Erm Note Lip Bhabour Sahib Una
Erm Note Lip Bhabour Sahib Una
IRRIGATION PROJECT BHABOUR SAHIB IN TEHSIL AND DISTT. UNA (HP) FOR
CONSIDERATION OF THE ADVISORY COMMITTEE OF DOWR, RD & GR,
MINISTRY OF JAL SHAKTI ON IRRIGATION, FLOOD CONTROL AND
MULTIPURPOSE PROJECTS
Himachal Pradesh is a mountainous state encompassing the transmission Zone from the Plains
to high terrains of Himalayas and standing up to the Tibetan plateau. The total geographical
area of Himachal Pradesh is 55673 Sq. Km. and situated between latitude 32 0 22’ 40’’ N to 320
12’ 40’’ N and Longitude 750 74’ 55’’ E to 790 04’ 22’’ E. The state comprises of 12 District
with 46 town and there are more than 17000 villages of which sum 12000 villages have
population less than 200 person.
The present Una district until 1st November, 1966 was one of the tehsils of the Hoshiarpur
district of Punjab. Consequent upon reorganization of Punjab, all the hill areas including Una
tehsil was transferred to Himachal Pradesh. Ever since, until September, 1972 it continued to
remain as tehsil of the then Kangra district. On the 1st September,1972 the Himachal Pradesh
Govt. reorganized the then Kangra district into three districts namely Una, Hamirpur and
Kangra. Una district consists of five Sub-Divisions (Una, Amb, Haroli, Bangana & Gagret),
five Tehsils (Una, Amb, Bangana, Haroli and Ghanari) and seven Sub-Tehsils (Bharwain,
Ispur, Jol, Bihru Kalan, Dulehar, Gagret at Kaloh, Mehatpur Basdehra) and is having five
Development Blocks (Una, Bangana, Gagret, Amb and Haroli).
The district Una, with its headquarter at Una town, has a geographical area of 1540 sq km and
covers 2.8 % area of the State. It lies between North latitude 31°18’00” & 31°55’00” and East
longitude 75°55’00” & 76°28’00” and is covered by Survey of India degree sheet No.53A &
44M. Towards the north, it is bounded by Kangra district, towards north and east by Hamirpur
and Bilaspur districts respectively and towards south-west by the State of Punjab.
As per census 2011, provisional population of Himachal Pradesh is 68.56 lacs. With literacy
rate of 83 % .the average density of population is 123 per sq. Km. almost 80% population is
engaged in agriculture. But agriculture accounts for only 18.80 % of gross state domestic
product. The low agriculture productivity partly attributes to the fact that the area available for
growing crops is limited to 10% of total lad of state, due to hilly terrain. The population
pressure on cultivated land is high and the land holding of farmers are very small i.e. 64% of
holdings are less than 1.0 hectare. And about 20% land holding ranges from 1.0 to 2.0 hectare.
Most of the holding is self-cultivated. Cereals, Pulses, Vegetables and horticultural crops
dominate the region. Only 20% of cultivable area has irrigation facilities, and rest has to
depend on the rain fed cultivation.
Four main tributaries of the Indus originate or pass through Himachal Pradesh, Haryana and
Rajasthan or by national hydroelectricity grid. Most of the state’s productive water resources
agriculture come from smaller perennial or seasonal monsoon fed streams. There are two rainy
seasons. About 25 percent of the precipitation occurred during the period from December to
March. With the remaining 75 percent during the monsoon months from June to Octobers.
Most of the cultivated area in the state is rain fed . Since the rains are erratic and irregular, it
effects the crop grown to a considerable extent. As result of this the farm harvest is sometimes
very low.
Emphasis has been made by the state Govt. to bring more area under irrigation so that farm
harvest can be increased. The state estimate almost 1,40,000 hectares to be under irrigation,
with about 55 percent of the area served by community systems, Indeed, state irrigation
legislation takes account of both systems although they have operated in different spheres. Both
state and community systems are small. There are only a few state systems with commands in
excess of 2000 hectares . Smaller schemes are typically flow (known as kuhls ) and lifts.
Communities have largely confined themselves to flow, although the state finances both. The
water source of kuhls is either perennial or seasonal springs or stream. Jal Shakti Vibhag is
engaged in irrigation development according to availability of finances.
Agriculture is the major occupation of the people of the district, with more than 70%
population engaged in the agriculture and allied sector. Major crops like maize, wheat, rice,
sugarcane, and pulses are grown, apart from vegetables in the district. Total cultivable area is
443 sq km and net area sown area is 388 sq km. Net area irrigated in the district is about 85 sq.
km. Ground water is the major source of water in the district for irrigation and domestic use.
There are large number of water supply wells, tube wells, springs, kulhs (water channels) and
lift irrigation schemes, implemented exclusively for irrigation purposes.
Since the rains are erratic and irregular, it affects the crop growth to a considerable extent. As a
result of this the crop harvest is very low. Emphasis has been made by the Government to bring
more and more area under irrigation.
In order to boost the agriculture development and enhance the farm income in the rural areas, it
is there for important to increase the productivity of the existing cultivated area, through
shifting from self-subsistence crop cultivation to diversified agriculture, and for this it is
necessary to adopt the cultivation of cash crops such as vegetables which is suitable in hilly and
high land agriculture for such accomplishment, overcoming the measure constraints, such as
shortage of irrigation facilities, farm roads and in sufficient market facilities is highly essential.
