DVC Quotation
DVC Quotation
Q/ST/231222/AA/231360/R0 1
TABLE OF CONTENTS
Sr.No. Description Page
1. SECTION 1: INTRODUCTION 3
2. SECTION 2 : PROCESS STAGES
2.1 Water Washing 5
2.2 Bleaching
2.3 Glycerolysis cum De-acidification
2.4 Transesterification
2.5 Methanol Rectification
2.6 FAME Distillation
2.7 Crude Glycerin Treatment
3. SECTION 3 : PROCESS STAGES
3.1 Water Washing 37
3.2 Bleaching
3.3 Glycerolysis cum De-acidification
3.4 Transesterification
3.5 Methanol Rectification
3.6 FAME Distillation
3.7 Crude Glycerin Treatment
3.8 Control panel
3.9 Erection material
3.10 THERMIC FLUID HEATER
3.11 Air compressor, air receivers
3.12 Cooling towers with pumping
4. SECTION 4: SPECIFICATION IN GENERAL
4.1 Specification Of Equipment 40
4.2 Specification Of Utilities
4.3 Makes Of Standard Bought out
4.4 Makes Of Instruments
5. SECTION 5 : GUARANTEES
5.1 Warranty of Equipment 40
5.2 Guarantees for Process Parameters
5.3 Typical Product Specification
5.4 Guarantees for the Utilities & chemicals
6. SECTION 6 : TECHNICAL SERVICES
6.1 Documentation 48
6.2 Additional documentation
6.3 Specialists Services
6.4 Services for Installation & Commissioning
7. SECTION 6 : BATTERY LIMITS & EXCLUSIONS
7.1 Battery Limits for Process 48
7.2 Battery Limits for Utilities
7.3 Key Exclusions
7.4 Exclusions from Scope of Supply of Seller
8. SECTION 8 : COMMERCIAL 50
Q/ST/231222/AA/231360/R0 2
SECTION 1 : INTRODUCTION
DVC is showing continuous phenomenal growth due to its in-depth technological expertise,
understanding of Industry’s needs in better way in today’s competitive environment and trust
developed over the years.
Process innovation, excellent project management skills and continued customer support are
our core strengths. The company has a team of technologists and engineers, who have vast
experience in the vegetable oil processing and extraction Industry.
DVC offers single point solutions to the processors for the following:
• Edible Oil Refinery for all major feed-stocks like Soybean, Sunflower, Rapeseed, Palm,
Rice Bran and Cottonseed oils.
• By-products processing in Refinery like Wet Gum Drying (Lecithin) and Acid Oil etc.
• Solvent Extraction Plants including Soy White Flakes production system by Flash De-
Solventization technique of the de-oiled soy meal.
• Complete PLC based process automation with reputed make hardware & field instruments
for its plants; this has helped in making PLC system affordable to every processor.
The company has its own equipment ISO certified manufacturing facility near Pune to
manufacture its state of art equipment with stringent quality control.
DVC has strong Customer Service arm, which ensures support to its customers on continual
basis. This dedicated wing of company also undertakes systematic technical audit of existing
process plants for identifying and addressing areas that need improvement in the process
plant, which can be converted for process optimization and quality of end product at best
possible commercial scale. Based on findings of technical audits the necessary modifications
/ up gradation in the existing plant are undertaken and completed in timeframe offered during
shutdown.
The company has long list of its satisfied domestic as well as overseas customers and many
of them have placed repeated orders showing their enhanced confidence.
Q/ST/231222/AA/231360/R0 3
DVC’s achievement includes:
➢ Over 200+ references including Europe, USA, Australia, Middle East & Africa.
With innovative skills in Process Development and Engineering, DVC is committed to serve the
Fats & Oils processing Industry in a best way in the times to come!
Thank you,
D.V. Chame
Promoter & CEO
Q/ST/231222/AA/231360/R0 4
SECTION 1. PROCESS STAGES
BIODIESEL COMPLEX
BLEACHING GLYCEROLYSIS
FFA: <10
CATALYST
1010 DEACIDIFICATION
FATTY ACIDS
FRESH TRANSESTERIFICATION
METHANOL GLYCEROL/HEAVY PHASE
HCL
RECTIFICATION FAME
DESOLVENTISATION ACIDULATION
FATTY
ACIDS
Q/ST/231222/AA/231360/R0 5
2.1 WATER WASHING
Q/ST/231222/AA/231360/R0 6
2.2 PRETREATMENT BLEACHING
Q/ST/231222/AA/231360/R0 7
2.3 GLYCEROLYSIS CUM DEACIDIFICATION
Q/ST/231222/AA/231360/R0 8
2.3 TRANSESTERIFICATION
The pre-treated feedstock is subjected to transesterification reaction. This is reaction of lipid with an
alcohol to form esters and a byproduct. It is in principle the action of one alcohol displacing another
to from an ester, termed as alcoholysis. It is a reversible reaction therefore excess of alcohol is used
to shift the equilibrium to product side.
