PROJECT : CONSTRUCTION OF NEW BOYS HOSTEL BUILDING AT ANNA UNIVERSITY CAMPUS,KANCHIPURAM
CLIENT : M/S. SNS FOUNDATION
CONSULTANT: M/[Link] ASSOCIATES
CONTRACTOR : M/[Link] CONSTRUCTIONS
Date Of Commencement : 08.08.2024
Date Of Completion : 06.02.2025
CONSTRUCTION PROGRAMME FOR CIVIL WORKS
TASK TASK YEAR 2024-2025
ACTIVITY ACTIVITY TOTAL JULY AUGUST SEPTEMBER OCTOBER NOVEMBER DECEMBER JANUARY FEBRUAR
[Link] TASK NAME PERIOD PERIOD DAYS 3 6 9 12 15 18 21 24 27 31 3 6 9 12 15 18 21 24 27 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15 18 21 24 27 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15 18 21 24 27 31 3 6 9 12 15 18 21 24 27 31 3 6 9
Site Boomi Pooja 13.06.24 13.06.24
i Pile RiG Mobilization 25.07.23 07.08.24 14
ii School Building Sub Structure
1 Building Pile foundation work 08.08.24 17.09.24 40
2 pile cap excavation and levelling work 20.09.24 27.09.24 7
3 pile cap shuttering and rebar fix 28.09.24 05.10.24 7
4 RCC Pilecap with Grade Beam 06.10.24 21.10.24 15
5 Basement level block work 22.10.24 29.10.24 8
6 Basement filling&consolidaration work 30.10.24 05.11.24 7
7 Flooring PCC 06.11.24 08.11.24 3
iii Ground Floor Super Structure
1 Column Casting work 09.11.24 15.11.24 7
2 Block work up to lintel level 16.11.24 22.11.24 7
3 Lintels &Column R.C.C 23.11.24 27.11.24 5
4 Roof Slab R.C.C and curing time 28.11.24 07.12.24 10
iv First Floor Super Structure
1 Column Casting work 08.12.24 14.12.24 7
2 Block work up to lintel level 15.12.24 19.12.24 5
3 Lintels &Column R.C.C 20.12.24 26.12.24 7
4 Roof Slab R.C.C and curing time 27.12.24 06.01.25 10
5 parapet wall brick work 07.01.25 09.01.25 3
V Staircase Head Room Work
1 Column Casting work 10.01.25 12.01.25 2
2 Block work up to lintel level 13.01.25 15.01.25 3
3 Roof Slab R.C.C and curing time 16.01.25 26.01.25 10
VI Ground Floor Finishes
1 Electrical 1st Fix (concealed pipeline) 10.12.24 16.12.24 7
2 Door & Widow Frame Fixing (Int&Ext) 17.12.24 23.12.24 7
3 Plastering Internal 18.12.24 01.01.25 15
4 White washing work and putty work 07.01.25 13.01.25 10
5 Floor Tiling work 15.01.25 29.01.25 15
6 Electrical 2nd Fix 30.01.25 01.02.25 5
7 Final Coat Painting 29.01.25 02.05.25 5
VII First Floor Finishes
1 Electrical 1st Fix (concealed pipeline) 07.01.25 13.01.25 7
2 Door & Widow Frame Fixing (Int&Ext) 10.01.25 15.01.25 5
3 Plastering Internal 15.01.25 25.01.25 10
4 Plastering External 10.01.25 25.01.25 15
5 Floor Tiling 20.01.25 29.01.25 10
6 Safety Grill Work Fixing 30.01.25 31.01.25 2
7 Roof Finishes 25.01.25 28.01.25 4
8 1st Coat Painting 29.01.25 01.02.25 4
9 Interior works (board and etc) 02.02.25 03.02.25 2
10 Electrical 2nd Fix 01.02.25 03.02.25 3
11 Final Coat Painting 30.01.25 04.02.25 6
12 Roof Damp proof Coat 01.02.25 04.02.25 4
13 Stair Hand Rail fix 03.02.25 05.02.25 3
VIII Hand over Inspection 05.02.25 05.02.25 1
IX Final Hand Over 06.02.25 06.02.25 1
Notes
a). Above said all works based on BOQ
b) As on site condition working days will change
c) Every coloumns 3 working days
d) weather calmities will differ some activity duration