At the time of formulation of Bhakra Dam project in the country. It was envisaged that about
90,000 acres of land between Nangal and Ropar previously in Punjab, will be Irrigated from the
water of Nagal Dam reservoir. But out of 90,000 acres of land 14876 acres of land is now on
integrated part of Himachal Pradesh as mentioned above and it is what natural that as per
project report of the Bhakhra Dam. This area should be covered from the water of Nangal Dam
reservoir. In Bhabour Sahib project phase 1 an area of 923 hectares was only taken up to
provide immediate irrigation facilities and in the second phase another area of 2640 hectares
had been proposed to the provided with irrigation facilities.
The area proposed in the project remained neglected for a long time, although the some should
have been provided with irrigation facilities, the yield of crop is bound to increase appreciably.
The intake for the water for the phase 2nd has been kept at the same place as per phase 1 which
is opposite to the famous Gurdwara known as Bhabour Sahib.
The requirement of water has been worked out in details month wise and the same is appended
in the body of the estimate. The contribution due to rain fall has also been considered. The
Nangal Dam reservoir in under the control of B.B.M.B. and in the meeting with whom it was
agreed upon that the same duty for supply of water to this area should be adopted, although in
fact due to better technical know-how and research in Agriculture project the requirement of
water is much more.
It will also not be out of place to mention here that the people of Himachal Pradesh were only
suffers in the construction of Bhakra Dam as large tract of their fertile land got submerged in
the Govind Sagar Lake but the benefit from the Dam has not reached even up to the
expectations of the nearby population of the state of Himachal Pradesh till now. The matter
regarding release of water from Bhakra Nagal Lake was therefore, discussed in the Zonal
Council meeting where in it was decided the requirement being very small, the Himachal
Pradesh state should be allowed to draw water for its land from the reservoir for which Bhakra
Management Board should release water accordingly.
A reference had been made to Bhakra Management Board regarding question of water for the
purpose of irrigation from Nangal Dam reservoir and accordingly. It was decided in the
meeting of Chief Engineers from beneficiary state and B.B.M.B. that 2.25 cusecs of water will
be released including losses per 1000 acres basic. Now the board has approved the lifting of
19.64 cusecs of water from Nangal Dam reservoir from a point below Gurdwara Bhabour Sahib
free of cost as per item no. 114.08 dated 19.09.1984 copy enclosed for ready reference and the
extract from the 114th meeting from B.B.M.B. held at Suraj Kund. (Copy Attached).
Most of the cultivated area in the state is rainfed. Since the rains are erratic and irregular, it
effects the crops growth to a considerable extent. As a result of this the crop harvest are very
low. Emphasis has been made by the govt. to bring more and more area under irrigation.
There are many inherent problems in the existing infrastructure of LIP Bhabour Sahib I & II
which have contributed to the low utilization of irrigation potential created. The problem in
further compounded due to the leakage in the conveyance system. The rising mains (CI pipes)
and pumping machineries of the project are badly damaged, outlived their life and become
beyond economical repairs. It requires replacement and redesign. The soil in some villages in
the command area of this project is highly suitable for manufacture of bricks. After the project
was completed, there was boom in construction industry in the post 1991 era, many brick kilns
had come up. The owners of land in the area had sold the layer of top soil up to depth 1.5m to
3.0m to brick kiln owners. This badly damaged the existing RCC pipe mains and distribution
lines making the system non-functional.
Detailed survey and investigation were carried out of the whole command area. It was observed
that a limited quantity of 19.64 cusec could be lifted from the source as per agreement with the
BBMB authority, allowing only 0.157 lps per hectare in the Lift Irrigation Project Phase Ist and
0.1556 lps in the LIP Phase 2nd from reservoir. However, in most of schemes constructed by
Jal Shakti Vibhag, water requirement is of the order 0.45 LPS to 0.60 LPS per hectare. The low
water requirement adopted in this project has resulted in severe chronic water scarcity in all the
cropping seasons. Presently, the water supplied is not sufficient to irrigate the command area of
this project, inviting the wrath of public criticism and poor output from this project.
Experience from prevailing irrigation practice in state shows that if the duty less than 0.45 LPS
-0.60 LPS per hectare is adopted, it will not result any benefit of irrigation to the farming
community. These duties are minimal necessary and are being adopted in the new upcoming
projects of state. After careful consideration of the cropping pattern a design water requirement
of 0.48 LPS has been adopted as most techno-economical feasible.
The detail of the area to be covered under the project has been worked out by deleting the area
being used for non- agricultural purposes. Out of 3563 hectares of land proposed in the original
project, only 906.84 hectare is irrigated presently from this project and 1296.0 hectare under
Abbadi & Brick Kiln or Industries. Ironically, the water levels go down during months of
December and January in day times when no water is released from the Bhakra dam to Nangal
dam. The intake area becomes dry and no pumping of water at headworks, causing shutdown of
the project. The project remains a show piece and source of criticism. This also affects the
pumping machinery. A suitable intake structure with positive suction is required. The
machineries which have gone beyond economical repairs or which have outlived its designed
life are required to be replaced.
Therefore, the project has now been proposed for extension, renovation & modernization of the
Lift Irrigation project providing irrigation facilities to a total CCA of 2266.71 hectares.
