ODC Projects - Weekly Meeting - Action Register 24-Oct-23 (Latest)

1. The document lists 11 projects with required actions and target dates to expedite activities at various sites and coastal locations. 2. Key actions include expediting the fabrication and delivery of materials, mobilizing vendors and crews, completing punch points and check sheets, and starting up equipment by targeted dates. 3. Dates listed for completing actions range from October 2023 to February 2024.

Uploaded by

rashidrushdi44
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
81 views30 pages

ODC Projects - Weekly Meeting - Action Register 24-Oct-23 (Latest)

1. The document lists 11 projects with required actions and target dates to expedite activities at various sites and coastal locations. 2. Key actions include expediting the fabrication and delivery of materials, mobilizing vendors and crews, completing punch points and check sheets, and starting up equipment by targeted dates. 3. Dates listed for completing actions range from October 2023 to February 2024.

Uploaded by

rashidrushdi44
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 30

ODC Projects_Marmul_Action Register

S. No. Project/Discp. Action Site /Coastal Target/ETA Open/


Date Close

Crossover & RV platform Fabrication need to Expedite Coastal 2023-10-30 Open

1 Amjad

1000123586
Solar panel vendor mobilization along with material (After RTU panel delivery) Costal 2023-10-30

Confirmation required for pipeline laying under 132 KV line 25-Oct-23


Costal Open
30-Oct-23

Delivery of fabricated spool to be expedited Costal xx Open

RTU Panel (ETA - 30-Oct-23), Wi-Max , Level transmitter (ETA - 7-Dec-23) , PT (ETA -
Coastal 2023-10-30 Open
30-Oct-23) & PG, RV

Required 2 nos of Mechanical crew for MSV-01/02 Site 2023-10-28 Open


MSV onplot Spool Fabrication delivery to be expedited Costal 2023-10-31 Open

Del. Of CI Skid to be expedited ETA. Costal 2023-10-31 Open

CMFM - ETA 27-Nov-23


Costal 2023-12-30 Open
Coiolis Meter -ETA - 30-Dec-23

Additional 1 no Internal Clamp Required


site 2023-10-30 Open

30-Oct-23 (12")
Required PE Liner Costal Open
10-Nov-23 (14")

2 Dihab Infill
* Expedite to start the 12" Jumbover Line (Mechanical) 29-Oct-23
site Open
* RDX Hammering & Excavation (Civil) 26-Oct-23

Need to Expedite MSV's Ball valves further to contiune work front in On-Plot Costal 2023-11-09 Open

Need to Expedite Existing Dhiab MSV (12" Tie-In) Ball valves Costal 2023-11-13 Open
*Civil crew to be mobilized for expediting the construction activity.
21/31- Oct-23
*1st civil crew by 5th Oct (MSV-01) Execution Stared
(MSV-03)
*2nd civil crew by 15Oct (MSV-03) (Currently Crew Allocated to GSR Punchlist) site Open
31-Oct-23 (MSV-
* 3rd civil crew by 15Oct (MSV-02)
02)
*4th Civil crew by Sub con. (ASA drawing available) Execution Stared
2 GNR
Pipeline AFC Drawings not yet Received & Re-Engineering Due to MSV orientation 15-Oct-23
Coastal Open
onplot piping drawing to be issued. 31-Oct-23

SOGL & MOL Crossing - Preliminary NOC detailed to be Updated Coastal 31-Oct-23 Open

Expedite to Mobilize OHL Subcontract to Site Coastal 4-Nov-23 Open

28-Oct-23
PL-05 HT to be expedite Site Open
6-Nov-23
3 GSR 30-Oct-23 (SS)
Final HT to carried out prior to External insulation (G-Stn) Site 1-Nov-23 (CS) Open
2-Nov-23 (GRE)

Outstanding material list to be identified and shared with ATNM costal team. Site 28-Dec-23 Open

4 Haima West

On plot spool fabrication to be expedited from Mispah site / Coastal 8-Feb-24 Open
15-Oct-23
5 Marmul North West PO to be released for Mono rail (3 Nos.) Coastal Open
30-Oct-23

GRE drain line fouling with GSR Project. RV pit. (Engineering Team Required) Costal 27-Oct-23 Open
6 MPFM
Required Mechanical Crew (1no) Site Open

