Holcim Catch Up Plan Rev 1.2

The document is a project plan for completing construction of a warehouse by Holcim. It outlines the original schedule and progress for various structural, masonry, and roofing activities. Several structural framing and masonry tasks are ahead of schedule, while most roofing and structural tasks are behind or just starting on schedule. The overall project progress is reported at 21.23% complete as of mid-July 2019.

Uploaded by

Kinz Tano
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
309 views2 pages

Holcim Catch Up Plan Rev 1.2

The document is a project plan for completing construction of a warehouse by Holcim. It outlines the original schedule and progress for various structural, masonry, and roofing activities. Several structural framing and masonry tasks are ahead of schedule, while most roofing and structural tasks are behind or just starting on schedule. The overall project progress is reported at 21.23% complete as of mid-July 2019.

Uploaded by

Kinz Tano
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
  • Project Overview
  • Detailed Project Schedule

Holcim Catch Up Plan Rev 1.

2
Activity ID Activity Name Original Performance % BL Project Start BL Project Finish Actual Start Actual Finish Qtr 2, 2019 Qtr 3, 2019
Duration Complete
Jun Jul
29d 0% May-29-19 Jul-03-19 May-01-19 Holcim Catch Up Plan Rev 1.2, 21.23%
Holcim Catch Up Plan Rev 1.2
Warehouse Overall 29d 0% May-29-19 Jul-03-19 May-29-19 Warehouse Overall, 21.23%