In the Instant proposal department is keen to provide assured irrigation for all area of 21
villages including. The proposed scheme shall cover the approximately 2266.71-hectare CCA
area, situated on the Right bank of Satluj reservoir of Nangal Dam. This Project proposed to
Cover 21 Nos. Villages & 21 Nos
Panchayats.
Una district is situated on the border of Himachal and Punjab. UNA is well connected by Roads
with all the major cities / towns of Himachal Pradesh as well as with the neighboring states.
UNA is accessible throughout the year and major mode of transportation is by road. Three
national highways (NH-503, NH-503A, NH-3) pass through the district. Una is located about
375 km (233 mi) north of New Delhi and 120 km (75 mi) from Chandigarh. Major bus stands
of the district are Una, Amb, Daulatpur, Gagret, Santokhgarh, Mubarikpur, Haroli and
Bangana. Major Modes of local commuting are Buses, Auto Rickshaw and Taxi.
The Una city is served by the Una Himachal railway station. It is connected by a single broad
gauge railway line, which is the only one in the whole state. It enters Una
from Nangal (Punjab) and runs all the way to Daulatpur Chowk. Three express trains
(Himachal Express Jan Shatabdi Express and Vande Bharat Express) connect it to Delhi daily.
The nearest domestic airport
are Chandigarh and Gaggal, and an airport with
international operations is in Amritsar. The
whole area is well connected with road
network comprising State highway, District Road
& village roads. The distance of Una from
various stations are listed below: -
State Capital Shimla =193 km
Railway station at Una =1.5 km
Railway Station Nangal =20 km
Airport at Chandigarh =160 km
Road Network
Other available facilities at site
Climate of the district is tropical to temperate in nature as the terrain varies from plains to high
hills. Temperature varies from minimum of 4°C in winter to the maximum of 46°C in summer.
The winter starts from the November and continues till the middle of March. Thereafter the
mercury continues rising till the set of monsoons which starts from the last week of June and
continues till the middle of September. The area receives rainfall during monsoon period
extending from June to September and also non-monsoon period (winter). The annual average
rainfall in the district is about 1040 mm. There are three rain gauge stations at Una, Amb and
Bangana in Una district, monitored by IMD.
The monthly season duration indicated below:-
1. Winter:- October to February
2. Summer:- March to June
3. Rainy:- July to September
The temperature in the different parts of the district varies according to the elevations. After the
end of February temperature increases gradually till June, which is the hottest month of the
year. Over most of the district the summer is hot. With the onset of the monsoon by about the
end of June there is decrease in temperature. During the summer maximum temperature ranges
between 40°C and 44°C and during winter, the maximum and minimum temperatures are 5°C
and 16°C respectively. After the withdrawal of the monsoon by about the middle of the
September temperatures decrease gradually at first and fairly rapidly after November. January
is generally the coldest month in association with cold waves in the wake of western
disturbances that affect the district.
In the southwest monsoon season, the humidity is high. In the post-monsoon, winter and the
early part of the summer the humidity is generally low particularly in the higher regions. By
June the humidity begins to increase.
(a) TOPOGRAPHY: Una lies in the western part of Himachal Pradesh, with the Shivalik
hills of the himalayas rolling on western side and Solah Singhi range on the eastern side.
The Satluj river alongside Shahtalai, known for the shrine of Baba Balak Nath passes through
south of district near Nangal Dam and Beas passes at the North of district near Pong Dam,
Talwara.
The altitude varies from more than 409 meters in plains to over 1000 meters in hills. Swan
River which is basically seasonal river and also known as soul of district Una flows 65 km right
across the Jaswan Valley towards south until it submerges in the Sutlej river near Anandpur.
The project area is situated in the valley side of lower Shivalik ranges on right bank of Satluj
River near Nagal dam. The Khads/Nallah are flowing from North to South direction and are
also mostly perennial. The rain/spring water of the catchment area flowing through natural
drains and generating the flow in all season along with the water released from tail race of
Bhakhra Dam. Cultivation and agriculture practices are performed by the local farmers in the
district.
The command area covered with good vegetation growth and have good soil cover. The area
falls on the Right bank of river Satluj of Nangal Dam reservoir and scattered to left bank of
Swan River. Cultivation and agriculture practices are performed by the local farmers at
relatively plain plateau. The water generally 20 to 30 meter deep in gorge near intake point &
spread in the downstream. Drainage grade in the command area is good & there is no problem
of water logging.
The Khad / Local Nallah are rain fed , but
contributing some flow from spring sources
in the catchment areas. These Khad/Local Nallahs
dried up during summer months and act as
natural drain during monsoon season. The dense
vegetation available on the upper reaches of area
indicating dense forest and middle and lower
reaches are having comparatively good
agricultural field. The habitation & small towns
are scattered and settled as per
convenience of the local public.
(b) GEOLOGY OF THE AREA: The
Geology of the area can be described under
two broad heads (i) Hilly areas,
comprising of upper, middle and lower Siwalik
formations. (ii) Quaternary sediments
constituting the valley area. The area is mainly
occupied by the Siwalik formation of Tertiary age with narrow longitudinal tectonic valley i.e.