Barrier installation to be finish for QRP+ QQ+ QIF2 & QIF2 Pipe Supports Coastal 30-Oct-23 Open

7 Qaharir Rationalization Balance 29 nos Punchpoint Completion to be expedited Site 30-Oct-23 Open

Balance Punch Point (31 nos) closeout need to be Expedite Site 30-Oct-23 Open

WI- Non-Availability Manifold CS Fittings :-1501 Nos Fittings affecting 398 Nos
Spool fabrication- Which need to be send for Roto post fabrication) as per PE Coastal 7-Nov-23 Open
Commitment It will be Delivered on First Week of Nov 23
8 Qata Infill PH2
Required Civil Drawings for Foundation MG 48- 6" Header MSV-16 to Existing MSV-
Coastal 23-Oct-23 Open
2/6 (Support Tag - STLSG6/SL6/SL6A/SLG6/STL6A/STL6)

8-Oct-23
Z6 notification & RV Calibration balance Site Open
22-Oct-23

9 Qata Qarmous (North & South Manifold/ Vendor to be Mobilized by 8.10.2023


IA- Atlas Copco
PLC Vendor (Mobilized) 12-Oct-23
Coastal Open
EMF-FCV- Emersion Required 25-Oct-23

A-check sheets closeout to be expedited, 94% Site Open

Expedite to start Transformer Energizaion (South Manifold) Site 19-Oct-23 Open


10 Rahab South West Costal 4-Jan-24 Open
Delivery of Corolis & EMFM to be expedited

11 Rahab Wider i9 Delivery of onplot material is to be expedited. Costal 28-Dec-23 Open

RV calibration & Installation (ETA Oct-23)+ CMFM (ETA Feb-24) + WCM (ETA Oct-
Costal 1-Jan-24 Open
23) + GWR LT (ETA Jan-24) (MSV-01/02)
RV calibration & Installation (ETA Oct-23)+ CMFM (ETA 15-Feb-24) + WCM (ETA
12 Thamoud Infill Costal 15-Feb-24 Open
Oct-23) + GWR LT (ETA Jan-24) (MSV-03)
22-Oct-23
MC Line Walk need to Expedite Site Open
27-Oct-23
21-Oct-23
PE Fusion Crew Required (Plan to start based on FDN Backfilling Progress status) Site Open
31-Oct-23

11-Oct-23 (MSV-
Structural support fabricatrion status to be expedited (MSV-01/02) 01)
Costal Open
Cross over Platform Fabrication to be expedite 31-Oct-23 (MSV-
02)

13 Thuleilat NE

Fbarication status for onplot MSV spools & Expedite the Fabricated material to sie. Costal 15-Nov-23 Open

18-Oct-23
New tarmac road RDX crossing lowering to expedited Site Open
10-Oct-23
ITR status for all the project to be updated.
Common Site Open
Punch point status to be updated
Updated as on : 24-Oct-23
PO # Project Name 0 M130 date
Remarks

Material partially recived at site (90% Received)


MSV-01
* 62/62 - Pipe Support reach to site and Installation done (52 nos)
* Crossover & RV Platform Fabricated Material Expedite to Site by 5-Nov-23
(Fabrication completed & Painting In-Progress)
MSV-02
* 63/63 - Pipe Support reach to site and Installation done (23 nos)
* Crossover & RV Platform Fabricated Material Expedite to Site by 5-Nov-23

4500936235 Amjad Project 21-Feb-24 21-Apr-24

* Based on RTU Delivery (25-Oct-23 @ Majan)

Engineering team confirmed to procced as per drawings (Above ground). Confirmation


required from UIE Team (Nimr)

MSV-01:-
* 28/39 SS Spool Fabrication Completed in Misfah,22 nos Fabricated spool recived from
Mispah to Site
MSV-02:-
* 23/33 SS Spool Fabrication Completed in Misfah,16 nos Fabricated spool recived from
Mispah to Site
* Githu (Fabrication focal Point) to be follow up and Expedite

