ODC Projects - Weekly Meeting - Action Register 24-Oct-23 (Latest)
ODC Projects - Weekly Meeting - Action Register 24-Oct-23 (Latest)
1 Amjad
1000123586
Solar panel vendor mobilization along with material (After RTU panel delivery) Costal 2023-10-30
RTU Panel (ETA - 30-Oct-23), Wi-Max , Level transmitter (ETA - 7-Dec-23) , PT (ETA -
Coastal 2023-10-30 Open
30-Oct-23) & PG, RV
30-Oct-23 (12")
Required PE Liner Costal Open
10-Nov-23 (14")
2 Dihab Infill
* Expedite to start the 12" Jumbover Line (Mechanical) 29-Oct-23
site Open
* RDX Hammering & Excavation (Civil) 26-Oct-23
Need to Expedite MSV's Ball valves further to contiune work front in On-Plot Costal 2023-11-09 Open
Need to Expedite Existing Dhiab MSV (12" Tie-In) Ball valves Costal 2023-11-13 Open
*Civil crew to be mobilized for expediting the construction activity.
21/31- Oct-23
*1st civil crew by 5th Oct (MSV-01) Execution Stared
(MSV-03)
*2nd civil crew by 15Oct (MSV-03) (Currently Crew Allocated to GSR Punchlist) site Open
31-Oct-23 (MSV-
* 3rd civil crew by 15Oct (MSV-02)
02)
*4th Civil crew by Sub con. (ASA drawing available) Execution Stared
2 GNR
Pipeline AFC Drawings not yet Received & Re-Engineering Due to MSV orientation 15-Oct-23
Coastal Open
onplot piping drawing to be issued. 31-Oct-23
SOGL & MOL Crossing - Preliminary NOC detailed to be Updated Coastal 31-Oct-23 Open
28-Oct-23
PL-05 HT to be expedite Site Open
6-Nov-23
3 GSR 30-Oct-23 (SS)
Final HT to carried out prior to External insulation (G-Stn) Site 1-Nov-23 (CS) Open
2-Nov-23 (GRE)
Outstanding material list to be identified and shared with ATNM costal team. Site 28-Dec-23 Open
4 Haima West
On plot spool fabrication to be expedited from Mispah site / Coastal 8-Feb-24 Open
15-Oct-23
5 Marmul North West PO to be released for Mono rail (3 Nos.) Coastal Open
30-Oct-23
GRE drain line fouling with GSR Project. RV pit. (Engineering Team Required) Costal 27-Oct-23 Open
6 MPFM
Required Mechanical Crew (1no) Site Open
Barrier installation to be finish for QRP+ QQ+ QIF2 & QIF2 Pipe Supports Coastal 30-Oct-23 Open
7 Qaharir Rationalization Balance 29 nos Punchpoint Completion to be expedited Site 30-Oct-23 Open
Balance Punch Point (31 nos) closeout need to be Expedite Site 30-Oct-23 Open
WI- Non-Availability Manifold CS Fittings :-1501 Nos Fittings affecting 398 Nos
Spool fabrication- Which need to be send for Roto post fabrication) as per PE Coastal 7-Nov-23 Open
Commitment It will be Delivered on First Week of Nov 23
8 Qata Infill PH2
Required Civil Drawings for Foundation MG 48- 6" Header MSV-16 to Existing MSV-
Coastal 23-Oct-23 Open
2/6 (Support Tag - STLSG6/SL6/SL6A/SLG6/STL6A/STL6)
8-Oct-23
Z6 notification & RV Calibration balance Site Open
22-Oct-23
RV calibration & Installation (ETA Oct-23)+ CMFM (ETA Feb-24) + WCM (ETA Oct-
Costal 1-Jan-24 Open
23) + GWR LT (ETA Jan-24) (MSV-01/02)
RV calibration & Installation (ETA Oct-23)+ CMFM (ETA 15-Feb-24) + WCM (ETA
12 Thamoud Infill Costal 15-Feb-24 Open
Oct-23) + GWR LT (ETA Jan-24) (MSV-03)
22-Oct-23
MC Line Walk need to Expedite Site Open
27-Oct-23
21-Oct-23
PE Fusion Crew Required (Plan to start based on FDN Backfilling Progress status) Site Open
31-Oct-23
11-Oct-23 (MSV-
Structural support fabricatrion status to be expedited (MSV-01/02) 01)
Costal Open
Cross over Platform Fabrication to be expedite 31-Oct-23 (MSV-
02)
13 Thuleilat NE
Fbarication status for onplot MSV spools & Expedite the Fabricated material to sie. Costal 15-Nov-23 Open
18-Oct-23
New tarmac road RDX crossing lowering to expedited Site Open
10-Oct-23
ITR status for all the project to be updated.
