Network Analysis
Network Analysis
Network Analysis
The need for the Project no longer exists and the Project is
terminated.
Upgrade
Product
Life Business
Operations
Divestment
Cycle Plan
I
D
E
Product
A
Organization
Performs Work
to achieve objectives
Projects Operations
. Temporary and Unique . Ongoing & repetitive
. Purpose to achieve objective . Objective is to sustain
And then terminate business
. Market demand
. Organizational need
. Customer request
. Technological advance
. Legal Requirement
• Project control
– This stage calls for periodic updating of the network
amongst other things to monitor the progress of the
Project, and making necessary changes in the
schedules to ensure completion of the Project as
close to the target time as possible.
• Project
Temporary endeavor undertaken to create a unique Product,
Service or Result.
• Work breakdown structure (WBS)
A work breakdown structure is a deliverable oriented grouping of
project elements that organizes and defines the total scope of the
project.
Work not in the WBS is outside the scope of the project.
As with the scope statement, the WBS is often used to develop or
confirm a common understanding of project scope. Each
descending level represents an increasingly detailed description of
the project elements.
• Activity
Is a task or item of work to be done, that consumes time, effort,
money or other resources.
• Event
– Events do not consume resources.
– Events are represented by circle
– An Event is realized only when all activities
terminating at it are completed.
start finish
B D
The number 5 over the arrow indicates the Time required for completion of the
activity
A
1 2
5
1 2
H C.E,G
I F G
H
E
F
4
2 G
A E I
H
1 5
6
C
B
D
3
D B C G B H
F
A
E D
G
I
G H
F
2 E
A D
5
1 B D F 9
41 D H
7 I
C 2
G D3 D4 8
3 6
E G(19) E
2 5
L L H(4)
C(20)
D1
D2
0
B(8) E F(18) E
1 E I(10)
0 4 6 7
L L
L
A(23)
D(16)
E(24)
E
3
L
20 G(19) 39
2 5
L L H(4)
C(20)
D1
8,39 D2
43, 67, 47
0 39, 57
B(8) F(18)
39 67
57 I(10)
1
0 4 6 7
L L
L
A(23)
D(16)
E(24)
23
23
3
L
Hence earliest completion of Project time
is 67 days
C (1-2) 20 0 20 18 38 18
D1 (4-5) 0 39 39 57 57 18
F (4-6) 18 39 57 39 57 0
D2 (5-6) 0 39 39 57 57 18
H (5-7) 4 39 43 63 67 24
I (6-7) 10 57 67 57 67 0
0 B (6)
1 8 E (3) 17 I (10) 28
0 4 6 7
15 18 28
C (8) D K (3)
H (5)
8 G (4) 12 J (16)
3 5
Activity I: 8 12
Total Float = 28 – 17 - 10 = 1 day
Activity F:
Total Float = 18-7-5 =6 days
If F absorbs all its float then I has no float, but if F absorbs only 5 days of its float then I still has its 1 day float
The float in an activity which can be used with out affecting float of any succeeding activity is called as Free Float
Consider activity K: If the tail event of this K activity is reached as late as possible and the Head event of the
activity starts as early as possible then the float for K is 17-8-3 = 6 days. This float of 6 days whose absorption
does not affect neither preceding activity nor the subsequent activity is called Independent Float
3 13 3 16
7
2 4 6 12
3 13 16
3
8
24 10 34
0 6
4 8 9
1
24 34
0
9
2
7 7 14 19 8
3 5 5 7
7 15 26
7 8 3-5(13-15) 2 In Progress
7 1 1
3 5 4 5 7 9 4-6(14-16) 4 In Progress
7 1 2
5 6 5-7(15-17) 5 Not started
5-8(15-18) 9 Not started
6-8(16-18) 8 Not started
6-9(16-19) 12 Not started
Updated Network after day 15 of the 7-9(17-19) 10 Not started
(Finished
Project 3 1 4-6) 2
1 4 1 8-9(18-19) 8 Not started
7 1 5
2 4 3 1 9
4 1
3 1
3
5
6 1
9
1
New critical path
3
8 2
8
1-2-3-4-14-16-18-19
6 2 3
0 7 5
4 1 1
1 8 9
2 3
0 9
7 5
2
1
Project duration
7
(Finished
3-5) 8
1
5
2 1 2
0
increased by 1 day
1 7 2
3 1 1
7
3 1
5
5 1
8
5
7 2
5
to 35 days
7 7 14 19 8 4-6(10-16) 4 In Progress
3 5 5 7
7 15 26 5-7(15-17) 5 Not started
5-8(15-18) 9 Not started
6-8(16-18) 8 Not started
1
0 15
10
15 27 35
Project duration
0 15
2
9
10 increased by 1 day
17 22
15
18 5 17
25
to 35 days
10/3/2020 Project Management Using Network Analysis
Probability Assessment in PERT Network
• 3 time estimates are used for every activity
• Most optimistic time (to): it is the duration of the
activity when everything goes well. It is assumed
that such performance can be improved only in
about 1% of the cases
• Most likely time (tm): Normal time the activity would
take. It is the time that would occur most often if the
activity was to be repeated several times under the
same conditions.