Una valley. The Una valley extends from Daulatpur to Santokhgarh and beyond the northern
border of Dun-Syncline in the area is a thrust plane called Soan Thrust. Apart from Una valley,
the rest of the area of the district is hilly. The younger valley fill deposits are Pleistocene to
Recent in age and constitute unconsolidated elastic sediments comprising chiefly granular
deposits interest ratified in the clays and clay-boulder beds. In the sub-mountain tracts along
the Siwalik Hills, the piedmont deposits comprising sand, gravel, pebbles, cobbles and boulders
occur. Coarse-grained deposits usually fringe the hills and grade into fine-grained aggregates
towards the central parts of the Una valley. The granular beds are interbedded with clays, of
varying thickness. In the low-lying area of Una valley i.e. Central parts of the valley and the
streams traversing the northern part of the valley finer elastic sediments comprising sand, silt
and clay chiefly occur. Era Period Formation Lithology Quaternary Recent Alluvium Sand,
gravel, pebble and cobble Lower Pleistocene to Recent Undifferentiated Sand, gravel, pebble,
cobble and soft sandstone Tertiary Lower Pliocene to Lower Pleistocene Upper Siwalik
Brownish clay, Conglomerate and shale Middle Miocene to Lower Pliocene Middle Siwalik
Gray sandstone, shale and brownish clay Lower Miocene to Middle Miocene Lower Siwalik
Red and purple sandstone and shale. The older valley fill deposits (Terraces) occur along the
left bank of the Soan river and on the northern slopes of the valley chiefly comprise gravel,
pebbles, boulders interstratified with thin clay lenses. The terrace formations in the Una valley
are older than the river alluvium. The piedmont deposits occur along the sub. Mountain tract of
Siwalik hills and comprise sand, pebbles, cobbles & boulders.
The upper Siwalik rocks are found in north and south east of the Una valley comprising of
indurated sands, sandstones, silts and brown clays. The conglomerate beds also occur at places.
Coarser sediments mainly comprise pebbles beds are prominent in the northwestern part of the
area. In the southern parts, the boulder bed forms the upper most part, consist of pebbles,
cobbles and boulders with intervening thin beds of clays. North of the valley, upper Siwalik
formations are chiefly represented by massive sandstone and conglomerate with beds of clay
and indurate sands. Sandstones are usually soft friable and pebbly.
The middle Siwalik includes hard, gray or brown colour sandstones with small proportion of
drab shales, orange clays and occasional beds of gravel. Between Kathaulas-kiKhad and
Panjoa-ki-khad there are two isolated outcrops of middle Siwalik rocks comprising of
moderately hard, massive medium to coarse grained micaceous sands tones with the thin
intercalations of clays.
The lower Siwalik comprises hard sandstones with clay nodules and purple shale. The
sandstone generally forms conspicuous strike ridges. The valley fill comprises 16
unconsolidated fluvial deposits consisting gravels, pebbles, cobbles and boulders intermixed
with clays. The various khads emerging on the left bank and joining Soan and formed piedmont
deposits and fan deposits those are likely to emerges as potential ground water horizons.
Soil characteristics Two types of soils are observed in the district viz., alluvial soil and non-
calcic brown soil. Most of the area in district is covered with alluvial soil and only about 25%
of the area i.e. hilly area in the district is covered with non-calcic brown soil. These soils are
restricted to major drainage courses. They consist of very deep dark brown to dark grayish
brown. Silty clayey loams are seasonally submerged. These are well drained and suitable for
perennial irrigation. pH is 8.0. They are low in N and P and medium in K.
1.8 POPULATION
(a) Affected and Benefited: This project command area of 2266.71 hectares lies on the right
bank of the river Sutlej opposite to Gurdwara Bhabour Sahib. The Command area consist of
Bangarh, Dehlan, Chattara, Jakhera, Behdala, Raipur, Basdehra, Charatgarh, Jatpur, Ajouli,
Udaipur, Lamlehra, Sasan, Nangran, Badehar, Judowal, Fatehpur, Chhatterpur Dhada, Bhatoli,
Morebar, Mehatpur, & Bharolian villages.
Since there was limitation for the supply of water and the pattern for the for the supply of water
was kept to be the same as in adjoining area of Punjab the intensity of irrigation is only 130%
out of this 50% available agriculture land will be supplied with water during Kahrif season and
75% during the Rabi season. Due to increasing awareness regarding benefits of irrigation,
multiple cropping pattern is also fast coming up 5% irrigation of land on account of this also
been taken into consideration.
After completion of this scheme, the living standard with the growth of agriculture
produce shall increase and will benefit a total population of 33285 persons.
(b) Occupation: The agriculture is the main occupation of the people of the area. More than
90% of the present population is directly or indirectly dependent on agriculture. Cultivators
generally have small land holdings. Both Rabi & Kharif crops are cultivated. Important crops
are wheat, maize and cash crops like vegetables, Oilseed and citrus etc. Presently the crops are
dependent upon rain fall.
The Project area is situated on the Right bank of a Satluj River, which flows at lower level.
Local nallah/ stream has not sufficient discharge throughout the year to meet the water needs of
crops, hence it is preferable to lift the water from Satluj Nangal Dam reservoir. The ground
water in this area is low and tapped for drinking purposes by means of deep hand pumps and
wells. No important economic minerals have been encountered so far from the present area.
1.10 PROJECT PROPOSAL
The project has been proposed for both phases of LIP Bhabour Sahib with existing source i.e.
Nangal Dam reservoir. The total command area covered under the project in 2 phases is as
following: -
PHASE-I
PHASE-II
A Command Area Development Project was formulated and approved by the Govt. of India
and the A/A& E/S accorded vide Commissioner –cum-Secy. to the Govt of H.P vide letter No.
