstructions at low level on access routes. Uneven
ground round plants.
THB 11/18/2025
2.3.2 Adequate and accessible man ways No issue
2.3.3 Unobstructed pressure/vacuum relief vents NA
2.3.4 Manifolding of vents reviewed NA
2.3.5 Documented vent sizing basis (process safety NA
2.3.6 manuals)
Winterization (including instrument connections) NA
Adequate lighting No issue
2.3.7
THB 11/18/2025
Lighting adequate Has enough lighting, no issue.
2.7.3
2.9.2 Fixed ladders - Is each ladder a reasonable Make door lock for the 13 Hung Implemented
alternative to a stair? Safety rungs, special monkey ladder for the
arrangements near edges of floors above ground ladder from the terrace to
level. Arrangements at top of ladder. Any the roof.
protection needed at top opening? Do ladder and
rungs extend 1067 mm above floor on a side step
off ladder? Any space between top rung and floor on
forward step of ladder?
THB 11/18/2025
2.9.3 Building exits marked and adequately lit? Safety Make exits for the 14 Tien Implemented
barriers to protect from road or rail traffic? workshop including exit
Two alternative escape routes is the general signs and diagram for it.
requirement unless impracticable for platforms of
small area or tall freestanding columns. Are escape
routes marked and protected to Fire Regulations
standard?
THB 11/18/2025
2.9.22 Other fire fighting equipment (hose reels, hydrants). Done. According to the design The fire alarm system is 21
Access to the above. Fire alarms. Fire detectors, and approval of fire being tested and
drench systems. Fire walls/doors, sealing of ducts. department, and had completed. Check the
Fire proofing of structural steelwork. Access for fire acceptance certification. deflect list.
appliances. Integrity of dikes/bunds. Safety
procedure covering auto-quench systems.
2.9.23 Maintenance and Operating Access
2.9.24 Valves and other If out of reach for operation Need to be checked and 22 Giap Implemented
operating controls or maintenance, consider confirmed.
the urgency and frequency
of operation. If access is
needed, either move it to a
more accessible position, fit
some form of remote
control or provide an
access platform.
THB 11/18/2025
2.9.29 Road and rail tankers Access to tanker with Confirmed by state design
handrail protection if approval.
operator has to go on top of
the tank.
2.10 Human Factors
2.10.1 Labeling of equipment, piping, critical valves, field Confirmed follow PID
2.10.2 instruments,
Location switches
of field instruments, etc. Confirmed follow the design
2.10.3 Sampling points NA
2.10.4 Operator task safety Need to do task risk 23 Giap Implemented
assessment for all.
2.10.5 Operator task ergonomics, incl all forms of start / Need to do task risk 24
shutdown / alarms and visibility under all Follow operating work assessment for all.
lights/weather conditions instruction
2.10.6 Opportunities of operator error Need to do task risk 25
assessment for all.
2.10.7 Non-routine tasks Make a PM program list for 26
all new devices
2.11 Chemical Exposure Hazards
2.11.1 Potential exposures
2.11.2 Engineering controls adequate - tested, visual
indication of adequate performance, acees for
changing filters
2.11.3 Building ventilation/fresh air intakes
2.11.4 Toxic gas monitors, alarms
2.11.5 Protective equipment location
2.11.6 Placarding / signs / lighting Need to send samples, 27 Tiên Implemented
parameters and production
quantity to Tien.
THB 11/18/2025
2.12.13 Thermal (hydrostatic) pressure relief (including heat-
traced sections)
2.12.14 Sight glasses and gauge glasses
2.12.15 External corrosion protection
2.12.16 Freeze protection
2.12.17 Insulation in place to protect people and materials for
high / low temperatures. Steam traps discharge to a
safe location.
