1
PROJECT MONITORING, PROJECT
REVISION, PROJECT COMPLETION
AND
SPECIAL PROJECTS
A. H. Monjur Morshed
Deputy Chief (Economics)
Project
2
A project is a one time job that has defined
starting and ending dates, a clearly
specified objective, or scope of work to be
performed, a pre-defined budget, and
usually a temporary organization that is
dismantled once the project is complete.
Every project is unique in that it requires
doing something different than was done
previously.
Project
3
Project is a group of multiple
interdependent activities that
require people and resources.
A project is any undertaking with a
defined starting point and defined
objectives by which completion is
identified.
A project is one time activity, never
to be exactly repeated again.
Project
4
A project involves a single, definable
purpose, end-item, or result, usually
specified in terms of cost, schedule,
and performance requirement.
A project in business and science is a
collaborative enterprise, frequently
involving research or design, that is
carefully planned to achieve a
particular aim.
Project Cycle
5
Project Cycle: A project goes
through phases of identification,
formulation, approval,
implementation, monitoring &
evaluation and completion.
Project Cycle
6
Programming
Evaluation Identification
Implementation Formulation
Financing
presentation (color) 04/15/25
Project Life Cycle
7
Conceptual Stage/Definition
Development/Planning
Implementation Stage/Execution
Termination Stage/Transfer
Project Management
8
Project management processes fall into five
groups:
Initiating
Planning
Executing
Monitoring and Controlling
Closing
Project Monitoring
9
Monitoring means keeping a track of
implementation process.
Monitoring means periodic checking of
progress of works against the targets laid
down in order to ensure timely
completion of the project.
The goal of project monitoring is ensuring
that the project is on time and on budget
and/or highlight any deviation from the
plan.
Areas
10
Project constraints:
- Scope,
- Quality,
- Schedule,
- Budget,
- Resources, and
- Risks.
Project Monitoring
11
Why do we monitor?
To detect and react appropriately to
deviations and changes to plans
What do we monitor?
Inputs
Time Money Resources Material
Usage Tasks quality/Technical Performance
Outputs
Progress CostsJob starts job completion
Design changes
Project Monitoring
12
When to we monitor? End of the project?
Continuously
Regularly
Logically
While there is still time to react
As soon as possible
At task completion
At pre-planned decision points
(milestones)
Project Monitoring
13
How do we monitor?
Calculate Critical Ratios
(actual progress / scheduled progress) X
(budgeted cost / actual cost)
Milestones
Reports
Tests and inspections
Project Control
14
What is Project Controling
is the process of making things happen in an
ordered manner or according to plan.
Control the triple constraints
time (schedule)
cost (budget, expenses, etc)
performance (specifications, testing results,
etc.)
Project Control
15
Schedule: Was the project completed on
time? (How long did we take?)