As per Base line Plan below mentioned Misc.items need to expedite,


* RTU Panel & Wi-Max - 30-Dec-22
* Level Transmitter - 31-May-23
* PH-Rajesh Singh Plan to Mobilize Site to 28-Oct-23 (MSV-01)
* PH-AP Singh Plan to Mobilize Site to 28-Oct-23 (MSV-02)
* MSV-01/02/03
- 180/180 nos spool Fabrication Completed. 143 nos fabricated spool Received to site
from Misfah.
- As per Revised baseline plan MSV-01/02/03 Completion by Jan-2023
- As per Revised baseline plan off-plot Completion by May-2023

* As per baseline plan CI Skid Delivery by 25-Jun-2023


* As per MTS CI Skid Delivery by 30-Oct-23

* As per baseline plan WCM Delivered.


* As per baseline plan Bulk Flow Meter Delivery by 28-Sep-2023
* As per baseline plan Corolis Meter Delivery by 30-Dec-2023

* 1/2 Welding Crews Allocated for 14" Pipe line (Once Additional Internal clamp reach
to site,plan to mobilize 1 no welding crew to site)

* 0/1 Welding Crew Planned for Pre-Fabrication Works (RDX/Wadi)

* As per baseline plan PE - Fusion activity start by 11-Jun-2023


* 12" PE Liner Yet to be Dispatch - 30-Oct-23
* 14" PE Liner 9KM Fabrication Completed, 1st batch delivered to site by10-Nov-23

* Waiting for Fabricated Bend from Nimr. Plan to shift to site by 28-Oct-23. Once shifted 4500938048 Dhiab Project 45329 45389
plan to Mobilize the PH-Irfan by 29-Oct-23 for RDX Pre-Fabrication
* RDX Hammering & Excavation Plan to start by 26-Oct-23 (Sub-SMHRAM)

VBA,DN15,CL300,FL,RB,316,316/PTFE,-29°C - 1 no
VBA,DN25,CL300,FL,RB,316,316/PTFE - 46 nos
VBA,DN50,CL150,FL,RB,CS,316/PTFE,SOUR - 1 no
VBA,DN50,CL150,FL,RB,LTCS,316/PTFE,BLTD - 1 no
VBA,DN50,CL150,FL,RB,316,316/PTFE,-29°C - 2 no
VBA,DN50,CL300,FL,FB,316,316/PTFE - 2 no
VBA,DN50,CL300,FL,RB,CS,316/PTFE,SOUR - 5 nos
VBA,DN50,CL300,FL,RB,316,316/PTFE,-29°C - 24 nos
VBA,DN80,CL150,FL,FB,CS,316/PTFE - 1 no
VBA,DN80,CL300,FL,RB,316,316/PTFE,-29°C - 8 nos
VBA,DN150,CL300,FL,RB,316,316/PTFE,-29°C - 3 nos
VBA,DN200,CL300,FL,RB,316,316/PTFE,SOUR - 2 nos
VBA,DN300,CL300,FL,RB,316,316,648mm - 2 nos
VBA,DN350,CL300,FL,RB,316,316/PTFE,SOUR - 2 nos
VBA,DN350,CL300,FL,FB,316,316/PTFE - 2 nos

* VBA,DN300,CL300,FL,RB,316,316,648mm - 3 nos
* VBA,DN50,CL300,FL,RB,316,316/PTFE,-29°C - 1 no
MML GNR
Development 9/2/2024 9/2/2024
Project

* SS Hydrotest Planned on 30-Oct-23 4500889273 GSR Project 7/30/2023 7/30/2023


* CS Hydrotest Planned on 1-Nov-23
* GRE Hydrotest Planned on 2-Nov-23

* Valves (250 nos) - 1st Slot by 22-Oct-23,2nd Slot by 10-Dec-23


* Pipeline Fittings (DN200 (4 no), DN150 (16 no), DN400 (1 no) ETA by 10-Nov-2023
* PE Liner - ETA by 8-Nov-23
* Flange (DN 15(106 no), DN100 (375 no), DN100 (46 no) - ETA by 28-Dec-23

Haima West
RMS-01 Infill
5/10/2024 7/9/2024
* 3/122 nos Fabrication Completed in Misfah Development
RMS-02 Phase 2 Project
* 0/70 nos Fabrication Completed in Misfah