2.12.18 Protective flange covers
2.12.19 Approved hoses and hose and connectors (no
improvisations)
2.12.20 Double check in critical lines for re-proving the
integrity after defects have been solved
2.13 Process Vents
2.13.1 Flammable liquid breather vents provided with flame
arrestors or conservation vents
2.13.2 Telltale pressure gauge or other indicator provided
between rupture disc and relief valve where a disc is
installed below a relief valve
2.13.3 Discharge piping from emergency pressure relief
devices unrestricted by 900 ells, excessive length or
flame arrestors
2.13.4 Provisions such as drain holes to prevent
accumulation of rainwater in discharge piping
2.13.5 Discharge piping adequately supported to withstand
reactive forces of pressure venting
2.13.6 Safe vent discharge locations
2.13.7 Manifolding of vents reviewed
2.13.8 Vent sizing basis; documentation
2.14 Ductwork
2.14.1 Cleanouts
2.15 Heat Exchangers, Jackets
2.15.1 Vent, drains
2.15.2 Thermal (hydrostatic) pressure relief
2.15.3 Maintenance access (tube bundle)
2.16 Machinery
2.16.1 Guarding
2.16.2 Short lengths of Consider: Pump glands,
revolving shafts inadequate pump coupling
guards. Fans. Conveyor
drives. Agitator/stirrer
shafts.
THB 11/18/2025
2.16.3 Belt drives Sometimes the bottom of
guard is open. Too large
an opening round shafts or
exposed lengths of
shafting.
2.16.4 Inspection openings If these give access to
moving machinery, fit wire
mesh or lock or bolt down
the cover. In some cases
an electrical interlock may
be needed between the
cover and the power
supply.
THB 11/18/2025
2.17.5 Preparation for maintenance (drain and vent
2.17.6 provided) cranes - Driver's access to cab and
Overhead
escape routes. Access for inspection and
maintenance, including the crab. Lubrication. Are
limit switches needed on travel or traverse?
Guarding. Railstops.
2.18 Containment
2.18.1 Spill containment
2.18.2 Fire water runoff
2.19 Process Controls / Control Room
2.19.1 Control room inherent safety (vs. process hazards)
2.19.2 Ventilation
2.19.3 Emergency lighting Already had emergency lights.
THB 11/18/2025
3.2.10 Non-return valve on steam outlet NA
3.2.11 Distribution piping - see Process piping NA
3.2.12 Condensate drainage adequate NA
3.3 Compressed Air Systems
3.3.1 Non-lubricated construction or non-flammable
synthetic lubricants used for compressor
3.3.2 Discharge pressures above 100 psig
3.4 Electrical
3.4.1 Transformer location
3.4.2 Motor control center(s)
3.4.3 area classification appropiate
3.4.4. all start /stop buttons tested
3.4.5 plant 'emergengency stop' button tested
3.5 Standby Emergency Utility Systems
3.5.1 Review provisions to satisfy process safety
requirements
4 WASTE HANDLING/TREATMENT
4.1 Inspect new facilities same as process facilities Estimate the volume of 28 Long Implemented
5 WAREHOUSE garbage after few months
of operation and then take
5.1 Flammable and combustible liquids the data record to Nhan for
5.2 Forklifts and Motorized Hand Trucks
5.2.1 Traffic safety
5.2.2 Non combustible fuel
5.3 Recommended Fire-Protection Systems in Place
7.3 Facility siting considering blast zones and worst case Need to check the scene and
scenarios take further actions later.
THB 11/18/2025
NOTE:
To extend the spreadsheet, highlight the last row of formatted cells above and drag the whole row down to where you want to end.
If necessary you can do this repeatedly.
NOTE: DO NOT USE CUT AND PASTE TO MOVE DATA FROM TEXT CELLS, USE COPY AND DELETE. DO NOT ADD OR DELETE ROWS FROM THESE SPREADSHEETS.
THB 11/18/2025
Hazard Study 5
Document Check
Use drop down lists for "Critical for Sart-up?" and "Action Status" columns.
Hazard study 5
Site and project data in the title box are automatically transferred from sheet 1 to other sheets.
worksheet
Action numbers are generated automatically. Do not insert or delete rows or columns to preserve the automatic numbering.
NOTE (version 1 - 2010):
Do not use "CUT AND PASTE" to move data from text cells. Use "COPY AND DELETE".
1
Process Safety
General
HSE&S Committee set Follow current setup of
Employee Participation
1.1 up and meeting schedule Amata.
Statement
issued
HSE&S reporting Follow current setup of
procedure & Amata.
1.2
responsibilities (routine
and incidents)
Using current rule and
1.3
Process Safety requirement of Amata
Information factory.
1.3 Review of
High Hazardous Folow HS Study 1.
1.3.1
Chemicals
Soft copy is available in the Translate MSDS to 29 QC leader. Implemented
factory to use. It will be Vietnamese to make it
reviewed and given to shift easier to train employees.
