SIGMA POWERTECH LIMITED
Plot 269/A, Adamzee EPZ, Narayanganj, Dhaka
DAILY WORK PROGRESS TRACKING REPORT
Date : 06.10.2024
Today's
Sl No. Description of Work Current Status Previous % of Completion Overall Progress (% )
Progress (% )
1 All Cable trench (outside Engine hall) covering with Checker plate Pending 90%
2 Engine hall doors canopy fabrication Pending 99%
3 Boiler instrument air line fabrication Pending 33%
4 Top ventilation fan installation and ducting Pending 99%
5 Lube Oil Tank Fabrication, erection & Piping work Pending 95%
Exhaust Stack platform, Beams, checker plates, Cross bracings,
6 Pending 99%
handrails fabrication & erection and nut bolt tightening,drain line fabrication
7 CAF platform gratings, handrails and stair,drain line fabrication & erection Pending 99%
8 Exhaust duct pipe insulation & cladding Pending 96%
9 Front Ventilation fan installation,duct fabrication & erection Pending 90%
10 Auxiliary side ventilation fan installation and ducting Pending 92%
11 Exhaust duct pipe Bellows & Rupture discs installation Pending 99%
12 Cooling pipe fabrication and erection In Progress 99% 0% 99%
13 Alternator Hot air duct & Structure fabrication and erection In Progress 99% 0% 99%
14 WTP shed fabrication and erection Pending 99%
15 Compressor installation and Piping Pending 98%
16 Boiler,Feed Water Tank,Blow down tank & pipeline insulation,cladding work In Progress 41% 9% 50%
17 Engine hall Overhead Crane delivery & Installation Pending 40%
18 Engine Maintenance Platform Gratings & Handrails Installation Pending 99%
19 Charge air duct erection and alignment Pending 99%
20 Engine Hall doors fabrication & installation Pending 97%
21 Engine hall Overhead Crane Structure fabrication & Erection In Progress 99% 0% 99%
22 Engine Hall structure & inside all equipment painting Pending 37%
23 Both side stack painting Pending 5%
24 Emergency generator shed fabrication Pending 48%
25 Lube Oil Tank base & Lube oil pump house civil construction Pending 99%
26 Engine Hall & MV,LV building rooftop parapet wall construction Pending 77%
27 WTP room civil work Pending 98%
28 Cable trench civil work Pending 96%
29 Engine hall civil work Pending 96%
30 LV & MV,Cotrol room civil work Pending 95%
31 Engine,Boiler & Lube oil tank pit construction Pending 59%
32 Lube oil tank base,boiler & blowdown tank dyke wall construction Pending 91%
33 Engine hall,LV & MV Building,WTP room dyke wall painting Pending 5%
34 AC purchase & installation for Control room & Switchgear room Completed 100%
35 Raw & Soft water tank base construction Completed 100%
Major Works Progress
36 Fire Tank base construction Pending 90%
37 Fire pumphouse construction Pending 5%
38 Fire Tank Fabrication In Progress 92% 0% 92%
39 Fire plan carried all equipment installation & piping work Pending 50%
40 WTP Equipment installation & Piping Pending 80%
41 Boiler all Auxiliaries and Mountings installation,pipelines fabrication & Erection In Progress 93% 0% 93%