SATIP-P-104-10 Rev 7 Final

This document is a typical inspection plan for high voltage cable projects at Saudi Aramco. It outlines 4 project phases: 1) Document Review, 2) Receiving Inspection, 3) Installation, and 4) Testing. Each phase contains specific tasks or activities to be inspected, the applicable quality procedures and records, and responsibilities for inspections by Saudi Aramco and contractors. Inspections include visual checks of cable storage, pulling, laying, dressing, identification, termination, and warning device installation, as well as material receiving and continuity/insulation testing.

Uploaded by

HatemS.MashaGbeh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (1 vote)
764 views2 pages

SATIP-P-104-10 Rev 7 Final

This document is a typical inspection plan for high voltage cable projects at Saudi Aramco. It outlines 4 project phases: 1) Document Review, 2) Receiving Inspection, 3) Installation, and 4) Testing. Each phase contains specific tasks or activities to be inspected, the applicable quality procedures and records, and responsibilities for inspections by Saudi Aramco and contractors. Inspections include visual checks of cable storage, pulling, laying, dressing, identification, termination, and warning device installation, as well as material receiving and continuity/insulation testing.

Uploaded by

HatemS.MashaGbeh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
  • Document Review: This section outlines the inspection and review process for cable termination and splicing records as part of the overall inspection plan.
  • Receiving Inspection: Details the receiving inspection procedures for cable installations, with reference to specific standards and regulations.
  • Installation: Covers the installation protocols including cable laying and equipment setups, ensuring compliance with installation standards.
  • Pre-Commissioning: Pre-commissioning checks focusing on cable continuity and insulation resistance tests to ensure readiness for commissioning.

SAUDI ARAMCO ID/PID FORM REV 1 - 010109(Standards Cutoff-March 2013) Rev 7 31-Mar-13

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

High Voltage (35.001 kV to 69 kV) Cable SATIP-P-104-10 30-Apr-13 Electrical


PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

1.0 DOCUMENT REVIEW

Cable Termination and Splicing


To be reviewed and approved prior to HV electrical work
1.1 Special Work Procedure SAIC-P-3215 SAIC-P-3215 RH RH at job site
Document Review

Cable Splicer Certification and Job Clearance Cards (JCC's) to be issued prior to
1.2
Project Job Clearance Cards
SAIC-P-3215 SAIC-P-3215 RH RH commencement of HV cable termination work.

Vendor Installation Manual- To be reviewed and approved prior to electrical work at


1.3
Cable Laying Method
See Remarks See Remarks RH RH job site
RECEIVING
2.0
INSPECTION
Cable Storage, Handling, and
2.1 Preservation SAIC-P-3201 SAIC-P-3201 H W Weekly Inspection by Contractor QC
Visual Inspection

Cable Material Receiving


2.2
Visual Inspection
SAIC-P-3216 SAIC-P-3216 H H

Continuity and Insulation Continuity (Volt-Ohm Meter) and Insulation (Megger)


2.3
Testing (On Cable Reel)
SATR-P-3211 SATR-P-3211 H W Testing.

Cable accessories include cable pulling lubricant, hot and


HV Cable Accessories cold shrink insulation tubing; electrical tape; cable straps
2.4 Material Receiving SAIC-P-3217 SAIC-P-3217 H W and ties; cable markers, crimp wire connectors; HV cable
Visual Inspection termination kits; bulk electrical nuts, bolts and washers;
crimping tools & dies.

3.0 INSTALLATION

Direct Buried
Cable Trench See SATIP-P-104-07 Below Grade Conduit and Duct
3.1
Visual Inspection
SAIC-P-3333 SAIC-P-3333 H H Bank.
(Before Cable Laying)
Cable laying method shall be in compliance with
Cable Pulling
3.2
Visual Inspection
SAIC-P-3218 SAIC-P-3218 H W manufacturer's instructions.
See also SATIP-P-111-01 Grounding and Bonding
Below Grade Cable Laying
SA PID hold point for all direct buried HV cables prior to
3.3 Visual Inspection For HV Cable, SAIC-P-3218 SAIC-P-3218 H H backfilling of cable.
Identification, and Backfilling

Page 1 of 2
SAUDI ARAMCO ID/PID FORM REV 1 - 010109(Standards Cutoff-March 2013) Rev 7 31-Mar-13

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

High Voltage (35.001 kV to 69 kV) Cable SATIP-P-104-10 30-Apr-13 Electrical


PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

Below Grade
3.4 Warning Device Installation SAIC-P-3333 SAIC-P-3333 H W
Visual Inspection
Cable dressing and termination work shall not proceed
until cable route and cable dressing in raceway (tray or
Cable Dressing, Cable Identification, and
3.5
Termination Visual Inspection
SAIC-P-3218 SAIC-P-3218 H H trench) has been inspected.
SA PID shall be notified on start of this activity for each
HV circuit.

4.0 PRE-COMMISSIONING

Cable Continuity
Continuity (Volt-Ohm Meter) and
4.1 and Insulation Testing SATR-P-3212 SATR-P-3212 H W Insulation (Megger) Test.
(Installed Cable)
Hi-Pot cable insulation and jacket test in accordance with
HV High-Potential cable manufacturer's instructions. If direct buried,
4.2
Withstand Testing
SATR-P-3214 SATR-P-3214 H H perform conductor insulation test before backfilling, and
jacket test after backfilling.
Cable Termination
4.3
Torque Testing
SATR-P-3213 SATR-P-3213 H W Hydraulic and mechanical crimping / bolting

Final Visual Inspection


4.4
(before energization certificate)
SAIC-P-3218 EIL H H Hold Point for Energization of Each HV Circuit.

GENERAL NOTES

The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust the
1
levels of Saudi Aramco participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization
3
representative is not present.

4 Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in attendance.

5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.

LEGEND
H Hold Point for QC Inspection/ Test R Review of Documents
W Witness Inspection/Test RH Review and Approval of Documents
S Surveillance I 100% Contractor Inspection

Page 2 of 2