* As per baseline plan RMS-01 Installation activity start by 13-Dec-2023


* As per baseline plan RMS-02 Installation activity start by 26-Dec-2023
* As per baseline plan RMS-03 Installation activity start by 3-Feb-2024
* As per baseline plan RMS-04 Installation activity start by 8-Feb-2024
MNW
Submitted the data sheet to PDO for approval and updated in the SPO
CTR approval is balance. 4500869466 Development 30-Jul-23 30-Jul-23
Project

Re-engineering required (Site Visit Done on 18-Oct-23)

Material recived, painting completed

* QRP RDX-09, QQ-28 Nos,QIF2- 10 Nos


* Ramp - 4nos
Qaharir
rationalization 30-Jul-23 30-Jul-23
4500938403
Project:-

Partially recived
Qata infill Ph-2
4500902558 28-Sep-23 27-Nov-23
Project

Open Up to week 3.
Z#6 Notification Already Raised, Z1 Notification required for Local Inspection
Notification
(MOTT has changed equipment tag, resulting delay in static inspection) All tag Given
from Site Except IA Compressor- IM Team need to take from Vendor
Clarification to be discussed with DOI Team
Qata Qarmous
Infill
30-Jul-23 30-Jul-23
development
Project

94% Completed (38 check sheets balance)

* In-Progress
* As per baseline plan Corolis Meter Delivery by 13-Dec-23 Rahab South
4500934912 2-Feb-24 2-Apr-24
* As per baseline plan EMFM Meter Delivery by 23-Jan-24 West

* As per baseline plan Piping material,Flanges & Fittings & valves to be delivered by 25-
Aug-2023
- BRF BW RED,A105,40/80,200X50 (ETA - 28-Sep-23)
- FLWN,F42,CL300,SOUR,4.8,DN150,SP-2321 (ETA - 25-Sep-23)
- FLWN,F42,CL300,SOUR,4.8,DN200,CR-3 (ETA - 25-Sep-23)
- FLWN,F52,CL300,SOUR,5.6,DN400,CR-3 (ETA - 25-Sep-23)
- FLWN,F42,CL300,SOUR,4.8,DN200,CR-3 (ETA - 25-Sep-23) Rahab Wider I9
- ELB BW,WPHY42,SOUR,90DEG,LR,4.8,DN200 (ETA - 10-Nov-23) 1-May-24 30-Jun-24
- ELB BW,WPHY42,SOUR,90DEG,LR,4.8,DN150 (ETA - 10-Nov-23) Project
- TERB,A860-WPHB2,SOUR,5.6x4.8,DN400x200 (ETA - 10-Nov-23)
- TERB,WPHY42,SOUR,4.8, DN200x150 (ETA - 10-Nov-23)
- BFB,A105N,SOUR,4.8x4.8,DN150x50 (ETA - 4-Oct-23)
- FLWN,A105, CL300,160, DN15 (ETA - 28-Dec-23)
- FLWN,F316, CL300,10S, DN100 (ETA - 28-Dec-23)
- FLWN,F316, CL300,10S, DN100 (ETA - 28-Dec-23)

* NTF Raised and need PDO Approval,ATE Raised MOC to Take out these material from
P1 Scope (Thamoud)
Thamoud Infill
4500930686 45107 45122
Development

* MSV-01
- Pipe Support Installation In-Progress (63/87 nos)

* MSV-02
- Pipe support fabrication need to Expedite (58/79 nos)

Thuleilat North
Schedule under Approval Schedule under Approval
MSV-01 East Project
* 26/67 Spool fabrication Completed in Misfah & 26 nos spool reached to site
MSV-02
* 24/67 Spool fabrication Completed in Misfah & 24 nos spool reached to site
* As per Baseline plan Spool Installation by 12-Dec-23

* Hammering Completed
* Pre-Fabrication Completed
* Excavation Completed
* Thamoud Infill - Closed
* Qaharir East - Closed
* Rahab SW - Closed
* Amjad
* Thuleilat NE
* Dhaib Infill
* GNR
* Haima West
Forecast date of completion (M110) Purpose value Brief Scope Current Plan % Current Act%