MSDS - easily available
leaders to provide to staff for
1.3.2 on site in appropriate
training. There is a share
locations and languages
disk that contains all MSDS.
Certificates of all
1.13.1 commissioning integrity
testing available
1.13.3
Testing program with
schedule
(Emergency Response
1.17.2 Facility EAP written
Plan)
Are new chemical or
1.17.3
process hazards such
that changes to existing
EAP are required?
2 Operating Instructions
2.5
Process hazards
adequately described
Have jacketed tank and
2.5.1 Thermal hazards chiller.
NA
2.5.2 Any other hazards
Tabulation of process
2.6 alarms, interlocks and
trips included
Follow SOP and engineering
2.6.1 Alarm and trip settings design
Follow SOP and engineering
2.6.2 Description of function design
2.7
made to separate
instructions, for
unloading and loading of
bulk materials
Step-by-step process
2.8
procedures provided for
each operating phase
including:
Have SOP to guide
2.8.1 Initial start-up operators in solving any
problems that may arise.
Have SOP to guide
2.8.2 Normal start-up operators in solving any
problems that may arise.
Have SOP to guide
2.8.3 Normal operation operators in solving any
problems that may arise.
Have SOP to guide
2.8.4 Normal shutdown operators in solving any
problems that may arise.
Emergency operations Have SOP to guide
2.8.5 including emergency operators in solving any
shutdown problems that may arise.
Have SOP to guide
2.8.6
Start-up following operators in solving any
emergency shutdown problems that may arise.
Start-up following a Have SOP to guide
2.8.7 operators in solving any
turnaround
problems that may arise.
Non-routine procedures Have SOP to guide
(e.g., equipment clean- operators in solving any
2.8.8 out, equipment problems that may arise.
preparation for
maintenance)
Auxiliary equipment Have SOP to guide
2.8.9 operators in solving any
operation
problems that may arise.
Operating limits clearly
2.9 defined in step-by-step
procedures
Control ranges/limits Operating limits are visible
2.9.1 at each machine.
specified
Consequences of Operating limits are visible
2.9.2 at each machine.
deviations given
Responses to Operating limits are visible
2.9.3 deviations/abnormal at each machine.
conditions specified
Operating limits are visible
2.9.4 Safe hold points specified at each machine.
3 Responsible Care
Community Awareness
3.1 and Emergency
Response
The emergency response
3.1.1
Communications training procedure is part of the
for key employees training that need to be
provided to the operators.
The emergency response
Education of employees procedure is part of the
3.1.2 on EAP, safety, health, training that need to be
and environmental provided to the operators.
The emergency response
Education of community procedure is part of the
3.1.3 on new process or training that need to be
change provided to the operators.
THB 11/18/2025
The emergency response
Outreach to educate procedure is part of the
3.1.4 responders, government training that need to be
officials, EAP provided to the operators.
The emergency response
Assessment of potential procedure is part of the
3.1.5 risks to employees from training that need to be
accidents provided to the operators.
The emergency response
Communication of procedure is part of the
3.1.6 emergency planning training that need to be
information to LEPC provided to the operators.
3.2.3
Use of site management Follow MOC procedure.
of change procedure
Use of site incident There is site incident
3.2.4
investigation procedure investigation procedure.
Documented sound
engineering practices
3.2.5 consistent with
recognized codes and
standards
Mechanical integrity
3.2.6
program implemented for
new unit or process
change
3.3
Employee Health and
Safety
Medical surveillance Need to be reviewed by 36 Tien and Implemented
program tailored to meet Tien and Nhan Nhan
3.3.1
needs of new process or
change
Personnel change to Need to be reviewed by 37 Tien and Implemented
3.3.2 Central Safety Committee Tien and Nhan Nhan
needed
Education of employees
3.4.2
and public about the
inventory and impact
evaluation
Need to add waste 39
Documentation that generated data of Diode
3.4.3
waste generation is not factory into current waste
increased by, or is report.
minimized in, the change
or
3.5 Distribution
4 Industrial Hygiene
Baseline records
confidentially filed and
Health assessments
results (i.e. fitness for
4.1 done at start
role) formally
employment?
communicated to relevant
managers?
