2 Mindtree - RWH Calculations1

This document contains calculations for rainwater harvesting at the Mindtree campus in Bangalore, India. It lists various surfaces on the property and their areas, runoff coefficients, and estimated monthly rainfall. It then calculates the potential rainwater harvest from the roof and non-roof areas for harvesting 25%, 50%, and 75% of the runoff. The maximum potential harvest is estimated at 68 cubic meters from the roof and 56 cubic meters from the non-roof areas. Currently, 59 cubic meters is being harvested from the roof, accounting for 92.75% of the potential. Rainfall data from 2010-2014 is also presented.

Uploaded by

Pranita Randive
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
78 views3 pages

2 Mindtree - RWH Calculations1

This document contains calculations for rainwater harvesting at the Mindtree campus in Bangalore, India. It lists various surfaces on the property and their areas, runoff coefficients, and estimated monthly rainfall. It then calculates the potential rainwater harvest from the roof and non-roof areas for harvesting 25%, 50%, and 75% of the runoff. The maximum potential harvest is estimated at 68 cubic meters from the roof and 56 cubic meters from the non-roof areas. Currently, 59 cubic meters is being harvested from the roof, accounting for 92.75% of the potential. Rainfall data from 2010-2014 is also presented.

Uploaded by

Pranita Randive
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd

Rainwater Harvesting Calculations_Mindtree, Bangalore

S.No Surface Type (sqmt.) Area in Runoff Rainfall in Cu.m.


Sq.m Coefficient m
1 Hardscape Area 3803.55 0.95 0.0123 44.44
2 Grass paver on ground 1279.94 0.50 0.0123 7.87
3 Turf area on Ground 147.24 0.25 0.0123 0.45
4 Landscape Area (shrubs, trees) on Ground 1636.27 0.20 0.0123 4.03
5 Roof Area 5770 0.95 0.0123 67.42
6 Roof garden at 3rd floor level 170 0.30 0.0123 0.63
7 Total Site Area of Mindtree campus 12807

Non-Roof Storm Water Harvesting System 25%(cum) 50%(cum) 75% (cum)


Total Required RWH in cu.m. (1+2+3+4) 56.79 14.20 28.40 42.60
8
Quantity recharged in Hoodi lake in cu.m. 56.79

Roof Storm Water Harvesting System 25%(cum) 50%(cum) 75% (cum)


Total Required RWH in cu.m. (5+6) 68.05 17.01 34.02 51.04
9 Provided RWH Tank capacity in cu.m. 59
Total Rainwater Harvested
Percentage of rain water harvested in the 92.75%
10
project
Place: Bangalore, Karnataka
Source - IMD Website Source - World weather online
Peak rainfall
Years Peak month rainfall in Max. no. of rainy days
Month
a year (mm) in month
2010 November 166.8 9
2011 August 237.5 23
2012 August 130.5 23
2013 September 249.3 18
2014 October 247.3 19
Avg for 5 years
Per Day Rainfall as per requirement (mm)
Rainfall in m
arnataka

Rainfall per day (Considering max.


rainy days of the month)

18.5
10.3
5.7
13.9
13.0
12.3
12.30
0.0123