Installation Checklist For Distribution Boards

Uploaded by

kumaramarendra98
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
889 views1 page

Installation Checklist For Distribution Boards

Uploaded by

kumaramarendra98
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd

INSTALLATION CHECKLIST FOR MCB DB

Project: Make:
Shop Drawing no: DB no:
Description of DB: Location

S No: Item Description Status Remarks

1 Make and quality as per spec.

DB frame grouted properly in wall (in floor if floor


2 mounted). Frame is painted, aligned square with the DB
and vertically in plumb.
Unused knockouts of the DB are closed with rubber
3 bushings

4 DB is earthed properly at two points. Check that the paint


at the earthing contact is removed.
5 Internal earth connected to earthing bolt.

6 All terminations in MCBs done with lugs.

7 Circuit identification provided with ferrules on the wires.

8 Incoming cable glanded properly. Gland is earthed. Gland is


held firmly with check nut.

DB name plate provided (Printed sticker / Aluminium


9 plates glued and screwed)

10 Doors of the DB opens fully and easily.

11 Pad locking arrangement provided on the DB.

12 All the wires have adequate loop, are dressed properly,

13 DB cleaned thoroughly.

14 All cables and wires meggered.

Internal wiring (from Incomer to outgoing bus bars) done


15 with factory formed cables.
Comments/Note -

Vendor Representative C&W Representative

Installation Ch list for MCB DB Rev 0 1 of 1