Q/ST/231222/AA/231360/R0 9
2.4 METHANOL RECTIFICATION
Q/ST/231222/AA/231360/R0 10
2.5 FAME DISTILLATION
Q/ST/231222/AA/231360/R0 11
2.6 CRUDE GLYCERIN TREATMENT
4. HOT WATER Hot water is added to reactor R1841 through the inline mixer
WASHING IM1845A and kept in circulation by Pump P1841. Bottom layer
of acidic water is drained in Tank T1844 and send to ETP by
pump P1844. Acid oil is drained in the tank T1843 and is
transferred by Pump P1843 to Storage.
Q/ST/231222/AA/231360/R0 12
SECTION 3 : SPECIFICATION OF EQUIPMENT
P302 PUMP
Pump for recirculation to washing reactor. Body CS with Suitable 01
Type: Centrifugal PVDF lining
Complete with casing, impeller, base plate,
mechanical seal and coupling & motor.
T307 TANK
Tank for receiving the wash water after CS with FRP Suitable 01
settling in the reaction vessel lining
P307 PUMP
Pump for conveying wash water to ETP Body CS with Suitable 01
Type: Centrifugal PVDF lining
Complete with casing, impeller, base
plate, mechanical seal and coupling &
motor
LIST OF INSTRUMENTS:
Sr. Instrument Description Qty.
No Code
1. PI 01 PRESSURE INDICATORS 1S
Pressure Indicators dial type with connection accessories
2. TI 21 TEMPERATURE INDICATORS 1S
Temperature indicators dial type with SS304 pockets for
connections.
Q/ST/231222/AA/231360/R0 13
3.2
Eq. Description MOC of Cap. Qty.
Code contact &Size
Parts
T611 TANK(Acid)
Tank for buffer storage of acid reagent. The cylindrical SS316 Suitable 01
tank with top lid is provided with necessary outlet nozzle
for acid.
B602 BLEACHER
Bleaching Reactor is designed to homogenize the earth SS304 Suitable 01
– oil slurry and providing necessary retention time
under vacuum of 50 mm of Hg for efficient bleaching.
The Bleacher is Cylindrical dished end design provided
with agitator complete with nozzles & manholes
Q/ST/231222/AA/231360/R0 14
Eq. Code Description MOC of Cap. Qty.
contact &Size
Parts
Q/ST/231222/AA/231360/R0 15
Eq. Code Description MOC of Cap. Qty.
contact &Size
Parts
C606 CYCLONE
Cyclone vessel for separation of steam from Carbon Steel Suitable 01
Oil & slurry during cleaning operations of
filters.
LIST OF INSTRUMENTS
Q/ST/231222/AA/231360/R0 16
3.3 GLYCEROLYSIS CUM DEACIDIFICATION
T1903 TANK
Tank for the storage of glycerin required for SS304 Suitable 01
Glycerolysis process, provided with necessary inlet
outlet nozzles, sight glass and measuring or
calibrated glass.
DEACIDIFICATION COLOUMN
Deodorizer Column comprise of Two Rated 01
Sections – Capacity
D802 1. TOP Section –STRIPPER
Stripper is cylindrical tower with dished end at top and SS304
bottom is mounted on the deodorizer vessel; it Packs SS316
comprises of structural packing bundles installed one
over the other vertically. At the top there is liquid
distributor for uniform distribution of oil.
D802A 2. LOWER Section – RETENTION VESSEL
Equipped with coils for Thermic Fluid and cooling SS304 Suitable
water, Sparge steam arrangement, Nozzles for
Temperature and pressure indication. Sight glass
and Manholes are also provided.
Design :- Thermic fluid Coils –
SS316 seamless Schedule10
Q/ST/231222/AA/231360/R0 17
Eq. Description MOC of Cap. Qty.