STRUCTURAL WORKS 23d 0% May-29-19 Jun-25-19 May-29-19 STRUCTURAL WORKS, 0%


Erection 11d 0% May-29-19 Jun-11-19 May-29-19 Erection, 67.86%
A1190 Rigid Frame Erection: GL I to K 3d 100% May-29-19 May-31-19 May-29-19 Jun-04-19 100%
A1200 Rigid Frame Erection: GL L to N 3d 100% May-31-19 Jun-04-19 May-29-19 Jun-03-19 100%
A1280 Rigid Frame Erection: GL O 4d 10% Jun-06-19 Jun-11-19 Jun-01-19
Rafter Installation 12d 0% Jun-06-19 Jun-21-19 Jun-07-19 Rafter Installation, 0%
A1810 GL J & K 3d 0% Jun-06-19 Jun-10-19 Jun-07-19
A1820 GL L& M 4d 0% Jun-13-19 Jun-17-19
A1830 GL N & O 4d 0% Jun-18-19 Jun-21-19
Side Framing (Railings) 15d 0% May-29-19 Jun-15-19 Side Framing (Railings), 0%
A1220 Side Railing Welding/Bolting 15d 0% May-29-19 Jun-15-19
A1230 Side Railing Installation 15d 0% May-29-19 Jun-15-19
A1240 Girt/Gutter Bracket Installation 15d 0% May-29-19 Jun-15-19
Roofing 23d 0% May-29-19 Jun-25-19 Jun-02-19 Roofing, 0%
Installation of Purlins 19d 0% Jun-01-19 Jun-24-19 Jun-02-19 Installation of Purlins, 0%
A1250 GL I to L 11d 0% Jun-01-19 Jun-15-19 Jun-02-19
A1260 GL Lto O 11d 0% Jun-11-19 Jun-24-19 Jun-03-19 0%
Installation of Cross Bracing 11d 0% Jun-13-19 Jun-25-19 Installation of Cross Bracing, 0%
A1870 GL I to K 3d 0% Jun-13-19 Jun-15-19
A1880 GL K to M 4d 0% Jun-17-19 Jun-20-19
A1890 GL Mto O 4d 0% Jun-21-19 Jun-25-19
Installation of Sagrods 11d 0% May-29-19 Jun-10-19 Installation of Sagrods, 0%
A1840 GL I to K 3d 0% May-29-19 May-31-19
A1850 GL K to M 4d 0% Jun-01-19 Jun-05-19
A1860 GL Mto O 4d 0% Jun-06-19 Jun-10-19
MASONRY WORKS 15d 0% May-29-19 Jun-17-19 May-29-19 MASONRYWORKS, 0%
CHB LAYING 10d 0% May-29-19 Jun-08-19 May-29-19 CHB LAYING, 68%
Perimeter 10d 0% May-29-19 Jun-08-19 May-29-19 Perimeter, 68%
A1000 GL I to L 10d 88% May-29-19 Jun-08-19 May-29-19 88%
A1010 GL Lto O 10d 68% May-29-19 Jun-08-19 May-29-19 68%
Interior 10d 0% May-29-19 Jun-08-19 May-29-19 Interior,80%
A1030 GL I to L 10d 80% May-29-19 Jun-08-19 May-29-19 80%
A1040 GL Lto N 10d 84% May-29-19 Jun-08-19 May-29-19 84%
Lintel Beams and Stiffener Columns 12d 0% Jun-01-19 Jun-17-19 Lintel Beams and Stiffener Columns, 0%
Perimeter 8d 0% Jun-01-19 Jun-11-19 Perimeter, 0%
A1050 GL I to L 4d 0% Jun-06-19 Jun-11-19
A1060 GL Lto O 4d 0% Jun-01-19 Jun-06-19
Interior 4d 0% Jun-11-19 Jun-17-19 Interior,0%
A1070 GL I to L 2d 0% Jun-11-19 Jun-14-19
A1080 GL Lto O 2d 0% Jun-14-19 Jun-17-19
Plastering 6d 0% May-30-19 Jun-06-19 May-30-19 Plastering, 0%
Interior 4d 0% May-30-19 Jun-04-19 May-30-19 Interior,36.36%
A1090 GL I to L 4d 40% May-31-19 Jun-04-19 May-31-19 40%
A1100 GL Lto O 4d 40% May-30-19 Jun-04-19 May-30-19 40%
Perimeter 6d 0% May-30-19 Jun-06-19 Perimeter, 0%
A1110 GL I to L 4d 0% May-30-19 Jun-04-19
A1120 GL Lto O 4d 0% Jun-01-19 Jun-06-19
ARCHITECTURAL WORKS 29d 0% May-29-19 Jul-03-19 Jun-05-19 ARCHITECTURALWORKS, 30.82%
Tinnery Works 29d 0% May-29-19 Jul-03-19 Jun-05-19 Tinnery Works, 30.82%
Roofing Installation (GL 1- 6) 24d 0% May-31-19 Jun-29-19 Jun-05-19 Roofing Installation (GL1- 6), 63.45%
A1420 GL I to K 3d 10% Jun-26-19 Jun-29-19 Jun-05-19
A1430 GL K to M 3d 0% May-31-19 Jun-04-19
A1440 GL Mto O 3d 0% Jun-04-19 Jun-07-19
Roofing Installation (GL 6-11) 29d 0% May-29-19 Jul-03-19 Jun-06-19 Roofing Installation (GL6-11), 70.21%
A1350 GL I to K 3d 10% Jun-29-19 Jul-03-19 Jun-06-19
A1370 GL K to M 3d 0% Jun-04-19 Jun-07-19
A1380 GL Mto O 3d 0% May-29-19 May-31-19
Metal Wall Cladding 15d 0% Jun-04-19 Jun-22-19 Metal Wall Cladding, 0%
A1450 GL 1, GL I to O 5d 0% Jun-04-19 Jun-10-19
A1460 GL O 5d 0% Jun-10-19 Jun-17-19
A1470 GL 11, GL I to O 5d 0% Jun-17-19 Jun-22-19
Painting Works 4d 0% Jun-03-19 Jun-06-19 Painting Works, 0%
A1360 Dwarf Wall: Surface Preparation 2d 0% Jun-03-19 Jun-05-19
A1390 Dwarf Wall: Epoxy PrimerApplication 2d 0% Jun-03-19 Jun-05-19
A1400 Dwarf Wall: 1st Coat Application 2d 0% Jun-03-19 Jun-04-19