4.2.4
* Need for change in
[periodic medical exam
4.2.6
* Inventory of possible
sources of exposure
4.2.7
* Inventory means to
restrict exposure
4.2.8
* Methods available to
monitor exposure
* Suitable personal
4.2.9 protection equipment
available
4.5
Local exhaust ventilation
systems
Performance of local
4.5.1 exhaust ventilation
systems
Local exhaust ventilation
4.5.2
systems placed on
inspection and
maintenance program
Control of chemicals
4.6
posing a potential
occupational mutagenic
or carcinogenic risk
4.6.1
Are control levels A, B, C
or D materials used
4.7
Hazard Communication
Program
4.7.1
Location inventory of
chemicals updated
4.7.2
Hazardous materials
identified per definitions
4.7.3
MSDS’s on file and
available to all employees
Chemical containers
4.7.4
labeled (or alternate
means of label
information provided)
4.7.6 Training
Review/confirm
4.8.1
conformance with
Corporate Industrial
Hygiene Program
Respirator selection per
4.8.2 selection charts and
specified in writing
4.8.4
Emergency “escape only”
respirators
4.8.7
Initial issues verified by
supervision
4.8.9
Replacement of
cartridges and canisters
4.8.10
Inspection and
maintenance
4.8.11
Breathing air
tested/tagged
4.8.12 Training
4.8.13
Smoking policy
established
5 Laboratory Control
Process Laboratory
5.1 Support Plan
communicated
5.2 Staffing adequate
5.3
Laboratory facilities
adequate
5.3.1 General
5.3.2 Emergency exits marked
5.3.3 Emergency lighting
5.4.2
Maintenance provisions
needed
5.5
Storage and handling
chemicals
5.5.1 Reagent storage
5.5.2
Segregation adequate
(oxidizers, acids)
5.5.3 Flammable liquid storage
Refrigerator for
5.5.4 flammables explosion-
proof
5.5.5 Sample storage
5.5.6 Sample disposal
5.5.7 Waste disposal
5.6 Compressed gases
Cylinder location safe
5.6.1 (e.g., away from heat
sources)
THB 11/18/2025
5.6.2
Quantities limited to
immediate requirements
5.6.3
Separation of flammable
and oxidizers
5.6.4
Toxic gas use limited to
small cylinders
5.6.5
Local exhaust ventilation
for toxic gases
5.6.6
SCBAs available for toxic
gases
5.6.7
Personnel trained in
SCBA use as needed
5.7 Laboratory procedures
5.7.1
Analytical procedures
written and verified
5.7.2
Sampling procedures
included
5.7.3
PPE requirements
specified
5.7.4 Training completed
5.8 Industrial Hygiene
6 Maintenance
6.1
Necessary maintenance
information in place
Design drawings: P &
6.1.1 IDs, electrical, piping,
etc., (as built)
6.1.2 Piping specifications
6.1.3 gaskets
6.1.4
Equipment purchase
orders
6.1.5 Equipment manuals
6.1.6 Vendor prints
Initial inspection and test
results, certificates
6.1.7 available, as well from
manufacturer as
authorities?
6.2 Resources adequate
6.2.1 Needs communicated
6.2.2 Plant manpower
Contract maintenance
6.2.3 (arrangements
completed)
6.2.4 Workshop facilities
6.3
Specialized
requirements
6.3.1 Requirements defined
6.3.2 Skills available
6.3.3 Equipment available
6.3.4 Procedures developed
6.3.5 Training completed
6.3.6
calibration schedule
monitoring equipment
6.3.7
Certificate obtained and
documented
6.4
Maintenance
management
6.4.1
Service contracts
arranged
Maintenance
6.4.2 management system in
place
6.5 Spare parts
6.5.1
Requirements defined by
Maintenance Department
6.5.2 Procurement complete
6.5.3 Start-up needs on hand
6.5.4 Storage security
Quality assurance
6.6 program in place for
critical equipment
Materials of
6.6.1
construction/quality of
maintenance materials
and parts
6.6.2 Workmanship
Preventive
6.7
maintenance/mechanica
l integrity program
developed
6.7.1 Machinery
6.7.2
Boilers and pressure
vessels
Critical equipment,
vessels, piping, check
6.7.3
valves, expansion
bellows, flexible piping
connectors, hoses
defined
Critical equipment
6.7.4
inspection and test
methods and frequencies
defined
Conservation vents,
6.7.5
flame arrestors, PSEs,
PSVs inspection and test
methods and frequencies
6.7.6
Critical instruments
defined
6.7.8
Proof-testing procedures,
validity
Maintenance of