Code contact &Size
Parts
P803 PUMP
Pump for circulating the oil in D802 and after SS304 Suitable 01
completion of Deodorization process the oil is
transferred to storage.
Type: Centrifugal
Complete with coupling and motor.
D804 SCRUBBER
Scrubber is designed for the separation of SS304 Suitable 01
distillate and volatiles from vapors coming out of
Deodorizer. The vapor scrubber is a cylindrical
column provided internally with structured
packing for vapor scrubbing. The scrubber is
equipped with manhole, sight glass and
distribution system for uniform distribution of
distillate on structured packing.
The scrubber is connected by vapor duct with
Deodorizer.
Q/ST/231222/AA/231360/R0 18
Eq. Description MOC of Cap. Qty.
Code contact &Size
Parts
LIST OF INSTRUMENTS
Q/ST/231222/AA/231360/R0 19
3.4 TRANS-ESTERIFICATION
P1801 PUMP
Pump for feed oil into the trans-esterification Carbon Steel & Suitable 01
process. SS304
Pumps complete with baseplate, coupling,
mechanical seal and FP motor.
T1850 TANK
Tank for the intermediate storage and feeding SS304 Suitable 01
the methanol into the process.
P1850 PUMP
Pump for charging methanol into the trans- Carbon Steel Suitable 01
esterification reactors.
Type: Centrifugal
Pumps is complete with baseplate, coupling,
mechanical seal and FP motor.
T1851 TANK
Tank for the intermediate storage and feeding SS304 Suitable 01
the catalyst solution in to the process.
P1851 PUMP
Pump for the metering the solution. LCP Suitable 01
Type; Plunger SS316
Pump is complete with base frame and FP
motor.
R1803 REACTOR
Reactor are equipped with agitator for SS304 Suitable 01
dispersing the catalyst and alcohol.
The vessel will be equipped with sight glass,
light glass, nozzles. Each reactor is provided
arrangement for sampling of the product.
The vessel is also equipped with mechanical
seal and variable speed drive.
Q/ST/231222/AA/231360/R0 20
Eqpt. Description MOC of Cap. & Qty.
Code contact parts Size
P1803 PUMP
Pump for re-circulation of mass in the reactor LCP Suitable 01
And transfer to further process. SS304
Type: Centrifugal
Pump is complete with baseplate, coupling,
mechanical seal and FP motor.
T1812 TANK
Tank for the intermediate storage of Carbon Steel Suitable 01
separated glycerin from the reactors.
P1812 PUMP
Pump for transferring the separated glycerin. Carbon Steel Suitable 01
Type: Centrifugal & SS304
Pump is complete with baseplate, coupling,
mechanical seal and FP motor.
T1833 TANK
Tank for hot water required for washing of SS304 Suitable 01
FAME provided with all necessary nozzles.
P1833 PUMP
Pump for transferring soft hot water to FAME LCP Suitable 01
wash tank T1807 SS304
Type: Centrifugal
Pump is complete with baseplate, coupling,
mechanical seal and FP motor.
T1811 TANK
Tank to store citric acid solution to SS316 Suitable 01
neutralize the alkalinity of the FAME
T1807 TANK
Tank for treatment of FAME with citric acid Carbon Steel Suitable 01
and water washing
Q/ST/231222/AA/231360/R0 21
Eqpt. Description MOC of contact Cap. & Qty.
Code parts Size
P1807 PUMP
Pump for transfer of FAME circulation & CS Suitable 01
drying. & SS304
Type: Centrifugal
Pump is complete with baseplate, coupling,
mechanical seal and FP motor.
D1808 DRYER
Dryer for removing residual moisture from Carbon Steel Suitable 01
the washed FAME. Provided with spray
nozzle assembly and necessary nozzles.
P1808 PUMP
Pump for the transfer of FAME to dryer CS & Suitable 01
Type: Centrifugal SS304
Pump is complete with baseplate, coupling,
mechanical seal and FP motor.
T1809 TANK
Tank for draining of washed soapy water. Carbon Steel Suitable 01
P1809 PUMP
Pump for conveying soapy water to further Carbon Steel Suitable 01
treatment.
Type: Centrifugal
Pump is complete with baseplate, coupling,
mechanical seal and FP motor.
EJ1800 EJECTOR
Ejector for the low suction pressure in the Carbon Steel Suitable 01
process.