• Most Pessimistic time (tp): It is the longest duration
expected under the assumption that every thing
goes wrong. There is only 1 % chance that the
activity will extend beyond this value.
• Expected Time (te) is given by (to + 4 tm + tp)/6
• Standard Deviation ( σ ) is given by (tp - to)/6
• Variance is given by ( σ )2
1 3 6 12
2 8 9 10
3 6 8 10
4 2 5 8
5 3 9 12
6 3 4 5
1-2 1 4 7
1-3 5 10 17
2-4 3 3 3
2-6 1 4 7
3-4 8 15 26
3-5 2 4 8
4-5 5 5 5
5-6 2 5 8
9, 8, 13 21 F E 5 4 5 8 3
G A, D, 12 8 3 4 0.25
C
0 A(10) 14
1 4 G(8)
0 14
D1(0)
13
22
3
14 6
22
B(8)
D(6)
C(5) F(5)
16
8
5
2 21
8
E(8)
0 A(10)
13
1
0 4 G(8)
D1(0) 13
13
3 21
B(8) 13
6
D(5) 21
C(5)
16
F(5)
8 5
16
2 E(8)
8
C(5) C B 5 4 8 14 6
16
F(5)
8 5
16 D B 6 4 11 15 2
2 E(8)
8
E B 8 5 9 15 2
F E 5 4 5 8 3
Critical Path
11
3
11 6
9
0
17
1
0 4
6 17
5
5
10
2 10
5
3
10 6
9
Normal Project Time = 17 days 0
16
Normal direct cost = Rs. 800/- 1 4
0
Total Project cost 5 16
= Normal direct cost + Indirect cost / day x Duration of the Project
= 800 + 120 x 17 = Rs. 2840 5
5
Critical path 1-2, 2-3, 3-4 10
2
Activity 1-3 and 2-4, each have a float of 2 days 5
Crashing activity critical with minimum cost slope i.e. activity 2-3 we get
10/3/2020 Project Management Using Network Analysis
10 Activity Normal Crash Normal Crash Cost
3 Time Time Cost Cost Slope
10
9
6 (days) (Days) (Rs.) (Rs.) (Rs.)
0
1-2 5 4 170 240 70
16
1
0 4 1-3 9 6 310 550 80
5 16
2-3 6 4 80 200 60
5
5
10 2-4 10 8 130 230 50
2
5
3-4 6 4 110 290 90
9
3
Project Time = 16 days 9 6
9
Direct cost = Rs. 800/- + 60 = Rs. 860
0
Total Project cost 15
1
= Direct cost + Indirect cost / day x Duration of the Project 0 4
4
15
= 860 + 120 x 16 = Rs. 2780
Critical path 1-2, 2-3, 3-4
5
Activity 1-3 and 2-4, each have a float of 1 days 5
10
Crashing critical activity with minimum cost slope i.e. activity 2-3 we get 2
5
0
1-2 5 4 170 240 70
15
1
0 4 1-3 9 6 310 550 80
4 15
2-3 6 4 80 200 60
5
5
10 2-4 10 8 130 230 50
Project Time = 15 days 2
5
Direct cost = Rs. 860/- + 60 = Rs. 920 3-4 6 4 110 290 90
Total Project cost
= Direct cost + Indirect cost / day x Duration of the Project
= 920 + 120 x 15 = Rs. 2720
Critical path: All paths are critical viz. 1-2-3-4; 1-2-4 & 1-3-4
Now Activity 1-3 and 2-4, do not have any float
Activity 2-3 has reached its crash duration and cannot be reduced further
Crashing options
a) Crash 1-2 & 1-3 at a crash cost of 70+80=Rs.150
b) Crash 2-4 & 3-4 at a crash cost of 50+90=Rs. 140
8 9
3 3
8 6 9 5
8 9
0 0
14 14
1 1
0 4 0 4
4 14 4 14
4 5
4 5
10 9
2 2
4 5
2-3 6 4 80 200 60
0 0
14 14
1 4 1 4
0 4 14 0 4 14
4 5
4 5
10 9
2 2
4 5
2-3 6 4 80 200 60
0 0
14 14
1 4 1 4
0 4 14 0 4 14
9
3
4 5 9 5
4 5 9
10 9
2 2 0
4 5 c 14
1
0 4
5 14
4
4
10
Option c) 2
4
Activity 2-3 which was at crash time has been relaxed by 1 day to 5 days. By
doing this it would be still at a time < its normal time.
Activity 1-2 has been crashed by 1 day to 4 days while activity 2-4 has been
relaxed to original 10 days
The crash cost from the original network would be 70+60+90=Rs.220
Therefore the Direct cost for this option of 14 days Project Time = 800+220=1020.
Indirect cost = 14x120=1680
Hence Total Project cost = 1680+1020=2700
Hence this c) option would be the best option