Cost: Did the project come in at cost?
(How much did we spend?)
Functionality: Do project deliverables
have the expected capability? (What can
they do?)
Quality: Do the deliverables perform as
well as promised? (How well can they do
it?)
PSC Committee
16
µt bs c`ex I Kg©¯’j KwgwU‡Z
Ae¯’vb
1| mwPe, cvwb m¤ú` gš¿Yvjq AvnevqK
2| gnvcwiPvjK, evsjv‡`k cvwb Dbœqb †evW© m`m¨
3| AwZwi³ mwPe (cwiKíbv), cvwb m¤ú` gš¿Yvjq m`m¨
4| AwZwi³ mwPe/ hyM¥-mwPe (Dbœqb), cvwb m¤ú` gš¿Yvjq m`m¨
5| Dc-cÖavb (mswkøó), cvwb m¤ú` gš¿Yvjq m`m¨
6| cÖwZwbwa,GbBwm- GK‡bK Ges cwiKíbv Kwgk‡bi mgš^q m`m¨
wefv‡Mi
7| cÖwZwbwa, cwiKíbv Kwgk‡bi †mP DBs m`m¨
8| cÖwZwbwa, AvBGgBwW Gi mswkøó wefvM m`m¨
9| cwiKíbv Kwgk‡bi †cÖvMÖvwgs wefv†Mi cÖwZwbwa m`m¨
10| A_© wefv‡Mi cÖwZwbwa m`m¨
11| cÖavb cÖ‡KŠkjx(cyi) cwiKíbv, evsjv‡`k cvwb Dbœqb m`m¨
†evW©
12| cÖavb cÖ‡KŠkjx(cyi) gwbUwis, evsjv‡`k cvwb Dbœqb m`m¨
†evW©
13| cÖKí cwiPvjK, mswkøó cÖKí, evsjv‡`k cvwb Dbœqb †evW© m`m¨
14| mswkøó ‡W¯‹ Awdmvi (cwiKíbv DBs), cvwb m¤ú` gš¿Yvjq m`m¨ mwPe
PSC Committee
17
KwgwU cÖK‡íi mdj ev¯Íevq‡bi Rb¨ cª‡qvRbxq
Kg©cš’v cÖYqb, cÖvwZôvwbK mg_©b Ges
Ab¨vb¨ wb‡`©kbv cÖ`vb Ki‡eb|
AvšÍtgš¿Yvjq Kvh©µ‡gi g‡a¨ mgš^qmvab Ges
cÖKíwUi mvwe©K ch©‡e¶Y I i¶Yv‡e¶Y Ki‡eb|
KwgwU Kgc‡¶ wZb gvm cici mfvi Av‡qvRb Ki‡eb|
KwgwU cÖ‡qvR‡b Ab¨ †Kvb Kg©KZ©v†K m`m¨
wn‡m‡e †Kv-AÞ Ki‡Z cvi‡eb|
PIC Committee
18
µt bs c`ex I Kg©¯’j KwgwU‡Z
Ae¯’vb
1. gnvcwiPvjK, evsjv‡`k cvwb Dbœqb †evW© AvnevqK
2. cÖavb cÖ‡KŠkjx(cyi) cwiKíbv, evsjv‡`k cvwb Dbœqb m`m¨
†evW©
3. cÖavb cÖ‡KŠkjx(cyi) gwbUwis, evsjv‡`k cvwb Dbœqb m`m¨
†evW©
4. mswkøó Dc-cÖavb / †W¯‹ Awdmvi (cwiKíbv DBs), m`m¨
cvwb m¤ú` gš¿Yvjq
5. mswkøó †W¯‹ Awdmvi (Dbœqb DBs), cvwb m¤ú` m`m¨
gš¿Yvjq
6. cwiKíbv Kwgk‡bi †mP DBs Gi cÖwZwbwa m`m¨
7. cwiKíbv Kwgk‡bi †cÖvMÖvwgs wefv†Mi cÖwZwbwa m`m¨
8. GbBwm- GK‡bK Ges cwiKíbv Kwgk‡bi mgš^q wefv‡Mi m`m¨
cÖwZwbwa
9. AvBGgBwW Gi mswkøó wefv‡Mi cÖwZwbwa m`m¨
10. A_© wefv‡Mi cÖwZwbwa m`m¨
11. cÖKí cwiPvjK (mswkøó cÖKí), evsjv‡`k cvwb Dbœqb m`m¨
†evW©
12. cÖwZwbwa, mswkøó wWRvBb mv‡K©j, evcvD‡ev, m`m¨
XvKv
13. mswkøó wbe©vnx cÖ‡KŠkjx, evsjv‡`k cvwb Dbœqb m`m¨ mwPe
†evW©
PIC Committee
19
cÖK‡íi mdj ev¯Íevq‡bi j‡¶¨ cÖ‡hvRbxq
mnvqZv/civgk© cÖ`vb Ki‡eb|
cÖK‡íi Kvh©µ‡gi ch©‡e¶Y, AMÖMwZ g~j¨vqb
Ges mgm¨v mgvavb Ki‡Z cÖKí ev¯Íevq‡bi mgq
Av‡jvPbvi gva¨‡g wm×všÍ cÖ`vb Ki‡eb|
KwgwU Kgc‡¶ wZb gvm ci ci mfvi Av‡qvRb Ki‡eb |
KwgwU cÖ‡qvR‡b Ab¨ †Kvb Kg©KZ©v †K m`m¨
wn‡m‡e †Kv-AÞ Ki‡Z cvi‡eb|
Monitoring Reports
20
IMED Reports
PSC Meeting Minutes
PIC Meeting Minutes
BWDB Monitoring Reports
BWDB Taskforce Reports
Project Evaluation?
21
A time-bound assessment that
systematically and objectively assesses
the relevance, performance, success and
effectiveness of ongoing and completed
programmes and projects.
Monitoring and Evaluation
22
Monitoring Evaluation
Who? Internal management Usually incorporates external inputs
responsibility – all levels (objectivity)
When? Ongoing Periodic – mid-term, completion, ex-
post
Why? Check progress, take remedial Learn broad lessons applicable to
action, update plans other programs/projects, policy
review, etc.