MSV-2 Nos (13.5X13.5X3.5) -


(4.5X4.5X2.5)
45403 1029712 30-Dec-99 30-Dec-99
RV Pits - 2 Nos
P/L-1--10"-20.7 Km
MSV-3 Nos
RV Pits - 2 Nos 3.5x3.5x
45389 1473462 0.6933 0.4699
P/L-1--14"-21 Km
P/L-2--12"-0.2 Km
MSV-5 Nos
MF-01 Nos
RV Pits - 3 Nos (13.5X13.5X3.5) - 75
(4.5X4.5X2.5) - 90
9/2/2024 4/22/5630 0.5273 0.353
(4.5X4.5X2.5) - 440
P/L-1--12"-7.4 Km
P/L-2--16"-12 Km
P/L-3--10"-0.5 Km

MSV - 4 Nos
RV Pits - 2 Nos -
8/15/2023 2645864 P/L-8 Nos 0.95 0.85888
F/L---08 Nos
OHL

MSV - 4 Nos
RV Pits - 4 Nos (2.6Lx2.6Bx2.6H)
5/10/2024 577708 P/L-1--08"-3.1 Km 0.548296 0.431916
P/L-2--06"-0.5 Km
P/L-3--06"-0.65 Km
MSV - 3 Nos
MF - 3 Nos
P/L-1--10"-7.90 Km P/L-6--10"-
0.64 Km
P/L-2--08"-3.80 Km P/L-7--10"-
1.25Km
20-Aug-23 3,030,455 P/L-3--08"-5.20 Km P/L-8--10"- 100.00% 90.77%
3.50 Km
P/L-4--08"-1.70 Km P/L-9--10"-
3.80 Km
P/L-5--10"-14.5 Km
FOC-35KM
OHL-3.5 KM

Station - 2 Nos
30-Sep-23 4,981,573 P/L-1--28"-25.0. Km 100.00% 93.30%
P/L-2--16"-23.5 Km

28-Sep-23 1,631,745 MF-3 75.12% 64.19%

MSV - 7 Nos
MF - 2 Nos
P/L-1--16"-7.0 Km
30-Aug-23 2,475,000 100.00% 92.05%
P/L-2--12"-4.0 Km
BH-1--12"-0.4 Km
BH-2--12"-0.4 Km
MF-2 Nos
2-Feb-24 776,669 56.84% 49.81%
P/L-1-08"-22 Km

MSV-3 Nos
RV Pits - 2 Nos
30-Jun-24 100,000 28.80% 27.82%
P/L-1--08"-1.1 Km
P/L-2--08"-3.4 Km

MSV-3 Nos
45161 204250 RV Pits - 2 Nos 0.86404 0.481447
P/L-1--08"-1.30 Km

MSV-2 Nos
RV Pits - 2 Nos
May-23 TBA 0.30168737584 0.304149
P/L-1--08"-6.9 Km
P/L-2--06"-0.2 Km
Project Permit Applicant
Project Engineer Works
Engineer
ATE + Ph No + Mail ID Cordinator Civil Mech Elec
PDO * Ref Ind

Anfal
Srinivas/
[email protected] Eby Thomas Mohsin Vishnu Deepak
Short Code - 96446263
Al Shekaili,
Amor Khalid DAR3
Srinivas/
[email protected] khalid.ksa.alshe Akilan Meeraj Vishnu
Deepak
Short Code - 808 [email protected]
m
Mohammad Ibrahim
Srinivas/
[email protected] Eby Thomas Meeraj Vishnu
Deepak
Short Code - 726

Mohammad Ibrahim
Srinivas /
[email protected] Sanjeev Yadav Mohsin Vishnu
Deepak
Short Code - 726

Syed,
Muhammad
Sita Rama Rao
DAR2 Srinivas /
[email protected] Sanjeev Yadav Mohsin Vishnu
<Muhammad.S Deepak
Short Code - 5507
[email protected]
o.om>
Ismaili, Siham
Fatma
DAK5 Srinivas /
[email protected] Eby Thomas Meeraj Vishnu
<Siham.SI.Ismail Deepak
Short Code - 5026
[email protected]>

Battashi, Amal
Senthilvel DAR3
Srinivas
[email protected] <Amal.AA.Batta Manish Sailor Mohsin Vishnu
Deepak
Short Code - 1155. [email protected]
>