6.7.9
combustion safety
controls on direct-fired
equipment
Inspection and testing
6.7.10
acceptance criteria
developed and
documented
This section (7) may be
ommitted if fully covered in
7 Commissioning HS4 and commissioning
activities complete
7.1
Commissioning plan and
schedule
Detailed, step-by-step Yes Long Implemented
7.1.1
plan written
Yes Long Implemented
7.1.2 Plan adequately reviewed
7.1.3
Responsibilities clearly
defined and understood
Plant verification of any Yes Long Implemented
7.1.4
equipment and systems
check-out done by
contractor
7.2
Construction inspection
by plant
Confirm line-by-line Yes Long Implemented
7.2.1
conformity to P & I Ds
verified by plant,
including
Yes Long Implemented
7.2.2 * Materials of construction
7.2.5
* Ranges of local Pls and
Tls
7.2.6
* All local Tls have
thermo wells
* Identities and relief Yes Long Implemented
7.2.7 pressure of PSEs &
PSVs
7.2.8
* Actuated valve failure
modes
7.4
Vents and pressure
relief valves
Shipping supports
7.4.1 removed from
conservation vents
Relief pressure of PSVs Yes Long Implemented
7.4.2
verified by test
7.8 Machinery
Alignment checked;
Yes Long Implemented
absence of excessive
7.8.1 forces on pump casings,
etc., from connected
piping
Pre-startup screens Yes Long Implemented
7.8.2
installed in pump suctions
Yes Long Implemented
7.8.3 Agitator impeller security
THB 11/18/2025
Cooling systems Yes Long Implemented
7.8.5
functional
Seal flush systems Yes Long Implemented
7.8.6
functional
Yes Long Implemented
7.8.7 Rotation checked
Yes Long Implemented
7.8.8 Vibration measurements
Yes Long Implemented
7.8.9 Performance tests
7.9
Instruments and control
systems
Program software Yes Long Implemented
7.9.1
checked
Instrument loop sheet Yes Long Implemented
7.9.2
index available
Pneumatic lines blown Yes Long Implemented
7.9.3
clean
Loop checking done and Yes Long Implemented
7.9.4
documented
Instrument calibrations Yes Long Implemented
7.9.5 done and documented
review methods
Alarm and trip points set Yes Long Implemented
7.9.6
and documented
All trips, alarms and Yes Long Implemented
7.9.7
interlocks tested
7.9.9
procedure for control of
trip defeats
Digital control system Yes Long Implemented
7.9.10
review and tests
Combustion safety
7.9.11 controls on direct-fired
equipment
* Equipment inspection,
7.9.12 adjustment and testing
documented
7.9.13 Punch list Yes Long Implemented
7.9.14 * Review status
7.9.15 * Daily update
* Priorities with respect to Yes Long Implemented
7.9.16
start-up acceptable
7.10 Water batching
8 Start-up
8.2.1
Instruction manual or
under separate cover
8.2.2
Reviewed and approved
if separate
8.3 Raw materials supply
8.4 Technical support
8.4.1 Adequate
8.4.2
Lines and limits of
authority clear
8.5 Maintenance support Yes Long Implemented
8.6 Process support Yes Long Implemented
8.7
Industrial hygiene
monitoring
8.8 Equipment monitoring
Performance Yes Long Implemented
8.9
measurements and tests
9.1
Check on local / national Check list available for
requirements? future local audits?
9.2 New Substances
Review of toxicity to Yes Long Implemented
9.2.1
environment
9.2.2
Persistency in the
environment
9.2.4
Destruction of substance
when necessary
9.3
Toxic Substances
Control Act (TSCA)
Project reviewed for any
9.3.1
new requirements which
might be imposed on the
plant location
9.3.2 under TSCA
9.4 Transportation
9.5 Emissions
Operating permits
Yes Long Implemented
obtained as directed by
9.5.1 the site or corporate
environmental
departments
9.6 Effluents
Off-site transportation
9.7.5 and disposal of
hazardous wastes
Reviewed with waste Yes Nhan Implemented
9.7.6
coordinator
9.7.7 Documentation
9.7.8 PCBs
Review equipment for
9.7.9 PCB hazardous
properties
9.8 Environment
9.8.1
monitoring schedules in
place
9.8.2 Yes Nhan Implemented
equipment calibrated
NOTE:
To extend the spreadsheet, highlight the last row of formatted cells above and drag the whole row down to where you want to end.