Common Site Open
Punch point status to be updated
Updated as on : 24-Oct-23
PO # Project Name 0 M130 date
Remarks
MSV-01:-
* 28/39 SS Spool Fabrication Completed in Misfah,22 nos Fabricated spool recived from
Mispah to Site
MSV-02:-
* 23/33 SS Spool Fabrication Completed in Misfah,16 nos Fabricated spool recived from
Mispah to Site
* Githu (Fabrication focal Point) to be follow up and Expedite
* 1/2 Welding Crews Allocated for 14" Pipe line (Once Additional Internal clamp reach
to site,plan to mobilize 1 no welding crew to site)
* Waiting for Fabricated Bend from Nimr. Plan to shift to site by 28-Oct-23. Once shifted 4500938048 Dhiab Project 45329 45389
plan to Mobilize the PH-Irfan by 29-Oct-23 for RDX Pre-Fabrication
* RDX Hammering & Excavation Plan to start by 26-Oct-23 (Sub-SMHRAM)
VBA,DN15,CL300,FL,RB,316,316/PTFE,-29°C - 1 no
VBA,DN25,CL300,FL,RB,316,316/PTFE - 46 nos
VBA,DN50,CL150,FL,RB,CS,316/PTFE,SOUR - 1 no
VBA,DN50,CL150,FL,RB,LTCS,316/PTFE,BLTD - 1 no
VBA,DN50,CL150,FL,RB,316,316/PTFE,-29°C - 2 no
VBA,DN50,CL300,FL,FB,316,316/PTFE - 2 no
VBA,DN50,CL300,FL,RB,CS,316/PTFE,SOUR - 5 nos
VBA,DN50,CL300,FL,RB,316,316/PTFE,-29°C - 24 nos
VBA,DN80,CL150,FL,FB,CS,316/PTFE - 1 no
VBA,DN80,CL300,FL,RB,316,316/PTFE,-29°C - 8 nos
VBA,DN150,CL300,FL,RB,316,316/PTFE,-29°C - 3 nos
VBA,DN200,CL300,FL,RB,316,316/PTFE,SOUR - 2 nos
VBA,DN300,CL300,FL,RB,316,316,648mm - 2 nos
VBA,DN350,CL300,FL,RB,316,316/PTFE,SOUR - 2 nos
VBA,DN350,CL300,FL,FB,316,316/PTFE - 2 nos
* VBA,DN300,CL300,FL,RB,316,316,648mm - 3 nos
* VBA,DN50,CL300,FL,RB,316,316/PTFE,-29°C - 1 no
MML GNR
Development 9/2/2024 9/2/2024
Project
Haima West
RMS-01 Infill
5/10/2024 7/9/2024
* 3/122 nos Fabrication Completed in Misfah Development
RMS-02 Phase 2 Project
* 0/70 nos Fabrication Completed in Misfah
Partially recived
Qata infill Ph-2
4500902558 28-Sep-23 27-Nov-23
Project
Open Up to week 3.
Z#6 Notification Already Raised, Z1 Notification required for Local Inspection
Notification
(MOTT has changed equipment tag, resulting delay in static inspection) All tag Given
from Site Except IA Compressor- IM Team need to take from Vendor
Clarification to be discussed with DOI Team
Qata Qarmous
Infill
30-Jul-23 30-Jul-23
development
Project
* In-Progress
* As per baseline plan Corolis Meter Delivery by 13-Dec-23 Rahab South
4500934912 2-Feb-24 2-Apr-24
* As per baseline plan EMFM Meter Delivery by 23-Jan-24 West
* As per baseline plan Piping material,Flanges & Fittings & valves to be delivered by 25-
Aug-2023
- BRF BW RED,A105,40/80,200X50 (ETA - 28-Sep-23)
- FLWN,F42,CL300,SOUR,4.8,DN150,SP-2321 (ETA - 25-Sep-23)
- FLWN,F42,CL300,SOUR,4.8,DN200,CR-3 (ETA - 25-Sep-23)
- FLWN,F52,CL300,SOUR,5.6,DN400,CR-3 (ETA - 25-Sep-23)
- FLWN,F42,CL300,SOUR,4.8,DN200,CR-3 (ETA - 25-Sep-23) Rahab Wider I9
- ELB BW,WPHY42,SOUR,90DEG,LR,4.8,DN200 (ETA - 10-Nov-23) 1-May-24 30-Jun-24
- ELB BW,WPHY42,SOUR,90DEG,LR,4.8,DN150 (ETA - 10-Nov-23) Project