Q/ST/231222/AA/231360/R0 22
3.5 METHANOL RECTIFICATION
T1855 TANK
Tank for the collection of wet methanol. Carbon Steel Suitable 01
P1855 PUMP
Pump for conveying wet methanol to CS & SS304 Suitable 01
rectification tower.
Type: Centrifugal
Pump is complete with baseplate, coupling,
mechanical seal and FP motor.
P1856 PUMP
Pump for circulation of wet methanol via heat CS & SS304 Suitable 01
exchanger E1857.
Type: Centrifugal
Pump is complete with baseplate, coupling,
mechanical seal and FP motor.
Q/ST/231222/AA/231360/R0 23
Eqpt. Description MOC of Cap. & Qty.
Code Contact Parts Size
T1859 TANK
Tank for receiving condensed methanol. Carbon Steel Suitable 01
P1860 PUMP
Pump for conveying reflux to distillation tower CI Suitable 01
for purification & conveying rectified methanol.
Type: Centrifugal
Pump is complete with baseplate, coupling,
mechanical seal and FP motor.
Q/ST/231222/AA/231360/R0 24
LIST OF INSTRUMENTS
Q/ST/231222/AA/231360/R0 25
3.6 FAME DISTILLATION
P2005 PUMP
Pump for conveying pitch through heat CS & SS304 Suitable 01
exchanger E2004.
Type of pump: Centrifugal
Pump complete with casing, impeller, base
plate, mechanical seal, and coupling and
FP motor.
P2007 PUMP
Pump to circulate and transfer condensed CS Suitable 01
methyl esters in scrubbing zone & &
conveying to storage. SS304
Type of pump: Centrifugal
Pump complete with casing, impeller, base
plate, mechanical seal, and coupling and
FP motor.
Q/ST/231222/AA/231360/R0 26
Eqipt. Description MOC of Cap. & Qty.
Code Contact Parts Size
Q/ST/231222/AA/231360/R0 27
LIST OF INSTRUMENTS
Sr. Instrument Description QTY
No Code
Q/ST/231222/AA/231360/R0 28
3.7 GLYCERIN TREATMENT
Q/ST/231222/AA/231360/R0 29
Eqpt. Description MOC of Capacity Qty.
Code Contact parts & Size
P1843 PUMP
Pump for pumping the acid oil from acid oil Body CS with Suitable 01
Tank T1843 storage. PVDF lining for
Type: Centrifugal contact parts
Pump complete with casing, impeller, base
plate, and mechanical seal and coupling and
motor.
T1842 TANK
Tank for receiving glycerin after settling in CS with FRP Suitable 01
reaction tank. lining
Cylindrical tank with conical bottom and is
complete with necessary inlet and outlet
nozzles.
T1844 TANK
Tank for receiving acidic water after washing in CS with FRP Suitable 01
reaction tank. lining
Cylindrical tank with conical bottom and is
complete with necessary inlet and outlet
nozzles.
P1844 PUMP
Pump to convey the acid water from acid water Body CS with Suitable 01
storage to ETP. PVDF lining for
Type: Centrifugal contact parts
Pump complete with casing, impeller, base
plate, and mechanical seal and coupling and
motor.
Q/ST/231222/AA/231360/R0 30
LIST OF INSTRUMENTS
Q/ST/231222/AA/231360/R0 31
3.8 CONTROL PANEL
Q/ST/231222/AA/231360/R0 32
3.9 ERECTION MATERIAL
Q/ST/231222/AA/231360/R0 33
3.10 Thermic Fluid Heater
Q/ST/231222/AA/231360/R0 34
3.10 PRS, AIR COMPRESSOR, AIR RECEIVERS
AC AIR COMPRESSOR
Air Compressor with receiver & built in dryer Carbon Suitable 01
Air compressor for providing necessary dry Steel
andclean instrument air required for various
instruments in Refinery.
AR AIR RECEIVER
Air receiver designed to supply continuous Carbon Suitable 01
airfor the Process instruments and equipment. Steel
Q/ST/231222/AA/231360/R0 35
3.11 COOLING TOWERS WITH PUMPING
Q/ST/231222/AA/231360/R0 36
SECTION 4 : SPECIFICATIONS IN GENERAL
2. The scope of piping will be as per the points indicated separately in the battery limits
in this offer. The Seller and Purchaser jointly to reach logical decision shall discuss
any point, which is not clearly specified in scope,
4. The thickness of insulation for pipelines and equipment shall be considered as per
insulation schedule, which is based on heat insulation requirement.