IMPORTANT NOTES
Actual Level of Effort Summary Page 1
Actual Work Uncontrolled Factors that may cause delays:
Remaining Work
Critical Remaining Work 1. Climate Change (Rainy Season)
Milestone
2. Safety
% Complete
Holcim Catch Up Plan Rev 1.2
Activity ID Activity Name Original Performance % BL Project Start BL Project Finish Actual Start Actual Finish Qtr 2, 2019 Qtr 3, 2019
Duration Complete
Jun Jul
A1410 Dwarf Wall: 2nd Coat Application 2d 0% Jun-03-19 Jun-04-19
A1480 Flooring: Epoxy Paint Application 2d 0% Jun-05-19 Jun-06-19
Hardwares & Accesories 6d 0% Jun-07-19 Jun-14-19 Hardwares & Accesories, 0%
A1490 Sliding Doors Installation 6d 0% Jun-07-19 Jun-14-19
MCC ROOM 3d 0% May-29-19 May-31-19 May-29-19 MCC ROOM, 70%
A1740 CHB Perimeter Laying 3d 70% May-29-19 May-31-19 May-29-19 70%
CONVEYOR GALLERY 9d 0% May-29-19 Jun-08-19 May-01-19 CONVEYOR GALLERY, 0%

Structural Works 6d 0% May-29-19 Jun-04-19 May-01-19 Structural Works, 45%


A1520 Gallert Structural Frame: Erection of Rigid Frames &Accesories 2d 100% May-29-19 May-30-19 May-01-19 May-15-19
A1530 Gallert Structural Frame: Checkered Plate Installation 4d 100% May-29-19 Jun-01-19 May-15-19 Jun-18-19 100%
A1540 Roofing: Purlins Laying 5d 100% May-29-19 Jun-03-19 May-20-19 Jun-02-19 100%
A1550 Roofing: Sagrod % Cross Bracing Installation 6d 100% May-29-19 Jun-04-19 May-29-19 Jun-04-19 100%
A1560 Wall Framing: Side Railing/ Girt Installation 6d 45% May-29-19 Jun-04-19 May-29-19 45%
Architectural Works 9d 0% May-29-19 Jun-08-19 May-29-19 Architectural Works, 0%
A1510 Roofing Installation 6d 90% May-29-19 Jun-04-19 May-29-19 90%
A1570 Wall Cladding Installation 6d 0% Jun-01-19 Jun-08-19
STREET LIGHTING FOUNDATIONS 18d 0% May-29-19 Jun-19-19 STREET LIGHTING FOUNDATIONS, 0%
A1680 Foundation Excavation 1d 0% May-29-19 May-29-19
A1690 Reinforcement & Form Fabrication 6d 0% May-30-19 Jun-05-19
A1700 Reinforcement & Form Installation 6d 0% Jun-06-19 Jun-13-19
A1710 Gravel Bedding 2d 0% Jun-14-19 Jun-15-19
A1720 Concreting & Curing 2d 0% Jun-17-19 Jun-18-19
A1730 Structure Backfilling 1d 0% Jun-19-19 Jun-19-19
ROADS & CURBS 4d 0% Jun-06-19 Jun-10-19 May-30-19 ROADS & CURBS, 0%
A1600 Line and Grading 2d 100% Jun-06-19 Jun-07-19 May-30-19 May-31-19 100%
A1610 Gravel Bedding Base Course 2d 100% Jun-06-19 Jun-07-19 Jun-02-19 Jun-03-19 100%
A1640 Concreting (1st Phase) 2d 0% Jun-06-19 Jun-07-19
A1670 Concreting (2nd Phase) 2d 0% Jun-08-19 Jun-10-19
Punchlisting/Turnover 15d 0% Jun-07-19 Jun-25-19 Punchlisting/Turnover, 0%
A1750 Structural Punchlist 2d 0% Jun-07-19 Jun-10-19
A1760 Architectural Punchlist 3d 0% Jun-15-19 Jun-18-19
A1780 Plumbing Punchlist 3d 0% Jun-19-19 Jun-21-19
A1800 Project Turnover 3d 0% Jun-22-19 Jun-25-19

IMPORTANT NOTES
Actual Level of Effort Summary Page 2
Actual Work Uncontrolled Factors that may cause delays:
Remaining Work
Critical Remaining Work 1. Climate Change (Rainy Season)
Milestone
2. Safety
% Complete