- TERB,A860-WPHB2,SOUR,5.6x4.8,DN400x200 (ETA - 10-Nov-23)
- TERB,WPHY42,SOUR,4.8, DN200x150 (ETA - 10-Nov-23)
- BFB,A105N,SOUR,4.8x4.8,DN150x50 (ETA - 4-Oct-23)
- FLWN,A105, CL300,160, DN15 (ETA - 28-Dec-23)
- FLWN,F316, CL300,10S, DN100 (ETA - 28-Dec-23)
- FLWN,F316, CL300,10S, DN100 (ETA - 28-Dec-23)
* NTF Raised and need PDO Approval,ATE Raised MOC to Take out these material from
P1 Scope (Thamoud)
Thamoud Infill
4500930686 45107 45122
Development
* MSV-01
- Pipe Support Installation In-Progress (63/87 nos)
* MSV-02
- Pipe support fabrication need to Expedite (58/79 nos)
Thuleilat North
Schedule under Approval Schedule under Approval
MSV-01 East Project
* 26/67 Spool fabrication Completed in Misfah & 26 nos spool reached to site
MSV-02
* 24/67 Spool fabrication Completed in Misfah & 24 nos spool reached to site
* As per Baseline plan Spool Installation by 12-Dec-23
* Hammering Completed
* Pre-Fabrication Completed
* Excavation Completed
* Thamoud Infill - Closed
* Qaharir East - Closed
* Rahab SW - Closed
* Amjad
* Thuleilat NE
* Dhaib Infill
* GNR
* Haima West
Forecast date of completion (M110) Purpose value Brief Scope Current Plan % Current Act%
MSV - 4 Nos
RV Pits - 2 Nos -
8/15/2023 2645864 P/L-8 Nos 0.95 0.85888
F/L---08 Nos
OHL
MSV - 4 Nos
RV Pits - 4 Nos (2.6Lx2.6Bx2.6H)
5/10/2024 577708 P/L-1--08"-3.1 Km 0.548296 0.431916
P/L-2--06"-0.5 Km
P/L-3--06"-0.65 Km
MSV - 3 Nos
MF - 3 Nos
P/L-1--10"-7.90 Km P/L-6--10"-
0.64 Km
P/L-2--08"-3.80 Km P/L-7--10"-
1.25Km
20-Aug-23 3,030,455 P/L-3--08"-5.20 Km P/L-8--10"- 100.00% 90.77%
3.50 Km
P/L-4--08"-1.70 Km P/L-9--10"-
3.80 Km
P/L-5--10"-14.5 Km
FOC-35KM
OHL-3.5 KM
Station - 2 Nos
30-Sep-23 4,981,573 P/L-1--28"-25.0. Km 100.00% 93.30%
P/L-2--16"-23.5 Km
MSV - 7 Nos
MF - 2 Nos
P/L-1--16"-7.0 Km
30-Aug-23 2,475,000 100.00% 92.05%
P/L-2--12"-4.0 Km
BH-1--12"-0.4 Km
BH-2--12"-0.4 Km
MF-2 Nos
2-Feb-24 776,669 56.84% 49.81%
P/L-1-08"-22 Km
MSV-3 Nos
RV Pits - 2 Nos
30-Jun-24 100,000 28.80% 27.82%
P/L-1--08"-1.1 Km
P/L-2--08"-3.4 Km
MSV-3 Nos
45161 204250 RV Pits - 2 Nos 0.86404 0.481447
P/L-1--08"-1.30 Km
MSV-2 Nos
RV Pits - 2 Nos
May-23 TBA 0.30168737584 0.304149
P/L-1--08"-6.9 Km
P/L-2--06"-0.2 Km
Project Permit Applicant
Project Engineer Works
Engineer
ATE + Ph No + Mail ID Cordinator Civil Mech Elec
PDO * Ref Ind
Anfal
Srinivas/
[email protected] Eby Thomas Mohsin Vishnu Deepak
Short Code - 96446263
Al Shekaili,
Amor Khalid DAR3
Srinivas/
[email protected] khalid.ksa.alshe Akilan Meeraj Vishnu
Deepak
Short Code - 808 [email protected]
m
Mohammad Ibrahim
Srinivas/
[email protected] Eby Thomas Meeraj Vishnu
Deepak
Short Code - 726
Mohammad Ibrahim
Srinivas /
[email protected] Sanjeev Yadav Mohsin Vishnu
Deepak
Short Code - 726
Syed,
Muhammad
Sita Rama Rao
DAR2 Srinivas /
[email protected] Sanjeev Yadav Mohsin Vishnu
<Muhammad.S Deepak
Short Code - 5507
[email protected]
o.om>
