0% found this document useful (0 votes)
408 views39 pages

Construction Planning & Management

* Interior painting quantity: 4440 m2 * Interior painting crew productivity: 11 m2/hour * Number of shifts per day: 3 * Hours per shift: 8 * Total hours per day: 3 * 8 = 24 * Total labor hours required = 4440 / 11 = 403 hours * Total days required = 403 hours / 24 hours per day = 16.79 days = 17 days * Exterior painting quantity: 3378 m2 * Exterior painting crew productivity: 14 m2/hour * Total labor hours required = 3378 / 14 = 241 hours * Total days required = 241 hours / 24 hours per day = 10.04 days = 11 days Therefore,

Uploaded by

Ankur Srivastava
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
408 views39 pages

Construction Planning & Management

* Interior painting quantity: 4440 m2 * Interior painting crew productivity: 11 m2/hour * Number of shifts per day: 3 * Hours per shift: 8 * Total hours per day: 3 * 8 = 24 * Total labor hours required = 4440 / 11 = 403 hours * Total days required = 403 hours / 24 hours per day = 16.79 days = 17 days * Exterior painting quantity: 3378 m2 * Exterior painting crew productivity: 14 m2/hour * Total labor hours required = 3378 / 14 = 241 hours * Total days required = 241 hours / 24 hours per day = 10.04 days = 11 days Therefore,

Uploaded by

Ankur Srivastava
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
  • Introduction to Construction Planning & Management: Overview of key topics in construction planning and management, including scheduling and project control.
  • Planning & Scheduling: Explains the necessity of planning and scheduling in construction, highlighting their roles and processes.
  • Objectives of Planning: Outlines various objectives such as feasibility, material estimation, and financial requirements essential for planning.
  • Stages of Planning: Describes three stages of planning: Preplanning, Detailed Planning, and Monitoring Schedules.
  • Need for Scheduling: Identifies why scheduling is critical for owners and contractors to manage construction efficiently.
  • Importance of Planning & Scheduling: Discusses consequences of poor planning and scheduling, such as delays and increased costs.
  • Types of Schedules: Differentiates between bar charts and network diagrams highlighting their uses in construction scheduling.
  • Bar Chart Usage: Explains the significance of bar charts in visualizing tasks across a timeline for better project management.
  • Constructing a Bar Chart: Guides on constructing bar charts, including questions to consider and additional information layers.
  • Steps to Construct a Bar Chart: Outlines a detailed step-by-step process for creating a bar chart including identifying activities and estimating durations.
  • Work Breakdown Structure: Covers the hierarchical organization of a project and its components to enhance management and accountability.
  • Benefits of Work Breakdown Structure: Highlights the advantages of using a WBS for defining scope, scheduling, and managing resources.
  • Estimate Activity Duration: Discusses methods to estimate activity duration based on historical records and standard practices.

PROJECT SCHEDULING:

IMPORTANCE, STEPS FOR BAR CRITICAL PATH METHODS: PROJECT


CHART, GANTT CHART PLANNING, EVENT TIMES, CRITICAL
PATHS, ACTIVITY TIES, ACTIVITY
FLOATS
PERT TECHNIQUE: UNCERTAINLTY,
PROJECT PLANNING, PROBABILITY
SAFETY IN
OF COMPLETION
CONSTRUCTION

QUALITY CONTROL IN
CONSTRUCTION COSNTRUCTION:INSPEC
COST MODEL: DIRECT
PLANNING & TION, TOTAL QUALTY
INDIRECT COST, TIME-
CONTROL, ISO 9000,
COMPRESSION MANAGEMENT
QUALITY ASSURANCE
TECHNIQUES
PROGRAM, RISK
CONTAINMENT

BASICS; PROJECT PHASES, PROJECT CONSTRUCTION MATERIAL:


DELIVERY SYSTEM, PROJECT TEAM MANAGEMENT, PROVISIONING
STEPS, INVENTORY

CONSTRUCTION EQUIPMENTS:
CONSTRUCTION LABOR: TYPES, IDENTIFICATION, ACTUAL OUTPUT,
PRODUCTIVITY, MULTISKILLING & EMPLOYMENT COST, ACQUISITION
SOCIAL ASPECTS OPTIONS, FILED VISITS
Planning & Scheduling
If you estimate or manage construction, you must plan
and schedule.

Project planning serves as a foundation for several related


functions including estimating, scheduling and
controlling. Planning involves the process of selecting
the one method and order of work to be used on a
project from among all the various methods and
sequences possible.