5. The mentioned makes of equipment in this offer, are subjected to delivery schedule
and may vary in case not meeting the project deliveries. However, such change shall
be brought to the Purchaser’s notice before taking such decision.
6. All the pressure vessels will be according to ASME standard, div1, and will be
calculated, constructed, inspected and tested as per engineering procedures. Other
non-pressure equipment will be according to good engineering practices.
Q/ST/231222/AA/231360/R0 37
4.2 SPECIFICATIONS OF UTILITIES
02 Cooling water
0
Temperature C 32
Pressure kg/cm2 03
Hardness mg/liter 1.8 -
3.5
Chloride content mg/liter 50
pH content 7-8
Langelier saturation index -0.25 to
+0.25
Sulphate Ppm < 1000
Sodium bicarbonate Ppm < 200
03 Compressed air
Pressure kg/cm2 6
0
Dew point C -20
04 Power
Phases N 3
Frequency Hz 50
Volts V 400
Q/ST/231222/AA/231360/R0 38
4.3 MAKES OF STANDARD BOUGHT OUT
EQUIPMENTS
INSTRUMENTS
Note – Above makes are w.r.t the equipment mentioned in Section 3 and subject to change
depending on availability.
Q/ST/231222/AA/231360/R0 39
SECTION 5 : GUARANTEES
5.1 WARRANTY OF EQUIPMENT
Seller provides warranty on the supplied equipment towards mechanical, workmanship & other
standard bought out supplied equipment for a period of (18) eighteen months after delivery or (12)
twelve months after commissioning whichever comes first, subjected to operation / handling of
equipment by the Purchaser as per Seller’s instructions. This warranty however is not applicable for
normal wear and tear of any supplies.
Within the warranty period as specified above, upon notification and confirmation of defective part(s)
or equipment, Seller shall provide a free replacement on one for one exchange basis. However, the
cost incurred for performing the replacement work including the service of the skilled and unskilled
labor is not within Seller’s scope.
B. FEED SPECIFICATIONS:
Q/ST/231222/AA/231360/R0 40
5.3 TYPICAL PRODUCT SPECIFICATIONS
b. CRUDE GLYCERIN
Q/ST/231222/AA/231360/R0 41
5.4 UTILITIES & CHEMICALS CONSUMPTIONS
Seller offers below consumption of utilities and chemicals during steady state operation of the plant
per metric ton of feedstock processed. The variation during measurement shall be +/- 10% and the
utilities to be measured for the sections offered by Seller. Methods for the determination of
Performance shall be worked out jointly between Seller and Purchaser.
1. PRETREATMENT OF FEEDSTOCK
Q/ST/231222/AA/231360/R0 42
BIODIESEL PRODUCTION
Sr. Parameter Unit Wash. Bleac Glycer Trans- FAME Rect. Glyc Total
No. h. olysis Ester. Dist. & Of Treat Cons.
De- MeOH
acid.
CHEMICALS
1. Phosphoric Kg/ - 0.5 - - - - - 0.5
acid MT
2. Activated Kg / - 10 - - - - - 10
Bleaching MT
Earth
3. Methanol Kg / - - - 130 - - - 130
MT
4. Catalyst Kg / - - - 8 - - - 8
(Sodium MT
methoxide –
100%)
5. Citric acid dry Kg/ - - - 0.7 - - - 0.7
MT
6. Refined Kg/ - - 110 - - - - 110
Glycerin (on MT
100% FFA
Basis)
7. Hydrochloric Kg/ - - - - - - <47 47
acid by weigh T
of heavy phase
Q/ST/231222/AA/231360/R0 43
SECTION 6 : TECHNICAL SERVICES
6.1 DOCUMENTATION
Seller shall provide two sets of the following documents in English as per schedule
mentioned below-
Proposed Equipment GA Layout Three weeks from the receipt of order along
with full advance
Foundation Drawings Three weeks from the receipt of approved
Equipment GA Layout from the Purchaser
Motor list, major equipment list and Utilities Four weeks from the receipt of order along
list with full advance
Process and instrumentation drawings Shall be discussed and mutually frozen by
Seller within Six weeks from the receipt of
order with full advance.
Electrical and instrument installation drawing Shall be discussed and mutually frozen by
Seller within Six weeks from the receipt of
order with full advance.
Operating instructions & Maintenance Two weeks prior to start-up of
Manual Pre-commissioning activity.