Ismaili, Siham
Fatma
DAK5 Srinivas /
[email protected] Eby Thomas Meeraj Vishnu
<Siham.SI.Ismail Deepak
Short Code - 5026
[email protected]>
Battashi, Amal
Senthilvel DAR3
Srinivas
[email protected] <Amal.AA.Batta Manish Sailor Mohsin Vishnu
Deepak
Short Code - 1155. [email protected]
>
Battashi, Amal
Anfal DAR3
Srinivas
[email protected] <Amal.AA.Batta Anfal Mohsin Vishnu
Deepak
Short Code - 96446263 [email protected]
>
Battashi, Amal
Senthilvel DAR3
Srinivas
[email protected] <Amal.AA.Batta Manish Sailor Mohsin Vishnu
Deepak
Short Code - 1155. [email protected]
>
Fatma
Srinivas
[email protected] Manykandan Meeraj Vishnu
Deepak
Short Code - 5026
Syed Ahmed
Srinivas
[email protected] Ved Sharma Meeraj Vishnu
Deepak
Short Code - 1572
Syed,
Muhammad
Anfal
DAR2 Srinivas
[email protected] Ved Sharma Mohsin Vishnu
<Muhammad.S Deepak
Short Code - 96446263
[email protected]
o.om>
Fatma
Srinivas
[email protected] Manykandan Mohsin Vishnu
Deepak
Short Code - 5026
remarks
. second welding crew to be released from GSR project and alocate them in Dhiab
project urgently We need additional 5 Nos of TIG machine alone with 6 Nos DG set up
for the on coming crew.
. Bending Activities delayd, to start Bending Activities immediately, continious
requirement of crane for bending activities
. Mechnical On plot crew to mobilize immediately and start the work.
. Electrical crew required
.
Need to Expedite MSV's Ball valves further to contiune work front in On-
Plot (costal) TD 9/11/2023
Need to Expedite Existing Dhiab MSV (12" Tie-In) Ball valves (costal) TD
13/11/2023
Saudia spools not came yet / date to come on 15th september
QAHARIR RATIONALIZATION PROJECT
A B
DISCIPLINE
TOTAL COMPLETED BALANCE TOTAL COMPLETED BALANCE
CIVIL 5 5 0 116 96 20
MECHANICAL - - - 95 90 5
ELECTRICAL 6 6 0 58 54 4
INSTRUMENT 2 2 0 37 35 2
TOTAL 13 13 0 306 275 31
A B
DISCIPLINE
TOTAL COMPLETED BALANCE TOTAL COMPLETED BALANCE
CIVIL - - - 6 0 6
PIPING - - - 5 1 4
INSTRUMENT - - - 2 2 0
TOTAL - - - 13 3 10
A B
DISCIPLINE
TOTAL COMPLETED BALANCE TOTAL COMPLETED BALANCE
CIVIL 7 7 0 180 155 25
MECHANICAL 14 14 0 256 223 33
ELECTRICAL - - - 59 59 0
INSTRUMENT 10 10 0 52 50 2
OPERATION - - - 1 0 1
TOTAL 31 31 0 548 487 61
OWL 1 0 1
A B
DISCIPLINE
TOTAL COMPLETED BALANCE TOTAL COMPLETED BALANCE
CIVIL 11 11 0 191 116 75
MECHANICAL 8 8 0 186 173 13
ELECTRICAL 8 8 0 65 55 10
INSTRUMENT - - - 16 10 6
TELECOM - - - 13 0 6
TOTAL 27 27 0 471 354 117
MML GSR PROJECT
MML GSR PROJECT-PUNCH LIST
A B DISCIPLINE
DISCIPLINE
TOTAL COMPLETED BALANCE TOTAL COMPLETED BALANCE
CIVIL - - - 61 30 31 CIVIL
MECHANICAL - - - 96 49 47 MECHANICAL
ELECTRICAL - - - 149 110 39 ELECTRICAL
INSTRUMENT 1 1 0 10 6 4 INSTRUMENT
TOTAL 1 1 0 316 195 121 TOTAL
MML GSR PROJECT-MSV-A-25001,25002,PL-1,2,4 & PL-8
PUNCH LIST
A B
TOTAL COMPLETED BALANCE TOTAL COMPLETED BALANCE
- - - 54 30 24
- - - 50 31 19
- - - 38 25 13
1 1 0 10 6 4
1 1 0 152 92 60