IPHU-(4) 86/ Loose dated 9.6.89 for Rs. 22.27 lac. The main scope was construction of field
channels and the execution was completed during 1992-93.
POTENTIAL UTILIZED: -
Out of 923 hect. of CCA created, Potential utilized is 369.20 Hect. which comes to 40 %.
IRRIGATION PROBLEMS:
1. The timely and adequate supply of irrigation water is not being made available to the
farmers of tail end village Dehlan.
2. The design water requirement has been taken as 0.157 Lps / Hect. against normal water
requirement of 0.45 – 0.60 Lps/ Hect. as the soil of the region being sandy.
3. Inactive WUAs, the beneficiaries do not adhere to Warabandi schedule.
4. Over Irrigation in head reaches.
5. Scattered CCA and long distribution network.
6. Theft of water through channels, outlets and even nakka plates.
7. Shortage of manpower
8. Most of field channels damaged at various locations by farmers resulting into loss of
water through seepage and less irrigation in a given time.
G/main G/main
S.No. Description. Unit. G/main No.3 Total.
No.1. No.2.
Completed. Completed. Completed.
1. RCC pipes 600
Mtrs. 29135 17260 44950 91345
mm to 150 mm dia.
2. AC pressure pipes
Mtrs. 276 - 3460 3736
400 mm to 150 mm.
3. C.I.pipes 450 mm
Mtrs. - 22 685 707
to 250 mm dia.
4 Total pipes
networks in Mtrs. 29411 17282 49095 95788
D/system.
VILLAGES BENEFITTED
1.Bangarh. 1.Raipur. 1.Udaipur.
2.Dehlan. 2.Basdehra. 2.Lamlehra.
3.Chattara. 3.Charatgarh. 3.Sasan.
4.Jakhera. 4.Jatpur. 4.Fatehpur.
5.Behdala. 5.Ajouli. 5.Nangran.
6.Badehar.
7.Judowal.
8.Bharolian.
9.Chhatterpur
A Command Area Development Project was formulated and approved by the Govt. of India
and the A/A& E/S accorded vide FC –cum-Secy. to the Govt of H.P (IPH) PW (B) - 6(1) 1/83
– Vol.-II dated 28.11.95 for Rs. 581.00 lacs. The main component of project was C/o field
channels and its execution was completed during the year 2000-01with its completion cost of
Rs.371.40 lacs.
POTENTIAL UTILISED: -
Out of 2640 hectare of CCA created, 1296.00 hect. stand diverted and now the net CCA
available is 1343.71 Hect. Potential utilized is 537.484 Hect. which comes to 40%.
IRRIGATION PROBLEMS: - .
1. Diversion of land for non-agriculture purpose, out of 2640 Hect CCA, 1296.29 Hect. of
land use has been changed for other activities such as residential, Bottling plant by
Indian Oil , Brick Kilns , Railway track, Navodya School and non-development of land
for agriculture along river Swan.
2. Damage caused to gravity main No. 2 by Brick Kilns owners. Out of total CCA of 455
Hect. only 30 Hect. is being utilized and 217 Hect. shall be further utilized after
completion / restoration work of gravity main No.2.And balance 207 Hect. land is
presently not cultivable and diverted for non-agriculture.
3. Scattered CCA and long distribution network, the tail end villages of Nangran,
Pekhubella and Judowal are approximately 12 KMs from head works.
4. Inactive WUAs, the beneficiaries do not adhere to Warabandi schedule.
5. Over Irrigation in head reaches.
6. Theft of water through channels, outlets and even nakka plates.
7. Shortage of manpower.
8. Construction over distribution network thus rendering the repairs difficult.
9. Most of field channels damaged at various location by farmers resulting into loss of
water through seepage and less irrigation in a given time.
a) Available Discharge: - The quantity of water 19.64 Cusec. Can be lifted from the Nangal
Dam Reservoir as per Agreement made between the BBMB Authorities and the State of
Himachal Pradesh. Whole the year good discharge available in Nangal Dam reservoir of
Satluj.
b) Water requirement/ design discharge: Crop water requirement of scheme Assessed on
the basis of recommended cropping pattern prepared after discussion with Agriculture
experts & SMS Department of Agriculture, Govt. of Himachal Pradesh. The base period for
the supply of water has been taken as 28 days and the depth of water required for each crop
has been obtained from the Director of Agriculture. The consideration for contribution from
rainfall has also been taken. Some allowances have also made for conveyance and
evaporation losses. The total water requirement is 1085.18 lps with pumping for 20 hours
for 2266.71 hectare in Kharif & 2266.71 hectare in Rabi season with Zaid crops in a CCA
of 453.37 hectare The statement for water requirement (Month wise) is attached. The total
water requirement for is 0.48 LPS/Hect.
Net Irrigable area = 2266.71 Hect.
Annual Irrigation before implementation of project = 1813.368 Hect.
Annual Irrigation after implementation of project = 4986.79 Hect.
Intensity of Irrigation = 220 %
Total Water requirement = 1085.18 lps
After Construction of this project, the command area would be provided with assured
irrigation for high yielding variety crops.
HYDROLOGY
2.1 WATER AVAILABILITY
The quantity of water 19.64 Cusec. Can be lifted from the Nangal Dam Reservoir for LIS
Bhabour Sahib (Phase-I & II) as per Agreement made between the BBMB Authorities and the
State of Himachal Pradesh. Whole the year good discharge available in Nangal Dam reservoir
of Satluj.