Scheduling is the determination of the timing and


sequence of operations in the project and their
assembly to give the overall completion time.
Planning & Scheduling
Why?
1. A plan and schedule is a road map (on paper) to
get from X to Y.
• Allows focus of attention on doing the job
• Can be communicated to all members of the
construction team
• Will free your mind for creative thinking
 Stages of project planning: pre-tender ,pre-construction
and detailed construction planning
 Process of development of plans and schedules: work
break-down structure, activity lists, assessment of work
content, estimating durations, sequence of activities.
 Planning techniques: Bar charts, Networks: basic
terminology, types, advantages
o Formulation and analysis of CPM networks(AOA , AON
and precedence networks)
o Formulation and analysis of PERT networks.
o Introduction to line of balance technique.
 Resource Scheduling- resource constraints and conflicts,
resource aggregation, allocation, smoothening and
levelling, calendaring networks.
 Other schedules derived from project schedules
Objectives of Planning
“To work out a BASE plan and different schedules to
achieve target completion with profit maximization”

To estimate in advance,(in practical and feasible


manner)
 Material required:- type, Qty, Time of delivery
 Equipment requirement :- type, Qty., time
 Labour Requirement :- type, qty, time
 Financial requirements ( estimated cash flow)
 Duration estimation
 Feasibility studies( ex. Economic evaluation)
Stages of Planning

1) Preplanning: (Owner and Consultant)


 Scope, Objective definition
 Feasibility
 Alternative
 Financial requirements
 Economic analysis

2) Detailed Planning
 Design, Estimate, Contract :- (Owner & consultant)
 Construction Planning ( Contractor -at HO)

3) Monitoring and controlling Schedules


:- Contractor in consultation of Consultant - at site
Need for Scheduling ?
• Owner
– Owner Requirement
– Communication of the Construction Plan
– Monitor and measure progress
• General Contractor/Sub Contractors/Supervisor
– Establish production goals
– Manage Changes
– Communication of the construction plan
Importance of Planning &
Scheduling
– Failure to plan and schedule leads to

• excessive labor cost,


• equipment waiting time,
• delays, waiting for materials,
• lack of coordination, and management inability to
react to unexpected events (weather, equipment
breakdowns, shortages)
• Productivity Loss
Types of Schedules
• Bar Chart
– Often called Gantt Chart

• Network Diagrams
– Arrow Diagram
– Precedence Diagram
– Often called Critical Path Method
(CPM)
Formats of Schedules
• Summary schedule
– Shows major work elements, such as Design,
Civil, Electrical, commissioning)
– Work should be broken down into activities that
comprise not more than 5% of total project
• Short-interval schedule
– Identifies work for upcoming 2-3 weeks
– Usually prepared by superintendent (Junior or
Assistant Engineers)
Bar Chart

• Developed by Henry Gantt


– Often called a Gantt Chart

• Definition
– A graphical description of a project consisting
of well-defined collection of tasks
Bar Chart
• Activities are represented by bars in
proportion to their duration.
– An activity is a task or closely related group of
tasks whose performance contributes to the
completion of the overall project
– Example: Excavate foundation

• Bar chart is usually graphed on a calendar

• Can be simple or detailed as necessary


Culvert
Example Bar Chart-
Culvert
Time

June July August September October


Excavation &
Backfill

Pilling

Abutment No. 1

Abutment No.2

Steel girder

Concrete Deck
Finishing
Operations
Constructing a Bar Chart
• When constructing a bar chart, the following
questions must be answered:
– What time units should be used? (days, weeks,
months)
– Should work days or calendar days be used?
– How do I schedule non-continuous work?
• Additional information may be added to the
basic bar chart
– Cost of activity (“cost-loaded schedule”)
– Labor required for each activity (“man-loaded”)
– Materials required for each activity (“resource-
loaded”)
Cost loaded Construction
Schedule

http://www.projectrisk.com
Man-Hours loaded Schedule
Labor Schedule

http://hafeezrm.hubpages.com
Steps to Construct a Bar Chart
• Identify Activities
• Estimate Activity Duration
• Develop Activity Sequence
• Construct Bar Chart
1. Identification of Activities

• Use the Work Breakdown Structure (WBS)


from the cost estimate
• Add activities as necessary
• Rule of thumb: no activity should comprise
more the 5% of the total scope of work
• Rule of thumb: activity duration should
range from 1 day to 15 days
Work Breakdown Structure
 Hierarchical organization of a system –
Continued until sub-system is reduced to a
manageable unit.
Work Breakdown Structure
 Hierarchical organization of a system – Continued until sub-
system is reduced to a manageable unit.