If necessary you can do this repeatedly.
NOTE: DO NOT USE CUT AND PASTE TO MOVE DATA FROM TEXT CELLS, USE COPY AND DELETE. DO NOT ADD OR DELETE ROWS FROM THESE SPREADSHEETS.
THB 11/18/2025
Hazard Study 5
Training Check
Use drop down lists for "Critical for Sart-up?" and "Action Status" columns.
Hazard study 5
Site and project data in the title box are automatically transferred from sheet 1 to other sheets.
worksheet
Action numbers are generated automatically. Do not insert or delete rows or columns to preserve the automatic numbering.
NOTE (version 1 - 2010):
Do not use "CUT AND PASTE" to move data from text cells. Use "COPY AND DELETE".
41
Yes
No
45
5
Job-specific training
5.1 Training matrix for each Production org chart for DIODE & 1 1 Yes Trinh Implemented Trainer for production -
Basic knowledge and working position provide training according to (Prod) Trinh/Giap
skills training matrix Trainers for Main Hung/Long
THB 11/18/2025
5.2 Critical Equipments - Define special knowledge & skill 2 2 Yes A.Long Implemented Need operating instruction for
Specialized knowledge Manufacturing processes need for operating these (Engineer) critical equipments at Diode
and skills Prod Mgr & Engineer Mgr equipments, manufacturing
are available on site processes
5.3 General process General working process to write / to develop WI, SOP 3 3 Yes Trinh Implemented for Prod & Main
knowledge related to proess (Prod)
5.4 Material MSDS & PPE list MSDS in Vietnamese is available 4 4 Yes HSES Implemented MSDS for materials are
Material hazards, for handling material at working area. (Tien) available at shared drive
MSDS’s HMIS label is available at RM
container
5.5 General Productioon TRA for production processes 5 5 Yes HSES Implemented Production processes in
Process hazards process (Tien) DIODE factory are available
5.6 apply standard template for SOP for Prod 6 6 Yes Trinh Implemented Giap is writing some SOP
Process procedures process procedure (Prod) similar to ICO factory.
include: operating limits, For new set up like pumping
consequences of bulk materials to production,
deviations, responses to filling machine ... Production
deviations/abnormal need support from Anh Long
conditions & Tialoc
5.7 emergency procedure Review & revise current 7 7 Yes HSES Implemented New HSES Manager will join
Emergency procedures emergency procedure include (Tien) in 20 Oct will work together
DIODE factory with Tien
5.8 TRA for Production / Provide training to team TRA 8 8 Yes Trinh Trainer for production -
Maintenance processes processes (Prod) Trinh/Giap
JSA Trainers for Main Hung/Long
Trainers for HSES - Tiên
5.9 New equipments at site Provide in-class & field training 9 9 Yes A.Long
Field training (Engineer)
5.1 Layout for emergency Layout for emergency equipments 10 10 Yes HSES
Location of emergency equipment at factory - fire (eye wash, shower, fire (Tien)
equipment, showers, fighting, shower, 1st aid, extinguisher..) are displayed at
alarms, fire-fighting exitlight,,, working area (Ground floor, 1st
equipment, etc. floor, 2nd floor)
5.11 LOPC - Provide training LOPC to team 11 11 Yes A.Long
- Containment sum for DIODE (Engineer) '- currently ICO factory is
Leak and spill prevention, factory. applying LOPC audit
reporting and mitigation monthly, to be applied the
same for Diode factory
5.12 Review & revise current DRILLs 12 12 Yes HSES temporary is HSES advisor.
Emergency drills Emergency drills procedure procedure with include Diode (Tien) This task will be led by HSES
factory Manager
6 Use current waste 1) to check existing capacity for 13 13 Yes HSES Implemented
warehouse to keep waste waste, waste handling, new waste (Tien)
from Diode factory handling, frequency of collecting
waste…
Compliance with OSHA 2) to review, revise current SOP
1910.120 for hazardous with include DIODE factory..
waste operations 3) check waste supplier capacity,
capabilities to handle the waste
THB 11/18/2025
7 include Diode factory to 1) to review, revise the current 14 14 Yes HSES temporary is HSES advisor.