2.2 PRECIPITATION
The catchment area receives precipitation from the S.W. monsoon as well as western
disturbances those pass over N.W. part of the country during the winter season. The S.W.
monsoon generally last from June to sept. but may occasionally extended up to early October.
The precipitation is mainly in the form of rain. The precipitation is generally in the form of
light and combined shower but sometimes may exceptionally be heavy enough to cause floods
in both streams.
2.3 EVAPORATION
No record of evaporation available from the catchment or adjoining area. The evaporation loss
in the catchment in general and at the reservoir site in particular are not of much concern. Low
wind velocity, lesser temperature gradient, thick vegetation cover etc. are the factors
responsible for less evaporation losses in the project area, evaporation expected to be highest
from March to June as high temperature in the area.
PUMPING MACHINARY: The old pumping machinery of LIS Bhabour Sahib (Phase-I & II)
has outlived and in the instant project proposal new pumping machinery has been proposed.
The total HP of submersible pumps is 450 H.P. and Total HP of centrifugal pumps is 2445 HP
is proposed.
RISING MAINS: The rising main GMSREW pipe of varying dia 150mm to 600 mm in a total
length of 14619 Rmt have been proposed. As the existing Rising mains are laid in CI pipe and
with the passage of time the existing R/mains are damaged and have leakage problem, hence
has been replaced with new GMSERW pipes after design for better supply of water to the
CCA.
MAIN DELIVERY TANK: The existing Main delivery tanks under the Lift Irrigation Project
Bhabour Sahib Phase I & II are in good condition and only 1 No. MDT has been proposed at
village Badehar of 300000 ltrs capacity. It has been proposed the renovation of 39 No. main
delivery tanks.
GRAVITY MAINS: 200mm to 600mm dia GMSERW pipe in a length of 39925 mtrs and
10325 mtrs HDPE pipe 180mm to 500mm PE 80 PN-6 has been taken for proper distribution of
entire CCA through proposed underground storage tanks.
OUTLETS: Provision of new of 1887 Nos. outlets has been proposed. Outlet chambers have
been proposed to further distribute the water to command area covering 1.0 to 1.50 hect. Area
chacks each. New Circular RCC Outlet chambers have been proposed to further distribute the
water to command area. The size of outlet chamber is 1440 mm diameter & proposed with
nominal reinforcement in Cement Concrete M-25 not less than 1:1.5:3 (One Cement:1.5 Sand:
3 Aggregates upto 20 mm size)
DISTRIBUTION NETWORK: In total 2266.71 hect CCA, the existing RCC distribution
network will be replaced with HDPE pipe of various dia. HDPE pipe has been proposed.
Because of undulating topography, it is preferred HDPE pipe main distribution system. HDPE
pipes are light in weight and have wide range of flexibility to operate under these conditions.
Class PE-80, PN-4 are made from Virgin Class of Polyvinyl material & have high durability.
Roughness coefficient C=145 for HDPE pipes taken.
Frictional Head losses in HDPE pipes = 4 flv 2/2gd by Darcy and weisbacks formula,
where f=0.010 , l= length in meters, d= diameter in m and v= velocity m/sec.
The Hazen William’s formula consider to find velocity= 0.4567 d 0.63 S0.54
Where d= diameter of pipe in mm , S=slope of hydraulic gradient=hf/100
hf= 103( QK/(3.1 x 10-2xd2.63) 1/0.54
Qk=Discharge in Kilo-litre per day.
Nearly 30% of total command area in the lower reaches proposed to be irrigating under micro
irrigation systems.
AUTOMATION: Provision for Providing & Installation of Supervisory control and data
acquisition (SCADA), a computer system & Software for gathering and analyzing real time
pump operational data, pump monitoring and control the pumping station with irrigation
scheduling, On/Off function alongwith Data acquisition, Networked data communication, Data
presentation on computer screen and keeping the data history for approximately three months,
has been kept in the proposal.
KISAN BHAWAN: There is one no. new Kisan Bhawan is Propsoed at village Dehlan
situated at a distance of 10km from the district headquarter for conducting various farmer
meetings and to conduct training activities for Water User Association(s) & beneficiaries.
The proposed Irrigation Scheme are located in an area with scattered population. The
population is settled primarily in small hamlets and majority is engaged in agriculture work
directly or indirectly. With the construction of this project, it is felt that there will be no
abnormal impact on the local population or on the surrounding human settlement. No impact on
the Flora and Fauna in and around the command area is anticipated.
No storage is envisaged in the topography, which will give no harmful impact on wild life and
its breeding areas. No place of cultural or religious importance will be affected and care has
been taken while be preparing the project report to see that there will be no damage to any
religious place. There are no tribal aboriginals settled in the area. Since no impoundment is
involved as such there will be no relocation or resettlement problems.
The proposed project is likely to be eco- friendly directly or indirectly as large chunk of
population will remain engaged in thereby increasing agriculture production and other
productions like dairy production. In the proposed cropping pattern stress has been laid for
fodder and barseen etc. moreover there have been migratory cattle herds and sheep herds
moving in the district including the project area, there by adding to ecology degradation
including extensive grazing. The higher production of straw and green fodder shall restrict such
movement of cattle and ultimately the project will prove eco-friendly.