Battashi, Amal
Anfal DAR3
Srinivas
[email protected] <Amal.AA.Batta Anfal Mohsin Vishnu
Deepak
Short Code - 96446263 [email protected]
>

Battashi, Amal
Senthilvel DAR3
Srinivas
[email protected] <Amal.AA.Batta Manish Sailor Mohsin Vishnu
Deepak
Short Code - 1155. [email protected]
>
Fatma
Srinivas
[email protected] Manykandan Meeraj Vishnu
Deepak
Short Code - 5026

Syed Ahmed
Srinivas
[email protected] Ved Sharma Meeraj Vishnu
Deepak
Short Code - 1572

Syed,
Muhammad
Anfal
DAR2 Srinivas
[email protected] Ved Sharma Mohsin Vishnu
<Muhammad.S Deepak
Short Code - 96446263
[email protected]
o.om>

Fatma
Srinivas
[email protected] Manykandan Mohsin Vishnu
Deepak
Short Code - 5026
remarks
. second welding crew to be released from GSR project and alocate them in Dhiab
project urgently We need additional 5 Nos of TIG machine alone with 6 Nos DG set up
for the on coming crew.
. Bending Activities delayd, to start Bending Activities immediately, continious
requirement of crane for bending activities
. Mechnical On plot crew to mobilize immediately and start the work.
. Electrical crew required
.

Note: the on plot activities to be commissioned by end of December 2023

Need to Expedite MSV's Ball valves further to contiune work front in On-
Plot (costal) TD 9/11/2023
Need to Expedite Existing Dhiab MSV (12" Tie-In) Ball valves (costal) TD
13/11/2023
Saudia spools not came yet / date to come on 15th september
QAHARIR RATIONALIZATION PROJECT

A B
DISCIPLINE
TOTAL COMPLETED BALANCE TOTAL COMPLETED BALANCE
CIVIL 5 5 0 116 96 20
MECHANICAL - - - 95 90 5
ELECTRICAL 6 6 0 58 54 4
INSTRUMENT 2 2 0 37 35 2
TOTAL 13 13 0 306 275 31

QATA INFILL PH-2 PROJECT

A B
DISCIPLINE
TOTAL COMPLETED BALANCE TOTAL COMPLETED BALANCE
CIVIL - - - 6 0 6
PIPING - - - 5 1 4
INSTRUMENT - - - 2 2 0
TOTAL - - - 13 3 10

MARMUL NORTH WEST PH-2

A B
DISCIPLINE
TOTAL COMPLETED BALANCE TOTAL COMPLETED BALANCE
CIVIL 7 7 0 180 155 25
MECHANICAL 14 14 0 256 223 33
ELECTRICAL - - - 59 59 0
INSTRUMENT 10 10 0 52 50 2
OPERATION - - - 1 0 1
TOTAL 31 31 0 548 487 61

OWL 1 0 1

QATA QARMOUS INFILL DEVELOPMENT PROJECT

A B
DISCIPLINE
TOTAL COMPLETED BALANCE TOTAL COMPLETED BALANCE
CIVIL 11 11 0 191 116 75
MECHANICAL 8 8 0 186 173 13
ELECTRICAL 8 8 0 65 55 10
INSTRUMENT - - - 16 10 6
TELECOM - - - 13 0 6
TOTAL 27 27 0 471 354 117
MML GSR PROJECT
MML GSR PROJECT-PUNCH LIST

A B DISCIPLINE
DISCIPLINE
TOTAL COMPLETED BALANCE TOTAL COMPLETED BALANCE
CIVIL - - - 61 30 31 CIVIL
MECHANICAL - - - 96 49 47 MECHANICAL
ELECTRICAL - - - 149 110 39 ELECTRICAL
INSTRUMENT 1 1 0 10 6 4 INSTRUMENT
TOTAL 1 1 0 316 195 121 TOTAL
MML GSR PROJECT-MSV-A-25001,25002,PL-1,2,4 & PL-8
PUNCH LIST

A B
TOTAL COMPLETED BALANCE TOTAL COMPLETED BALANCE
- - - 54 30 24
- - - 50 31 19
- - - 38 25 13
1 1 0 10 6 4
1 1 0 152 92 60