current site emergency emergency procedure to include (Tien) This task will be led by HSES
procedure DIODE factory… Manager
2) SOP for evacuation for DIODE
New emergency & current factory ( include rescuse
response training items…)
requirements 3) details training plan for
emergency response
4) ERP procedure
8 Training & validate training 1) workers are trained & qualified 15 15 Yes Trinh Implemented Production ; QA ; Main :
before working at production shop (Prod) HSES training
Measurement of training floor. plan/records/evaluation
effectiveness, 2) provide training according to
certification (where training plan, training record,
applicable) evaluation record after the training
9 Training materials & Training - Having traing records, tests for 16 16 Yes Trinh Implemented Trainer for production -
record all training courses. (Prod) Trinh/Giap
Formal documentation
- Training materials are Trainers for Main Hung/Long
of training
documented
10 Trainers ; Training validation define score to pass training. 17 17 Yes Trinh Implemented
Team assessment of Having test after training (Prod)
training effectiveness Train the trainers. List of qualified
trainers
THB 11/18/2025
NOTE:
To extend the spreadsheet, highlight the last row of formatted cells above and drag the whole row down to where you want to end.
If necessary you can do this repeatedly.
NOTE: DO NOT USE CUT AND PASTE TO MOVE DATA FROM TEXT CELLS, USE COPY AND DELETE. DO NOT ADD OR DELETE ROWS FROM THESE SPREADSHEETS.
THB 11/18/2025
Hazard Study 5
Hazard Study Review
Use drop down lists for "Critical for Sart-up?" and "Action Status" columns.
Hazard study 5 worksheet Site and project data in the title box are automatically transferred from sheet 1 to other sheets.
NOTE (version 1 - 2010): Action numbers are generated automatically. Do not insert or delete rows or columns to preserve the automatic numbering.
Do not use "CUT AND PASTE" to move data from text cells. Use "COPY AND DELETE".
THB 11/18/2025
THB 11/18/2025
NOTE:
To extend the spreadsheet, highlight the last row of formatted cells above and drag the whole row down to where you want to end.
If necessary you can do this repeatedly.
NOTE: DO NOT USE CUT AND PASTE TO MOVE DATA FROM TEXT CELLS, USE COPY AND DELETE. DO NOT ADD OR DELETE ROWS FROM THESE SPREADSHEETS.
THB 11/18/2025
Hazard Study 5
Supplementary Checklist for New Sites
Use drop down lists for "Critical for Sart-up?" and "Action Status" columns.
Hazard study 5 worksheet Site and project data in the title box are automatically transferred from sheet 1 to other sheets.
NOTE (version 1 - 2010): Action numbers are generated automatically. Do not insert or delete rows or columns to preserve the automatic numbering.
Do not use "CUT AND PASTE" to move data from text cells. Use "COPY AND DELETE".
1 Plant Security
1.2 Access
1.3 Fencing
1.4 Visitor controls
1.5 Vehicle controls
1.6 Restrictions posted
1.7 Communications
1.8 Normal
1.9 Emergency back-up
THB 11/18/2025
2 Safety Program
2.1 Accountability
2.2 Program
Conformance with Corporate
2.3
Safety Standards
Conformance with BU safety
2.4
standards
2.5 Sirens
4.1 Accountability
Level of protection
established per insurance
5.2
requirement and Corporate
Risk Department
THB 11/18/2025
Training conducted per
5.3
standard
Equipment provided per
5.4
standard
Municipal fire department (or
5.5
equivalent)
Response time and
capabilities consistent with
5.6
location needs and fire
protection organization
5.7 Liaison established
5.8 Familiarization
5.9 Drills
Process Safety
6
Management
Location coordinator
6.1
appointed
6.2 Program
Operating manager and Site
6.3 Responsible Engineer
appointed?
6.4 Training conducted
Hazard study leader
6.5
identified and trained?
THB 11/18/2025
NOTE:
To extend the spreadsheet, highlight the last row of formatted cells above and drag the whole row down to where you want to end.
If necessary you can do this repeatedly.
NOTE: DO NOT USE CUT AND PASTE TO MOVE DATA FROM TEXT CELLS, USE COPY AND DELETE. DO NOT ADD OR DELETE ROWS FROM THESE SPREADSHEETS.
THB 11/18/2025