Presently the ground water being exploited by deep hand pump used for drinking purposes.
4.2.2 FORESTS:
Neither any village is adversely affected due to construction of this project nor will any
population be displaced. No rehabilitation is required
4.2.5 RESETTLEMENT.
No resettlement required
4.2.6 WIND
There is very rare occurrence of hurricanes/cyclones and no tornadoes have been reported from
the life memory.
Known sources of pollution are nil as there is no industry in the command area and
surroundings .
No fish life in the stream exists and appearance of crocodiles is also reported nil.
a) The area is thinly population with wild animals like Pig, Foxes, Jackals, etc.
b) Rare/dying species are :-Nil.
c) Breeding/ Feeding area:-No distribution is envisaged to such areas.
d) Migration routes:- No effects shall be created.
e) Potential wild life sanctuary: No proposal
f) Flora & Fauna in Sub-merged area:- NIL.
4.3.4. TOURISM.
There is no existing or likely tourist resorts nearby nor any important religious archeological
recreation center wild life sanctuary and Parks in the command area of the project.
4.4 ENVERONMENTAL
Under ground water is already of potable quality and no changes are anticipated. The ground
water table is quite low and no specific change in the ground water table is expected. Moreover
almost the entire area is well drained and is made up of high permeability strata.
No proposal of construction of reservoir to store huge quantity of water and area to be served is
not so large. So the change in the Macro or Micro climate conditions is negligible.
PHYSICAL FEATURE
5.1 GEOGRAPHICALY DISPOSTITION.
District Una is located between the co-ordinates 31 o to 32o N and 76o to 77o E Project area lies
in Una Constituency of the Una district Tehsil Una between the co-ordinates 31 o 17’ 30’’ N to
31o 30’ 0.0’’ N and 76o 15’ 0.0’’ E to 76o 22’ 30’’ E. The proposed headworks are located at
co-ordinates 31° 24' 09" N & 76° 22 ' 01"E to downstream of Bhakhra Dam & upstream of
Nangal Dam near Gurudwara Bhabour Sahib.
No flood control required in the area as whole and no provision under this head made in the
estimation. Whole area is situated 40 to 50 meter above the flood stream and banks are
channelized with good vegetation growth and hard natural rocks.
The intake structures are exiting i..e of LIS Bhabour Sahib (Phase-I & Phase-II) and project is
proposed for ERM only, hence no diversion of water or flood control measures have been kept
in the DPR.
6.2 DRAINAGE
The natural drainage exist in the area and no problem of water logging seen or observed during
the investigation. No provision under this head made in this DPR.
No provision of the power generation has been kept in the project as it is purely irrigation
project.
7.2 NAVIGATION
No Canal work, no dam and no storage reservoir proposed. Hence no Navigation provision has
been taken in the estimation.
CONSTRUCTION PROGRAMME
8.1 INTRODUCTION
The execution work of Medium Irrigation Project will be started after Techno-economical
clearance from competent authority, Govt. of India and availability of funds from Union Govt.,
State Govt. It is proposed to complete this project within Two working years. Accordingly,
construction planning has been made with a view to complete the project within the stipulated
period.
Consistent with the programme is accelerated completion of project within three years and to
have an effective qualitative aspect of work, necessary design and construction organizations
have been planned for execution of project. While all designs, specifications and planning shall
be under the charge of Chief/Superintending Engineer, all construction activities shall be under
the charge of one Executive Engineer- Jal Shakti Division No. I Una. Over all in – charge of
work including design etc. will be Chief/Superintending Engineer. There will be one sub-
divisions which including three sections with the complete staff of Surveyors, Draftsmen and
headed by Junior Engineer. No additional staff required.
The special tools & plants has not been taken in the estimate.
Year wise activity chart and funds required shown in the Table under Chapter 03 Irrigation
Planning.
There are many inherent problems in the existing infrastructure of LIP Bhabour Sahib I & II
which have contributed to the low utilization of irrigation potential created. The problem in
further compounded due to the leakage in the conveyance system. The rising mains (CI pipes)
and pumping machineries of the project are badly damaged, outlived their life and become
beyond economical repairs. It requires replacement and redesign. The soil in some villages in
the command area of this project is highly suitable for manufacture of bricks. After the project
was completed, there was boom in construction industry in the post 1991 era, many brick kilns
had come up. The owners of land in the area had sold the layer of top soil up to depth 1.5m to
3.0m to brick kiln owners. This badly damaged the existing RCC pipe mains and distribution
lines making the system non-functional.
Detailed survey and investigation were carried out of the whole command area. It was observed
that a limited quantity of 19.64 cusec could be lifted from the source as per agreement with the
BBMB authority, allowing only 0.157 lps per hectare in the Lift Irrigation Project Phase Ist and
0.1556 lps in the LIP Phase 2nd from reservoir. However, in most of schemes constructed by
Jal Shakti Vibhag, water requirement is of the order 0.45 LPS to 0.60 LPS per hectare. The low
water requirement adopted in this project has resulted in severe chronic water scarcity in all the
cropping seasons. Presently, the water supplied is not sufficient to irrigate the command area of
this project, inviting the wrath of public criticism and poor output from this project.