Focus on Inputs, activities, results Results, purpose, objective
Project Revision
23
Revision
Inter-item Cost Adjustment
Time Extension
Revision of Investment
24 Project
Why Revision
If planned objectives are not achievable
and changed;
If cost is increased due to currency;
fluctuation and/or CDVAT cost changed;
If national pay scale and other allowances
are enhanced;
If physical items’ cost is increased or
decreased;
Why Revision
25
If design needs changes;
If procurement/ contract price is higher
than approved DPP cost;
If approved cost of other items are
increased/ decreased
Project Steering Committee recommends
for revised DPP if necessary.
Revision of Investment
26
Project
Two times revision allowed
No post factor approval
If need 3rd revision- Prior permission from Planning
Minister for processing
1st Revisions
Prepare in RDPP format;
Ministry approves Revised Project cost up to 15% or
40 crore increase/ decrease with the recommendation
of DPEC except change in purpose, mode of funding,
source of funding, vehicle, manpower
With the above conditions if cost up to 15%
increase /decrease Planning Minister approves the
project
Department Project
27
Evaluation Committee (DPEC)
Terms of Reference:
Appraisal of the acceptability of Study
proposal in the context of Development Plan
Examination of Financial, Economic and
Technical viability of Study proposal
Examine the acceptability of first revised DPP
Suggest necessary amendment/ modification
alterations if necessary
Formulate recommendations for approval by
the competent authority.
Revision of Investment
28
Project
On October, 2016 a circular was issued for
approval procedure of revised project
Major modifications as follows:
If new items are included in the revised project,
no need to place it to ECNEC meeting.
If project cost is increased due to increase of land
price and increase of CD-VAT, the Administrative
Ministry is empowered to amend the project.
If there is any mistake of economy code
description for approved items of the project,
Administrative Ministry is empowered to amend it.
Revision of Investment
29
Project
Respective Ministry issue approval letter of
the project approved by Concern Minister
Concern sector of Planning Commission
issue approval letter of the project
approved by Planning Minister
ECNEC wing of Planning Division issue
approval letter of the project approved by
ECNEC
Respective Ministry can not issue the
administrative order of the project without
approval letter of Planning Commission
Inter-item Cost Adjustment
30
Quantity of items not changed
Cost of revenue item adjusted with other
revenue item
Item under capital cost adjusted with other
item under capital cost
CD/VAT can’t be adjusted with any other
item
Cost of land can’t be allocated to other
item but cost of other item can be
allocated to land acquisition
Time Extension of Project
31
without cost change
Respective Minister extends project
duration up to 1 year with the
recommendation of IMED before 2nd
revision
For more than one year or 2nd time
extension Member of Planning Commission
approves
For 3rd time Planning Minister approves
project duration
Project Identification
32
Development Project
Investment Project Technical Assistance Self Financed Project
Project
Technical Assistance Project
33
Technical assistance is non-financial
assistance provided by local or
international specialists. It can take the
form of sharing information and
expertise, instruction, skills training,
transmission of working knowledge, and
consulting services and may also involve
the transfer of technical data.
Technical Assistance Project
34
projects and programme design
project management
capacity building
strategy development
design and implementation of
monitoring and evaluation systems
feasibility studies and needs analyses
human resources development
Project Approval
35
Technical Assistance
Project Proposal (TAPP)
Minister of Minister of
Sponsoring Ministry is Planning is the
the Approval Authority of Approval Authority of
Project Costing Project Costing
up to Tk. 10 crore over to Tk. 10 crore
Study Project
36
For Feasibility Study
A feasibility study is simply an assessment
of the practicality of a proposed plan or
project.
A feasibility analysis is used to determine
the viability of an idea, such as ensuring a
project is legally and technically feasible as
well as economically justifiable. It tells us
whether a project is worth the investment—
in some cases, a project may not be doable.
Study Project
37
The goals of feasibility studies are as
follows:
To understand thoroughly all aspects of a
project, concept, or plan
To become aware of any potential
problems that could occur while
implementing the project
To determine if, after considering all
significant factors, the project is viable—
that is, worth undertaking
Study Project
38
Proposal for Feasibility Study (PFS)
Minister of Minister of
Sponsoring Ministry is Planning is the
the Approval Authority of Approval Authority of
Project Costing Project Costing
up to Tk. 5.00 crore over to Tk. 5 crore
Project Completion Report
39
(PCR)
A. Project description
B. Implementation position
C. Financial and physical programme
D. Achievement of objectives of the
project
E. Benefit analysis
F. Monitoring and auditing
G. Descriptive report
40
Thank You