Q/ST/231222/AA/231360/R0 44
6.4 SERVICES FOR INSTALLATION & COMISSIOING
A. SELLER’S SCOPE
1. Provide skilled personnel to carry out installation of equipment and erection material
supplied by seller at the Project site for the activities described below.
2. Undertake erection in areas of mechanical & piping and of equipment & accessories
supplied by Seller as mentioned in this proposal.
3. Undertake final alignment of all equipment and pressure testing of all pipe lines after erection.
4. To carry out insulation and cladding of equipment, tanks and piping inside the plant.
5. Undertake electrical cabling work and instrument & control panel installation.
6. Carry out mechanical runs of all the plant, machinery and equipment.
7. Provide welding machine, cutting set and consumables like welding rod, gas, etc.
8. Provide skilled & unskilled man-power support for the erection, piping & commissioning activities
B. PURCHASER’S SCOPE
1. Carry out of complete civil and supply, including site grading and preparation, factory and utilities
buildings, equipment and machinery foundations, rack foundation within plant
Battery limits.
2. Carry out of casting of foundations and grouting of base plates of equipment.
3. The equipment will be installed on the foundations, aligned and foundation bolts inserted by us
before the same are released to you for grouting and finishing.
4. Provide lifting equipment like chain block, crane, etc.
5. Carry out building lighting and earthing network.
6. Supply of uninterrupted facilities like power, steam and water at specified points.
7. Provide site office with facilities to keep and safeguard all engineering documents as well as
special tools belonging to us.
8. Free issue of all machinery, equipment, components and accessories kept by Purchaser to
Seller as and when required to carry out erection.
9. Provide Personal Protection Equipment like Helmet, safety glasses, belt, etc.
10. Obtain all necessary licenses, permissions, and sanctions such as approvals by Factory
inspectorate, Boiler inspectorate, explosive authorities, electrical inspectorate, pollution
authority and other statutory authorities.
11. The safety and fire-fighting facilities at project site.
Food, Accommodation, Local Conveyance to all the personnel of Seller and Seller’s Sub-
contractor.
Q/ST/231222/AA/231360/R0 45
SECTION 7: BATTERY LIMITS AND EXCLUSIONS
7.1 BATTERY LIMITS OF PROCESS
A: PRE-TREAMENT
WASHED OIL:
Washed oil line is to be terminated at the outlet of the Tank T303 by Seller.
UCO/ TALLOW:
UCO / Tallow line is to be provided by the Purchaser at the strainer F601 near suction of the
pump P601.
BLEACHING EARTH:
Bleaching earth as per specifications of Seller is to be provided by the Purchaser at the tank
DH632 of bleaching plant.
SPENT EARTH:
Spent earth is to be left at the ground floor via chute below PLF601 & PLF602. Purchaser to
make arrangement for further disposal.
DEACIDIFIED OIL:
De-acidified oil line is to be terminated by Seller at the outlet of the Heat Exchanger E805.
Purchaser to make arrangement of storing de-acidified oil.
B. BIODIESEL PRODUCTION
PRETREATED OIL:
Pretreated oil line is to be provided by the Purchaser at the suction of pump P1801
METHYL ALCOHOL:
Methyl alcohol is to be provided by the Purchaser at the tank T1850.
CITRIC ACID:
Citric acid solution is to be provided by the Purchaser at the tank T1811.
GLYCERIN:
Crude Glycerin line is to be terminated by Seller at the outlet of heat exchanger E1814.
Q/ST/231222/AA/231360/R0 46
PROCESS WATER:
Process Water is to be provided by purchaser at inlet of tank T333.
FAME:
FAME line is to be terminated by Seller at the outlet of the heat exchanger E2006.
WASH WATER:
Wash water line is to be left by Seller at the outlet of pumps P307 & P1825A. Purchaser to carry
the same for further treatment.
STEAM:
Steam line as per Seller’s specification is to be made available by the Purchaser at the inlet of
Pressure Reducing Stations in Process House.
*Note: Steam Boiler, Boiler Feed water & condensate water and its piping in in Purchaser’s scope.
INSTRUMENT AIR:
Instrument air as per Seller’s specification within the Process House, is to be provided by Seller.
(Compressor & receiver in Seller’s scope)
POWER:
Power cable along with the earthing shall be connected by the Purchaser at the main isolator of the
common control panel supplied by the Seller.