Building #1

Foundation Structure Interior

Excavation Footings

Isolated Footings Continuous Footings


24

Work breakdown structure

 Project activities are determined by,


 splitting the total scope of the project work into hierarchical work
breakdown levels
( sub-projects, tasks, work packages and activities.)
• Each activity with its duration and resources forms the database
for planning, scheduling and monitoring of the project.
• How many activities in a Project?
 Too large:- complexity and cost of planning increases
 Too small:- impossible to develop realistic schedules and resource
allocation
 Define separate task for,
 those activities which involve different resources, or
 those activities which do not require continuous performance.
Sewage Pumping Station-WBS
SPS (civil Works)

Receiving Chamber Fine Screen Ch, Raw Sewage Sump

Excavation Footings Walls

Excavation, PCC, RCC Raft, flooring, coating


BENEFITS OF THE WORK BREAKDOWN
STRUCTURE (WBS) TECHNIQUE

• It forms the basis for,


• defining the scope of work,
• identifying activities,
• scheduling the work-logic,
• structuring the organization,
• assigning responsibilities,
• estimating costs,
• codifying systems,
• organizing data and
• analyzing the sources of risks.
2. Estimate Activity Duration
• How to estimate duration:
– From company’s historic records
– From asking superintendent or foreman
– From standard estimating guide
– From calculation using the Labor Hour
Productivity equation
3. Estimate Activity Duration

• Labor-Hour Productivity Method

– Total labor-hours required for an activity =


labor-hours /Unit x no. of units
total labor hours
Total days = labor-hours / day

total labor hours


Total days = crew size x hrs/day
• Find the duration (days) of an interior and
exterior painting activities with quantities of 4440
m2 and 3378 m2 respectively, using crews of 11
m2/hours and 14 m2/hours for the interior and
exterior painting activities respectively. Assume
three shifts of 8-h for each activity.

Solution
Interior painting duration = 4440 / 24x11 = 16.8 or 17 days
Exterior painting duration = 3378 / 24x 14 = 10 days
Total work hours = 27 days
3. Establish the Sequence of
Work
• Sequencing needs to take into account the
relationships between activities.

• There are four types of relationships that


need to be taken into account.
1. Physical:
• Exists between two or more activities when one
cannot start until another is partially or totally
complete (i.e., cannot pour footings until they have
been formed)
2. Establish the Sequence Of
Work (continued)
2. Safety:
Exists when simultaneous performance of two
activities can result in a safety hazard (i.e., in
multi-story construction it is at times unsafe for
crews to be working under one another)
3. Resource:
Due to limited resource availability, two activities
may not be able to use a resource at the same
time (i.e., a crane cannot be used for both
pouring walls and erecting steel)
4. Preferential:
• How the contractor wishes certain activities to be
sequenced
Draw the Bar Chart “ Final Design &
Work Order for a Building”

Final Design & Work Order

Work
Design
Order

Site Detailed Tender Selection of


Drawings Documents Tendering
Surveys Design Contractors
Preparation

Award of
Number of Activities - 7 Work Order
Estimate Activity Duration
Activity Description Time of Completion (Weeks)

A Site Surveys 4

B Detailed Design 6

C Preparation of 3
Drawings
D Tender Documents 2
Preparation
E Tendering 4
F Selection of 1
Contractors

G Award of Work 1
Order

Establish Sequence
Establish Sequence of Works
A. Site Surveys: Types-----
B. Detailed Design
C. Preparation of Drawings
D. Tender Documents Preparation: Specification,
contract related etc.,
E. Tendering
F. Selection of Contractors
G. Award of Work Order

Which Activities can Overlap ?


Which Activities can Overlap
• A&B
• B&C
• C&D only

What would be the minimum time of


completion ?
BAR CHART
Another Example
Bar Chart
Immediate
Immediate Estimated
Estimated
Activity
Activity Predecessor
Predecessor Completion
Completion Time
Time
AA None
None 90
90
BB A
A 15
15
CC B
B 55
DD G
G 20
20
E
E D
D 21
21
F
F A
A 25
25
GG C,F
C,F 14
14
HH D
D 28
28
II A
A 30
30
J
J D,I
D,I 45
45
90
105

90 115
A 15 129
B 5 149 194
C 20
D 194
21
E 25
F
14
G
28
H
30
I 45

You might also like