Experience from prevailing irrigation practice in state shows that if the duty less than 0.45 LPS
-0.60 LPS per hectare is adopted, it will not result any benefit of irrigation to the farming
community. These duties are minimal necessary and are being adopted in the new upcoming
projects of state. After careful consideration of the cropping pattern a design water requirement
of 0.48 LPS per hectare has been adopted as most techno-economical feasible.
The detail of the area to be covered under the project has been worked out by deleting the area
being used for non- agricultural purposes. Out of 3563 hectares of land proposed in the original
project, only 906.84 hectare is irrigated presently from this project. Ironically, the water levels
go down during months of December and January in day times when no water is released from
the Bhakra dam to Nangal dam. The intake area becomes dry and no pumping of water at
headworks, causing shutdown of the project. The project remains a show piece and source of
criticism. This also affects the pumping machinery. A suitable intake structure with positive
suction is required. The machineries which have gone beyond economical repairs or which
have outlived its designed life are required to be replaced.
Therefore, the project has now been proposed for extension, renovation & modernization of the
Lift Irrigation project providing irrigation facilities to a total CCA of 2266.71 hectares.
The survey works for Rising Mains, Distribution Mains and intake structures carried out and L-
sections of all the structures presented in the DPR.
9.3 COMMUNICATION & AVAILABILITY
Sites are connected with all-weather road upto main station and further linked with
local/Village roads for local communications & Transportation.
Availability of construction material and its transportation is not a problem. Sand, stone
aggregates, hard stone are available locally at Basal. Cement & steel available on all the HP
agro industries Stores, HP Civil Supplies Corporations at Jawalamukhi & Kangra. GMSERW
pipes & Pumping machinery available at Hissar/Delhi. HDPE pipes shall be provided by the
manufacturer directly and prominent are M/S Rockwell Industries Gagret having annual rate
contract. Road link to the sites are all weather and good communication facilities available.
Transportation from road to sites are possible through head load of 100 meters. Approved lead
chart from the department shall be considered for analysis & costing.
Ground Water:- The available groundwater in the command area is deep, > 30 meters, and it
is not considered for irrigation planning. Due to this scheme no adverse effect to the ground
water will happen.
Drainage Survey :- The main drainage in the area is natural nallahs , which during monsoon
flow & fed by the adjoining streams. The drainage grade in the command area is good & there
is no problem of water logging anticipated.
Hydro Power :- The scheme is for irrigation purpose and no provision made to generate the
power from this scheme.
INTERSTATE/INTERNATIONAL ASPECT
At the time of formulation of Bhakra Dam project in the country. It was envisaged that about
90,000 acres of land between Nangal and Ropar previously in Punjab, will be Irrigated from the
water of Nagal Dam reservoir. But out of 90,000 acres of land 14876 acres of land is now on
integrated part of Himachal Pradesh as mentioned above and it is what natural that as per
project report of the Bhakhra Dam. This area should be covered from the water of Nangal Dam
reservoir. In Bhabour Sahib project phase 1 an area of 923 hectares was only taken up to
provide immediate irrigation facilities and in the second phase another area of 2640 hectares
had been proposed to the provided with irrigation facilities. The intake for the water for the
phase 2nd has been kept at the same place as per phase 1 which is opposite to the famous
Gurdwara known as Bhabour Sahib.
The requirement of water has been worked out in details month wise and the same is appended
in the body of the estimate. The contribution due to rain fall has also been considered. The
Nangal Dam reservoir in under the control of B.B.M.B. and in the meeting with whom it was
agreed upon that the same duty for supply of water to this area should be adopted, although in
fact due to better technical know-how and research in Agriculture project the requirement of
water is much more.
It will also not be out of place to mention here that the people of Himachal Pradesh were only
suffers in the construction of Bhakra Dam as large tract of their fertile land got submerged in
the Govind Sagar Lake but the benefit from the Dam has not reached even up to the
expectations of the nearby population of the state of Himachal Pradesh till now. The matter
regarding release of water from Bhakra Nagal Lake was therefore, discussed in the Zonal
Council meeting where in it was decided the requirement being very small, the Himachal
Pradesh state should be allowed to draw water for its land from the reservoir for which Bhakra
Management Board should release water accordingly.
A reference had been made to Bhakra Management Board regarding question of water for the
purpose of irrigation from Nangal Dam reservoir and accordingly, It was decided in the
meeting of Chief Engineers from beneficiary state and B.B.M.B. that lifting of 19.64 cusecs of
water from Nangal Dam reservoir from a point below Gurdwara Bhabour Sahib free of cost as
per item no. 114.08 dated 19.09.1984 copy enclosed for ready reference and the extract from
the 114th meeting from B.B.M.B. held at Suraj Kund. (Copy Attached).
12.1 GENERAL
Benefit cost ratio has been worked out in detail in the attached statement taking to account the
difference in value of the produce in the pre-irrigation and post irrigation stage.
COST ESTIMATES
13.1 GENERAL
The Estimate has been prepared to arrive at the capital cost of the Medium Irrigation Project.
Detailed estimate of cost for civil works is based mainly upon various sample design/drawing
finalized for important structures and somewhere unitary based the rates are based as per
Himachal Pradesh Schedule of rates. Base Month & Year of the project cost is October 2023.
The enhanced labour rates as per 2023 Govt of Himachal Pradesh notification and most
competitive prevailing market rates have been considered to work out the analyzed rates on the
basis of HP-PWDSR-2020 & 2009. The best possible shortest route and economical mode of
transportation shall be considered to work out the cost of carriage.