EARTHING SYSTEM
Earthing cable and instrument earthing is to be provided by Purchaser up to the electrical & Control
Panel.
Q/ST/231222/AA/231360/R0 47
6.4 KEY EXCLUSIONS:
Q/ST/231222/AA/231360/R0 48
6.5 EXCLUSIONS FROM THE SCOPE OF SELLER
Q/ST/231222/AA/231360/R0 49
SECTION 7: COMMERCIAL
6.1 PRICE SUMMARY
A. PRICE BASIS
• The above-mentioned prices are EX-WORKS, JEJURI or SUB-SUPPLIERS.
• The charges towards packing & forwarding are included in price.
• GST, transportation and transit insurance are excluded and to Purchaser’s account.
• The above prices are in reference to Seller’s equipment and plant design parameters, any
deviation in later stage of the project will be at additional price settled mutually.
• The charges towards third party inspection will be extra and to be borne by Purchaser.
• Facility for internet, email and telephonic communication for Seller’s personnel at Site to be
provided by Purchaser
• Purchaser shall complete all site activities before arrival of installation & commissioning
engineer / team at site.
• All Travel and stay expenses including return tickets, airport transfer, local conveyance,
accommodation, food, laundry, etc. for Seller’s personnel or Seller’s subcontractors, to be
provided by Purchaser.
• Medical facility in case of emergency to be provided by Purchaser.
• During installation any failure of the machines, purchaser has to provide support and if possible,
arrange the same locally for which charges has to be paid by seller.
B. STATUTORY VARIATION
The above prices quoted are based on the prevailing rate of the tax and duties. Any Additional
cost due to variation in rates or structure of tax and duties, new implementation of taxes and
duties shall be borne by the Purchaser.
Q/ST/231222/AA/231360/R0 50
C. TERMS OF PAYMENT
For Supply
40% Advance to be credited to Seller’s account on the date of the purchase order by Purchaser.
Balance along with all applicable taxes, duties, levies and charges against Proforma Invoice
before dispatch
For Services
40 % advance along with order and balance 60% against progressive bills including all
applicable duties, taxes and any other levies.
For delay beyond the agreed period, for reasons not attributed to the Seller, services will be
charged additionally @ 15,000 INR/man-day.
E. VALIDITY
Our proposal is valid for your acceptance till one month from the date of this proposal and is
subject to our confirmation thereafter.
F. DELIVERY
For supply of equipment: The goods shall be ready for dispatch in 20 weeks on Ex-Works
Basis from the receipt of confirmed Purchase Order on Seller along with advance payment.
The Partial shipment of material shall be allowed considering the exhaustive scope of supply.
G. INSPECTION
The Purchaser is free to carry out inspection at Seller’s works OR workshops of sub-suppliers
of seller on advance notice of minimum 5 days prior to inspection. The cost towards lodging,
boarding and conveyance required for inspection shall be borne by the Purchaser. All third party
inspection cost to be borne by Purchaser.
H. CANCELLATION
In case of cancellation of the order the Purchaser is liable to compensate for the cost incurred
on work carried till the date of the cancellation by Seller.
Q/ST/231222/AA/231360/R0 51
I. FORCE DE MAJEURE
Force majeure shall mean any circumstances beyond the reasonable control of the Seller
which prevent or impede the due the performance of the Agreement including but not limited
to war or hostilities or war like conditions such as acts of God, Riot or civil commotion, epidemic,
famine, earthquake or flood, fire or other natural physical disaster or denial of use of any railway
port or airport or shipping services or other means of transport or strike lockout or other industrial
action.
Federal, State, local Municipal legislation, Ruling or Ordinance, notice order or any situation
affecting the Agreement. The mere shortage of labor or materials or utilities will not constitute
force majeure unless caused by circumstances which are themselves force majeure. The Seller
shall not be held responsible for any loss or damages caused by such reasons.
K. EXCESS MATERIAL
The erection material, wrong supplies due to mistakes & tools tackles after completion of the
work will be property of the DVC. Purchaser shall allow DVC’s representative to take back such
material to DVC’s workshop.
L. JURISDICTION
All disputes and differences arising out of or connected with this transaction failing amicable
settlement shall be referred to jurisdiction of courts of Pune or the place is to be decided jointly
if such disputes occur.
FOR
DVC PROCESS TECHNOLOGISTS
Q/ST/231222/AA/231360/R0 52